Anda di halaman 1dari 6

Fire Safety Journal 64 (2014) 81–86

Contents lists available at ScienceDirect

Fire Safety Journal


journal homepage: www.elsevier.com/locate/firesaf

Quantifying life safety Part II: Quantification of fire protection systems


Cornelius Albrecht
Worcester Polytechnic Institute, Worcester, MA, USA

art ic l e i nf o a b s t r a c t

Available online 4 February 2014 In part I of the paper, an assembly building was analyzed in order to compute the failure probabilities,
Keywords: and thus the safety level, of current code-compliant buildings. In this second part, various fire protection
Performance-based design systems are modeled within the fire and egress simulations in order to quantify their magnitude of
Life safety impact. Since all fire protection systems can fail to perform as designed on demand, the potential failure
ASET–RSET along with its probability is accounted for in an event tree analysis. Comparing the resulting failure
Probabilistic risk assessment probabilities of the performance-based analyses with and without fire protection systems yields
Event tree information about the magnitude of impact of the fire protection systems on the level of safety and
Sensitivity analysis hence allows a direct, objective, and quantitative comparison to other systems and designs. Accounting
for the cost of the systems, a direct cost–benefit analysis can be conducted.
& 2014 Elsevier Ltd. All rights reserved.

1. Introduction achieved, a look was taken at the interaction between systems,


since this can improve the overall effectiveness.
Many modern prescriptive fire codes require the installation of In the following sections, the modeling of the most common
fire protection systems for specific occupancies and/or circum- fire protection barriers is shown for the standard fire scenario
stances. Additionally, such fire protection systems are usually introduced in part I of the paper and for others if particular
required by the authorities having jurisdiction (AHJ) during the significance was identified. As systems are always subject to failure
permit process as a part of the prescriptive codes and also as with a corresponding failure rate or probability, the following
compensation measures to compensate shortcomings to the pre- analyses consider two scenarios each, as shown in Fig. 1. The
scriptive requirements. In the latter case, they are agreed upon to reliabilities of the fire protection systems are taken from BS 7974
target a specific risk emanating from a specific shortcoming. While [2, p. 76]. The analysis was conducted using an optimized
this sounds good in theory, the result is usually a trade-off based probabilistic response surface method [3].
on the various opinions and interests of the stakeholders. The It should be noted that herein, only the impact on life safety is
actual performance of the system usually remains unquantified considered. A system may also have impacts on other protection
and a direct cost–benefit comparison to other systems is impos- goals, such as structural fire resistance and, last but not least,
sible. According to Ramachandran [1, p. 12] the cost of meeting the insurance premiums, so that the findings here can only be
current (prescriptive) building fire safety regulations can generate regarded as partial optimization/justification and are not generally
costs as high as 9% of the total building cost and additional high transferable.
annual maintenance burdens. Keeping these numbers in mind, the
quantitative impact on the life safety should indeed be analyzed
carefully in order to optimize and justify these costs.
2. Automatic detection system
In part I, the failure probability p^ f of a life safety design
was introduced as a metric to quantify and objectively compare
The effect of an automatic detection system is the early
designs. Herein, the same metric is used to quantify the perfor-
notification of the occupants and thus has the advantage of
mance of fire protection systems compared to a case without the
reduced alarm/pre-movement times. In order to model the effect,
system. The analyses were conducted for various systems, so that
the stochastic models from part I of this paper for the pre-
they can be directly compared. Different systems and thresholds to
movement times are adjusted: the occupants will be guided by
determine the available safe egress time (ASET) were analyzed.
voice instructions directly after the alarm and thus the mean pre-
While each system has an individual impact on the safety level
movement time shortens to 90 s with a standard deviation of 25 s
instead of the former 180/45 s assumption. Only inducing changes
on the evacuation side of the equation has the big advantage
E-mail address: cornel.albrecht@gmail.com that the previous fire simulations can be “recycled”, saving large

0379-7112/$ - see front matter & 2014 Elsevier Ltd. All rights reserved.
http://dx.doi.org/10.1016/j.firesaf.2014.01.002
82 C. Albrecht / Fire Safety Journal 64 (2014) 81–86

Table 2
Results of the system analysis for a detection system.

Detection system ps=f ; detec: sys: (%) p^ f ; scenario (%) p^ f ;s jp^ f ;f (%) p^ f ; sys: (%)

Standard scenario 90 21 19.3


Optical density 10 68 6.8 26
Standard scenario 90 1.7 1.6
FED criterion 10 5.4 0.5 2
Fig. 1. Modeling of the fire protection systems and their potential failure within an Hidden scenario 90 3.9 3.5
event tree. Optical density 10 99 9.9 13.4
Standard scenario 90 1 0.9
FED criterion 10 40 4 4.9

Table 1
Results of the reliability analyses and sensitivities for the three predominant
variables for the smoke detection. system, this is an improvement of the safety level by a factor of
approximately 2.6 for both criteria.
Scenario α^ tg α^ num: occ: α^ premove: p^ f (%)
An even greater impact can be observed for the hidden fire
Standard with detection, Opt.  0.7 0.4 0.5 21.4 scenario: also considering the 90% reliability, the p^ f ;f becomes 3.5%
Standard w/o detection, Opt.  0.6 0.5 0.6 68.2 for the optical density threshold and 0.9% for the FED criterion.
Standard with detection, FED  0.9 0.2 0.2 1.7
The p^ f ;s 's are 10% and 4%. The total probabilities considering a 10%
Standard w/o detection, FED  0.9 0.2 0.4 5.4 failure of the alarm system yield 13.4% for the optical density and
4.9% for the FID. Comparing these values to the failure probabilities
Hidden with detection, Opt.  0.6 0.4 0.6 3.9
Hidden w/o detection, Opt.  0.6 0.6 0.6 99.2 without an alarm system installed results into an improvement
of the safety level by a factor of around 7-8 times for both criteria.
Hidden with detection, FED  0.9 0.2 0.2 1.0
Hidden w/o detection, FED  0.7 0.4 0.5 39.9
All results are shown in Table 2.
Concluding, an alarm system2 is a very efficient way to shorten
the alarm and pre-movement times which provides significantly
amounts of computational resources. “Recycling” in this case more time for the occupants until untenable conditions are
means that the initial support points from the CFD fire simulations reached. Being alarmed at an early stage of the fire also reduces
can be used again as only the support points within the evacuation the danger of impassable exit routes. The highest impact can be
simulation have changed. For the subsequent iteration steps observed for fires that otherwise would grow to a fully developed
within the solving process, new support point has to be calculated, stage undetected.
of course, for both fire and evacuation simulation. To analyze the
influence of a smoke detection and alarm system, the standard fire
scenario was analyzed for the comparison with the other systems. 3. Smoke and heat exhaustion
Additionally, the hidden fire scenario was also analyzed as an
early detection will have a very large effect here. Even though it Smoke and heat exhaustion (SHE) systems have the effect that
was found (see part I) that the smoke detectors actuate after the harmful impacts of the fire on the occupants are delayed and/
around 40 s on average, only the stochastic model for the pre- or mitigated due to the extraction of smoke and heat. Hence, SHEs
movement time was adjusted to 90/25 s in order to remain aim at the ASET part of the limit state. For the consideration in the
conservative and to retain comparability. The reliability of a analyses, the SHE system has to be included into the fire simula-
commercial smoke detection system is chosen to be 90% according tion. The reliability of an SHE system to work as designed on
to BS 7974 [2]. The results are summarized in Table 1. demand is given with also 90% in the BS 7974 [2].
It should be noted that for the FED reliability analyses, the To show the effect, a total of eight 1 m2 natural in-roof
algorithm has to shift the input for the fire development time to SHE vents were added to the simulations. This is far more than
reach 1 MW t g to approximately 10 s to obtain the design point required by the German assembly building codes [4], but as the
(ASET ¼ RSET).1 Such short times for the fire growth phase may be building serves as a multi-purpose assembly room they might also
mathematically correct but are unrealistic for the actual fire be used for natural lighting during the daytime. The vents have an
development. Hence, the “real” values for the failure probabilities assumed opening time of 15 s after the first smoke detector
are likely to be far less conservative. The formulation of other fire actuates. The fire scenario was chosen to be the standard scenario
scenarios and better (stochastic) modeling may be the subject of while two cases were assumed. In the first case, the detection
further research work. system is only installed to open the vents but not to alarm the
Analyzing the calculated failure probabilities with the event occupants, whereas in the second case, a full alarm is issued upon
tree approach shown in Fig. 1 and assuming a 90% reliability (or a actuation so that the pre-movement time is also reduced (see
10% probability of failure) of the smoke detection and alarm above). The results for the optical density threshold are compiled
system to work as designed on demand leads to p^ f ;s ¼ 19:3% and in Table 3.
p^ f ;f ¼ 6:8% for the standard scenario using the optical density The FED criterion was not reached for any of the calculated
threshold and p^ f ;s ¼ 1:6% and p^ f ;f ¼ 0:5% for the FED criteria. support points until the fire simulations were terminated at 1200 s
Hence, the total probabilities of failure including the alarm system (20 min), which was defined as the absolute maximum time3 in
and its possible malfunction are 26% for the optical density and 2% which a fire compartment has to be fully evacuated, regardless of
for the FED criterion. Compared to the case without an alarm the fire effects. This means that the SHE system herein mitigates

1 2
The shift herein describes the iterative search of the optimal input para- It is considered in this paper that an alarm system is effective in alarming the
meters in the algorithm. In this case, this means ASET can theoretically only be occupants. Unfortunately, many conventional alarm systems fail to accomplish this
equal to RSET if t g is close to 10 s, which is a theoretical value (mathematically goal. The need for further research in proper and effective alarming of the
correct but not practically applicable) since reaching 1 MW in 10 s implies an occupants is underlined by the outcome of the analyses herein.
3
extremely fast, deflagration-like fire growth. This also constitutes a serviceability limit for the normal use of the building.
C. Albrecht / Fire Safety Journal 64 (2014) 81–86 83

Table 3
Results of the reliability analyses and sensitivities for the three predominant
variables for the SHE cases using the optical density threshold.

Scenario α^ tg α^ num: occ: α^ premove: p^ f (%)

SHE without alarm, Opt.  0.8 0.3 0.4 14.7


SHE with alarm, Opt.  0.9 0.2 0.2 5.4
Failure of SHE (standard), Opt.  0.6 0.5 0.6 68.2

Table 4
Results of the system analysis for a SHE system.
Fig. 2. Modeling of the SHE system with a coupled alarm system.
SHE system ps=f ; detec: sys: (%) p^ f ; scenario (%) p^ f ;s jp^ f ;f (%) p^ f ; sys: (%)

Standard scenario 90 14.7 13.2


Optical density 10 68 6.8 20

the threat of being severely harmed or incapacitated by toxic and


heat effects scenario beyond simulation capability for the parti-
cular scenario, implying an unquantified, but implicitly very high
actual level of safety.
Using the systematic approach shown above leads to
p^ f ;s ¼ 13:2% and p^ f ;f ¼ 6:8%, adding up to a total of 20% probability
of failure if a SHE system with 10% probability of failure and
without alarm is installed as shown in Table 4. Compared to the
case without SHE installed, which led to a probability of failure of
68%, it can be concluded that the SHE system without alarm
Fig. 3. Schematic course of the heat release rate for the sprinkler model.
increased the safety for the optical density threshold by a factor of
greater than 3.
If the occupants are also alarmed by an alarm system, the occupants of the fire-sprinkler interaction, such as generation of
pre-movement time is reduced which leads to a conditional hot steam, disruption of the smoke/heat stratification, etc.
probability p^ f ;s ¼ 4:9% and a total SHE system probability of failure In order to find a simple and effective sprinkler activation
of 11.7%, decreasing the failure probability by a factor of 5.8. model for the standard scenario, sprinklers were introduced into
Additionally assuming that an audible alarm works as designed the fire simulation, being located right above the fire in the bar
with proper instructions to the occupants with a reliability of 95% area. The sprinklers were chosen to have an activation tempera-
leads to the event tree in Fig. 2 and a total failure probability ture of 68 1C and a response time index (RTI) of 100 m0.5s0.5, which
of 12%. describes a commonly used sprinkler for office/assembly occu-
In conclusion, the SHE system has a very large effect on the life pancy in Germany. A parameter study was performed, varying t g
safety as it significantly reduces the possibility of reaching the and HRRmax (also known as Q_ max ) and subsequently correlating
optical density threshold during egress and nearly completely the activation time to those variables. The results showed a nearly
mitigates the asphyxiant and heat effects of the fire. Even if the perfect linear correlation between t g and the activation time
egress is delayed by reaching high optical densities, no immediate ðρt g ; Act: 4 0:98Þ, while the HRRmax was insignificant. Therefore,
threat is imposed on the occupants (for this particular building for the standard scenario the activation time was modeled as a
and scenario). factor κ act: of t g . This κ act: -factor was calculated to be 1.7, so that the
sprinklers were modeled to activate at 1:7  t g within the simula-
tion. Considering the design fire, the sprinklers activate after a fire
incubation phase, but long before the HRRmax plateau or even
4. Suppression systems before 1 MW is reached. After sprinkler activation, the HRRmax,spr.
(or Q_ max; spr: ) is assumed to be constant and then to decay linearly.
Fire suppression systems, such as sprinklers, have an effect on The reliability of sprinkler systems to work as designed on
both ASET and RSET. Usually, the effect on the fire is modeled demand is given as 95% (maximum value) in Great Britain [2] and
within the HRR. Models, for example in the SFPE Engineering even 98% in Germany [8] if the system is planned, built, and
Guide [5, p. 94] assume that upon sprinkler activation, the HRR is maintained in compliance with the German sprinkler guidelines
instantly retained at a steady level with subsequent decay as [9]. A recent study by Frank et al. [10] for New Zealand shows
shown in Fig. 3. The activation time is dependent on the fire sprinkler reliabilities in the same range (slightly lower). The lack of
parameters as well as the response time index (RTI) of the sufficient data is also identified therein as the “key protection
sprinklers. Upon activation, it is assumed herein that the HRR system for successful performance-based fire design”.
plateaus for 300 s and then linearly decays in another 300 s. This The results of the analyses are shown in Table 5. It is evident
approach can be considered very conservative, as a study by that the results for the optical density are nearly identical with the
Madrzykowski et al. [6] shows that the activation time is faster results from the un-sprinklered standard scenario. An in-depth
and the effect of the sprinkler on the HRR is usually more effective analysis showed that this is suitable, as the optical density thresh-
(i.e. near-instant extinguishment of the fire). old is usually reached before t ¼ 1:7  t g . Additionally, the optical
Another option is the direct modeling of the interaction of density is a momentary threshold, so that the sprinkler has no
sprinkler systems with the fire as, for example, done by Bryner significant influence on the reliability for this particular case. A
et al. [7], which could also account for various side-effects on the large effect is observed for the FED criterion where the probability
84 C. Albrecht / Fire Safety Journal 64 (2014) 81–86

Table 5 Table 7
Results of the reliability analyses and sensitivities for the three predominant Results of the reliability analyses and sensitivities for the three predominant
variables for the sprinklered standard scenario. variables for the sprinklered ultra-fast scenario.

Scenario α^ t g α^ num: occ: α^ premove: p^ f (%) Scenario α^ tg α^ num: occ: α^ premove: p^ f (%)

Sprinkler, Opt.  0.6 0.5 0.6 67.9 Sprinklered, ultra-fast, Opt.  0.6 0.6 0.6 99.5
Standard w/o sprinkler, Opt.  0.6 0.5 0.6 68.2 Un-sprinklered, ultra-fast, Opt.  0.6 0.6 0.6 99.5

Sprinkler, FED  0.8 0.2 0.5 0.015 Sprinklered, ultra-fast, FED  0.4 0.3 0.6 0.9
Standard w/o sprinkler, FED  0.9 0.2 0.4 5.4 Un-sprinklered, ultra-fast, FED  0.7 0.3 0.6 14.3

Table 6 once again, that the results are very specific for the building and
Results of the system analysis for a sprinkler system. the fire scenarios considered and, therefore, cannot be generalized.

Sprinkler system ps=f ; detec: sys: (%) p^ f ; scenario (%) p^ f ;s jp^ f ;f (%) p^ f ; sys: (%)
5. Organizational fire protection and trained personnel
Standard scenario 98 0.015 0.015
FED criterion 2 5.4 0.11 0.12
Organizational fire protection and trained personnel may have
the biggest impact on the system reliability as it can affect
of failure is significantly lower than for the un-sprinklered sce- multiple scenarios and parameters within the fire protection and
nario. As the threshold is reached later ðt 4 1:7  t g Þ and is cumu- life safety system. Yet the effect is usually implicit and thus very
lative and time-integrated, the lower release of heat and hard to model or quantify as no data is currently available.
asphyxiant gases directly affects the ASET. Looking closer at the Additionally, the organizational fire protection includes various
results, one might even argue again whether the scenario is prone aspects of which some may be complied with (e.g. presence of
to failure at all, as the design point of the convolution (see above) evacuation maps) while others are neglected completely (e.g.
pushes t g near zero, which is mathematically correct but not propping smoke doors open). Some of the imaginable effects of
necessarily physically realistic. As for the sensitivities, t g , the pre- highly trained staff or even dedicated fireguard personnel within a
movement time and the number of occupants have a high holistic organizational fire protection concept include, but are not
influence. Additionally, the HCN-yield has a significant impact on limited to:
the results ðα^ yHCN ¼ 0:3Þ based on the stochastic model, which, as
mentioned before, is based on literature values and engineering  Effect on the scenarios:
judgment with conservative assumptions. ○ Reduction of the fire initiation frequency due to proper
A system analysis was performed to demonstrate the impact of maintenance of, for example, electric installations.
a sprinkler system, taking into account the possibility of a failure ○ Lower failure probabilities due to well-maintained fire
of 2% thereof. There is no evident impact on the optical density for protection systems.
the reasons stated above. For the FED criterion, the total prob- ○ Higher probability of success of the manual intervention, as
ability of failure is 0.12% and thus about 44 times lower than the the staff is familiar with the use of fire extinguishers and
un-sprinklered scenario with a 5.4% probability of failure as shown responds more quickly to a fire.
in Table 6. Considering the reason stated above, the relative level ○ Lower probability of severe scenarios like the ultra-fast fire
of safety is even higher implicitly. due to the use of inflammable (temporary) decoration and
the prohibition of firework usage.
4.1. Influence of a sprinkler system on the ultra-fast fire ○ Faster egress due to evacuation management (e.g. live voice
communication instead of alarm sound or taped messages).
As mentioned above, the sprinklers did not have a large impact  Effect on the parameters used:
when assessing the standard fire for optical density, as they ○ Reduction of fire load.
usually actuate later compared to the other systems. Madrzy- ○ Use of inflammable materials or retardants for slower fire
kowski et al. [6] conclude from a comparison of sprinklered and development, changing t g .
un-sprinklered experiments and simulations that a sprinkler could ○ Limiting the number of occupants by strictly enforcing
have prevented the Station Fire disaster where an ultra fast fire maximum allowable capacities.
occurred. Hence, the ultra-fast scenario from above was re- ○ Reducing the warning and/or pre-movement times.
evaluated together with the sprinkler model introduced. The
results are compiled in Table 7. It can be seen again that the As absolutely no data to quantify the effects of well-trained
sprinklers do not have any significant influence on the visibility personnel could be found, no direct influences are considered
(optical density threshold) as this criterion is reached shortly after herein. The detailed modeling of these effects constitutes an
the fire starts. Yet a significant impact can be seen for the FED interesting topic for further research. Omitting the influence
criterion, which is nearly completely mitigated due to the reduc- entirely penalizes those building operators who invest into orga-
tion of the maximum heat release rate and the early termination nizational fire protection. Hence, a very simplistic approach shall
of the fire. It should be noted that herein, the fire was assumed to be assumed: if the organizational fire protection is considered
start at floor level which conservatively implies a comparatively appropriate within a building, the reliability of manual interven-
late actuation. Also, as stated above, the sprinkler model (plateau tion is assumed to increase to, for example, 75% instead of 25%
and linear decay) can be considered conservative. with low organizational consideration. This has a significant effect,
In conclusion, the sprinkler system does have a very large as the manual intervention is a critical early decision gate within
effect, as the possibility of occupants being severely threatened of the event tree. This means that the success of the manual
incapacitation is mitigated. Yet a risk of delaying the safe egress intervention ultimately leads to a safe state where no hazard is
and thus inflicting injuries due to smoke inhalation could not be imposed on the occupants. Hence, pf ;s always leads to a zero
prevented according to the models utilized. It should be noted, probability of failure so that pf ;f fully controls the sub-tree but is
C. Albrecht / Fire Safety Journal 64 (2014) 81–86 85

Fig. 4. The complete event tree considering all fire protection systems.

Table 8 The result of the interaction case is shown in Table 8 for the
Results of the reliability analyses and sensitivities for the three predominant optical density, along with some comparative values. Interestingly,
variables for the sprinkler–SHE-interaction standard scenario with alarm compared the effect of the sprinkler is now significant despite having no
to the other cases. effect without the SHE vents. This is most certainly due to the fact
Scenario α^ tg α^ num: α^ premove: p^ f
that the SHE system delays the smoke filling of the room by
occ:
pushing the design point forward in time to a degree that the
Sprinkler–SHE-interaction  0.9 0.2 0.2 3.1 sprinkler system can now affect the optical density by cutting the
SHE w/ alarm, Opt.  0.9 0.2 0.2 5.4 HRR. This shows a significant interdependency of fire protection
Sprinkler, Opt.  0.6 0.5 0.6 68.0 systems and the necessity to appropriately model those effects.
Standard w/o sprinkler or SHE, Opt.  0.6 0.5 0.6 68.2
The FED threshold was not reached in any of the simulations.
Hence, the toxic and heat effects are completely mitigated beyond
directly dependent on the protection system reliability. Thus, the simulation capability for the standard scenario.
failure probability of the protection system acts as a plain multi- If all possible interactions are considered within the event tree,
plier for pf ;f . simple multiplication and addition can be used to evaluate the
A simple example shows the influence of the organizational system: all branches are independent minimal cut-sets of the
fire protection: assuming a 75% failure probability of the manual system and interaction (correlation) effects are modeled within
intervention for the standard scenario using the FED threshold the scenario. The total probability of failure of the system for the
ðp^ f ¼ 5:4%Þ leads to a total system probability of failure of 4%, standard fire scenario using the optical density threshold is
while a 25% failure probability obviously leads to only 1.35% in a pf ; sys: ¼ 0:00157.
system analysis (implying that a good organizational fire protec-
tion increases the safety level by a factor of three for the particular
case).
7. Conclusions and outlook

The analyses herein dealt with the quantification of various


6. Full system analysis and interaction effects common fire protection systems for an assembly building. In order
to quantify the impact, appropriate models were developed to
In order to assess the full system performance and to identify consider these systems within performance-based numerical fire
the most effective fire protection fire protection systems, a simulation methods. The models were implemented and prob-
complete system analysis is performed for the standard scenario abilistically analyzed in order to compute the probability of failure
assuming all fire protection systems described above are installed. of the life safety design including the fire protection system. This
An overview of the system is given in the event tree shown in Fig. 4. probability of failure can be considered a safety metric achieved by
All the branches within the event tree and their corresponding the design. Since all fire protection systems can fail to work as
probability of failure can be found. The only scenario that cannot be designed on demand, their possible failure has to be accounted for
assessed directly is the combination of sprinklers and SHE system, within an event tree analysis to avoid and overestimation of the
as this scenario needs additional consideration due to the inter- safety level. An additional look was taken at interaction effects
dependency of both protection systems: if the SHE system works as between fire protection systems since a combination of systems
designed, a great share of the heat is removed directly through the can yield an even higher impact.
vents which could cause a delay in the heat-dependent sprinkler The overall result of all systems considered and accounting for
actuation. Hence, a similar analysis as for the sprinklers was their potential failure can then be calculated using event tree
performed. Again, a very high correlation ðρtg ; Act: 4 0:98Þ was found analysis. The resulting failure probability can be used to quantita-
between t g and the sprinkler actuation time, but the factor tively, directly, and objectively compare designs and fire protection
increases to 1.8, implying the aforementioned delay. systems. Considering the cost of the systems, the methodology
86 C. Albrecht / Fire Safety Journal 64 (2014) 81–86

even allows for a cost–benefit analysis. This ultimately leads to Appendix A. Calculations
more economic fire protection design without sacrificing safety.
Yet it was also found that the results are highly dependent on In the following, the simplified equations for the analyses are
the parameters, scenarios and models used, foremost as the input given for the four scenarios with their respective conditional
data statistics and thus the stochastic models are far from being probability of failure.
sufficiently accurate. Especially for the sprinkler system a different
model will lead to very different results, i.e. even a shorter A.1. Failure probability considering a system and its failure
actuation time would significantly increase the safety level. Hence,
a lot of research is needed in this area in order to sufficiently In order to compute the effect of a protection system, its
account for the systems used. The examples shown herein can be effectiveness needs to be calculated considering that the system
regarded as a first step towards the explicit quantification of the can fail with a given failure probability. It is assumed herein that in
impact of fire protection systems. case of a failure of a protection system, the scenario defaults to the
scenario without the protection system installed. Partial failure
7.1. A semi-probabilistic life safety concept such as, for example, working but under-designed systems are
disregarded herein and constitute interesting further research.
Currently, the application of performance-based life safety In case of the detection system for the optical density, for
concepts is rather arbitrary when it comes to the input data and example, considering a 10% failure probability of the system and a
the safety concept chosen. The classic deterministic approach 21% failure probability if the system is working and the 68% failure
ignores the high level of uncertainties, especially in the input probability of the system is not working, respectively, the overall
parameters and thus only allows for a calculation where the level failure probability of the system considering its possible failure can
of conservativeness remains unquantified. Adding a safety factor be calculated to
κ into the life safety equation ðASET 4 κ  RSETÞ does add some Probability of failure in case the system is working:
safety, yet the actual improvement also remains unquantified, so p^ f ¼ 0:9  0:21 ¼ 0:19 ðA:1Þ
that the concept was even considered flawed [11]. In addition, a
Probability of failure in case the system is not working:
direct and objective comparison to the deemed-to-satisfy pre-
scriptive codes is not possible. p^ f ¼ 0:1  0:68 ¼ 0:068 ðA:2Þ
Using the methodology above allows for the quantification but
And the total probability then yields
would even allow the derivation of a semi-probabilistic safety
concept that implicitly ensures the acceptable level of safety by p^ f ; total ¼ 0:19 þ 0:068 ¼ 0:26: ðA:3Þ
using safety factors γ i for the most influential parameters. These
The factor at which the building is safer compared to the case
safety factors can be based on, for example on a 90-quantile of
without the system is a simple comparison of the probability
their underlying distribution, so that for a normal distributed
without the system compared to the probability with the system
parameter
considering the system's potential failure, so that
1
1 þ αi  Φ ðpf ;req: Þ  V i 0:68
γi ¼ ; ð1Þ κ system ¼ ¼ 2:6: ðA:4Þ
1 þ 1:28  V i 0:26
1
where αi is the sensitivity, Φ ðÞ the inverse normal distribution,
pf ;req: the required maximal allowable failure probability, and V i References
the coefficient of variation of the underlying normal distribution.
Currently, pf ;req: is unknown and it was found that the resulting [1] G. Ramachandran, The Economics of Fire Protection, E & FN Spon; Routledge,
failure probabilities are highly dependent on the chosen models, London, UK; New York, NY, 1998.
[2] BS 7974, Application of Fire Safety Engineering Principles to the Design of
scenarios and input parameters with their according distributions. Buildings. Code of Practice, Technical Report, British Standards Institution
Thus, pf ;req: has to be derived from repetitive calculations of various (BSI), 2001.
building occupancies, with defined models, scenarios, thresholds, [3] C. Albrecht, D. Hosser, A response surface methodology for probabilistic life
safety analysis using advanced fire engineering tools, Fire Saf. Sci. 10 (2011)
and parameters in order to calibrate mean level of safety. A safety 1059–1072, http://dx.doi.org/10.3801/IAFSS.FSS.10-1059.
concept then has to prescribe these exact features and provide [4] MVStättV, Musterverordnung über den Bau und Betrieb von Versammlungs-
the safety factors in a way similar to the approach outlined by stätten (Muster-Versammlungsstättenverordnung - MVStättV), Technical
Report, IS-Argebau, 2005.
Fleischmann [12]. [5] E. Rosenbaum, et al., SFPE Engineering Guide to Performance-Based Fire
Providing a basis for risk-informed design using performance- Protection, 2nd ed., National Fire Protection Association (NFPA) and Society
based methods by prescribing various input parameters would of Fire Protection Engineers (SFPE), 2007.
[6] D. Madrzykowski, N.P. Bryner, S. Kerber, The NIST Station Nightclub Fire
lead to performance-based designs with the same objectively investigation: physical simulation of the fire, Fire Prot. Eng. 31 (2006) 34–46.
proven safety level as prescriptive codes. This improves the [7] N.P. Bryner, D. Madrzykowski, W.L. Grosshandler, Reconstructing the Station
acceptance and constitutes the performance-based methods as Nightclub Fire: computer modeling of the fire growth and spread, in:
Proceedings of the 11th International Interflam Conference (INTERFLAM
real and equal alternative to prescriptive design. In addition, it
2007), vol. 2, InterScience Communications, 2007, pp. 1181–1192.
would make the process comprehensible and transparent among [8] DIN EN 1991-1-2/NA, National Annex – Nationally Determined Parameters –
all parties. Eurocode 1 – Actions on Structures – Part 1–2/NA: General Actions – Actions
on Structures Exposed to Fire, Technical Report, Normenausschuss Bauwesen
(NABau) im DIN Deutsches Institut für Normung e.V., 2010.
[9] VdS CEA 4001, Spinkleranlagen, Planung und Einbau, Technical Report, VdS
Acknowledgments Schadensverhütung GmbH, November 2008.
[10] K. Frank, M. Spearpoint, N. Challands, Uncertainty in Estimating the Fire
Control Effectiveness of Sprinklers from New Zealand Fire Incident Reports,
This work was supported by a fellowship within the Postdoc- Fire Technology OnlineFirst, 2012, OnlineFirst. http://dx.doi.org/10.1007/
Program of the German Academic Exchange Service (DAAD). The s10694-012-0297-2.
author would like to thank Prof. Brian Meacham and the Depart- [11] V. Babrauskas, J.M. Fleming, B.D. Russell, RSET/ASET a flawed concept for fire
safety assessment, Fire Mater. 34 (2010) 341–355.
ment of Fire Protection Engineering at Worcester Polytechnic [12] C. Fleischmann, Is prescription the future of performance-based design? Fire
Institute for the support. Saf. Sci. 10 (2011) 77–94, http://dx.doi.org/10.3801/IAFSS.FSS.10-77.

Anda mungkin juga menyukai