NISHIN METAL CORPORATION

DATE ISSUED : 12 APRIL 2018 SHEET NO. 1


DATE START : 15 MAY 2018 PREPARED BY :
DATE FINISH : 29 JUNE 2018 Construction of NIPPON PREMIUM BAKERY PROJECT Santo Tomas Project Kenneth Bryan M. Umadhay, C.E.
REFERENCE NO. : NN-17-048-8 CHECKED BY :
CLIENT : TPCI LOT 10, BLOCK 2, FPIP II - SEZ, SAN RAFAEL, STO. TOMAS, BATANGAS Chester Mark E. Balisme, C.E.
INDEX

WORK DESCRIPTION MAY 2018 JUNE 2018 JULY 2018 REMARKS


1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7

I. PROJECT DURATION
(MOBILIZATION)
MOBILIZATION, PREPARATION &
II. (PREPARATION)
MACHINE/MATERIALS DELIVERY

(STAGING)
III. SCOPE OF WORKS BY OTHERS

a Purlin Checking, Alignment & Markings

b Rollforming & Fabrication Works

c Installation of Chicken Wiremesh

d Installation of Clips

Installation of Aluminum Foils &


e
Glasswool Insulations

f Installation of Roof Panels

g Installation of Gutter

Installation of Flashings & Other Bended


h
Accessories

i Installation of Eaves & End Closers

j Installation of Metal Sidings

k Installation of Mouldings

l Housekeeping

n Inspection / Punchlist

NOTE: OFFICE AREA


PRODUCTION AREA A
PRODUCTION AREA B1
PRODUCTION AREA B2