ID Task Name Duration Start Finish Predecessors Jun '18 Jul '18 Aug '18 Sep '18 Oct

ecessors Jun '18 Jul '18 Aug '18 Sep '18 Oct '18 Nov '18
28 04 11 18 25 02 09 16 23 30 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26
1 Pembangunan Gedung Kantor Kelurahan 120 days Wed Wed Pembangunan Gedung Kantor Kelurahan Sukatani
Sukatani 18/07/18 14/11/18 18/07 14/11
2 KONTRAK 1 day Wed Wed KONTRAK
18/07/18 18/07/18
3 PEKERJAAN PERSIAPAN 14 days Wed Tue
18/07/18 31/07/18
4 Persiapan lokasi pekerjaan 7 days Wed Tue 2SS
18/07/18 24/07/18
5 Pengkuran dan pemasangan bowplank 7 days Wed Tue 4SS
18/07/18 24/07/18
6 Direksi keet dan gudang material 7 days Wed Tue 5SS
18/07/18 24/07/18
7 Pemasangan identitas proyek 7 days Wed Tue 6SS
18/07/18 24/07/18
8 Pagar pengamanan proyek 7 days Wed Tue 7SS
18/07/18 24/07/18
9 Bongkar bangunan existing 7 days Wed Tue 8
25/07/18 31/07/18
10 PEKERJAAN STRUKTUR 70 days Wed Tue
25/07/18 02/10/18
11 Pekerjaan Pondasi (K-275) 21 days Wed Tue
25/07/18 14/08/18
12 Galian tanah 7 days Wed Tue 9SS
25/07/18 31/07/18
13 Urugan tanah kembali 7 days Wed Tue 19SS
01/08/18 07/08/18
14 Urugan pasir dibawah pondasi, sloof t 7 days Wed Tue 12SS
= 5 cm 25/07/18 31/07/18
15 Lantai kerja t = 5 cm (pondasi + sloof) 7 days Wed Tue 14SS
25/07/18 31/07/18
16 Pondasi Plat 100 x 100 cm (P1) 7 days Wed Tue
01/08/18 07/08/18
17 Bekisting 7 days Wed Tue 18SS
01/08/18 07/08/18
18 Pembesian 7 days Wed Tue 15
01/08/18 07/08/18
19 Cor ready mix K-275 7 days Wed Tue 17SS
01/08/18 07/08/18
20 Pedestal beton 40/20 7 days Wed Tue
01/08/18 07/08/18
21 Bekisting 7 days Wed Tue 22SS
01/08/18 07/08/18
22 Pembesian 7 days Wed Tue 18SS
01/08/18 07/08/18

Task Milestone External Tasks


SUKATANI PROJECT Split Summary External Milestone
Progress Project Summary Deadline

Page 1
ID Task Name Duration Start Finish Predecessors Jun '18 Jul '18 Aug '18 Sep '18 Oct '18 Nov '18
28 04 11 18 25 02 09 16 23 30 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26
23 Cor ready mix K-275 7 days Wed Tue 21SS
01/08/18 07/08/18
24 Pedestal beton 20/20 7 days Wed Tue
01/08/18 07/08/18
25 Bekisting 7 days Wed Tue 22SS
01/08/18 07/08/18
26 Pembesian 7 days Wed Tue 18SS
01/08/18 07/08/18
27 Cor ready mix K-275 7 days Wed Tue 21SS
01/08/18 07/08/18
28 Pedestal beton Ø 30 7 days Wed Tue
01/08/18 07/08/18
29 Bekisting 7 days Wed Tue 22SS
01/08/18 07/08/18
30 Pembesian 7 days Wed Tue 18SS
01/08/18 07/08/18
31 Cor ready mix K-275 7 days Wed Tue 21SS
01/08/18 07/08/18
32 Sloof beton 20/40 (S1) 7 days Wed Tue
08/08/18 14/08/18
33 Bekisting 7 days Wed Tue 34SS
08/08/18 14/08/18
34 Pembesian 7 days Wed Tue 29
08/08/18 14/08/18
35 Cor ready mix K-275 7 days Wed Tue 33SS
08/08/18 14/08/18
36 Sloof beton 15/20 (S2) 7 days Wed Tue
08/08/18 14/08/18
37 Bekisting 7 days Wed Tue 34SS
08/08/18 14/08/18
38 Pembesian 7 days Wed Tue 29
08/08/18 14/08/18
39 Cor ready mix K-275 7 days Wed Tue 33SS
08/08/18 14/08/18
40 Pekerjaan Beton Lantai 1 ( K-275 ) 42 days Wed Tue
08/08/18 18/09/18
41 Kolom beton (K) Ø 30 14 days Wed Tue
08/08/18 21/08/18
42 Bekisting 14 days Wed Tue 43SS
08/08/18 21/08/18
43 Pembesian 14 days Wed Tue 39SS
08/08/18 21/08/18
44 Cor ready mix K-275 14 days Wed Tue 42SS
08/08/18 21/08/18

Task Milestone External Tasks


SUKATANI PROJECT Split Summary External Milestone
Progress Project Summary Deadline

Page 2
ID Task Name Duration Start Finish Predecessors Jun '18 Jul '18 Aug '18 Sep '18 Oct '18 Nov '18
28 04 11 18 25 02 09 16 23 30 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26
45 Kolom beton 20/40 (K1) 14 days Wed Tue
08/08/18 21/08/18
46 Bekisting 14 days Wed Tue 43SS
08/08/18 21/08/18
47 Pembesian 14 days Wed Tue 39SS
08/08/18 21/08/18
48 Cor ready mix K-275 14 days Wed Tue 42SS
08/08/18 21/08/18
49 Kolom beton 20/20 (K2) 14 days Wed Tue
08/08/18 21/08/18
50 Bekisting 14 days Wed Tue 43SS
08/08/18 21/08/18
51 Pembesian 14 days Wed Tue 39SS
08/08/18 21/08/18
52 Cor ready mix K-275 14 days Wed Tue 42SS
08/08/18 21/08/18
53 Kolom beton 15/15 (KP) 14 days Wed Tue
05/09/18 18/09/18
54 Bekisting 14 days Wed Tue 55SS
05/09/18 18/09/18
55 Pembesian 14 days Wed Tue 115SS
05/09/18 18/09/18
56 Beton Cor 1:2:3 14 days Wed Tue 54SS
05/09/18 18/09/18
57 Pasangan pondasi batu kali pondasi 14 days Wed Tue 39SS
tangga 08/08/18 21/08/18
58 Sloof tangga 20 x 15 14 days Wed Tue
05/09/18 18/09/18
59 Bekisting 14 days Wed Tue 60SS
05/09/18 18/09/18
60 Pembesian 14 days Wed Tue 54SS
05/09/18 18/09/18
61 Cor ready mix K-275 14 days Wed Tue 59SS
05/09/18 18/09/18
62 Tangga beton 14 days Wed Tue
05/09/18 18/09/18
63 Bekisting 14 days Wed Tue 64SS
05/09/18 18/09/18
64 Pembesian 14 days Wed Tue 59SS
05/09/18 18/09/18
65 Cor ready mix K-275 14 days Wed Tue 63SS
05/09/18 18/09/18
66 Balok latei 12/12 14 days Wed Tue
05/09/18 18/09/18

Task Milestone External Tasks


SUKATANI PROJECT Split Summary External Milestone
Progress Project Summary Deadline

Page 3
ID Task Name Duration Start Finish Predecessors Jun '18 Jul '18 Aug '18 Sep '18 Oct '18 Nov '18
28 04 11 18 25 02 09 16 23 30 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26
67 Bekisting 14 days Wed Tue 64SS
05/09/18 18/09/18
68 Pembesian 14 days Wed Tue 59SS
05/09/18 18/09/18
69 Beton Cor 1:2:3 14 days Wed Tue 63SS
05/09/18 18/09/18
70 Urugan pasir bawah tebal = 5 cm 14 days Wed Tue 57SS
08/08/18 21/08/18
71 Pekerjaan Beton Lantai 2 ( K-275 ) 42 days Wed Tue
22/08/18 02/10/18
72 Kolom beton (K) Ø 30 14 days Wed Tue
05/09/18 18/09/18
73 Bekisting 14 days Wed Tue 74SS
05/09/18 18/09/18
74 Pembesian 14 days Wed Tue 107FS-7
05/09/18 18/09/18 days
75 Cor ready mix K-275 14 days Wed Tue 73SS
05/09/18 18/09/18
76 Kolom beton 20/40 (K1) 14 days Wed Tue
05/09/18 18/09/18
77 Bekisting 14 days Wed Tue 78SS
05/09/18 18/09/18
78 Pembesian 14 days Wed Tue 75SS
05/09/18 18/09/18
79 Cor ready mix K-275 14 days Wed Tue 77SS
05/09/18 18/09/18
80 Kolom beton 20/20 (K2) 14 days Wed Tue
05/09/18 18/09/18
81 Bekisting 14 days Wed Tue 78SS
05/09/18 18/09/18
82 Pembesian 14 days Wed Tue 75SS
05/09/18 18/09/18
83 Cor ready mix K-275 14 days Wed Tue 77SS
05/09/18 18/09/18
84 Kolom beton 15/15 (KP) 14 days Wed Tue
19/09/18 02/10/18
85 Bekisting 14 days Wed Tue 86SS
19/09/18 02/10/18
86 Pembesian 14 days Wed Tue 116SS
19/09/18 02/10/18
87 Beton Cor 1:2:3 14 days Wed Tue 85SS
19/09/18 02/10/18
88 Balok beton 30/40 (B1) 21 days Wed Tue
22/08/18 11/09/18

Task Milestone External Tasks


SUKATANI PROJECT Split Summary External Milestone
Progress Project Summary Deadline

Page 4
ID Task Name Duration Start Finish Predecessors Jun '18 Jul '18 Aug '18 Sep '18 Oct '18 Nov '18
28 04 11 18 25 02 09 16 23 30 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26
89 Bekisting 21 days Wed Tue 90SS
22/08/18 11/09/18
90 Pembesian 21 days Wed Tue 45
22/08/18 11/09/18
91 Cor ready mix K-275 21 days Wed Tue 89SS
22/08/18 11/09/18
92 Balok beton 20/30 (B2) 21 days Wed Tue
22/08/18 11/09/18
93 Bekisting 21 days Wed Tue 90SS
22/08/18 11/09/18
94 Pembesian 21 days Wed Tue 45
22/08/18 11/09/18
95 Cor ready mix K-275 21 days Wed Tue 89SS
22/08/18 11/09/18
96 Balok latei 12/12 14 days Wed Tue
19/09/18 02/10/18
97 Bekisting 14 days Wed Tue 98SS
19/09/18 02/10/18
98 Pembesian 14 days Wed Tue 87SS
19/09/18 02/10/18
99 Beton Cor 1:2:3 14 days Wed Tue 97SS
19/09/18 02/10/18
100 Ring balok beton 15/30 21 days Wed Tue
22/08/18 11/09/18
101 Bekisting 21 days Wed Tue 90SS
22/08/18 11/09/18
102 Pembesian 21 days Wed Tue 45
22/08/18 11/09/18
103 Cor ready mix K-275 21 days Wed Tue 89SS
22/08/18 11/09/18
104 Plat lantai beton 21 days Wed Tue
22/08/18 11/09/18
105 Bekisting 21 days Wed Tue 90SS
22/08/18 11/09/18
106 Pembesian 21 days Wed Tue 45
22/08/18 11/09/18
107 Cor ready mix K-275 21 days Wed Tue 89SS
22/08/18 11/09/18
108 Plat lantai beton torren 14 days Wed Tue
12/09/18 25/09/18
109 Bekisting 14 days Wed Tue 110SS
12/09/18 25/09/18
110 Pembesian 14 days Wed Tue 107
12/09/18 25/09/18

Task Milestone External Tasks


SUKATANI PROJECT Split Summary External Milestone
Progress Project Summary Deadline

Page 5
ID Task Name Duration Start Finish Predecessors Jun '18 Jul '18 Aug '18 Sep '18 Oct '18 Nov '18
28 04 11 18 25 02 09 16 23 30 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26
111 Cor ready mix K-275 14 days Wed Tue 109SS
12/09/18 25/09/18
112 PEKERJAAN ARSITEKTUR 63 days Wed Tue
05/09/18 06/11/18
113 Pekerjaan Pasangan 35 days Wed Tue
05/09/18 09/10/18
114 Pasangan Hebel tebal 10 cm 28 days Wed Tue
05/09/18 02/10/18
115 Lantai 1 14 days Wed Tue 44FS+14
05/09/18 18/09/18 days
116 Lantai 2 14 days Wed Tue 115
19/09/18 02/10/18
117 Plesteran + Acian 1 : 5 28 days Wed Tue
12/09/18 09/10/18
118 Lantai 1 14 days Wed Tue 115SS+7
12/09/18 25/09/18 days
119 Lantai 2 14 days Wed Tue 116SS+7
26/09/18 09/10/18 days
120 Pekerjaan Railing Tangga Stainless 7 days Wed Tue 144
31/10/18 06/11/18
121 Pekerjaan Batu Tempel 7 days Wed Tue 120SS
31/10/18 06/11/18
122 Logo dan Nama Kelurahan 7 days Wed Tue 120SS
31/10/18 06/11/18
123 Plesteran + Acian kolom beton 21 days Wed Tue
19/09/18 09/10/18
124 Lantai 1 14 days Wed Tue
19/09/18 02/10/18
125 K1 14 days Wed Tue 118SS+7
19/09/18 02/10/18 days
126 K1" 14 days Wed Tue 125SS
19/09/18 02/10/18
127 Lantai 2 14 days Wed Tue
26/09/18 09/10/18
128 K1 14 days Wed Tue 119SS
26/09/18 09/10/18
129 K1" 14 days Wed Tue 128SS
26/09/18 09/10/18
130 Pekerjaan Kusen, Pintu, dan Jendela 14 days Wed Tue
Aluminium Warna 03/10/18 16/10/18
131 Kusen Type PJ1 14 days Wed Tue 119SS+7
03/10/18 16/10/18 days
132 Kusen Type P1 14 days Wed Tue 131SS
03/10/18 16/10/18

Task Milestone External Tasks


SUKATANI PROJECT Split Summary External Milestone
Progress Project Summary Deadline

Page 6
ID Task Name Duration Start Finish Predecessors Jun '18 Jul '18 Aug '18 Sep '18 Oct '18 Nov '18
28 04 11 18 25 02 09 16 23 30 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26
133 Kusen Type P2 14 days Wed Tue 131SS
03/10/18 16/10/18
134 Kusen Type P3 14 days Wed Tue 131SS
03/10/18 16/10/18
135 Kusen Type P4 14 days Wed Tue 131SS
03/10/18 16/10/18
136 Kusen Type J1 14 days Wed Tue 131SS
03/10/18 16/10/18
137 Kusen Type J2 14 days Wed Tue 131SS
03/10/18 16/10/18
138 Kusen Type J3 14 days Wed Tue 131SS
03/10/18 16/10/18
139 Kusen Type BV1 14 days Wed Tue 131SS
03/10/18 16/10/18
140 Loket 1 14 days Wed Tue 131SS
03/10/18 16/10/18
141 Pekerjaan Lantai 21 days Wed Tue
10/10/18 30/10/18
142 Pasangan Lantai ( Homogenius 21 days Wed Tue
Tile ) HT Uk. 60 x 60 cm 10/10/18 30/10/18
143 Lantai 1 14 days Wed Tue 131SS+7
10/10/18 23/10/18 days
144 Lantai 2 14 days Wed Tue 143SS+7
17/10/18 30/10/18 days
145 Plint 10 x 60 21 days Wed Tue
10/10/18 30/10/18
146 Lantai 1 14 days Wed Tue 143SS
10/10/18 23/10/18
147 Lantai 2 14 days Wed Tue 144SS
17/10/18 30/10/18
148 Keramik Tangga Homogenius Tile ( 14 days Wed Tue 144SS
HT ) 17/10/18 30/10/18
149 Step nozing tangga 10 x 30 14 days Wed Tue 144SS
17/10/18 30/10/18
150 Lantai Keramik 20 x 20 Toilet 14 days Wed Tue
17/10/18 30/10/18
151 Lantai 1 14 days Wed Tue 144SS
17/10/18 30/10/18
152 Lantai 2 14 days Wed Tue 144SS
17/10/18 30/10/18
153 Lantai Keramik 20 x 25 Toilet 14 days Wed Tue
17/10/18 30/10/18
154 Lantai 1 14 days Wed Tue 144SS
17/10/18 30/10/18

Task Milestone External Tasks


SUKATANI PROJECT Split Summary External Milestone
Progress Project Summary Deadline

Page 7
ID Task Name Duration Start Finish Predecessors Jun '18 Jul '18 Aug '18 Sep '18 Oct '18 Nov '18
28 04 11 18 25 02 09 16 23 30 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26
155 Lantai 2 14 days Wed Tue 144SS
17/10/18 30/10/18
156 Border dinding keramik 8 x 20 14 days Wed Tue
toilet 17/10/18 30/10/18
157 Lantai 1 14 days Wed Tue 144SS
17/10/18 30/10/18
158 Lantai 2 14 days Wed Tue 144SS
17/10/18 30/10/18
159 Pekerjaan mozaik motif keramik 14 days Wed Tue 144SS
bintang homogenius tile 1,2 x 1,2 m 17/10/18 30/10/18
160 Pekerjaan Plafond dan Atap 28 days Wed Tue
19/09/18 16/10/18
161 Kuda - kuda baja ringan 21 days Wed Tue 75
19/09/18 09/10/18
162 Penutup atap genteng keramik 21 days Wed Tue 161SS
19/09/18 09/10/18
163 Nok genteng keramik 21 days Wed Tue 161SS
19/09/18 09/10/18
164 Listplank GRC 30 cm 21 days Wed Tue 161SS
19/09/18 09/10/18
165 Plafond GRC Rangka Hollow 4 x 4 / 2 14 days Wed Tue 131SS
x4 03/10/18 16/10/18
166 Plafond gypsum hollow 4 x 4 / 2 x 4 14 days Wed Tue 131SS
03/10/18 16/10/18
167 List Plafond 10 cm 14 days Wed Tue 131SS
03/10/18 16/10/18
168 Pekerjaan Pengecatan 14 days Wed Tue
03/10/18 16/10/18
169 Pek. Pengecatan Plafond 3 lapis 14 days Wed Tue 165SS
03/10/18 16/10/18
170 Pek. Pengecatan dinding 3 lapis ( 14 days Wed Tue 165SS
Vinilex, Catylac, Nipon ) 03/10/18 16/10/18
171 Pengecatan Kolom 14 days Wed Tue 165SS
03/10/18 16/10/18
172 PEKERJAAN PLUMBING DAN SANITAIR 21 days Wed Tue
10/10/18 30/10/18
173 Closet duduk 21 days Wed Tue
10/10/18 30/10/18
174 Lantai 1 14 days Wed Tue 143SS
10/10/18 23/10/18
175 Lantai 2 14 days Wed Tue 144SS
17/10/18 30/10/18
176 Pek. Pas closet jongkok + flush setara 21 days Wed Tue
TOTO, american Standart Wasser 10/10/18 30/10/18

Task Milestone External Tasks


SUKATANI PROJECT Split Summary External Milestone
Progress Project Summary Deadline

Page 8
ID Task Name Duration Start Finish Predecessors Jun '18 Jul '18 Aug '18 Sep '18 Oct '18 Nov '18
28 04 11 18 25 02 09 16 23 30 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26
177 Lantai 1 14 days Wed Tue 143SS
10/10/18 23/10/18
178 Lantai 2 14 days Wed Tue 144SS
17/10/18 30/10/18
179 Floor drain 21 days Wed Tue
10/10/18 30/10/18
180 Lantai 1 14 days Wed Tue 143SS
10/10/18 23/10/18
181 Lantai 2 14 days Wed Tue 144SS
17/10/18 30/10/18
182 Pipa air bersih PVC 21 days Wed Tue
10/10/18 30/10/18
183 1" 14 days Wed Tue 143SS
10/10/18 23/10/18
184 1/2" 14 days Wed Tue 144SS
17/10/18 30/10/18
185 Pipa air kotor PVC 21 days Wed Tue
10/10/18 30/10/18
186 Lantai 1 dan lantai 2 21 days Wed Tue
10/10/18 30/10/18
187 4" 21 days Wed Tue 143SS
10/10/18 30/10/18
188 3" 21 days Wed Tue 143SS
10/10/18 30/10/18
189 2" 21 days Wed Tue 143SS
10/10/18 30/10/18
190 Pemasangan kran air 7 days Wed Tue 189SS+14
24/10/18 30/10/18 days
191 Tangga monyet 7 days Wed Tue 190SS
24/10/18 30/10/18
192 Tangki fiber glass 1000 liter 7 days Wed Tue 190SS
24/10/18 30/10/18
193 Pas. Westafel lengkap + cermin 7 days Wed Tue 190SS
24/10/18 30/10/18
194 IPAL Biofil instalasi lengkap 7 days Wed Tue 190SS
24/10/18 30/10/18
195 Pek. Sumur bor, pompa dan pompa dorong 7 days Wed Tue 190SS
( lengkap) 24/10/18 30/10/18
196 Menara air 7 days Wed Tue 190SS
24/10/18 30/10/18
197 PEKERJAAN INSTALASI M/E 35 days Wed Tue
03/10/18 06/11/18
198 Pekerjaan Instalasi Listrik 35 days Wed Tue
03/10/18 06/11/18

Task Milestone External Tasks


SUKATANI PROJECT Split Summary External Milestone
Progress Project Summary Deadline

Page 9
ID Task Name Duration Start Finish Predecessors Jun '18 Jul '18 Aug '18 Sep '18 Oct '18 Nov '18
28 04 11 18 25 02 09 16 23 30 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26
199 Panel induk MDP 7 days Wed Tue 202
17/10/18 23/10/18
200 Panel pembagi 7 days Wed Tue 199SS
17/10/18 23/10/18
201 Instalasi penerangan ( kabel 2 x 1,5 14 days Wed Tue
setara etema, lengkap assesories ) 03/10/18 16/10/18
202 Lantai 1 14 days Wed Tue 131SS
03/10/18 16/10/18
203 Lantai 2 14 days Wed Tue 202SS
03/10/18 16/10/18
204 Instalasi daya 14 days Wed Tue
03/10/18 16/10/18
205 Lantai 1 14 days Wed Tue 131SS
03/10/18 16/10/18
206 Lantai 2 14 days Wed Tue 202SS
03/10/18 16/10/18
207 Stop kontak ( kabel 2 x 1,5 setara 14 days Wed Tue
etema, lengkap assesories ) 03/10/18 16/10/18
208 Lantai 1 ( Setara broco, 14 days Wed Tue 131SS
Panasonic, Clipsal ) 03/10/18 16/10/18
209 Lantai 2 ( Setara broco, 14 days Wed Tue 202SS
Panasonic, Clipsal ) 03/10/18 16/10/18
210 Saklar tunggal ( kabel 2 x 1,5 14 days Wed Tue
setara etama, lengkap assesories ) 03/10/18 16/10/18
211 Lantai 1 ( Setara broco, 14 days Wed Tue 131SS
Panasonic, Clipsal ) 03/10/18 16/10/18
212 Lantai 2 ( Setara broco, 14 days Wed Tue 202SS
Panasonic, Clipsal ) 03/10/18 16/10/18
213 Saklar ganda ( kabel 2 x 1,5 setara 14 days Wed Tue
etama, lengkap assesories ) 03/10/18 16/10/18
214 Lantai 1 ( Setara broco, 14 days Wed Tue 131SS
Panasonic, Clipsal ) 03/10/18 16/10/18
215 Lantai 2 ( Setara broco, 14 days Wed Tue 202SS
Panasonic, Clipsal ) 03/10/18 16/10/18
216 Lampu TL RM 2 x 18 W 14 days Wed Tue
03/10/18 16/10/18
217 Lantai 1 14 days Wed Tue 131SS
03/10/18 16/10/18
218 Lantai 2 14 days Wed Tue 202SS
03/10/18 16/10/18
219 Lampu DL 18 W 14 days Wed Tue
03/10/18 16/10/18
220 Lantai 1 14 days Wed Tue 131SS
03/10/18 16/10/18

Task Milestone External Tasks


SUKATANI PROJECT Split Summary External Milestone
Progress Project Summary Deadline

Page 10
ID Task Name Duration Start Finish Predecessors Jun '18 Jul '18 Aug '18 Sep '18 Oct '18 Nov '18
28 04 11 18 25 02 09 16 23 30 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26
221 Lantai 2 14 days Wed Tue 202SS
03/10/18 16/10/18
222 Lampu taman 7 days Wed Tue
31/10/18 06/11/18
223 Lanscape 7 days Wed Tue 256SS+7
31/10/18 06/11/18 days
224 Instalasi AC 14 days Wed Tue
03/10/18 16/10/18
225 Lantai 1 14 days Wed Tue 131SS
03/10/18 16/10/18
226 Lantai 2 14 days Wed Tue 202SS
03/10/18 16/10/18
227 AC 1 PK 14 days Wed Tue
03/10/18 16/10/18
228 Lantai 1 14 days Wed Tue 131SS
03/10/18 16/10/18
229 Lantai 2 14 days Wed Tue 202SS
03/10/18 16/10/18
230 Pek. Penangkal petir lengkap 14 days Wed Tue 131SS
03/10/18 16/10/18
231 PEKERJAAN PAGAR 21 days Wed Tue
10/10/18 30/10/18
232 Galian tanah pondasi 7 days Wed Tue 119
10/10/18 16/10/18
233 Pasangan pondasi batu kali 1 : 5 7 days Wed Tue 232SS
10/10/18 16/10/18
234 Sloof beton 15/25 7 days Wed Tue
10/10/18 16/10/18
235 Bekisting 7 days Wed Tue 233SS
10/10/18 16/10/18
236 Pembesian 7 days Wed Tue 233SS
10/10/18 16/10/18
237 Cor ready mix K-225 7 days Wed Tue 233SS
10/10/18 16/10/18
238 Kolom Beton 15/15 7 days Wed Tue
17/10/18 23/10/18
239 Bekisting 7 days Wed Tue 240SS
17/10/18 23/10/18
240 Pembesian 7 days Wed Tue 237
17/10/18 23/10/18
241 Cor ready mix K-225 7 days Wed Tue 239SS
17/10/18 23/10/18
242 Pasangan bata ringan ( hebel) pagar 7 days Wed Tue 237
17/10/18 23/10/18

Task Milestone External Tasks


SUKATANI PROJECT Split Summary External Milestone
Progress Project Summary Deadline

Page 11
ID Task Name Duration Start Finish Predecessors Jun '18 Jul '18 Aug '18 Sep '18 Oct '18 Nov '18
28 04 11 18 25 02 09 16 23 30 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26
243 Plesteran + Acian 1 : 5 7 days Wed Tue 242SS
17/10/18 23/10/18
244 Ring balok beton15/20 7 days Wed Tue
17/10/18 23/10/18
245 Bekisting 7 days Wed Tue 246SS
17/10/18 23/10/18
246 Pembesian 7 days Wed Tue 242SS
17/10/18 23/10/18
247 Cor ready mix K-225 7 days Wed Tue 245SS
17/10/18 23/10/18
248 Pek. Pintu gerbang utama pagar hollow 3 7 days Wed Tue 243
cm x 3 cm 24/10/18 30/10/18
249 PEKERJAAN PAVING DAN PENYELESAIAN 14 days Wed Tue
24/10/18 06/11/18
250 Pekerjaan paving block 14 days Wed Tue 247
24/10/18 06/11/18
251 Kanstin taman 10.20.40 14 days Wed Tue 250SS
24/10/18 06/11/18
252 Tiang Bendera 14 days Wed Tue 250SS
24/10/18 06/11/18
253 Rumput gajah mini 14 days Wed Tue 250SS
24/10/18 06/11/18
254 Pohon Mangga 14 days Wed Tue 250SS
24/10/18 06/11/18
255 Pohon Palem 14 days Wed Tue 250SS
24/10/18 06/11/18
256 Tanaman pucuk merah 14 days Wed Tue 250SS
24/10/18 06/11/18
257 Saluran air hujan area bangunan buis 1/2 14 days Wed Tue 250SS
Ø 30 24/10/18 06/11/18
258 Pekerjaan perapihan 14 days Wed Tue 250SS
24/10/18 06/11/18
259 PEMASANGAN DAYA LISTRIK 7 days Wed Tue 248
31/10/18 06/11/18
260 PHO 8 days Wed Wed 259 PHO
07/11/18 14/11/18 14/11

Task Milestone External Tasks


SUKATANI PROJECT Split Summary External Milestone
Progress Project Summary Deadline

Page 12