Issue: 02
Date: 2016-06-06
Start
Check and set the DIP Check and install Y-shaped clock cables.
switches of the subracks.
Install the OMU board. Install Ethernet cables for the OMU board.
(Optional) Install the SAU (Optional) Install Ethernet cables for the SAU board.
board.
a
Install Ethernet cables for the FG2a/FG2c/FG2d
Install signal cables. board.
End
Install E1/T1 cables.
a
a Introduction to Power Cables and PGND Cables
You need to make the terminals of the external power cables and Positive Ground (PGND)
cables on site. Upon delivery, the terminals of the inter-cabinet PGND cables are available
and have been installed on one end.
2
1 Installing Power Cables and PGND Cables
When installing the cables, set the power distribution switches for the PDF and PDB output
terminals to "OFF".
Crimp the power cable terminals and PGND cable terminals on the cabinet side.
Use diagonal pliers to cut the rectangular cover plate at the top of the N68E cabinet, then
route the power cables into the cabinet.
3
1 Installing Power Cables and PGND Cables
When installing the cables, set the power distribution switches for the PDF and PDB output
terminals to "OFF".
Crimp the power cable terminals and PGND cable terminals on the cabinet side.
4
1 Installing Power Cables and PGND Cables
When installing the cables, set the power distribution switches for the PDF and PDB output
terminals to "OFF".
Ensure that three PGND cables are present on the mounting bar at the back of the adjacent
cabinets and one end of these cables is pre-installed.
Interconnect the three PGND cables at the upper, middle, and lower parts of the mounting
bar at the back of the adjacent cabinets.
5
2 Checking and Setting the DIP Switches on the Subracks
DIP switch
DIP switch Rear view of
the subrack
The DIP bits are numbered in ascending order from bit 1 to bit 8. 0 indicates that a DIP
switch is on, and 1 indicates that a DIP switch is off.
1 to 5 Subrack numbers
6
2 Checking and Setting the DIP Switches on the Subracks
The DIP switch uses odd parity check. Therefore, the number of 1s in the eight bits must be
an odd number. The detailed procedure is as follows:
(3) Note that the setting of bit 8 remains unchanged. Count the number of 1s. If the number is
even, set bit 6 to 1. If the number is odd, set bit 6 to 0.
The following table lists the settings of the DIP switches when the subracks are numbered
from 0 to 3 and bit 8 is set to "OFF".
Subrack Bit
Number
1 2 3 4 5 6 7 8
0 0 0 0 0 0 0 1
0
ON ON ON ON ON ON ON OFF
1 0 0 0 0 1 0 1
1
OFF ON ON ON ON OFF ON OFF
0 1 0 0 0 1 0 1
2
ON OFF ON ON ON OFF ON OFF
1 1 0 0 0 0 0 1
3
OFF OFF ON ON ON ON ON OFF
7
3 Conducting the Power-on Check on the Cabinet
Set the PDF switches that correspond to the cabinet and all the switches of the PDB to
"OFF".
Set the multimeter to the buzzer scale and ensure that the input and output of the PDB are
not short-circuited. If there are short-circuits, the multimeter beeps.
Multimeter
Set the corresponding switches of the PDF to "ON", and set all the switches
of the PDB to "OFF".
Set the multimeter to the voltage scale, and ensure that the voltage on the input terminals of
the PDB is normal.
The PDB performs self-check and registration immediately after it is powered on. (Both
the RUN and ALM indicators are ON and the buzzer beeps.)
8
3 Conducting the Power-on Check on the Cabinet
Set the switches of the PDF to "ON". Ensure that the output voltage of the PDB and the
input voltage of the subrack are normal. Ensure that the power-on status of the fan boxes in
the subrack and of the boards is normal.
Normal power-on status: The RUN indicator on the board is ON or blinks. The STATUS
indicator on the fan box blinks.
On the PDF side, set all the output switches and PDB switches that correspond to the
cabinet to "OFF".
9
4 Installing the OMU Board
Wear an ESD wrist strap or a pair of gloves before installing the board.
One OMUc board occupies one slot. The active and standby OMUc boards must be
installed in slots 0 to 3, slots 20 to 23, or slots 24 to 27 in the MPS. Slots 24 and 25 are
recommended.
Insert the board into the subrack along the guide rail.
Turn the two ejector levers inwards, press the screws on the front panel, and rotate them
clockwise.
10
5 Installing the SAUc Board (Optional)
Wear an ESD wrist strap or a pair of gloves before installing the board.
One SAUc board occupies one slot. It’s recommended that the SAUc be installed at the
back of the MPS subrack.
Insert the board into the subrack along the guide rail.
Turn the two ejector levers inwards, press the screws on the front panel, and rotate them
clockwise.
11
6 Installing Signal Cables
a Introduction to Cables
RJ45 SCUb
/ BITS
/ BITS
12
6 Installing Signal Cables
a Introduction to Cables
Type of Connectors at Both Position of Connectors at Both
Cable Appearance
Ends Ends
Unshielded RJ45 (must be made on site) SCUb board in the MPS or main
straight-through TCS
network cable
\ DDF
\ DDF
13
6 Installing Signal Cables
a Introduction to Cables
Type of Connectors at Position of Connectors at Both
Cable Appearance
Both Ends Ends
14
6 Installing Signal Cables
The inter-TNUa cable is classified by length into three types: 2.2 m, 2.7 m, and 9.7 m. The 2.2 m long
cable connects adjacent subracks in the same cabinet, the 2.7 m long cable connects non-adjacent
subracks in the same cabinet, and the 9.7 m long cable connects different cabinets.
Ensure that the inter-TNUa cable in the MPR or TCR is correctly installed.
The subracks in the figure are MPSs and EPSs or all TCSs.
The two plugs at one end of the inter-TNU cable have the same function, and they are not
differentiated when being connected to the active and standby TNU boards.
15
6 Installing Signal Cables
The subracks in the figure are MPSs and EPSs or all TCSs.
The two plugs at one end of the inter-TNU cable have the same function, and they are not
differentiated when being connected to the active and standby TNU boards.
16
6 Installing Signal Cables
Ensure that the SFP+ high-speed cables between SCUb boards in the MPR or TCR are correctly installed.
If the 10G LINK indicators on either SCUb board connected by the SFP+ high-speed cables blink, the cables
are securely connected.
17
6 Installing Signal Cables
18
6 Installing Signal Cables
The subracks in the figure are MPSs and EPSs or all TCSs.
The SFP+ high-speed cables between the SCUb boards are close to the front door of the cabinet. Once the
cables are installed, be careful not to drop them when you open the front door.
Connect cables according to the cable layout in the figure. Do not connect redundant cables, because
redundant cables will cause transmission loopback.
19
6 Installing Signal Cables
20
6 Installing Signal Cables
There are two central subracks in the figure: MPS and main TCS. These two subracks need to be
interconnected by inter-subrack Ethernet cables so that an OM channel is formed.
The Ethernet cable between the SCUb boards are close to the front door of the cabinet. Once the
cables are installed, be careful not to drop them when you open the front door.
Connect cables according to the cable layout in the figure. Do not connect redundant cables, because
redundant cables will cause transmission loopback.
21
6 Installing Signal Cables
The Y-shaped clock cable is classified by length into three types: 2.0 m, 2.5 m, and
9.7 m. The 2.0 m long cable connects adjacent subracks in the same cabinet, the 2.5 m
long cable connects non-adjacent subracks in the same cabinet, and the 9.7 m long
cable connects different cabinets.
Ensure that the Y-shaped clock cable in the MPR is correctly installed.
Insert one end of the cable into CLKIN port of the SCUb.
Insert the other end of the cable into CLKOUT port of the GCUa/GCGa/GCUb/GCGb.
22
6 Installing Signal Cables
There are two types of BITS clock cables: 75-ohm coaxial clock cable and 120-ohm clock
conversion cable. The methods of installing the two types of cables are the same.
Insert one end of the cable into CLKIN 0 or CLKIN 1 port of the GCUa/GCGa/GCUb/GCGb.
23
6 Installing Signal Cables
24
6 Installing Signal Cables
Install the female N connector of the jumper into the Protect port of the surge protector.
Attach the female N connector of the cable to the male N connector of the jumper.
Install the SMA connector of the GPS clock input signal cable into the ANT port on the
GCGa/GCGb board.
25
6 Installing Signal Cables
Insert one end of the cable into the RJ45 port of the OMUc.
LMT/U2000
LMT/U2000
26
6 Installing Signal Cables
Insert one end of the cable into the RJ45 port of the SAUc.
27
6 Installing Signal Cables g
Insert one end of the cable into the RJ45 port of the FG2a/FG2c/FG2d.
28
6 Installing Signal Cables h
Installing Ethernet Cables Between the XPUa/XPUb/XUPc and
j the CBC (Optional)
Insert one end of the cable into the RJ45 port of the XPUa/XPUb/XPUc.
29
6 Installing Signal Cables
Two cabling modes are available for the E1/T1 cable in the same cabinet but in different subracks:
overhead cabling mode: route the cable from the bottom to the top; underfloor cabling mode: route the
cable from the top to the bottom.
Route the E1/T1 cables in the same subrack but connected to a different board first in the middle slots
and then in the side slots. Cables are routed left for slots 20 to 27 and are routed right for slots 19 to 14.
Route the E1/T1 cables on the same board but connected to different ports from the bottom to the top.
Bind the E1/T1 cables Lay the E1/T1 cables horizontally Stack the E1/T1 cables on the cable ladder
on the cable ladder on the cable ladder
Route four E1/T1 Route the cables to Bind the cables Route the cables
cables each time the cabinet side on the cabinet side along the cabinet side
On the cabinet side, bind all the cables into groups, with every four cables in one group. From the inside
to the outside, bind every two adjacent groups together.
30
6 Installing Signal Cables
2. Overhead Cabling
CAUTION
When soldering the E1/T1 cable connector for the DDF, ensure that the E1/T1 connector is disconnected
from the board to protect the board from possible leakage current.
31
6 Installing Signal Cables
3. Underfloor Cabling
Route the E1/T1 cable along the cabinet.
Guide the E1/T1 cable through the cable trough, and then guide the E1/T1 cable to the front
of the E1/T1 interface board.
Route the cables neatly and bind them with cable ties.
Insert the DB44 connectors of the E1/T1 cable into the E1/T1 interface board.
CAUTION
When soldering the E1/T1 cable connector for the DDF, ensure that the E1/T1 connector is disconnected
from the board to protect the board from possible leakage current.
32
6 Installing Signal Cables
CAUTION
When installing optical cables, do not look into the optical port with naked eyes because the laser may
injure your eyes.
Extra optical cables can be wrapped adjacently on the fiber management tray below the subrack. The optical
cables at the outlet of the cabinet and those outside the cabinet must be coated with corrugated pipes.
Encase the optical cables in corrugated pipe. Then, guide the corrugated pipe to the overhead and
underfloor cabling areas and fix it in place.
Guide one end of the optical cable to the corresponding subrack of the board along the column, and then route
the optical cable upwards along the cable trough to the corresponding board.
Remove the dustproof caps from the optical port and the optical cable connector, and then connect the
connectors to the TX and RX ports on the board.
Route the cables neatly and bind them with cable ties.
33
6 Installing Signal Cables
CAUTION
When connecting the optical cable, do not look into the optical port with naked eyes because the laser may
injure your eyes.
Extra optical cables can be wrapped adjacently on the fiber management tray below the subrack. The optical
cables at the outlet of the cabinet and those outside the cabinet must be coated with corrugated pipes.
Use cable ties to bind the optical splitters/combiners to the cable trough.
Route the end with two LC/PC optical connectors (the end marked A and B in the figure) along the cable
trough, and then to the optical ports on interface boards. Coil the redundant part of the optical fibers on the
fiber spool if the optical fibers are too long. Route the end with one LC/PC optical connector (the end marked
C in the figure) along the cable trough to one side of the cabinet and then upwards.
Coat the optical fibers with corrugated pipes. Route the optical fibers upwards or downwards into the
cabinet based on the onsite cabling route, and bind the optical fibers to the wire bushing.
A B
Adapter
34
6 Installing Signal Cables
The EMU EMI has two types: type A and type B. The methods of installing the RS485 communication
cable for type A and type B are the same. The following steps use the type-B EMI as an example to
describe how to install the RS485 communication cable.
Before connecting the EMU to the RS485 communication cable, ensure that bits 4, 3, 2, and 1 on the DIP
switch SW_ADDR in the EMU are correctly set to be OFF, OFF, ON, and ON, respectively.
Attach the DB9 male connector at one end of the RS485 communication cable to the DB9 female connector
on the EMI.
Attach the RJ45 connector at the other end of the RS485 communication cable to the J1 serial port on the
power distribution box.
35
7 Checking the Hardware Installation
No. Item
1 In the equipment room, no packing cartons, cases, or boards are placed about at random. All
items are placed in specific locations.
2 There are no cable ties or other sundries in the cable racks (troughs), at the bottom of the
cabinets, or around the cabinets.
3 There are no cable tie cuts or other sundries under the floor. The ESD floor, if available, is clean
and in good condition.
4 If the equipment such as maintenance terminal and alarm box is installed, it should be placed in
accordance with the engineering design and be connected properly.
b
No. Item
2 Plastic cover plates are properly installed at the top of and at the bottom of the cabinets.
5 The DIP switches of the subracks and boards are correctly set.
6 The surfaces of the cabinets are clean without any fingerprints or smudges. There is no dust,
excessive cable tie ends, or other sundries either inside or outside each cabinet.
36
7 Checking the Hardware Installation
No. Item
1 The installation positions of the power cables are in accordance with the schematic
drawing of the power distribution.
2 The signal cables are routed in accordance with the engineering design.
4 The OT terminals of the power cables and PGND cables are in proper contact with the
flat washers and spring washers. The bare wires and lug handles at the OT terminals
are tightly wrapped with insulating tapes or heat-shrinkable tubes.
5 The power cables and PGND cables are bound separately from other cables.
6 The grounding bars and PGND bars are finally connected to one grounding conductor,
with the earth resistance less than ten ohms.
8 An extra length is left for the signal cables at the point where they are come down from
the cable rack.
9 The optical cables at the outlet of the cabinet and those outside the cabinet are covered
with corrugated pipes. Sharp edges on the corrugated pipes are eliminated to prevent
injury. Both ends of the pipes are fastened.
37
7 Checking the Hardware Installation
No. Item
10 The optical connectors not in use are covered with protective caps.
11 No AC power cables or water supply pipes are routed in parallel with the E1/T1 cables
outside the cabinet within a distance of 20 cm.
12 The E1/T1 cables are kept at least one meter away from the outside down leads and the
reinforcing steel bars of the exterior wall of the building.
14 All the cables are neatly and tightly bound. The cable ties are evenly spaced and face
the same direction.
15 The labels or nameplates at both ends of all the cables are correct, legible, and in order.
The labels or nameplates face the same direction.
38
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Industrial Base Bantian Longgang
Shenzhen 518129
People's Republic of China
www.huawei.com