A. PREAMBLE
About 11.80 TMC of water will be pumped through 8 nos. of vertical turbine
pumps each of 3000 HP and conveyed through 1635mm dia pressure main in 12 rows
each of length 6.75 km to drop into the delivery cistern. The main canal takes off from
the cistern and runs for a length of 97.100 Km with the required Distributory system.
SALIENT FEATURES
Location : On River Godavari @KM41.100 &
KM41.20 of AGLB.
Longitude: 810 – 39’-45” E
Latitude : 170 – 15’ -30”
Village : Purushothapatnam
Mandal : Seethanagaram
District : East Godavari
State : Andhra Pradesh
Project Cost : Rs.674.52 Crores
Water Allocation : 11.80 TMC
Ayacut : 1,85,906 Acres
C. Land Acquisition:
6068.03 acres of land is acquired so far against 6119.53 acres required.
Balance land to be acquired is 51.50 Acres.
E. Cumulative Expenditure:
F. Bottlenecks
1) Balance land to be acquired is 51.50 Acres in which there are 2 Nos of court cases
pending for which land acquisition process is held up to an extent of 26.79 Acres
in S. Annavaram (village). Status is quo-orders. For which constant pursuance is
being made by the Government pleader of Land Acquisition. Due to this land
acquisition problem an extent of 23,081 acres is held up.
2) The work of 5 Nos. HPCL/GAIL crossings has to be taken up, for which amount
has to be deposited to the concerned authorities by the agency and the agency is
being pursued for the deposition of amount. Due to this 5 Nos of HPCL/GAIL
crossings and pending of some part of works (i.e., canal execution and
construction of structures) and an extent of 3720 acres is being held up.