15:08:38
DATOS
CALCULO
BURDEN = B
SUB DRILLING = 0.3 B
ESPACIAMIENTO = 1.25 B
VOLUMEN = H x B x E
= 9.906 m x Bm x 1.25 Bm
= 12.3825 B2 m3
= 18.57 B2 lib
1m = 0.0032 m3
= 2533.5433
453.592
= 5.59 lib / m
Ecuacion 1
Ecuacion 2
0.7 B
-( 9.906 + 0.7 B - 3.33 B2 )
0.3 B Donde
X= - b +/- b2 + 4ac
2a
REEMPLAZANDO SE TIENE:
Burden = B = 1.62 m
Espaciamiento = 1.25 B = 2.03 m
Volumen ( Rotura x Taladro ) = 12.38 B2 = 32.65 m3
Tonelaje = 46.43 B2 = 122.45 Ton/Tal
Libras de anfo = 18.57 B2 = 48.98 lib anfo/Talad HSQ
DATOS
Costo Broca + Accesorios = 215.22 US$ / Und Broca Botones RIM 12º 4" =
Broca Rimadora 12º 5" =
Costo equipo Perforacion = 12.50 US$ / Hr Broca Botones R32 51mm =
Broca Cruz R32 51mm =
Tiempo de Perforac. ( Rend. Broca ) = 80.00 Hr Broca Retractil R32 2-1/2" =
Adaptador Piloto T38 x 12º =
Rendimiento Broca = 762.00 m / broca Barra Extension SP R32 x 5´ =
Barra SP T38 x 4' =
Ton / Taladro = 122.45 Ton / Taladro Shank 1238 T38 x 575 mm =
Shank AdapL400 R32x380 m =
Altura de banco = 9.91 m
Alquiler Jumbo =
Horas Prog. Perforacion =
Costo Jumbo =
Costo Broca =
Shank R32 =
Barra =
Adaptador =
Rimadora =
CALCULO Total =
= 1,215.22
762.00
= 1.59 US$ / m
1.59 US$
= m
122.45 Ton x 1 Taladro
Taladro 9.91 m
= 1.59
12.36
315.00 US$
564.00 US$
74.04 US$
28.77 US$
141.50 US$
149.00 US$
138.00 US$
240.00 US$
275.00 US$
102.60 US$
9,000 US$/mes
24 Hrs/Dia
12.5 US$ / Hr
pp mp
2,500 762
2,825 861
3,542 1,080
7,910 2,411
7,910 2,411
74.04 US$
65.52 US$
52.26 US$
23.40 US$
US$
215.22 US$
Tiempo Perf.
80.00 Hr
06/24/2018
15:08:38
HSQ
Pag 2
06/24/2018
15:08:38
DATOS
COSTO PRECIOS
Anfo = 0.21 US$ / Lib Examon 0.47 US$/Kg
Emulsion Semexa 65% 1-1/2" x 12" 0.59 US$/Cart
Dinamita = 0.13 US$ / Cartucho Dinamita semexa 65% 7/8" x 7" 0.13 US$/Cart
Cordon detonante 3P 0.12 US$/m
Retardos Fanel = 1.03 US$ / Unidad Carmex 7´ 0.45 US$/Pza
Fanel blanco 4 mts 1.04 US$/Pza
Cordon Detonante = 0.12 US$ / Pie Fanel rojo 4 mts 1.04 US$/Pza
Fanel standar rojo 8 m 1.50 US$/Pza
Camion Anfocar = 0.00 US$ / Hr Fanel standar rojo 15 m 2.20 US$/Pza
Fulminante # 8 0.08 US$/Pza
Chispeo = 0.08 US$ / Pie Guia de Seguridad 0.08 US$/m
Mecha rapida Ignic 0.26 US$/m
Mano de Obra = 2.00 US$ / Hr
CALCULO
PU CONSUMO TOTAL
19.09US$
= Taladro
122.45 Ton
Taladro
HSQ
DATOS
CALCULO
1,451.67 Ton
= dia
122.45 Ton x 1 Tal x 762.00 m x
Tal 9.91 m 80.00 Hr
= 1,451.67
1,332.93
= 1.09
= 1.1 Perforadoras
1,451.67 Ton
= Dia
122.45 Ton x 1 Tal
06/24/2018
15:08:38
Tal 9.91 m
= 1,451.67
12.36
= 117.4 m / dia
43,550 Ton
30 Dias
1,452 Ton / Dia
Produccion ( TPD )
1 dia x Efic.Perf
24 Hr x 0.47
1 dia
06/24/2018
15:08:38
HSQ
Pag 4
06/24/2018
15:08:38
CARGUIO ESTELA
DATOS
CALCULOS
TONELADA POR PASE ( SCOOP ) = Yds3 / Pase x Densid. rota x Factor Cuchara
= 4.65
1.00
60 min
= Hr
120.00 seg x 1 min
pase 60 seg
= 30 Pase / Hr
= 94.81 Ton / Hr
= 0.8 Scoop
COSTO DE CARGUIO ( US$ / Ton ) = ( Costo por Hr del Equipo ) / ( Produccion Ton / Hr )
60.00 US$
= Hr
94.81 Ton
Hr
HSQ
= 0.63 US$/Ton Pag 5
06/24/2018
15:08:38
LIMPIEZA ESTELA
DATOS
CALCULOS
TONELADA POR PASE ( SCOOP ) = Yds3 / Pase x Densid. rota x Factor Cuchara
= 7.75
1.00
60 min
= Hr
480.00 seg x 1 min
pase 60 seg
= 7.5 Pase / Hr
= 37.18 Ton / Hr
= 1.95 Scoop
COSTO DE LIMPIEZA ( US$ / Ton ) = ( Costo por Hr del Equipo ) / ( Produccion Ton / Hr )
60.00 US$
= Hr
37.18 Ton
Hr
HSQ
= 1.61 US$/Ton Pag 6
06/24/2018
15:08:38
TRANSPORTE ESTELA
DATOS
CALCULOS
= 27.00 min
60 min
= Hr
27.00 min
viaje
= 2.22 Viaje / Hr
= 43.1 Ton / Hr
= 27.00 min
5.00 min
= 5.4 Camiones
= 5.0 Camiones
= 4 Camiones en Operacion
1 Camiones en Stand By
= 178.05 Ton / Hr
COSTO DE TRANSPORTE ( US$ / Ton ) = Nº de Camiones x Costo Hr camion + Costo Mant. Nº Camiones Sd-by
Produccion Camion Ton/ Hr
DATOS
CALCULOS
TONELADA POR PASE ( SCOOP ) = Yds3 / Pase x Densid. rota x Factor Cuchara
= 3.44
1.00
60 min
= Hr
480.00 seg x 1 min
pase 60 seg
= 7.5 Pase / Hr
= 16.52 Ton / Hr
= 2.4 Scoop
60.00 US$
= Hr
8.26 m3
Hr
= 8.69 US$/Ton
= 8.09 US$/Ton
HSQ
Pag 8
06/24/2018
15:08:38
DATOS
CALCULOS
TONELADA POR PASE ( SCOOP ) = Yds3 / Pase x Densid. rota x Factor Cuchara
= 5.16
1.00
60 min
= Hr
480.00 seg x 1 min
pase 60 seg
= 7.5 Pase / Hr
= 27.32 Ton / Hr
= 0.8 Scoop
COSTO DE TRANSPORTE ( US$ / Ton ) = ( Costo por Hr del Equipo ) / ( Produccion Ton / Hr )
60.00 US$
= Hr
27.32 Ton
Hr
= 2.20 US$/Ton
= 0.50 US$/Ton
HSQ
COSTO TOTAL RELLENO ( US$ / Ton ) = 2.70 US$/Ton Pag 9
06/24/2018
15:08:38
MALLA DE PERFORACION
Burden = 1.62 m
Espaciamiento = 2.03 m
PERFORACION
VOLADURA
LIMPIEZA
CARGUIO
TRANSPORTE
RELLENO CEMENTADO
RELLENO DETRITICO
Pag 10
REQUERIMIENTO EQUIPOS ESTELA PRODUCCION
REQUERIMIENTO VENTILADORES =
REQUERIMIENTO DE BOMBAS =