Executive Summary
Introduction
This evaluation, of a range of activities
undertaken in 2006/2007 as part of the Methodology
Governance Hub’s Project Partnership
Framework and Pilot Learning A sample of projects
Programme, was carried out by Kath representing the full spectrum of
Gordon and Terry Wolf between activity was selected for
January – April 2007. analysis.
The evaluation identifies the issues arising out of the learning activities and
the Project Partnership Framework itself, using a thematic analysis of both
cross-cutting and learning strand specific themes. It is qualitative rather than
quantitative, due in part to the nature of the available data, but also to the
need to draw out as much learning as possible from the pilot projects.
Project Partnership Framework
The Governance Hub’s initial tendering procedure for activities to meet their
business objectives did not produce the response needed, with very few
tenders received from voluntary organisations. To address this issue the Hub
designed the Project Partnership Framework which enabled them to contract
with sector organisations for relatively small scale projects.
Feedback from project partners about their experience of working with the
Governance Hub through the framework was very positive.
‘The Hub has been The evaluation has identified some minor issues
very effective in relating to communication and the speed with
being responsive to which things had to be completed, but overall
local approaches. partners felt that the processes for commissioning,
The relationship has monitoring and evaluation worked very well. Hub
been a model of staff were described as friendly and supportive,
good practice.’ and partners felt that the projects represented
good value for the money and time spent.
There were many successes amongst the projects sampled, but also a few
examples of approaches that didn’t work quite so well:
• The recruitment projects tested out different ways of attracting new people
into trusteeship, demonstrating that the interest is there if organisations
think creatively and provide some support for new trustees.
• The e-learning programme has already attracted more than 300 learners
and has received very good feedback from trustees using it.
Learning points
The report concludes with some key learning for future work relating to:
Conclusion
The evaluation examined the activities undertaken through the Project
Partnership Framework and the Pilot Learning Programme. The success of
this activity and the way in which it was commissioned and managed has
helped the Governance Hub to raise the profile of governance issues and its
own role. This report suggests that this important work is in its very early
stages and needs to be continued in order to reach a much wider audience
and to embed the learning into the voluntary and community sector. It is still
too soon to assess what impact the pilot learning activity has had, but it is
anticipated that this will become more evident over the next few years.