Project name: Akzo Nobel factory Expansion - Phase 2
Date Schedule
VO
Issued Doc. No. To Description delay VO Issued by Remark
Number
dd.mm.yy (DAY)
22.05.13 001 DCC Slope stability improvement and dewatering no Thanh DCC signed
22.05.13 002 DCC Revised FC drawing for Silo and brewhouse no Thanh DCC signed
25.05.13 003 DCC Structural FC drawings of Silo and brewhouse no Thanh DCC signed
25.05.13 004 DCC Submit Quot of investigation works and constructing the boiler's plinth yes Thanh DCC signed
30.05.13 005 DCC start demolition works of villa, fence, water tank, tower tank yes Thanh DCC signed
31.05.13 006 DCC Investigation works and constructing the boiler's plinth yes Thanh DCC signed
04.06.13 008 DCC Installation of Anchorge steel plate yes Thanh DCC signed
05.06.13 009 DCC FC drawing - Brewhouse slot drain (05-A-001 rev 03 dated 04.06.13) yes Thanh DCC signed
11.06.13 010 DCC FC drawing - Brewhouse and Silo - issued dated 07.06.13 yes Thanh DCC signed
12.06.13 011 DCC Disconnect to VBL's waste water system no Thanh DCC signed
14.06.13 012 DCC Acnhor plate 100x400x100 yes Thanh DCC signed