PILESET CALCULATION USING MODIFIED HILEYS' FORMULA

( E * W * H ) * ( W + e^2 * P )
Ru =
( S + C/2 ) * ( W + P )

Where: E = Efficiency of hammer


Ru = Ultimate resistance of pile, in tonnes
W =  Weight of striking hammer, in kg
H = Height of free fall of hammer, in m
S = Final set, or penetration of pile per blow, in mm
P =  Weight of pile, in kg
C = Temporary compression, in mm
e = Coefficient of restitution
W.L = Working load of pile, in tonnes

Diameter of pile : 400 mm Unit Weight : 384 kg/m


Hammer used : 11T Hydraulic Hammer
Pile Type : Spun Pile
Efficiency of Hammer : E = 75 %
Hammer Weight : W = 10000 kg
Assume penetration of pile : L = 12 m
Weight of pile : P = 4608 kg
Ram Height : H = 0.67 m
Assume temporary compression : C = 14 mm (Assumed) ~15mm
Coefficient of Restitution : e = 0.4
Factor of safety : F.O.S. = 2
Pile Working Load :  W.L. = 195 Tonne

Pile size Wt./m P S Ru W.L F.O.S


Remark
(mm) (kg/m) (kg) (mm/10blow) (tonne) (tonne)
400 384 4608 6.00 485.99 195 2.5 OK,Passed
400 384 4608 8.00 473.53 195 2.4 OK,Passed
400 384 4608 10.00 461.69 195 2.4 OK,Passed
400 384 4608 12.00 450.43 195 2.3 OK,Passed
400 384 4608 14.00 439.70 195 2.3 OK,Passed
400 384 4608 16.00 429.48 195 2.2 OK,Passed
400 384 4608 20.00 410.39 195 2.1 OK,Passed
400 384 4608 25.00 388.79 195 2.0 Failed