- Q = 3.5 m3/s
- S= 0.0022
- n = 0.014
- Z= 0
1) Tirante:
1 2 1
𝑄= ∗ 𝐴 ∗ 𝑅3 ∗ 𝑆 2
𝑛
1 2
3.5𝑚/𝑠 = ∗ 2𝑦 2 ∗ (𝑦/2)3 ∗ (0.0022)1/2
0.014
1
3.5𝑚/𝑠 = ∗ 𝑦 8/3 ∗ (0.0022)1/2
0.014
𝒚𝟎 = 𝟎. 𝟗𝟑𝟐𝟏 𝒎
2) Por max eficiencia hidráulica:
- B = 1.864
- P= 3.7286
- A= 1.7378
- R= 0.4661
- T= 1.864
- F= 0.666 “Flujo Subcritico”
3) Energías:
Energía aguas arriba
𝑣0 2
𝐸𝐿𝐶1 = 𝐸𝐿𝐶0 + 𝑦0 +
2𝑔
2.0142
𝐸𝐿𝐶1 = 239 + 0.9321 +
2 ∗ 9.81
𝑣0 2
𝐸𝐿𝐶4 = 𝐸𝐿𝐶𝑛 + 𝑦0 +
2𝑔
2.0142
𝐸𝐿𝐶4 = 237.5 + 0.9321 +
2 ∗ 9.81
3 3
𝑣0 2 2 2.0142 2 𝑚3
𝑞 = 1.71 ∗ (𝑦0 + ) = 1.71 ∗ (0.9321 + ) = 2.0782
2∗𝑔 2 ∗ 9.81 𝑠−𝑚
𝒎𝟑
𝒒 = 𝟐. 𝟎𝟕𝟖𝟐
𝒔−𝒎
𝑄 3.5
𝐵= = = 1.68 ≈ 1.7 𝑚 → 𝑩 = 𝟏. 𝟕 𝒎
𝑞 2.0782
𝑄 3.5 𝑚3 𝒎𝟑
𝑞= = = 2.05 → 𝒒=𝟐
𝐵 1.7 𝑠−𝑚 𝒔−𝒎
2 2
𝑑𝑐 = 0.46714 ∗ 𝑞 3 = 0.46714 ∗ (2)3 → 𝒅𝒄 = 𝟎. 𝟕𝟒𝟏𝟓 𝒎
𝒅𝟐 𝒅𝟏
= 𝟔. 𝟏𝟖 ; = 𝟎. 𝟑𝟓𝟔 (𝒗𝒂𝒍𝒐𝒓𝒆𝒔 𝒊𝒏𝒕𝒆𝒓𝒑𝒐𝒍𝒂𝒅𝒐𝒔)
𝒅𝟏 𝒅𝒄
𝑑1
𝑑1 = ∗ 𝑑𝑐 = 0.356 ∗ 0.7415 𝑚 = 0.264 𝑚
𝑑𝑐
𝑑2
𝑑2 = ∗ 𝑑1 = 6.18 ∗ 0.264 𝑚 = 1.63 𝑚
𝑑1
9) Cálculo de la elevación del pozo amortiguador, previamente debe calcularse las
velocidades V1 y V2.
𝑄 3.5
𝑉1 = = = 7.79 𝑚/𝑠 → 𝑽𝟏 = 𝟕. 𝟕𝟗 𝒎/𝒔
𝐴1 0.264 ∗ 1.7
𝑄 3.5 𝑚
𝑉2 = = = 1.26 → 𝑽𝟐 = 𝟏. 𝟐𝟔 𝒎/𝒔
𝐴2 1.63 ∗ 1.7 𝑠
𝑣1 2 (7.79)2
𝐸𝐿𝐶2 = 𝐸𝐿𝐶1 + 𝑑1 + = 240.14 − 0.264 − = 236.783 𝑚
2𝑔 2 ∗ 9.81
2 𝐿
cot 𝛼 = = → 𝑳 = 𝟒𝒎𝒕
1 1.98
∴ Base de la Poza = 1 m
Altura de la Poza = h = BL+𝑑2 = 0.49 + 1.63 = 2.12 m ≈ 2.20 𝒎
Espesor de la base de la Poza = 0.20 m.
Se presenta el diseño hidráulico que comprende el uso de sistemas informáticos para la
determinar las secciones que comprende una poza de disipación como se mostrará a
continuación: