Analisis Pembebanan
Beban vertikal
qv = qsandar+qpipa
qv = 1.0879 KN/m
Mv = 0,125*qv*Lp2
Mv = 0.54395 KNm
Beban Horizontal
qh = qsandar
qh = 1 KN/m
Mh = 0,125*qh*Lp 2
Mh = 0.5 KNm
Kontrol Lendutan
Lendutan ijin
δijin = Lp/240
δijin = 0.00833 m
Tulangan Lentur
Digunakan tulangan 2
76.2 mm
0.0879 KN/m
1 KN/m
2m
2.4E+08 N/m2
2E+11 N/m2
1011285 mm4
22700 mm3
29.05 Mpa
240 Mpa
160 mm 300
35 mm 265
200000 Mpa
0.8425
0.0619
0.0371
0.0058
0.0056
0.8167
0.75
5 KNm
118.5 mm
160 mm
6.1224 KNm
2.7250 Mpa
9.7196
0.0121
228.68 mm2
13 mm
1.7222
D13
2.54 2 1.27
Jarak antara tiang railing :
2m
Berat beton bertulang :
25 KN/m3
Berat beton tak bertulang
24 KN/m3
22 KN/m3
Momen
(KNm)
0.0000
-2.1875 0.625 0.008333
-0.0200 0.633333
-0.2100
1.8502
1.4832
0.9517
0.0858
0.3375
0.1828
2.4738
1.2369
1.3
1.8
1.2369 KNm
-3.5755 KNm
-4.82792 KNm
29.05 Mpa
420 Mpa
200 mm
20 mm
200000 Mpa
0.8425
0.0291
0.0212
0.0033
0.0032
0.8167
0.75
4.827921 KNm
172 mm
1000 mm
5.9117 KNm 25.4 15.875
0.1998 Mpa
17.0092
0.0005
12.7
573.3333 mm2
16 mm
2.8504
333.3333
200
0.0002
0.0032
551.8134 mm2
13 mm
4.1557
200
200
aran dan Trotoar seperti gambar di atas.
KN
N
N
N
N
mm
mm2
Smax 1 menentukan
φ10 - 50
φ10 - 100
Perencanaan Slab Lantai Jembatan & Pelat Injak
Data Slab Lantai Jembatan
Bahan Struktur
Mutu baja :
Untuk baja tulangan dengan D > 12 mm : U- 39
Tegangan leleh baja, fy = U * 10 = 390
Untuk baja tulangan dengan D < 12 mm : U- 24
Tegangan leleh baja, fy = U * 10 = 240
Bidang vertikal yang ditiup angin merupakan bidang samping kendaraan dengan tinggi
2 m di atas lantai jembatan h= 2
Jarak antara roda kendaraan x= 1.75
Transfer beban angin ke lantai jembatan PEW = [ 1/2 * h / x * Tew ]
PEW =
QMS 5 KN/m
QMA 2.69 KN/m
PTT 157.5 KN
PEW 1.008 KN
∆T 12.5 ᴼC
MOMEN SLAB
Faktor Daya Keadaan
No Jenis Beban
Beban Layan Ultimate
1 Berat sendiri KMS 1 1.3
2 Beban mati tambahan KMA 1 2
3 Beban truk "T" KTT 1 1.8
4 Beban angin KEW 1 1.2
5 Pengaruh temperatur KET 1 1.2
KOMBINASI -1
Faktor Momen (-) Momen (+)
No Jenis Beban
No Jenis Beban
Beban KNm KNm
1 Berat sendiri 1.3 1.2037 0.3242
2 Beban mati tambahan 2 0.8093 0.4198
3 Beban truk "T" 1.8 41.8226 37.6724
4 Beban angin 1.2 0.2677 0.2411
5 Pengaruh temperatur 1.2 0.0087 0.0437
Total Momen ultimate slab, Mu =
7. Pembesian Slab
Momen Tumpuan
ρ < ρmax
Luas tulangan yang diperlukan As' = ρ * b * d =
Diameter tulangan yang digunakan
Jumlah tulangan yang diperlukan n = As / ( π / 4 * D2 ) =
Jarak tulangan terpasang
Digunakan tulangan bagi 7
Momen Lapangan
ρ < ρmax
112,5 KN
Mpa
/ᴼC
Mpa
Mpa
m
m
KN/m3
KN/m
KN/m
DLA = 0.4
KN
permukaan lantai jembatan akibat
m/det
KN/m
78.7956 KNm
fc' = 29.05 Mpa
fy = 390 Mpa
h= 200 mm
d' = 35 mm
Es = 200000 Mpa
β1 = 0.8425
b = β1 * 0,85 * fc'/fy * 600 / ( 600 + fy ) = 0.0323
ρmax = ρb * ( 0,003 + fy / Es ) / 0,007 = 0.0229
ρmin = 1,4 / fy = 0.0036
ρmin = √ fc' / 4 * fy = 0.0035
φ= 0.8167
Mu = 78.7956 KNm
d= 165 mm
b= 1000 mm
Mn = Mu / φ = 96.4845 KNm
Rn = Mn * 10-6 / ( b * d2 ) = 3.5440 Mpa
m = fy / 0,85 * fc' = 15.7943
ρ = 1 / m * ( 1 - √ 1 - 2 * m * Rn / fy ) = 0.0099
As = ρ * b * d = 1625.8929048 mm2
D 16 mm
n = As / ( π / 4 * D2 ) = 8.0833
s=b/n 111.11111111
D16 - 100
ρ' = 0.0049
maka
ρ' = 0.0049
As' = ρ * b * d = 812.94645238 mm2
D 13 mm
n = As / ( π / 4 * D2 ) = 6.1222
s=b/n 142.85714286
D13 - 125
69.4132 KNm
fc' = 29.05 Mpa
fy = 390 Mpa
h= 200 mm
d' = 35 mm
Es = 200000 Mpa
β1 = 0.8425
b = β1 * 0,85 * fc'/fy * 600 / ( 600 + fy ) = 0.0323
ρmax = ρb * ( 0,003 + fy / Es ) / 0,007 = 0.0229
ρmin = 1,4 / fy = 0.0036
ρmin = √ fc' / 4 * fy = 0.0035
φ= 0.8167
Mu = 69.4132 KNm
d= 165 mm
b= 1000 mm
Mn = Mu / φ = 84.9957 KNm
Rn = Mn * 10-6 / ( b * d2 ) = 3.1220 Mpa
m = fy / 0,85 * fc' = 15.7943
ρ = 1 / m * ( 1 - √ 1 - 2 * m * Rn / fy ) = 0.0086
As = ρ * b * d = 1416.9253588 mm2
D 16 mm
n = As / ( π / 4 * D2 ) = 7.0444
s=b/n 125
D16 - 100
ρ' = 0.0043
maka
ρ' = 0.0043
As' = ρ * b * d = 708.46267941 mm2
D 13 mm
n = As / ( π / 4 * D2 ) = 5.3354
s=b/n 166.66666667
D13 - 150
c = n * Ast / b = 12.836629463 mm
c = n * Asl / b = 11.186804343 mm
ormasikan ke beton dihitung sbb :
Icr = 1/3 * b * c3 + n * Ast * ( d - c )2 = 297920425.57 mm4
Icr = 1/3 * b * c3 + n * Ast * ( d - c )2 = 265129657.14 mm4
yt = h / 2 = 100 mm
Mcr = fr * Ig / yt = 2.52E+07 Nmm
c
* Ie tumpuan ) + 1/48 * P * Lx3 / ( Ec * Ie tumpuan ) = 2.12 mm
c
* Ie lapangan ) + 1/48 * P * Lx3 / ( Ec * Ie lapangan ) = 2.36 mm
mm
mm
112,5 KN
DLA = 0.4
KN
KN/m3
KN/m2
m
m
KNm
KNm
ρ = 1 / m * ( 1 - √ 1 - 2 * m * Rn / fy ) = 0.0067
As = ρ * b * d = 1112.6984329 mm2
D 13 mm
n = As / ( π / 4 * D2 ) = 8.3797
s=b/n 111.11111111
D13 - 100
112,5 KN
DLA = 0.4
KN
KN/m3
KN/m2
m
m
KNm
KNm
ρ = 1 / m * ( 1 - √ 1 - 2 * m * Rn / fy ) = 0.0071
As = ρ * b * d = 1166.9244772 mm2
D 16 mm
n = As / ( π / 4 * D2 ) = 5.8015
s=b/n 166.66666667
D16 - 150
Perencanaan Diafragma & Balok Girder
h h
s'
Gaya Lintang
V = 1 / 2 * QMS * s = 4.2 KN
VU = KMS * V = 5.46 KN
Perhitungan tulangan diafragma
Momen tumpuan
Momen tumpuan
Tulangan Geser
Perencanaan Girder
Data Jembatan Specific Gravity
Uraian Dimensi Berat
Jenis Bahan
Panjang balok girder L= 25 m (KN/m3)
Jarak antar girder s= 1.7 m Beton bertulang wc = 25
Tebal plat lantai jemb h0 = 0.2 m Beton wc' = 24
Tebal lapisan aspal + overlay ha = 0.1 m Aspal waspal = 22
Tinggi genangan air hujan th = 0.05 m Air hujan wair = 9.8
Jarak antar diafragma sd = 5m
Jarak antar railing sr = 2m
Analisis beban
a. Beban Mati
1) Berat sendiri balok girder
Bj q
Luas penampang M2
(KN/m ) (KN/m)
3
1 0.0975 25 2.4375
2 0.3 25 7.5
3 0.327 25 8.175
qgirder = 18.1125
Pd = bd * hd * sd * Bj = 10.2 KN
qs = hs * ss * Bj = 8.5 KN/m
A B C D E F G H I J K
A B E F G H I J K
A B C D E F G H I J K
2,5 X 10 M
Pembebanan
q qu
Faktor Beban Ultimate
KN/m KN/m
qgirder = 18.1125 1.3 23.54625
qs = 8.5 1.3 11.05
qma = 4.59 2 9.18
Total qbeban mati = 43.77625
Reaksi Perletakkan ƩV
RAV = RKV
RAV = RKV = ( 25 * q + 6 * P) / 2
RAV = RKV = 859.3231 KN
Bidang Lintang
0 DA (L=0) = RAV - P = 755.283125 KN
2.5 DB (L=2,5) = RAV - P - 2,5*q = 645.8425 KN
5 DC (L=5,0) = RAV - 2P - 5*q = 432.361875 KN
7.5 DD (L=7,5) = RAV - 2P - 7,5*q = 322.92125 KN
10 DE (L=10,0) = RAV - 3P - 10*q = 109.440625 KN
12.5 DF (L=12,5) = RAV - 3P - 12,5*q = 0 KN
Bidang Momen
MA (L=0) = 0 = 0 KNm
MB (L=2,5) = RAV*2,50 - P*2,50 - 0,5*q*L2 = 1751.40703 KNm
MC (L=5,0) = RAV*5,00 - P*5,00 - 0,5*q*L 2
= 3229.2125 KNm
MD (L=7,5) = RAV*7,50 - P*7,50 - P*2,50 - 0,5*q*L
= 2
4173.31641 KNm
ME (L=10,0) = RAV*10,0 - P*10,0 - P*5,00 - 0,5*q*L
= 2 4843.81875 KNm
MF (L=12,5) = RAV*12,5 - P*12,5 - P*7,50 - 0,5*q*L
= 2
5240.71953 KNm
b. Beban Hidup
Pada pengaruh geran dan beban dinamis, pada tegangan akibat beban garis "P" dikalikan
dengan koefisien kejut sehingga dapat memberikan hasil maksimum, sedangkan beban
merata "q" dan beban "T" tidak dikalikan dengan koefisien kejut.
Koef. Kejut
K = 1 + 20/(50 + L) L= 25 m
K = 1.266667
A B C D E F G H I J K
GP DA
GP DB
GP DC
GP DD
GP DE
GP DF
L= 25 m
P = 106.4921 KN
q = 20.36169 KN/m
x = 0 - 12,5 m
Perhitungan GP Lintang Beban Hidup "D" Koef. Beban Lalu lintas = 1.8
x koef. Y Dx Du
Titik
(m) (satuan) (KN) (KN)
DA 0 1 361.0132 649.823798
DB Negatif 2.5 -0.1 192.9677 347.341802
DB Positif 2.5 0.9 299.4598 539.02762
DC Negatif 5 -0.2 131.4142 236.545624
DC Positif 5 0.8 237.9064 428.231442
DD Negatif 7.5 -0.3 69.8608 125.749446
DD Positif 7.5 0.7 176.3529 317.435265
DE Negatif 10 -0.4 8.307371 14.9532687
DE Positif 10 0.6 114.7995 206.639087
DF Negatif 12.5 -0.5 -53.24606 -95.842909
DF Positif 12.5 0.5 53.24606 95.8429091
Gaya Momen
Diagram GP Momen
Titik Beban P koef. Y Tinggi y
(m) (satuan)
0 1 0
2.5 0.9 2.25 Tinggi y = ((L - x) / L) * x
5 0.8 4
7.5 0.7 5.25
10 0.6 6
12.5 0.5 6.25
GP MA
GP MB
GP MC
GP MD
GP ME
GP MF
GP MF
Mx = P * y + (L * y) / 2 * q
P= 106.4921 KN
q= 20.36169 KN/m
L= 25 m
x= 0 - 12,5 m
Tulangan Geser
Tulangan Kulit
h pada girder, h = 1700 mm > 400 mm, maka perlu digunakan tulangan kulit
Cc = Selimut + Sengkang = 60
Fs = 2 / 3 * Fy = 260
Spasi tulangan kulit s = 380 * (280 / fs) - 2,5 * Cc = 259.2308
Sisa spasi bersih tinggi gelagar (h')
h - 2 * selimut - 2 * d sengkang - nbaris tulangan*dtulangantarik- (nbaris tulangan -1)*25 - dtulangan tekan = 1288
mm
kNm
OK
mm2
mm
mm2
mm2
mm
mm
mm
mm
kNm
Mpa
Mpa
mm
mm
mm
mm
mm
mm
mm
mm
MPa
mm
kNm
OK
mm2
mm
mm2
mm2
mm
mm
mm
mm
kNm
Mpa
Mpa
mm
mm
mm
mm
mm
mm
mm
mm
MPa
mm
kNm
OK
mm2
mm
mm2
mm2
mm
mm
mm
mm
kNm
Mpa
Mpa
mm
mm
mm
mm
mm
mm
mm
mm
MPa
mm
kNm
OK
mm2
mm
mm2
mm2
mm
mm
mm
mm
kNm
Mpa
Mpa
mm
mm
mm
mm
mm
mm
mm
mm
MPa
mm
kNm
OK
mm2
mm
mm2
mm2
mm
mm
mm
mm
mm
Mpa
mm
mm
buah
mm
200
390
Tulangan Lentur
Momen rencana ultimit Girder,
Mutu beton :
Mutu baja tulangan :
Tebal slab beton,
Lebar badan Girder,
Tinggi Girder,
Lebar sayap T-Girder diambil nilai yan
Rn < Rmax OK
m = fy / 0,85 * fc' = 15.7943
angan yang diperlukan :
ρ = 1 / m * ( 1 - √ 1 - 2 * m * Rn / fy ) = #VALUE!
angan minimum, ρmin = 1.4 / fy = 0.00359
ngan yang diperlukan, As = r * beff * d = #VALUE! mm2
tulangan yang digunakan, D 32 mm
As1 = p/4 * D2 = 804.25 mm2
ulangan yang diperlukan, n = As / As1 = #VALUE!
Digunakan tulangan, 14 D 32
As = As1 * n = 11259.47 mm2
td = 50 mm
sengkang yang digunakan, ds = 10 mm
ulangan tiap baris, nt = 6
sih antara tulangan, mm
X = ( b - nt * D - 2 * td - 2 * ds) / (nt - 1) = 93.6 mm
> 35 mm OK
Tulangan Lentur
Momen rencana ultimit Girder,
Mutu beton : K-
Mutu baja tulangan : U-
Tebal slab beton,
Lebar badan Girder,
Tinggi Girder,
Lebar sayap T-Girder diambil nilai yang terkecil dari :
Diambil lebar efektif sayap T-Girder
Jarak pusat tulangan terhadap sisi luar beton, d' = 150 mm
Modulus elastis baja, Es = 2.00E+05 MPa
Faktor bentuk distribusi tegangan beton,
m = fy / 0,85 *
Rasio tulangan yang diperlukan :
ρ = 1 / m * ( 1 - √ 1 - 2 * m * Rn / f
Rasio tulangan minimum,
Mu = 0.00 kNm
350 fc' = 29.05 Mpa
39 fy = 390 Mpa
ts = 200 mm
b= 780 mm
h= 1700 mm
L/4 = 1250 mm
s/2 = 850 mm
12 * ts = 2400 mm
beff = 850 mm
ton, d' = 150 mm d' = 255 mm
Es = 2.0.E+05 MPa
b1 = 0.8425
m * ( 1 - √ 1 - 2 * m * Rn / fy ) = 0
ρmin = 1.4 / fy = 0.00359
Luas tulangan yang diperlukan, As = r * beff * d = 0.00
Diameter tulangan yang digunakan, D 32
As1 = p/4 * D2 = 804.25
Jumlah tulangan yang diperlukan, n = As / As1 = 0.00
Digunakan tulangan, 19 D 32
As = As1 * n = 15280.71
Tebal selimut beton, td = 50
Diameter sengkang yang digunakan, ds = 10
Jumlah tulangan tiap baris, nt = 6
Jarak bersih antara tulangan,
X = ( b - nt * D - 2 * td - 2 * ds) / (nt - 1) = 93.6
> 35 mm OK
mm2
mm
mm2
mm2
mm
mm 9.525
mm
mm
PERHITUNGAN GELAGAR JEMBATAN BALOK-T
1 0.0975
2 0.3
3 0.327
0.7245
Lebar girder b= 0.50 m
Tinggi girder h= 1.20 m
Dimensi Diafragma : Lebar diafragma bd = 0.30 m
Tinggi diafragma hd = 0.80 m
Tebal slab lantai jembatan ts = 0.20 m
Tebal lapisan aspal + overlay ta = 0.10 m
Tinggi genangan air hujan th = 0.05 m
Tinggi bidang samping ha = 3.05 m
Jumlah balok diafragma sepanjang L, nd = 6 bh
Jarak antara balok diafragma, sd = L/nd = 5m
B. BAHAN STRUKTUR
Mutu baja :
Untuk baja tulangan dengan Ø > 12 mm : U - 39
Tegangan leleh baja, fy = U*10 = 390 Mpa
Untuk baja tulangan dengan Ø ≤ 12 mm : U - 24
Tegangan leleh baja, fy = U*10 = 240 Mpa
Specific Gravity :
Berat beton bertulang, wc = 25.00 kN/m3
Berat beton tidak bertulang (beton rabat), w'c = 24.00 kN/m3
Berat aspal padat, wa = 22.00 kN/m3
Berat jenis air, ww = 9.80 kN/m3
C. ANALISIS BEBAN
Gaya geser dan momen pada T-Girder akibat berat sendiri (MS) :
VMS = 1/2 * QMS * L = 363.256 kN
MMS = 1/8 * QMS * L =
2
2270.352 kNm
Gaya geser dan momen pada T-Girder akibat beban tambahan (MA) :
VMA = 1/2 * QMA * L = 57.163 kN
MMA = 1/8 * QMA * L2 = 357.266 kNm
4. BEBAN LALU-LINTAS
Gaya geser dan momen pada T-Gider akibat beban lajur "D" :
VTD = 1/2 * ( QTD * L + PTD ) = 222.36 kN
MTD = 1/8 * QTD * L + 1/4 * PTD * L =
2
1717.00 kNm
a= 5.00 m
b= 5.00 m
Panjang bentang Girder, L= 25.00 m
Gaya geser dan momen pada T-Gider akibat beban truk "T" :
VTT = [ 9/8 * L - 1/4 * a + b ] / L * P TT = 200.81 kN
MTT = VTT * L/2 - PTT * b = 1722.6563 kNm
Gaya geser dan momen yang terjadi akibat pembebanan lalu-lintas, diambil yg memberikan
pengaruh terbesar terhadap T-Girder di antara beban "D" dan beban "T".
Gaya geser maksimum akibat beban, T VTT = 200.81 kN
Momen maksimum akibat beban, D MTD = 1717.00 kNm
Gaya geser dan momen pada Girder akibat pengaruh temperatur, diperhitungkan terhadap
gaya yang timbul akibat pergerakan temperatur (temperatur movement) pada
tumpuan (elastomeric bearing) dengan perbedaan temperatur sebesar :
DT = 20 °C
Koefisien muai panjang untuk beton, α= 1.0.E-05 °C
Panjang bentang Girder, L= 25.00 m
Shear stiffness of elastomeric bearing, k= 15000 kN/m
Temperatur movement, d = α * DT * L= 0.0050 m
Gaya akibat temperatur movement, FET = k * d = 75.00 kN
Tinggi Girder, h = 1.20 m h= 1.20 m
Eksentrisitas, e = h / 2 = 0.60 e = h/2 = 0.60 m
Momen akibat pengaruh temperatur, M = FET*e = 45.000 kNm
Gaya geser dan momen pada Girder akibat pengaruh temperatur (ET) :
VET = M/L = 1.800 kN
MET = M = 45.000 kNm
Gaya gempa vertikal pada girder dihitung dengan menggunakan percepatan vertikal ke
bawah minimal sebesar 0.10 * g ( g = percepatan gravitasi ) atau dapat diambil 50%
koefisien gempa horisontal statik ekivalen.
Wt = Berat total yang berupa berat sendiri dan beban mati tambahan
KP = kekakuan struktur yang merupakan gaya horisontal yang diperlukan untuk menimbulkan
satu satuan lendutan.
g = percepatan grafitasi bumi, g= 9.81 m/det2
Berat total yang berupa berat sendiri dan beban mati tambahan :
Wt = QMS + QMA
Berat sendiri, QMS = 29.06 kN/m
Beban mati tambahan, QMA = 4.57 kN/m
Panjang bentang, L= 25.00 m
Berat total, Wt = (QMS + QMA)*L = 840.8375 kN
Ukuran Girder, b= 0.50 m h= 1.20 m
Momen inersia penampang Girder, I = 1/12 * b * h3 = 0.072 m4
Modulus elastik beton, Ec = 23453 Mpa
Ec = 23452953 kPa
Kekakuan lentur Girder, Kp = 48 * Ec * I / L3 = 5187 kN/m
Waktu getar, T = 2*p* √ [ Wt / (g * KP)] = 0.8077 detik
f * Vc = 270.395 kN
Perlu tulangan geser
f * Vs = Vu - f * Vc = 742.908 kN
Gaya geser yang dipikul tulangan geser, Vs = 990.544 kN
Data Perhitungan
Panjang jembatan Ljembatan = 50 m
Lebar total jembatan Btotal = 9.92 m
Tinggi girder induk hgirder = 1.7 m
Tebal lapisan aspal ta = 0.2 m
Elevasi permukaan air banjir ebanjir = + 11 m
Elevasi dasar sungai edasar = + 2
Elevasi muka jalan/jembatan ejalan = + 13.5
Berat jenis tanah γtanah = t/m3
Sudut geser tanah φ= ᴼ
Tegangan tanah dasar yang diizinkan τtanah = kg/cm2
Mutu beton K= 250 20.75 Mpa
Mutu baja U= 39 390 Mpa
Direncanakan pondasi dgn kedalaman dari muka tanah htanah = 20 m
Tanah timbunan (oprit) untuk abutmen, digunakan tanah yang telah dipadatkan dan
sesuai dengan spesifikasi dari Bina Marga, sehingga mencapai kondisi sudut geser :
φ= 0ᴼ
Dimensi Abutmen
1.15
Struktur Bawah
BJ Beton 25 KN/m3
BJ Tanah = 17.2 KN/m3
11
Lebar Abutmen Atas = 12 m
10 Lebar Abutmen Bawah = 12 m
12 x= 1.6578 m
13
x
Beban merata akibat berat timbunan tanah setinggi 0,6 m yang merupakan ekv. Beban :
0,60 * Ws = 10.32 KN/m3
φ' = tan-1 (KφR * tan φ) = 21
Ka = tan ( 45ᴼ - φ' / 2 ) =
2
0.4724