ID: 2016-ISFT-382
Abstract: This paper studies and analyzes the impact of Metropolitan Electricity Authority (MEA), 40 MW and
rooftop photovoltaic (Rooftop PV) generation penetration Provincial Electricity Authority (PEA), 60 MW.
level and its locations on the voltage levels of low-voltage
(LV) distribution network of Provincial Electricity Authority Traditional LV distribution network of the power system in
(PEA), Thailand. The configuration of distribution power Thailand is a passive network, only considered a single
network, solar insolation and real load profile in the studied direction power flow [4] and not support or designed for
area are analyzed and simulated by using DIgSILENT Rooftop PVs, especially, connected to LV network. This
Power Factory. This research focused on the behavior of penetration would impact the LV power quality (PQ) on the
voltage level variation at the point of common coupling LV network.
(PCC) and the dead end (DE). The key simulation results Generally, PQ issues could be voltage variations and current
indicate that the over voltage occurred at the PCCs and harmonics [5]. In Thailand, according to power quality
DEs when Rooftop PVs concentrate above 16% around DEs standards about voltage variations, LV network’s voltage
of the studied network. As a result, PEA regulation on PVs level is limited between ± 10% (0.9-1.1 p.u.) of its nominal
penetration level may need to be further revised so that the voltage level.
appropriated amount of Rooftop PV can be allowed to be
connected to the LV networks. From this study, various MEA prepares regulation for support Rooftop PVs
impact factors of Rooftop PVs can be revealed such as the connected to its LV network as follow:
amount and duration of the of PV generated power, the load
profile, the locations and penetration levels of the installed 1. Capacity of Rooftop PV generates less than 10 kW per
Rooftop PVs and, last but not least, the structure of the house.
distribution networks.
2. Overall of capacity in LV network must be less than
1. INTRODUCTION 15% of rate distribution transformer.
In recently years, among of renewable energy resource, PEA prepares regulation for support Rooftop PVs connects
solar power is one of the promising resource. Solar power to PEA’s LV network, as follow:
has been installed in many areas worldwide. Today
1. Case of single-phase Rooftop PVs less than 25% of
technologies of PV are continuously developed, and cost of
rate distribution transformer is allowed to connected to
PV system rapidly reduces to less than 1$ per watt [1]. It is
LV network, and less than 10 kW per house is allowed
clear that, solar power will be increasing in the future. For
energize per phase.
example, in Japan, a system in Gunma province has been
studied by measuring and observating on 550-houses 2. Case of three-phase Rooftop PVs less than 80% of rate
Rooftop PVs connected to LV network with overall capacity distribution transformer is allowed to connect to LV
of 2.2 MW, 4.1kW per house. The key result indicates that network, and less than 56 kW is allowed to energize.
over voltage occurred when Rooftop PVs generated peak
power and load is very low [2] and Rooftop PVs are As mentioned above, all these criteria is questionable.
concentrating around DE [3]. Therefore, Thailand should study impact of Rooftop PVs
connects to LV network, in order to revise the regulation
Thailand government promotes a policy using PV system in and find methods to solve or alleviate this problem by
the next 10 years with the target 1,000 MW. This policy utilities.
promotes installing Rooftop PVs and Building Integrated
PV (BIPV) by using feed in tariff (FIT), 6.85 baht per watt- This research focused on voltage variation issue, when
hour. In year 2013, government distributes this target to Rooftop PVs connects to Thailand LV network. The studied
area is PEA’s LV network in urban, Nakhon Ratchasima
province, Thailand. Based on the data from the department unavailable load of each house, therefore, this study utilized
of energy, Thailand, this area is well known in high solar total watt-hour usage of every house. This data has been
insolation [6]. received from CIS (Customer Information System) program
from PEA in 1 billing cycle and was then divided into
2. METHODOLOGY percentage of usage real and reactive power of each house.
2.1 STUDIED ELECTRICAL NETWORK
Data of solar insolation selected at 12.30 pm, 18 May 2012,
As shown in figure 1, the studied electrical network is radial due to highest. Which is about 1,166 w/m2.
and consist of 250 kVA distribution transformer, cable of 95
2.3 ROOFTOP PV POWER GENERATION
mm2 (main line), cable of 50 mm2 (sub main line), terminal
buses and load buses. This network supplies electrical Power generation of Rooftop PV can be calculated by (1)
power to 279 customers via 2 feeders. The data from GIS and an efficiency of DC to AC conversions can be
(Geographic Information System) program from provided expressed by (2)
by PEA is used. Meters have been connected to phase A for
65 units, phase B for 69 units, phase C for 3 units, three- PPV=Insolation × Area × EFFPV cells × EFFDCtoAC (1)
phase meters for 3 units and unknown data 130 units.
Distance of this network is 2.38 circuit-kilometers. ( × 3 is EFFDCtoAC=INSPV × CCPV × COPPV × EFFPV (2)
the amount of houses at terminal bus. Where,
PPVis power generation of Rooftop PV
EFFPV cellsis an efficiency of PV modules
INSPVis efficiency installing PV array (90%)
CCPVis efficiency temperature PV array (85%)
COPPV is efficiency wiring losses (97%)
EFFINVis efficiency inverter (94%)
From the measurement by Google Earth application, the
total rooftop area in this study is 28,500 m2. By onsite
surveying and detailed consideration on the rooftop
characteristic, this studied define the PV module installation
area of 40%. Poly crystalline silicon PV from Sharp
Company, model ND-120T1D with 12.1% efficiency is
Fig. 1. Studied electrical network selected.
2.2 LOAD PROFILE AND SOLAR INSOLATION From the calculation, the average of power generation from
Rooftop PV for each house is 4 kW. Additionally, PEA has
The recorded load profile received from TOU (Time of Use) define that a distribution transformer operates, at PF 0.9,
meter installed at the studied distribution transformer. then this studied considers the amount of 45 customer
Duration of record was in April-May 2012. The solar houses or about 16% of 279 houses where PV system was
insolation data has been received from the faculty of installed, connected and generated 180 kWp to this LV
Physics, Silpakorn University, Thailand. The load profile network.
and the solar insolation in one day are shown in figure 2.
3. SOLUTION AND RESULT
3.1 SOLUTION
Watt
Var Because this studied unknown data of meters connected to
Insolation this LV network, 130 units. Therefore define load and LV
network were balance three-phase network.
Firstly, by utilizing DIgSILENT program, the base case has
been simulated. The result indicates that the voltage levels
of PCCs and DEs in this network are in between 0.971-
0.990 p.u. as shown in figure 3. As expected, the highest
0 1 2 3 4 5 6 7 8 9 10111213141516171819202122 23 voltage level is at secondary of the distribution transformer.
Based on the studied condition, the lowest voltage level
Fig. 2. Load profile and solar insolation on 1 day occurs at DE 02 and DE 19, which are 0.971 p.u.. At the
The studied data of real power and receive power is 76,410 farthest distance, i.e. DE 03 (about 0.414 km), the voltage
W and 38,115.2 Var (at 11.00 am, 25 May 2012), level is 0.973 p.u.
respectively, is selected due to the lowest load. Because
th
V International Symposium on “Fusion of Science & Technology”, New Delhi, India, January 18-22, 2016 ♦ 539 ♦
Impact of Photovoltaic Power Generation on Voltage Level of Low-Voltage Distribution Systems
0.9500
0.00 0.10 0.20 0.30 0.40 [km] 0.50
Voltage, Magnitude
1.00 DE 19
0.973 p.u.
0.97
0.00 0.10 0.20 0.30 0.40 [km] 0.50
Voltage, Magnitude
1.03
1.01
0.99 DE 19
0.973 p.u.
0.97
0.00 0.10 0.20 0.30 0.40 [km] 0.50
Voltage, Magnitude
th
V International Symposium on “Fusion of Science & Technology”, New Delhi, India, January 18-22, 2016 ♦ 540 ♦
Impact of Photovoltaic Power Generation on Voltage Level of Low-Voltage Distribution Systems
th
V International Symposium on “Fusion of Science & Technology”, New Delhi, India, January 18-22, 2016 ♦ 541 ♦