Work in Progress
Description of Work Done Today
- Bracing supports for Pedestal Forms
-Installation of anchor bolts and checking elevations and alignments
-Cutting and bending for stirrups ground beams/ foundation block works
-Curing of concrete covering with hiesian cloth
-Signing of QP Permits and Excavation Certificates
Obstruction None
(存在问题)
Summary of Resources (资源汇总)
No of labor(工人人数) 1-project engineer,1 - Driver
Worker : 1.Dev Narayan 2.Sat Nerayan 3.Kishori Yadav 4.Ram Kumar
5.Kahmud Mandal 6.BJ Mochi
List of Tools (工具清单) 1 unit- Plate compactor ,1 unit- Bar cutter machine, 1 unit- wood cutter
machine, 4- knipex, 2- shovel , 1- wheel borrow, 1 –Fabricated wooden
box, 1 roll- extension wire, 1 unit – concrete vibrator, 1- water tank , 1
roll – hessian cloth
Material / Consumable Petrol ,plywood, wooden, re- bars
Work in detailed Progress - Bracing supports for Pedestal Forms – completed ready for pouring
concrete
-Installation of anchor bolts and checking elevations and alignments –
completed ready for pouring concrete
-Cutting and bending for stirrups ground beams/ foundation block
works – on going
-Curing of concrete covering with hiesian cloth
-Signing of QP Permits and Excavation Certificates
Work Planned for Next Day :
-Concrete curing of footing slabs with water
-Pouring of concrete at Foundation footing Pedestals
-Signings of QP permits
Planning of Resources (资源计划)
No of labor(工人人数) 1-project engineer,1- Driver
Worker : 1.Dev Narayan 2.Sat Nerayan 3.Kishori Yadav 4.Ram
Kumar 5.Kahmud Mandal 6.BJ Mochi
List of Tools (工具清单) 1 unit- Plate compactor ,1 unit- Bar cutter machine, 1 unit-
wood cutter machine, 4- knipex, 2- shovel , 1- wheel borrow, 1
–Fabricated wooden box, 1 roll- extension wire, 1 unit –
concrete vibrator, 1- water tank , 1 roll – hessian cloth
Page 1 of 6
PPE (劳保用品) Hard hat, safety shoes, gloves, safety goggles ,
Material / Consumable (材料消耗) Petrol,plywood, wooden,Rebars
Site Alexander D. Orongan Recorded by : Alexander D. Orongan