[Type here] detailed work procedure of /floor and wall tiling [Type here]

Material Consumption statement


S.NO Items of work Unit Cement White Surkhi Fine Coarse Bricks Stone Stone Brick Water
. Bag Lime Cum Sand Sand Nos grite Ballast Ballast proof
Cum Cum Cum cum Cum Cum compou
nd
Kg
1 2 3 4 5 6 7 8 9 10 11 12 13
Lime conc. With 40 mm gauge Brick Ballast
1 Cum 0.15 0.30 1.00
100:16:32
Lime conc. With 40 mm gauge Brick Ballast
2 Cum 0.18 0.36 1.00
100:18:36
Cement conc. With 40 mm gauge Brick
3 Cum 2.25 0.48 1.00
Ballast 1:6:12
Cement conc. With 40 mm gauge Brick
4 Cum 2.83 0.50 1.00
Ballast 1:5:10
Cement conc. With 40 mm gauge Brick
5 Cum 3.44 0.50 1.00
Ballast 1:4:8
Cement conc. With 40 mm gauge Stone
6 Cum 6.74 0.45 0.90
Ballast 1:2:4
Cement conc. With 40 mm gauge Stone
7 Cum 4.49 0.465 0.92
Ballast 1:3:6
Cement conc. With 40 mm gauge Stone
8 Cum 3.44 0.50 1.00
Ballast 1:4:8
9 R.C.C. work with 20 mm stone grit in 1:2:4 Cum 6.66 0.45 0.90
R.C.C. work with 20 mm stone grit in
10 Cum 8.68 0.425 0.85
1:1/2:3
11 Brick work with white lime and surkhi in 1:2 Cum 0.11 0.22 460
12 Brick work with white lime and surkhi in 1:3 Cum 0.08 0.24 460
Brick work with cemennt and fine sand in
13 Cum 1.26 0.27 460
1:6
Brick work with cemennt and fine sand in
14 Cum 1.57 0.27 460
1:5
Brick work with cemennt and fine sand in
15 Cum 1.86 0.27 460
1:4
Brick work with cemennt and fine sand in
16 Cum 2.48 0.27 460
1:3
R.B. work with cemennt and coarse sand in
17 Cum 3.74 0.33 425
1:3
20 mm thick DPC with cement and coarse
18 Sqm 0.27 0.02 0.27
sand in 1:2
[Type here] detailed work procedure of /floor and wall tiling [Type here]

25 mm thick DPC with cement, coarse sand


19 Sqm 0.25 0.011 0.023 0.25
stone grite in 1:1/2:3
10 mm thick plaster with cement and fine
20 Sqm 0.063 0.013
sand in 1:6
21 12 mm thick plaster in 1:3 Sqm 0.152 0.015
22 12 mm thick plaster in 1:4 Sqm 0.114 0.015
23 12 mm thick plaster in 1:5 Sqm 0.091 0.015
24 12 mm thick plaster in 1:6 Sqm 0.075 0.015
25 15 mm thick plaster in 1:6 Sqm 0.095 0.019
12 mm thick plaster with cement, white
26 Sqm 0.075 0.0024 0.012 0.0024
lime, coarse sand and fine sand in 1:1:1:5
12 mm thick plaster with cement, white
27 Sqm 0.075 0.0021 0.010 0.005
lime, coarse sand and fine sand in 1:1:2:4
12 mm thick plaster with cement, white lime
28 Sqm 0.057 0.057 0.019
and fine sand in 1:1:6
29 Extra for rough face plaster Sqm 10% extra on each item
15 mm thick plaster rough face with cement,
30 Sqm 0.09 0.019
lime and fine sand in 1:1:6
31 3 mm neat cement floating coat Sqm 0.03
Making drip coarse with cement and coarse
32 Mt 0.108 0.00068
sand in 1:3
33 15 mm thick sand faced plaster in 1:2 Sqm 0.285 0.099 0.080
34 Struck cement pointing in 1:2 Sqm 0.045 0.003
35 15 mm thick Dado in 1:2 Sqm 0.30 0.015
36 15 mm thick Dado in 1:3 Sqm 0.182 0.015
37 20 mm thick Dado in 1:2 Sqm 0.40 0.018
20 mm thick marble dado with 8 mm thick
38 Sqm 0.23 0.015 0.108
topping
20 mm thick marble dado with 5 mm thick
39 Sqm 0.182 0.015 0.173
topping
40 15 mm thick CC floor in 1:2:4 Sqm 0.219 0.011 0.023
41 40 mm thick CC floor in 1:2:4 Sqm 0.296 0.02 0.04
25 mm thick Granolothick marble floor with
42 Sqm 0.189 0.012 0.022 0.108
5 mm thick surface coat (topper)
25 mm thick Granolothick marble floor with
43 0.160 0.012 0.022 0.123
5 mm topping
40 mm thick Granolothick marble floor with
44 Sqm 0.331 0.020 0.040 0.108
5 mm topping
40 mm thick Granolothick marble floor with
45 Sqm 0.302 0.020 0.040 0.173
8 mm topping
[Type here] detailed work procedure of /floor and wall tiling [Type here]

6 mm china white glazed tileswith cement


46 Sqm 0.344 0.108
and coarse sand in 1:3
47 Brick on edge floor sand filled Sqm 0.03 59
48 Flat Brick floor sand filled Sqm 0.024 38
49 Brick edging along apron Rm 0.021 0.0023 4.35
Mud phaska with cement and coarse sand in
50 Sqm 0.100 0.0108 38
1:3
51 RCC Jali 25 mm-40 mm Sqm 0.26
52 RCC Jali 65 mm-75 mm Sqm 0.45
53 RCC 1:2:4 with river single Sqm 6.10 0.45 0.85
54 Laying 60/80 mm thick interlocking tiles Sqm 35
55 White washing three coat Sqm 0.325 kg/sqm
56 Cement wash Sqm 0.013 kg/sqm
Finishing walls with two coat waterproof White 0.018 Snow 0.36
57 Sqm
cement paint over one coat primer cement kg/sqm cem kg/sqm
0.075 0.124
58 Two coat painting over one coat primer Sqm Primer Paint
ltr/sqm ltr/sqm
Wax 0.05
59 Wax polish for floor Sqm
polish kg/sqm
60 M.S. iron work Qtl 2.50% Wastage on steel