Anda di halaman 1dari 2

M Design & Build

Borey New World, #06, St. 20, Veng Sreng, Phnom Penh
mdesignbuild.blogspot.com
facebook.com/mdesignandbuild168
info.mdesignbuild@gmail.com
015 800 030 / 011 773 779

Date: 29-Jun-18
Quote No.: 180629010
Client Information
Name: Angelo Braceria
Address: Phnom Penh
Phone:
QUOTATION
No. Descriptions Unit Quantity Price Total Price
A Renovation work
1 Tear off the existing front fence
2 Remove the existing front house pavement
3 Tear off the existing ground floor walls + windows
4 Tear off the existing first floor walls + windows
5 Remove the existing ground floor tiles lump sum 1 $ 1,500 $ 1,500
6 Remove the existing first floor tiles
7 Remove the extisting first floor ceiling
8 Remove the existing entrace metal roof
9 Dump the trash
TOTAL A $ 1,500
B Finishing work
1 Plaster the wall corner lump sum 1 $ 300 $ 300
2
2 Cement-polish top surface concrete floor (GF+1F) m 216 $ 17 $ 3,672
TOTAL B $ 3,972
C MEP work
1 Install the electrical system
lump sum 1 $ 3,900 $ 3,900
2 Install the plumbing system
TOTAL C $ 3,900
D Decoration work
I Ground Floor
1 Pedestrain pavemnt lump sum 1 $ 450 $ 450
2
2 Cement-polish exterior pavement m 55 $ 17 $ 935
2
3 Cement-polish front stair m 8 $ 17 $ 136
4 Logo and text set 1 $ 730 $ 730
5 Entrance steel awning set 1 $ 1,230 $ 1,230
2
6 Cement-polish interior wall m 45 $ 15 $ 675
2
7 Interior stone wall m 28 $ 25 $ 700
8 Entrance steel frame + glass door set 1 $ 1,200 $ 1,200
9 Steel sliding window set 3 $ 680 $ 2,040
10 Backyard steel door set 1 $ 250 $ 250
11 I-steel frame set 1 $ 480 $ 480
12 Toilet renovation lump sum 1 $ 460 $ 460
2
13 Ceiling paint m 28 $ 10 $ 280
2
14 Beam paint m 45 $ 10 $ 450
15 Wall shelf m 12 $ 220 $ 2,640
16 Stair Shelf m 1.7 $ 220 $ 374
17 Kitchen awning set 1 $ 450 $ 450
18 Curtain set 11 $ 110 $ 1,210
19 Kitchen glass door set 1 $ 220 $ 220
20 Kitchen glass window set 1 $ 180 $ 180
21 Handrail spray paint lump sum 1 $ 350 $ 350
II First Floor
1 Cement-polish exterior wall m2 23 $ 15 $ 345
2
2 Cement-polish interior wall m 25 $ 15 $ 375
2
3 Interior stone wall m 52 $ 25 $ 1,300
4 Entrance steel frame + glass door set 1 $ 1,200 $ 1,200
5 Steel sliding window set 4 $ 680 $ 2,720
6 Beam paint m2 45 $ 10 $ 450
7 Wall shelf m 16 $ 220 $ 3,520
8 Ceiling steel grid set 2 $ 220 $ 440
9 Curtain set 11 $ 110 $ 1,210
10 Wardrobe m 3.2 $ 550 $ 1,760
11 Desk set 1 $ 220 $ 220
12 Glass handrail m 12 $ 220 $ 2,640
13 Toilet renovation lump sum 1 $ 720 $ 720
TOTAL D $ 32,340
GRAND TOTAL $ 41,712
Payment terms and conditions:
◦ Upon signing this quotation, 30% deposit of the sum shall be made to M Design & Build.
◦ Upon 50% completion of the work, 50% of the sum shall be made to M Design & Build.
◦ Upon final completion of the work, the ramaining 20% of the sum shall be made to M Design & Build.
Note:
◦ An extra work not list in this quotation is subject to be add price.
Duration:
◦ 75 days

We trust that the above quote meets your requirement and look forward to your favorable reply.

Authorized Signature, Agreed and Confirmed,

M Design & Build Client Signature

Anda mungkin juga menyukai