Anda di halaman 1dari 7

STTS WIDEBODY AIRCRAFT FACILITY

METHOD STATEMENT FOR INSTALLATION OF PVC/G.I CONDUITS

METHOD STATEMENT FOR INSTALLATION OF PVC/G.I CONDUITS

Document No: P103-STTS-GEC-ASI-MS-ELE-011

REV. DATE DESCRIPTION GENFOCUS ASI/WSP


PREPARED APPROVED

000 27-05-18 Issued for Approval QA/QC PM

DOCUMENT No. REV DATE


Page 0 of 7
P103-STTS-GEC-ASI-MS-ELE-011 000 27-05-2018
STTS WIDEBODY AIRCRAFT FACILITY
METHOD STATEMENT FOR INSTALLATION OF PVC/G.I CONDUITS

1.0 PURPOSE

1.1 The purpose of this method statement is to define procedure to be followed during
installation of PVC/G.I conduits for concealed wall/enclosed area.

2.0 SCOPE

2.1 The scope of this method statement is to provide guidelines for installation of PVC/G.I
conduits for All works shall be conducted in conformance with relevant project drawings
/specifications and good industry practices.

3.0 TOOLS AND RESOURCES

3.1 Measuring tape


3.2 Drilling machine
3.3 Pipe bending machine
3.4 Threading machine with die-set
3.5 Hack saw / jig saw
3.6 Bend springs
3.7 Ladder/Mobile Scaffold
3.8 Portable Hand Tools

4.0 RESPONSIBILITY

4.1 PROJECT MANAGER:

4.1.1 To be the focal point for all over interfaces and other communications with the
company and contractor as required during project execution.

4.1.2 Ensure that adequate quality measures are being undertaken.

4.1.3 He shall identify and secure necessary resources, determining the task that must be
completed, assigning the tasks and delegating authority.

DOCUMENT No. REV DATE


Page 1 of 7
P103-STTS-GEC-ASI-MS-ELE-011 000 27-05-2018
STTS WIDEBODY AIRCRAFT FACILITY
METHOD STATEMENT FOR INSTALLATION OF PVC/G.I CONDUITS
4.1.4 He is responsible for planning of site organization, resource mobilization,
subcontracting, site operation, construction methods and scheduling.

4.1.5 Ensure all the keys staffs are on site during execution.

4.1.6 He shall coordinate all site safety issues to HSE Personnel for corrective Action.

4.1.7 Main point of contact on site for safety issues.

4.2 SITE ENGINEER/ SUPERVISOR

4.2.1 Responsible for the coordination of all electromechanical activities, coordination with
other discipline and between various subcontractors on sites

4.2.2 Ensure all permits are available for works on site and all safety precautions are taken.

4.2.3 Responsible to ensure sufficient and adequate resources are secured and provided to
MEP subcontractor.

4.2.4 To direct and coordinate with MEP subcontractor and other MEP Engineers for
effective execution on site.

4.2.5 To report back to Division Manager/ Project Manager relevant MEP progress,
bottlenecks cost control and other issues.

4.2.6 Reviewing MEP Daily, Weekly & Monthly Progress reports.

4.2.7 Responsible for completing of all MEP punch items and project close out, handover
documentation and operation maintenance manual, training etc.

4.3 QA/QC ENGINEER

4.3.1 Ensure all inspections are raised and conducted as per the contract specifications,
approved shop drawings & Method statements.

4.3.2 Ensure all current issues of procedures, approved material and shop drawing and
standards are available at the point of use.

DOCUMENT No. REV DATE


Page 2 of 7
P103-STTS-GEC-ASI-MS-ELE-011 000 27-05-2018
STTS WIDEBODY AIRCRAFT FACILITY
METHOD STATEMENT FOR INSTALLATION OF PVC/G.I CONDUITS
4.3.3 Ensure the total quality control for installation work. He shall liaise with Company for
inspection of installation works.

4.3.4 Inspect for any damage during, handling and storage.

4.3.5 Monitor the quality of work & insure that fulfilment of specified requirement and that
all quality records related to work are completed.

4.3.6 Ensure the work is completed as per quality requirements.

4.3.7 Contractor shall inspect the same work to initiate IRF for company approval.

4.3.8 Maintain Comprehensive inspection and test records for any further references

4.4 HSE OFFICER

4.4.1 Toolbox talk has to be conducted and all the hazards have to be identified before starting
the work.

4.4.2 To make sure that Personnel Protective Equipment’s (PPE) are used by the Task Force
during execution at site.

4.4.3 Risk related to the activity shall be assessed and addressed as required.

4.4.4 To provide training for the work force in order to execute the activity safely.

4.4.5 Carry out regular and random inspection on site and record observation.

5.0 PROCEDURE

5.1 Preparation Work

5.1.1 Before commencement of any conduit installation, the following are required to be
carried out:
5.1.1.1 Check the conduits & accessories to be installed and details are as indicated on an
approved shop drawing / site condition.

DOCUMENT No. REV DATE


Page 3 of 7
P103-STTS-GEC-ASI-MS-ELE-011 000 27-05-2018
STTS WIDEBODY AIRCRAFT FACILITY
METHOD STATEMENT FOR INSTALLATION OF PVC/G.I CONDUITS
5.1.1.2 Confirm sizes and items used are as per approved shop drawings.

5.1.1.3 Check material to be used are approved.

5.1.1.4 Check work area is clean and safe.

5.2 Installation of PVC Conduits

5.2.1 Location of PVC circular junction boxes or other junction boxes as per approved
shop drawings will be marked on the shutter when it is made ready.

5.2.2 All such junction boxes will be fixed with nails on the shutter based on the
marking and Continuous conduiting will be carried out with standard conduit
lengths, couplers etc.

5.2.3 Where bends or offsets are required, the straight conduits will be manually bent
using suitable helical bend spring to the required radius.

5.2.4 Wherever conduits and accessories are required to be jointed, solvent cement will
be used.

5.2.5 Expansion couplers will be used where conduit crosses structure expansion
joints.(If applicable)

5.2.6 Entire runs of conduits will be tied to the reinforcement bars firmly with tie-wire
in Order to avoid movements during concreting.

5.2.7 After de-shuttering, all conduits and boxes will be cleaned and checked to
commence the wiring.

5.2.8 All conduits concealed into the block work, plaster will be covered along the
entire Lengths.

5.2.9 Pull boxes shall be provided where conduit run is more than 15 meters or
subjected to more than 2 no’s 90 degree bends.

5.2.10 Thermocol shall be provided in walls before shuttering and casting to avoid
chipping at successive stages for final fixture location adjustment.

DOCUMENT No. REV DATE


Page 4 of 7
P103-STTS-GEC-ASI-MS-ELE-011 000 27-05-2018
STTS WIDEBODY AIRCRAFT FACILITY
METHOD STATEMENT FOR INSTALLATION OF PVC/G.I CONDUITS

5.2.11 Thermocol are cut into required size and to be inserted into correct location.

5.2.12 Fix Thermocol to the wall structural steel at the correct location and level of
services as per approved shop drawing.

5.2.13 Conduits are cut at right angle and desired length. Ensure the Conduit
installations are in straight line.

5.2.14 Cutting and chasing to be done as per the marked locations for the service
drops and fix the conduit.

5.2.15 Attendance during concrete pouring shall be provided to ensure that conduits
and boxes are not displaced.

5.2.16 Ensure that any conduits found damaged needs to be replaced immediately.

5.3 Installation of G.I Conduits

5.3.1 Shifting of materials shall be done by sufficient manpower. All necessary safety
precautions as per established procedure shall be implemented during shifting and
installation.

5.3.2 The routes for the surface conduits will be marked based on the approved shop
drawings and coordinated with other services at site.

5.3.3 Prior to erection, all burrs and sharp edges shall be removed from the conduit with
reamer together with any dirt, oil or paint, which may be present.

5.3.4 Standard length of conduits shall be cut to the required length.


5.3.5 G.I. Conduits threading shall be done using a threading machine and correct size
die-set. Threads will be kept to a minimum when showing from couplings and
boxes.

5.3.6 Where required conduits of size 20mm and 25mm shall be bend to the required
radius using manual bending machines.

5.3.7 Check all mechanical connections are internally smooth for pulling wiring in no
burrs or sharp edge will be allowed.

DOCUMENT No. REV DATE


Page 5 of 7
P103-STTS-GEC-ASI-MS-ELE-011 000 27-05-2018
STTS WIDEBODY AIRCRAFT FACILITY
METHOD STATEMENT FOR INSTALLATION OF PVC/G.I CONDUITS

5.3.8 Spacer bars are fixed in regular interval not exceeding 1.2m and the distance from
either side of any box.

5.3.9 Ensure the Conduit installations are in straight line.

5.3.10 All terminal boxes are marked on the appropriate location (i.e. wall or ceiling) as
per approved shop drawing and fixed with metal screws and plugs.

5.3.11 Suitable braze bushes are used where conduit enters the boxes to avoid any
damage to the wires.

5.3.12 Wherever necessary draw wires shall be pulled into conduit runs and kept at pull
boxes for future use.

5.3.13 Any rusting of steel conduits occurred during construction shall be removed.

DOCUMENT No. REV DATE


Page 6 of 7
P103-STTS-GEC-ASI-MS-ELE-011 000 27-05-2018

Anda mungkin juga menyukai