Indian Journal of Science and Technology, Vol 9(30), DOI: 10.17485/ijst/2016/v9i30/99009, August 2016 ISSN (Online) : 0974-5645
Abstract
This paper focuses to reduce the real power losses in a real-time radial distribution system by performing Optimal Capacitor
Placement (OCP) using Genetic Algorithm (GA), thereby enhancing the reliability of the entire system. Reliability analysis
on Amrita power house II, Amrita University, Ettimadai campus, Coimbatore operating at 22kV/415V system is carried out
using ETAP software. System status subjected to different failures as ca se studies are considered. System performance
is analyzed using Adaptive Newton Raphson method. Suggestions for suitable placement of capacitor banks with optimal
size and cost is proposed by performing OCP using GA. Comparison of the results of reliability analysis is done with and
without capacitor placement. Optimal capacitor placement helps in achieving optimal cost with suitable size and location
of the capacitor bank, which is evident from the report obtained from the ETAP software. Out of load bus and breaker
failure condition, the predominant remark was the considerable increase in real power loss of the overall system. Thus, the
optimal capacitor placement found to be the most suitable solution for reduction of real power losses in a radial distribution
system. Results of analysis illustrates that the increased value of sustained interruption system indices like System Average
Interruption Frequency Index (SAIFI), System Average Interruption Duration Index (SAIDI) and preferably Customer
Average Interruption Duration Index (CAIDI) indicates that the system is highly unreliable without capacitors. The results
obtained after capacitor placement indicates reduction in real power losses and thus decrease of reliability indices value.
The expected energy that is not getting supplied to the consumer can be estimated and the cost incurred for loss can be
reduced with the reliability assessment. Thus long and short term planning could be carried out. Improvements can be
done by including more system reliability assessment indices. Total cost incurred due to unreliable condition of the system
can be found out. This work would allow further extension by introducing FACTS devices for reliability enhancement.
Keywords: Customer Average Interruption Duration Index, Genetic Algorithm, Optimal Capacitor Placement Relibaility
Indices, Radial Distribution System, Reliability Assessment
of building new power transmission and distribution identified taking into account the power factor variation
lines increasingly complicated and time-consuming. on the buses. Optimal capacitor placement (OCP)15-18 is
Making existing lines as well as new ones more efficient carried out using Genetic Algorithm (GA) and optimal
and economical, then becomes a compelling alterna- location is identified which helps the power factor of the
tive. Therefore, the reliability issues are to be seriously buses to be corrected nearer to unity, the total cost of the
considered for the analysis and planning the power sys- system is optimized and subsequently reliability indices
tem. Power system reliability falls under the category is improved. The work is discussed in the following sec-
of system adequacy and system security. System ade- tions. Section I introduces the work, Section II deals with
quacy evaluation technique is used in security domain to the reliability assessment and its indices in distribution
evaluate security based reliability. This is also helpful in system, Section III discusses the test system, Section IV
evaluating the risk based security limits. System security handles the performance of the test system under differ-
is usually associated with system planning and operation. ent unconditional scenarios of the equipment in terms
Thus, quality of electric supply consists of reliability as of reliability indices, Section V deals with the Optimal
one of its important aspect. Therefore reliability as such Capacitor Placement (OCP) using Genetic Algorithm
is based on the probability and consequence. Initially, (GA) and Section VI concludes the work.
the researches focused towards the reliability aspect of
transmission system. Further, the reliability studies were
towards the generation and distribution side of the power 2. Reliability Assessment and its
network. Minimal cut-set approach for failure modes and Indices in Distribution System
its effects were generally adopted for reliability studies
towards transmission and distribution side of the power 2.1 Necessity and Importance of Reliability
network1. Based on the Load Supplying Capability (LSC) Assessment
and load forecast, failure determination of transmission
Managing bulk system reliability for a utility is essential.
line is carried out. Deterministic Indices like system
Measurement of actual system reliability provides feedback
Load Supplying Capability (LSC), Generation Utilization
to the planners on the performance of executed plans. It
Factor, Transmission Reserve Factor and Reliable
gives feedback to operation personnel on reliability effects of
Transmission Capacity along with Probabilistic Indices
operating and maintenance practices. Reliability Assessment
like Loss of Load Probability (LOLP) and Loss of Load
helps in system planning for long and short terms. System
Expectations (LOLE) are considered for reliability evalu-
reliability can be grouped into the two distinct aspects i.e. in
ation under transmission system2-7. Reliability criterion
terms of system security and system adequacy.
mainly focuses on the concepts of probability of failure
System security involves the ability of the system to
and expected frequency of failure. Even, the concept of
respond to disturbances and remain in secure operation
reliability enhancement using Thyristor Controlled Series
meeting the customer demand. In order to maintain the
Capacitor (TCSC) is introduced with the development of
desired level of adequacy and to ensure against excessive
FACTS technologies. Multi module TCSC will be operated
shortages, additional reserve must be maintained. And,
in both Module level and Common level protection mode
system adequacy relates the existence of sufficient genera-
to ensure reliability. State space model for module created
tion, transmission and distribution facilities within the
based on Markov Process, is evaluated based on system
system to satisfy the customer load demand. It is associ-
and delivery point indices8-13. But, depending on the
ated with the system steady state conditions and system
load point of view the reliability analysis plays major role
planning for long and short terms. In case of adequacy
towards the distribution network. This paper deals with
and security, the higher the reserve margin the higher the
the reliability analysis of a real-time radial distribution
system reliability but at a substantial economic cost.
system. The system considered is Amrita’s power house
II, Amrita University, Ettimadai campus, Coimbatore
2.2 Reliability Indices in a Distribution
operating at 22kV/415V. The reliability analysis on the
system is analyzed using ETAP software14. Reliability Network
assessment under different equipment failure condition The reliability of a network could be judged on the basis
is taken into account. Out of which, the critical failure is of reliability indices. Sustained Interruption System
2 Vol 9 (30) | August 2016 | www.indjst.org Indian Journal of Science and Technology
M. P. Pranitha and K. R. M. Vijaya Chandrakala
(1)
Usually, SAIFI is calculated with the statistics based on
number of customers. Increased value of system average
interruption frequency index indicates high reliability.
System Average Interruption Duration Index (SAIDI)
indicates the total duration of interruption for the aver-
Figure 1. Single line diagram of Amrita’s Power house-II,
age customer experiences sustained interruption over a
Amrita University, Ettimadai campus, Coimbatore.
predefined time expressed as f/customer year.
Vol 9 (30) | August 2016 | www.indjst.org Indian Journal of Science and Technology 3
Optimal Capacitor Placement based Improved Reliability Assessment of a Distribution System
Table 1. Probable Failure and Repair Rates for Each Table 2. System Data
Component COMPONENTS RATINGS BUS TOTAL
Probable Failure Probable Repair Power Grid 22kV Bus 1 1
Component
Rate (failure/yr) Rate (repair/yr) 500
Switch 0.003 43.8 kVA,22kV/433 Bus 3
Transformer V
Fuse 0.003 43.8
(ONAN, star- 500 kVA,
Cable 0.05 1095 Bus 3 3
delta) 22kV/433 V
Generator 0.032 43.8 250 kVA,
Bus 3
Transformer 0.015 43.8 22kV/433 V
0.467 MVA Bus 6
Lumped load 0.02 175.2 Lumped loads 0.438 MVA Bus 7
Bus 0.001 4380 (lighting loads,
0.646 MVA Bus 8 5
Static load 0.02 175.2 motor loads,
transformers) 0.078 MVA Bus 9
0.415 MVA Bus 12
a total load capacity of 1.814 MVA. CAIDI as reliability Static load
0.041 MVA Bus 7 1
index under distribution network is used for justifying (DC motor)
the reliability status of the system is shown in Table 2. 890 mtrs
b/w bus 1 &
In this study, load buses i.e. Bus 6, Bus 7, Bus 8, Bus 9 bus 2
and Bus 12 are made out of service individually and the b/w bus 1 &
25 mtrs
bus 2
reliability assessment is done. During the load bus failure
b/w bus 2 &
the real power losses increases. The real power losses on 1080 mtrs
bus 3
performing the load flow analysis using adaptive Newton b/w bus 3 &
Raphson (NR) method under subsequent bus failures 20 mtrs
bus 7
with CAIDI is computed and shown in Figure 2. Since the b/w bus 3 &
Cable 15 mtrs 8
load buses are connected through bus coupler, the fail- bus 6
ure of each bus will have slight impact on others. From b/w bus 3 &
20 mtrs
the Figure 2, Bus 7 failure caused the impact on the total bus 8
system with increased value of CAIDI to be 28.07 (hr/cus- b/w sync
25 mtrs panel &
tomer interruption) and higher overall system real power
bus 4
losses of 100kW which indicates the system to be highly
b/w sync
unreliable when compared to other load buses. 25 mtrs panel &
bus 5
4.2 Breaker Failure
Circuit breakers are kept at the lines connecting the load
bus. Each breaker is made open individually and reliabil-
ity indices are found out. CAIDI during breaker failure is
plotted in Figure 3. Breaker failures at bus 6 have highest
CAIDI of 27.7 (hr/customer interruption) and real power
losses (153kW) when compared to other bus impacts.
Therefore, identified unreliable condition during breaker
failure is predominant at bus 6.
When compared with the normal condition CAIDI
during bus 7 failure and breaker failure at bus 6 have higher
value of indices and real power flow losses. It indicates that
the system is highly unreliable during the above cases.
The suggested solution for increasing reliability of the Figure 2. Customer Average Interruption Duration
radial distribution system is by locating the capacitors in Index (CAIDI) and real power losses under load bus failure
the load buses which would help the reliability in terms condition.
4 Vol 9 (30) | August 2016 | www.indjst.org Indian Journal of Science and Technology
M. P. Pranitha and K. R. M. Vijaya Chandrakala
(4)
Where,
Nbus – Number of candidate buses; xi – 0 or 1 possible,
depending on availability; C0i – Installation cost; C1i – Per
kvar cost of capacitor bank; Qci – Capacitor bank size in
kvar; Bi – number of capacitor banks; C2i – Operating cost
of per bank, per year; T – Planning period in years; C2 –
Cost of each kWh loss; l – load levels ; Tl – Time duration in Figure 4. OCP results at the buses of the Amrita distribution
hours of load level l; P1L – Total system loss at load level l14. system using ETAP software under bus 7 failure.
Vol 9 (30) | August 2016 | www.indjst.org Indian Journal of Science and Technology 5
Optimal Capacitor Placement based Improved Reliability Assessment of a Distribution System
6. Conclusion
Improved planning for a real-time radial distribution sys-
tem of Amrita Power House II operating at 22kV/415V is
suggested. The system is analyzed using ETAP software/
Reliability Assessment mode. The system was subjected
to two case studies. Firstly, load buses were made to fail Figure 9. Real power losses at Amrita distribution system
one by one and correspondingly reliability index CAIDI after OCP using ETAP software under breaker failure at
and total system real power loss were studied. Secondly, bus 6.
6 Vol 9 (30) | August 2016 | www.indjst.org Indian Journal of Science and Technology
M. P. Pranitha and K. R. M. Vijaya Chandrakala
breaker failure at all the load buses were concurrently 7. Billinton R, Wangdee W. Impact of utilising sequential
removed one after the other and CAIDI with total real and non-sequential simulation techniques in bulk elec-
power loss of the system were noted. The significant tric system reliability assessment. Proceedings of IEEE
increase in the CAIDI and real power losses due to bus on generation, transmission and distribution. 2005 Sep;
7 failure and breaker failure at bus 6 would make the 152(5):623-28.
8. Philip R Van Horne, Carol N Schoenberger. TRAP: An
system highly unreliable. Therefore, Optimal Capacitor
Innovative Approach to Analyzing the Reliability of
Placement (OCP) was suggested using Genetic Algorithm
Transmission Plans. IEEE Transaction on Power Apparatus
(GA) technique. With optimal choice on the no. of capac- and Systems. 1982 Jan; 101(1):11-16.
itors to be installed in the distribution system under the 9. Urbanek J, Piwco RJ, Larsen EV, Damsky BL, Furumasu
contingencies of bus 7 failure and breaker failure at bus 6 BC, Mittlestadt W, Eden JD. Thyristor Controlled Series
lead to reduced CAIDI value and total system real power Compensation prototype installation at the slatt 500kV
losses. Therefore, the reliability of the Amrita distribution substation. IEEE Transaction on Power Delivery. 1993 Jul;
system is improved. 8(3):1460-69.
10. Godart TF, Imece AF, McIver JC, Chebli EA. Feasibility of
thyristor controlled series capacitor for distribution substa-
7. Appendix tion enhancement. IEEE Transaction on Power Delivery.
1994 Jul; 8(3):362-68.
Amrita’s power house II system data description is tabu-
11. Fotuhi-Firuzabad M, Roy Billinton, Sherif Omar Faried.
lated below in Table 2.
Transmission system reliability evaluation incorporating
HVDC links and FACTS devices. IEEE Transaction on
8. References Power Systems. 2001 Jul; 1:321-26.
12. Distribution Reliability Working Group. IEEE guide for
1. Roy Billinton, Murty Bavaraju P. Transmission planning Electric power distribution reliability indices. IEEE Power
using a reliability criterion, part i: a reliability criterion. and Energy Society. 2012 May; p. 1-43.
IEEE Transaction on Power Apparatus and Systems. 1970 13. Roy Billinton, Ronald N Allan. Reliability Evaluation
Jan; 89(1):28-34. of Engineering systems. Plenum Press Series on Power
2. Billinton R, Kumar S. A comparative study of system versus Engineering. 2002 Jan.
load point indices for bulk power systems. IEEE Transaction 14. Morton DP, Callister R. Spirometry measurements during
on Power Systems. 1986 Aug; 1(3):148–55. an episode related transient abdominal pain, ETAP 16.2. Int
3. Billinton R, Grover MS. Reliability evaluation in distribu- J Sports Physiol Perform. 2006 Dec; 1(4):336-46.
tion and transmission Systems. Proceedings of IEEE. 1975 15. Baran ME, Wu FF. Optimal capacitor placement on radial
May; 122(5):517-23. distribution system. IEEE Transaction on Power Delivery.
4. Banerjee SK, Reddy BR. Reliability calculation for electrical 1989 Jan; 4(1):725-34.
transmission systems on the basis of mean failure indices. 16. Anwar S Siddiqui, Farrukh Rahman MD. Optimal capacitor
IEEE Transaction on Reliability. 1983 Oct; 32(4):346-49. placement to reduce losses in Distribution system. WSEAS
5. Fotuhi-Firuzabad M. Roy Billinton, Sherif Omar Faried. transactions on power system. 2012 Jan; 7(1):12-17.
Power system reliability enhancement using Thyristor 17. Davoodi Majid, Davoudi Mohsen, Ganjkhany Iraj, Aref
Controlled Series Capacitor. IEEE Transaction on Ali. Optimal capacitor placement in distribution networks
Powersystem. 1999 Feb; 14(1):369-74. using genetic algorithm. Indian Journal of Science and
6. James A Momoh, Yanchun Wang, Elfayoumy Mahmoud, Technology. 2012 Jul; 5(7):3054-58.
Mittelstadt Bill, Agarwal SK Adapa R. A value-based reli- 18. Khalesi Navid, Javadian Sayed Ali Mohammad. Distribution
ability enhancement scheme for bulk transmission system system reliability with considering variation in DG and load
planning. IEEE Transactions on Power system. 1998 Nov; consumption. Indian Journal of Science and Technology.
13(4):1541-47. 2011 Oct; 4(10):1285-89.
Vol 9 (30) | August 2016 | www.indjst.org Indian Journal of Science and Technology 7