upto ISP
and its development plan
B. Exclusions
1. Selection of permanent and perennial water source.
2. Collection of gauge readings & data, identifying the category of land, land availability for
reservoir, identification of least useful government land, north east coordinates from survey of
India etc.
3. Obtaining or communication with any Government agencies for data collection.
4. Study & mark out possible alignment for laying water line from identified source of Intake Well to
the plant location.
5. Finding out corresponding revenue drawings from respective Tehsil Office and compiling entire
stretch from Intake Well to Plant location.
6. Detailed topographical survey and pipe routing starting from Intake Well locations,
Intermediate reservoir and proposed site of plant, picking up all important physical features
falling on the proposed route.
7. Any type of survey or liasoning activity.
D. Time schedule
1. Submission of FR - 60 days after receipt of all information / input from Client / various agencies
involved in the subject project.
2. Submission of DPR -120 days after receipt of all information / input from Client / various agencies
involved in the subject project.