Annexure 2
DELEGATION OF POWERS IN RESPECT OF WORKS EXPENDITURE TO THE BUILDING AND WORKS COMMITTEE AND OFFICIALS OF THE
INSTITUTE
Sl. Designation of the
Nature of Power Extent of Power Condition
No. Officer/Authority
Provided:
The party to whom the work is to
be awarded is asked to quote his
Award of work: rates and he complies with other
(i) Without calling competitive requirements of the tendering.
tenders 1. The rates are found reasonable
and when compared with latest rates
10. (ii) Ab-initio after infructuous call Director 5,00,000/- at which similar work had been
of awarded in the recent past.
tenders or with a firm which has 2. The execution of which cannot
not wait till formalities connected with
quoted tendering are completed.
3. There is likely to be no reasons
from other contractors.
4. The work to be done is urgent.
12. Grant of extension of time for Dean IPM upto 15% extra time
completion of works
Expenditure on carriage of
17. materials in Director Full Powers
emergent cases
Note: “The Director shall be empowered to take action in all matters not covered in the above lists”
*