2500GT Slipway Construction Gantt Chart

0 1 2
Totals
Relative Relative % Planned Actual 2014
# Scope of Works Cost Weight Done Start Duration Start Duration 0 8 9
Months 0 1 2
1 Site investigation/Hydrographic survey 100.00% 0 1 0 1
2 Site clearing, Lay-out, Bench Marking and Staking 0.00% 1 2
2.1 Sile clearing 0.00% 1 1
2.2 Staking 0.00% 1 1
2.3 Bench marking 0.00% 2 1
2.4 Layout 0.00% 2 1
3 Installation of Temporary Facilities 0.00% 1 2
3.1 Clearing 0.00% 1 1
3.2 continuation of fence 0.00% 1 1
3.3 Bunk houses 0.00% 1 2
4 Fabrication of carriage, rollers, sheave anchoring 0.00% 2 11
4.1 Pin
4.2 Roller
4.3 Roller house
4.4 Carriage
4.5 Sheave housing and sheave anchoring
4.6 Assmbly and installation of carriage on rails
5 Riprap Works 2 5
5.1 Above waterline
5.2 Below waterline
6 Earthworks 3 12
6.1 Excavation and grading of groundway
6.2 Backfilling
7 Casting/Purchase of RC piles 2 4
8 Causeway Works 3 12
8.1 Driving of reinforced concrete sheet piles
8.2 Driving of steel sheet piles including copperdam
8.3 Earth filling for causeway construction
8.4 install Rebars for Capping of RC Steel sheet piles
8.5 Install formworks
8.6 Pouring ready mix concrete
9 Rail foundation works including backhauling 5 12
9.1 Driving of RC piles for rail foundations
9.2 Cutting and Chipping of RC Piles
9.3 Sub base course in way of rail foundation
9.4 Lean concreting
9.5 Install Rebars
9.6 Install formworks
9.7 Install anchorbolts/anchoring for backhauling pulley
9.8 Pouring ready mix concrete
9.9 Install rails
10 Winch foundation and winch motor installation 10 6
10.1 Driving of RC piles for rail foundations
10.2 Cutting and Chipping of RC Piles
10.3 Sub base course in way of rail foundation
10.4 Lean concreting
10.5 install rebars and anchoring for mainhauling pulley
10.6 install formworks
10.7 Pouring ready mix concrete
10.8 Install winch
11 Cofferdam Works 12 6
11.1 Install whaler reinforcement
11.2 install dewatering pump
11.3 dewater for dry construction of rail foundation end
11.4 remove pump and reinforment
11.5 remove copperdam
12 Dredging Works 17 1
13 Site clearing and debris disposals 17 1
14 Final Inpection 18 1
15 Dry run and drydocking test 18 1
3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

2014 2015 2016


10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2
3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
20 21 22 23 23

2016
3 4 5 6 7
20 21 22 23 24
EQUIPMENT DAILY MONITORING

SCOPE OF WORKS MANPOWER EQUIPMENT


I. CAUSEWAY & COPPERDAMING
Steel Sheet Pile Driving & Removal 7
2-Crane
Earthworks - Cutting & Filling 5
2 Bachoe
Payloader
2-Dumptruck
Installation of Waller Block 6 Crane & Bachoe
1 Crane
1-Bachoe
Sheet Wall Concrete Capping ( Rebars, Formworks 8
& Concreting} Transit Mixer
Electrical Trench , Light Tower & Bollard Post Crane
Square Pile driving & Connector Beam Works Crane, Bachoe

II. RAIL FOUNDATION WORKS

Driving of RC Piles 7
1 - Crane
Chipping Works of RC Piles 4 2 Jackhammer
Base Preparation of Rail Foundation 6
Fabrication & Installation of Rebars 6
Installation of Anchor Bolts & Rail SettingPlate 2
Formworks- Installation 8
Pouring of Ready Mix Concrete 12 Transit Mixer
Water Curing 1

III. MANPOWER SCHEDULE

Foreman 1
Steelman 5
Carpenter 5
Mason 4
Welder 4
Rigger 4
Helpers 15
Vibro Operator 2
Total Manpower Needed 40
IV. HEAVY EQUIPTMENT SCHEDULE
35T Crane 1
Sheet Feeder Crane 1
Excavator/Bachoe 2
Payloader 1
Dumptrucks 2
Primemover Truck 1
Transit Mixer N/a
JANUARY ' 2016
week 1 week 2 week 3 week 4 week 5
Target Completion 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2

49 days( Feb. 20)

54 days(Mar. 30)

10 Days(Mar 10)

June' 2016
June' 2016
August' 2016

21 days(Mar. 14)

14 days(Mar. 21)
7-Apr
21-Apr
22-Apr
26-Apr
28-Apr
FEBRUARY ' 2016
week 5 week 6 week 7 week 8 week 9 week 10
3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 1 2 3 4 5 6 7 8
MARCH ' 2016 APRIL ' 201
week 10 week 11 week 12 week 13 week 14 week 15
9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12
APRIL ' 2016
week 15 week 16 week 16
13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
WORK, MANPOWER & EQUIPTMENT SCHEDULE FOR PRIORITY WORKS

SCOPE OF WORKS MANPOWER EQUIPTMENT


I. CAUSEWAY & COPPERDAMING
Steel Sheet Pile Driving & Removal 7 2-Crane
2 -Bachoe,
Earthworks - Cutting & Filling 5 Payloader,
Dumptrucks
Installation of Waller Block 6 Crane & Bachoe
Sheet Wall Concrete Capping ( Rebars, Formworks 8
& Concreting} Transit Mixer
Electrical Trench , Light Tower & Bollard Post Crane
Square Pile driving & Connector Beam Works Crane, Bachoe

II. RAIL FOUNDATION WORKS


Driving of RC Square Piles 7 Crane
Chipping Works of RC Piles 4 2 Jackhammer
Base Preparation of Rail Foundation 6
Fabrication & Installation of Rebars 6
Installation of Anchor Bolts & Rail Setting Plate 2
Formworks- Installation 8
Pouring of Ready Mix Concrete 12 Transit Mixer
Water Curing 1

III. MANPOWER SCHEDULE


Foreman 1
Steelman 5
Carpenter 5
Mason 4
Welder 4
Rigger 4
Helpers 15
Vibro Operator 2
Total Manpower Needed 40
IV. HEAVY EQUIPTMENT SCHEDULE
35T Crane 1
Sheet Feeder Crane 1
Excavator/Bachoe 2
Payloader 1
Dumptrucks 2
Primemover Truck 1
Transit Mixer N/a
JANUARY ' 2016
week 1 week 2 week 3 week 4 week 5
Target Completion 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2

49 days( Feb. 20)

54 days(Mar. 30)

10 Days(Mar 10)

June' 2016
June' 2016
August' 2016

24 days(Mar. 14)
14 days(Mar. 21)
7-Apr
21-Apr
22-Apr
26-Apr
28-Apr
FEBRUARY ' 2016
week 5 week 6 week 7 week 8 week 9 week 10
3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 1 2 3 4 5 6 7 8
MARCH ' 2016 APRIL ' 201
week 10 week 11 week 12 week 13 week 14 week 15
9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12
APRIL ' 2016
week 15 week 16 week 16
13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30