Achmad Oktoriandy; Dibimbing oleh Ir. Muhammad Amin MS. dan Ir. Bochori,
MT., IPM.
RINGKASAN
ii Universitas Sriwijaya
yang awalnya 3.001,63 ton atau 2,10% menjadi 1.124,28 ton atau 0,78%, sehingga
coal losses pada rangkaian unit coal crushing plant telah memenuhi kriteria coal
losses perusahaan yaitu ≤ 2%.
Kata Kunci : Pengecilan ukuran butir, rangkaian unit coal crushing plant, coal
losses.
Achmad Oktoriandy: Supervised by Ir. Muhammad Amin, MS. and Ir. Bochori,
MT., IPM.
Analisis Coal Losses pada Rangkaian Unit Coal Crushing Plant 3 (CCP 3)
Di PT Muara Alam Sejahtera.
SUMMARY
Size reducing process at PT Muara Alam Sejahtera using a crushing plant unit start
from the feed entering the hopper at ± 500mm will then received by belt conveyor
1 as belt feeder and then continue to belt conveyor 2. After that then goes to primary
crusher (double roll crusher) and then goes to secondary crusher (double roll
crusher) with continuity and the outputs are around 50 mm. The result goes to belt
conveyor 3 and stock to be sold to the consumer. The amount of feeds are reducing
due to coal losses.
The determination of PT Muara Alam Sejahtera crusher production is declared good
with losses ≤ 2%. Coal losses in the crushing plant unit 3 are 3,001.63 ton/month
(2.10%) of the incoming feed amount, which means that it has exceeded the
company's tolerance limit. Losses from the coal crushing palnt caused by some spot
that is, at hopper caused by the size of the feed is larger than the size of grizzly and
the direct dumping method is not supervised enough by the dump man, at belt
conveyou 2 caused by the opening of skirt boards wheel at the first belt, at belt
conveyor 3 cause by the position of belt conveyor and roller is not touching eah
other on falling material position.
The attempt to reduce the coal losses are, at hopper, controling the size of the feed
entering the hopper not larger than 500 mm and intensing the supervision, at belt
conveyor 2, closing the skirt boards side belt with a rubber with 3 meter width and
0.10 meter height, and at belt conveyor 3, adjusting roller position so the roller and
belt conveyor touching each other and the belt move on the line. After the process
of repair of coal losses decreased from 9.21 ton/hour to 3.43 ton/hour. The amount
of coal losses reduction are from 3,001.63 ton or 2.10% to 1,124.28 ton or 0.78%.
So the coal losesse at coal crushing plant units are at below 2%.
iv Universitas Sriwijaya