Anda di halaman 1dari 393

TOTAL 395 HOJAS

BASES DE DISEÑO ESTRUCTURAL


(Incluyendo Portada)

PROPOSITO

Para Revisión
 NOMBRE CONTRATO EPC POR EL SISTEMA DE
PROYECTO DESULFURIZACION DE GASES - FGD - PARA
LA CENTRAL TARAPACÁ Para Aprobación

 NOMBRE FGD CENTRAL TARAPACÁ Para Construcción


SISTEMA
Para Oferta
 N° DOCUMENTO DCTO413-C8-VVT-000-001
Para Información
 TITULO BASES DE DISEÑO ESTRUCTURAL

 CLIENTE ENDESA S.A.

F 29-12-2014 JCR VBS NCR Para Aprobación

E 22-12-2014 JCR VBS NCR Para Aprobación

D 25-11-2014 JCR VBS NCR Para Aprobación

C 27-10-2014 JCR VBS NCR Para Aprobación

B 30-09-2014 JCR VBS NCR Para Aprobación

A 24-09-2014 JCR VBS NCR Coordinación Interna - - -

PREP. REV. APR. REV. REV. APR.


Rev
FECHA DESCRIPCION
.
STX HI ENDESA S.A.

PROPIETARIO:

CONTRATISTA:
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-001

Contenido
 
1.  ALCANCE ......................................................................................................................... 3 
2.  APLICACIONES ................................................................................................................ 3 
3.  ANTECEDENTES ............................................................................................................... 3 
4.  CÓDIGOS, ESPECIFICACIONES Y NORMAS ...................................................................... 4 
5.  DOCUMENTOS ENTREGABLES ........................................................................................ 6 
5.1.  DISEÑO BÁSICO ........................................................................................................ 8 
5.2.  DISEÑO DE DETALLES ............................................................................................. 10 
6.  PARÁMETROS GEOTÉCNICOS PARA EL DISEÑO DE FUNDACIONES ............................. 12 
6.1.  DISEÑO DE FUNDACIONES PARA ESTRUCTURAS ALTAS ........................................ 12 
6.1.1.  FUNDACIÓN DIRECTA EN HORIZONTE H2 ...................................................... 12 
6.1.2.  ANCLAJES DE FUNDACIÓN .............................................................................. 12 
6.1.3.  CASO ESPECIALE ESTRUCTURAS ALTAS .......................................................... 13 
6.2.  DISEÑO DE FUNDACIONES PARA ESTRUCTURAS BAJAS ........................................ 13 
6.2.1.  FUNDACIÓN DIRECTA EN HORIZONTE H1 O H3 ............................................. 13 
7.  SOLICITACIONES ........................................................................................................... 14 
7.1.  CARGA MUERTA (D) ............................................................................................... 14 
7.2.  CARGAS VIVAS (L) ................................................................................................... 14 
7.2.1.  DENSIDAD MATERIALES .................................................................................. 15 
7.3.  VIENTO (W) ............................................................................................................ 15 
7.4.  SISMO (E) ............................................................................................................... 16 
7.4.1.  ACCIÓN SÍSMICA HORIZONTAL ....................................................................... 16 
7.4.2.  ACCIÓN SÍSMICA EN LA DIRECCIÓN VERTICAL ............................................... 17 
7.4.3.  AMORTIGUAMIENTO Y FACTOR R. ................................................................. 18 
7.4.4.  MÉTODO DE ANÁLISIS .................................................................................... 18 
7.4.5.  PORCENTAJE DE MASA SÍSMICA DE LAS CARGAS VIVAS ................................ 20 
7.4.6.  DEFORMACIONES SÍSMICAS ........................................................................... 20 
7.4.7.  DISEÑO PARTICULAR DE FUNDACIONES DE TRANSFORMADORES ................ 21 
7.4.8.  DISEÑO PARTICULAR DE MUROS CORTAFUEGO ............................................ 23 
7.4.9.  DISEÑO  PARTICULAR  DE  ESTANQUES  CONTENEDORES  DE  LÍQUIDOS 
APOYADOS EN SUELO ................................................................................................... 24 
7.5.  EFECTOS DE TEMPERATURA (T) ............................................................................. 25 
7.5.1.  TEMPERATURA EXTERIOR (Te) ....................................................................... 25 
7.5.2.  TEMPERATURA DE LOS GASES (Tg) ................................................................ 25 
7.6.  PRESIÓN DEL FLUIDO (F) ........................................................................................ 25 
7.7.  FUERZAS DEBIDAS A EQUIPOS MÓVILES ............................................................... 25 
7.8.  OTRAS SOLICITACIONES ......................................................................................... 26 
8.  COMBINACIONES DE CARGA ........................................................................................ 27 
9.  REACCIONES ................................................................................................................. 30 
10.  APOYOS DESLIZANTES, FIJOS, JUNTAS DE EXPANSIÓN Y DE DILATACIÓN. .................. 30 
1 de 392

Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-001

11.  DISEÑO DE OBRAS DE HORMIGÓN ............................................................................... 31 
11.1.  GENERAL ............................................................................................................. 31 
11.2.  CONSIDERACIONES ESPECIALES DE DISEÑO DE OBRAS CIVILES ........................ 32 
12.  DISEÑO DE ESTRUCTURAS DE ACERO ........................................................................... 34 
12.1.  GENERAL ............................................................................................................. 34 
12.2.  MATERIALES ....................................................................................................... 35 
12.2.1.  ACERO ESTRUCTURAL ..................................................................................... 35 
12.2.2.  PERNOS DE CONEXIÓN ................................................................................... 36 
12.2.3.  PERNOS DE ANCLAJE ...................................................................................... 36 
12.2.4.  SOLDADURA .................................................................................................... 37 
12.3.  UNIONES ............................................................................................................. 37 
12.4.  ESBELTECES MÁXIMAS ....................................................................................... 38 
12.5.  PERFILES MÍNIMOS ............................................................................................ 38 
12.6.  DEFORMACIONES MÁXIMAS .............................................................................. 38 
12.7.  PERNOS DE ANCLAJE Y LLAVES DE CORTE ......................................................... 39 
13.  ESTIPULACIONES DE DISEÑO PARA OTROS MATERIALES O ESTRUCTURAS ................. 40 
ANEXO 1: CRITERIOS DE DISEÑO ESPECIFICOS PARA ESTANQUES ...................................... 41 
ANEXO 2: CRITERIOS DE DISEÑO ESPECIFICOS PARA SDA ................................................... 59 
ANEXO 3: CRITERIOS DE DISEÑO ESPECIFICOS PARA PIPE RACK ....................................... 145 
ANEXO 4: CRITERIOS DE DISEÑO ESPECIFICOS SILO DE CAL Y CENIZAS RECICLADAS ........ 195 
ANEXO 5: CRITERIOS DE DISEÑO ESPECIFICOS PARA FLY ASH SILO ................................... 247 
ANEXO 6: CRITERIOS DE DISEÑO ESPECIFICOS PARA DISEÑO DE DUCTOS ........................ 303 

2 de 392

Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-001

BASES DE DISEÑO ESTRUCTURAL

1. ALCANCE

El objetivo del presente documento es definir los criterios de cálculo, los datos
técnicos, cargas y parámetros de cálculo adoptados para el diseño civil-estructural
de todas las obras, ya sea estructuras metálicas, estructuras de hormigón u otras,
ductos, dampers, juntas de expansión, pasillos, plataformas y escalas, entre otros,
del Sistema de Desulfurización de Gases – FGD – para la Central Tarapacá.
Todas las obras civil-estructurales del proyecto quedan dentro del alcance de este
documento.

2. APLICACIONES

Para los aspectos que se encuentren omitidos en esta especificación, los códigos
o normas especificados en la sección 4 deberán ser adoptados.

Cuando las especificaciones técnicas del contrato, normas o códigos aplicables al


diseño de las obras de este proyecto sean distintas de esta especificación, la
condición más rigurosa será adoptada.

El orden jerárquico de aplicación es: en primer lugar esta especificación, luego las
especificaciones técnicas del contrato, seguido de los otros códigos y normas, y
finalmente los Design Criteria particulares de las obras, anexos a este documento

3. ANTECEDENTES

 Documentos de Licitación para Contrato DCT-04.13 EPC por el Sistema de


Desulfurización de Gases – FGD – para la Central Tarapacá.
 Apéndices N° 1, 2 y 3, a los documentos de licitación del contrato.
 Serie de Preguntas y Respuestas N° 1 y N° 2, del proceso de licitación.
 Aclaración del Contratista.
 Minuta de reunión - Aclaraciones a la oferta 28/01/2014
 13203-05-01-IICW-ITE-001 Versión A Características Garantizadas
Estructuras Metálicas y Obras Civiles.
 Kick off meeting administrativo (3-6-14)
 Kick off meeting ingeniería civil-estructural (6-8-14 y 29-8-14)

3 de 392

Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-001

4. CÓDIGOS, ESPECIFICACIONES Y NORMAS

Se deberán usar las últimas ediciones de los siguientes códigos, normas y ETG a
excepción de aquellas cuya versión se encuentre especificada:

 Especificaciones Técnicas del contrato DCB01-12


 INN-NCh 3171: Diseño estructural – Disposiciones generales y
combinaciones de carga
 ANSI/AISC 360-05: Specification for Structural Steel Buildings
 AISI S100: Specification for the Design of Cold-Formed Steel Structural
Members
 ACI 318: Building Code Requirements for Reinforced Concrete.
 Decreto N° 60: MINVU - Aprueba reglamento que fija los requisitos de
diseño y cálculo para el hormigón armado y deroga decreto nº 118, de 2010
 INN-NCh 2369: Diseño sísmico de estructuras e instalaciones industriales
 ETG-1.015: Especificaciones técnicas generales – Diseño sísmico
 INN-NCh 432 Of.71: Cálculo de la acción del viento sobre las
construcciones. NCh 432 n2010. Diseño estructural – Cargas de Viento
(esta norma se aplicara de manera complementaria solo cuando no exista
información especifica en la versión del año 71).
 AISE Technical Report N°13. Guide for the Design and Construction of Mill
Buildings, 2003.
 API 650: Welded Steel Tanks for Oil Storage
 EN 1991-4:2006 Eurocode 1 – Actions on Structures – Part 4 : Silos and
Tanks
 EN 1993-4.1:2007 Eurocode 3 – Design of Steel Structures – Part 4-1 :
Silos
 INN-NCh 1537: Diseño estructural de edificios. Cargas permanentes y
sobrecargas de uso
 RCSC: Specification for structural joints using ASTM A325 or A490 bolts,
2004
 ETG-1.020: Especificaciones técnicas generales – Diseño sísmico
equipamiento eléctrico y de control
 ASCE/SEI 7: Minimum Design Loads for Buildings and Other Structures
 AISC: Steel Construction Manual
 ICHA: Manual de diseño estrcutural - Acero
 INN-NCh 170: Hormigones - Requisitos Generales
 INN-NCh 211: Barras con resaltes en obras de hormigón armado
 INN NCh 204: Barras laminadas en caliente para hormigón armado
 INN-NCh 1928: Albañilería armada – Requisitos para el diseño y cálculo
 INN-NCh 2123: Albañilería confinada - Requisitos para el diseño y cálculo
 JIS G 3101 : 2010: Rolled steels for general structure
4 de 392

Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-001

 JIS G 3106 : 2008: Rolled steels for WELDED structure


 KS D 3503 : 2008: Rolled Steel for General Structure
 KS D 3515 : 2008: Rolled Steel for Welded Structure
 KS B 1010 : 2009: Sets of high strength bolt, hexagon nut and plain washer
for friction grip joints
 ASTM A36: 2012: Standard Specification for Carbon Structural Steel
 ASTM A325: 2014: Standard Specification for Structural Bolts, Steel, Heat
Treated, 120/105 ksi Minimum Tensile Strength.
 ASTM A490: 2014: Standard Specification for Structural Bolts, Alloy Steel,
 ASTM A307: 2010: Standard Specification for Carbon Steel Bolts and Studs,
60000 PSI Tensile Strength.
 Heat Treated, 150 ksi Minimum Tensile Strength.
 NCh1198Of.2006, Diseño en Madera

El orden en que aparecen detallada la normativa indica prioridad, sólo aplica


la norma siguiente cuando la anterior no cubra un determinado tema.

5 de 392

Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-001

5. DOCUMENTOS ENTREGABLES

Por documentos entregables se entiende la totalidad de planos, memorias de


cálculo, especificaciones técnicas, informes, cubicaciones, entre otros, que
guarden relación con el diseño civil-estructural del proyecto y tal como se describe
en las cláusulas 5.06.01, 5.06.02 y 5.06.03 de las Especificaciones Técnicas de
los documentos de licitación, estos deben ser entregados a CELTA, de manera
oportuna para su revisión, de acuerdo al programa de desarrollo de ingeniería
acordado y que asegura holgura temporal suficiente para la materialización de las
obras en terreno y cumplimientos de los plazos comprometidos.

El contratista establecerá una calendarización de reuniones periódicas de


trabajo de ingeniería entre el ejecutor del diseño civil-estructural y el Revisor
Sísmico Independiente (RSI), coherente con cronograma de obras. A dichas
reuniones asistirá CELTA, con la finalidad de hacer un seguimiento al
programa de ingeniería.

Como se estableció en las especificaciones técnicas del contrato, el diseño


de todas las obras del proyecto debe ser revisado y aprobado por el Revisor
Sísmico Independiente (RSI).

La revisión del proyecto debe contemplar como mínimo los siguientes puntos:

 Diseño de todas las fundaciones.


 Diseño de pernos de anclaje, placas bases, placas de corte y sillas.
 Diseño de todas las estructuras de acero, incluyendo estructuras de
soporte, ductos, sillas de ductos, equipos en general, Absorbedor (SDA),
estanques, tolvas, pasillos, pasarelas, plataformas, escalas, tuberías, y
toda aquella que tenga una función estructural o sismorresistente.
 Diseño de todas las conexiones: pernos, soldaduras, placas, entre otros.
 Diseño de juntas de expansión.
 Diseño de estructuras de hormigón armado, albañilería, madera o
cualquier otro material.

El RSI recibirá conjuntos de documentos para revisión “autosustentables” e


integrales, es decir, que contengan toda la información necesaria para llevar a
cabo una revisión sin tener que pedir documentos adicionales. Dicho de otra
forma, el RSI hará la revisión por obra. Cada obra debe contar con su memoria de
cálculo estructural; con todo el conjunto de planos de las estructuras que ésta
verifique; todos los documentos de referencia, como son: mecánica de suelos,
datos técnicos de equipos, descripción de condiciones de operación, reacciones
provenientes de otras estructuras (previamente aprobadas), etc.; y cualquier otra

6 de 392

Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-001

información que sea relevante para los cálculos contenidos en el documento. Esto
facilita la revisión y agiliza la aprobación.

La revisión de la Ingeniería civil-estructural por parte de CELTA se lleva a


cabo posterior a la aprobación sin comentarios por el Revisor Sísmico
Independiente (RSI).

El Contratista se compromete a que durante el desarrollo del proyecto entregará a


CELTA todos los modelos estructurales computacionales, desarrollados para el
diseño de las obras. Se compromete a que estos modelos estarán disponibles
para CELTA durante todo el desarrollo del proyecto y que en la entrega para
CELTA de los paquetes de revisión aprobados por el RSI se incluirán estos
modelos, en la versión correspondiente.

En general, para el modelamiento, elementos con funciones estructurales como


membranas, silos, casing, tolvas, paneles y similares requieren ser analizados
mediante el uso de elementos finitos.

Se usara el programa SAP 2000 y uso de software como SAFE para análisis /
verificación de Fundaciones.

Tal como lo establece las cláusulas 5.06.01, 5.06.02 y 5.06.03 de las


Especificaciones Técnicas del contrato los entregables mencionados serán
desarrollados por el Contratista en 2 etapas de ingeniería o servicios:

7 de 392

Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-001

5.1. DISEÑO BÁSICO

El diseño básico debe definir las dimensiones generales de las obras civiles,
estructuras metálicas, y la disposición general de los equipos en relación con ellas.

El proyecto básico incluye en general los siguientes documentos:

- Memoria de cálculo de las obras civiles y estructuras.


- Planos de diseño básico de obras civiles y estructuras.
- Especificaciones Técnicas necesarias para la construcción.
- Cubicaciones de las obras civiles y estructuras.

El Contratista entregará planos de diseño básico de cada una de las obras civiles
y estructuras metálicas, con sus dimensiones y formas, indicando las cargas que
actúan sobre ellas y todas las condiciones que deberán cumplirse al hacer el
diseño de detalles.

Los planos de diseño de estructuras metálicas deben indicar la disposición general


y dimensiones de la estructura, las dimensiones y calidad del acero de los perfiles.
Los planos de diseño de obras civiles y estructuras de hormigón armado deben
indicar dimensiones generales.

Se debe entregar una cubicación aproximada de la cantidad de excavaciones,


hormigones de distinta calidad, acero de refuerzo, estructuras metálicas de
distintos tipos, etc., para cada una de las obras civiles, estructuras de hormigón
armado, estructuras metálicas y movimiento de tierra.

Las Memorias de Cálculo deben permitir visualizar con claridad y seguir la forma
en que se han planteado y resuelto los problemas de estabilidad y diseño
estructural.

El contenido de las Memorias de Cálculo es básicamente el que se detalla a


continuación:

- Descripción o esquema de la obra (o referencia a planos en que está definida).


- Antecedentes:

 Relación de los planos e informes técnicos que contiene la información


de terreno (topografía, geología, geotecnia, etc.).
 Relación de los planos y documentos de los proyectos eléctrico y
mecánico.
 Otros antecedentes.

8 de 392

Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-001

- Criterios de diseño y bases de cálculo:

 Cargas normales.
 Cargas eventuales.
 Combinaciones de cargas y coeficientes de seguridad.
 Normas y Recomendaciones de cálculo.
 Criterios de estabilidad y diseño estructural.
 Materiales por emplear en los diferentes elementos.
 Antecedentes constructivos que condicionaron el diseño (etapas de
concretadura, etapas de excavación, etc.).

- Características de equipos y elementos no estructurales

Deberán señalarse las cargas originadas (incluido el peso propio) por la operación
normal o eventual de los equipos, ductos (piping) u otros elementos no
estructurales señalando el documento o los cálculos que dan origen a esos datos.

- Desarrollo del cálculo:

Resolución de los problemas de estabilidad y resistencia de materiales mediante


el uso de fórmulas, métodos de cálculo o programas de computación. Se ilustrará
con los diagramas y figuras que sean necesarios para su fácil comprensión y
revisión.

En esta etapa se definirá cuáles apoyos serán de tipo deslizante, fijo o empotrado
y la ubicación de las juntas de expansión, según el punto 10.

Los resultados del cálculo se presentarán en cuadros resumen ilustrados con las
figuras correspondientes.

Consideraciones generales

El concepto estructural será simple de manera tal que el comportamiento de


la estructura sea fácilmente comprendido y modelado. Las fuerzas aplicadas
deben alcanzar las fundaciones y soportes mediante trayectorias de cargas
claras regulares y directas. No se utilizarán estructuras irregulares.

El sistema estructural debe ser redundante. El daño de elementos aislados


no debe generar demandas torsionales.

El daño debiera ocurrir en elementos fácilmente reparables

9 de 392

Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-001

El diseño básico, ya chequeado por el Revisor Sísmico Independiente (RSI),


debe ser sometido a la aprobación de CELTA con al menos 60 días de
anticipación al inicio del desarrollo del diseño de detalles.

5.2. DISEÑO DE DETALLES

El diseño de detalles se ejecutará a partir de los diseños básicos aprobados


por el Revisor Sísmico Independiente y CELTA.

El diseño de detalles, ya chequeado por el Revisor Sísmico Independiente


(RSI), será sometido a la aprobación de CELTA con al menos 60 días de
anticipación al inicio programado de la construcción de las obras o del inicio
de la fabricación de las estructuras.

El grado de desarrollo de los planos de detalles debe ser tal que permita la
completa construcción de las obras.

El proyecto de detalles, incluye en general, los documentos que se indican en el


siguiente listado:

o Memoria de cálculo de armaduras para estructuras de hormigón armado y


obras civiles.
o Memoria de cálculo de las uniones apernadas y soldadas de las estructuras
metálicas.
o Planos de disposición general: Adaptación o Modificación de los planos de
disposición general preparados en el Proyecto Básico, proveniente de
cambios en las dimensiones y características de los equipos.
o Planos de excavación: Con indicación de dimensiones, cotas de nivel,
taludes, sistemas de sostenimiento de la roca, pernos de anclaje de
revestimiento cuando éste sea necesario, canales de drenaje. En estos
planos se indica la cubicación de los distintos tipos de material por excavar.
Eventualmente estos planos podrán formar parte de los planos de
dimensiones.
o Planos de dimensiones de Obras Civiles: Con indicación de las
dimensiones de todos los elementos estructurales así como todos los
detalles constructivos de las Obras Civiles que sean necesarios para la
instalación y el montaje de los equipos, tales como recesos en los primeros
hormigones, principales etapas de hormigonado, anclajes, ductos, placas y
otros elementos embebidos en los hormigones, en conformidad con los
planos de los Suministradores de los equipos. En los cortes transversales,
debe indicarse claramente la ubicación de las fundaciones. Por otra parte,
deben contener detalles de los distintos tipos de juntas, de elementos de
apoyo tales como placas metálicas y de neopreno, de sistemas de drenaje,

10 de 392

Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-001

mallas de tierra y en general, todo elemento que deba quedar embebido en


el hormigón.
o Planos de hormigón armado:
 Planos de armaduras de refuerzo:
Con indicación de la disposición e individualización de todas las
armaduras detallando, a una escala apropiada, zonas con armadura
particularmente compleja. Se deberá indicar, además, el
recubrimiento de las armaduras, calidad del acero de refuerzo y de
hormigón y la cubicación de este último material. También incluyen el
detalle y distribución de pernos de anclaje de estructuras de
hormigón ancladas en la roca.

 Listas de armaduras de refuerzo:


Con detalle de la forma, dimensiones, cantidad y peso de las
armaduras. Según la importancia de la obra, pueden ir en un plano
separado o bien formar parte del plano de armaduras de refuerzo.

o Planos de estructuras metálicas.


 Planos de montaje:
Con indicaciones de su secuencia y de todos aquellos antecedentes
e indicaciones que permitan el correcto montaje de la estructura.

 Planos de fabricación de estructuras metálicas:


Con indicación de todas las dimensiones y detalle de los elementos
constitutivos de la estructura para su correcta fabricación. Estos
planos incluyen la correspondiente lista de materiales y su
cubicación.

o Planos varios

Otros planos, tales como planos de rellenos, de secuencia de construcción, de


inyecciones, etc.

11 de 392

Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-001

6. PARÁMETROS GEOTÉCNICOS PARA EL DISEÑO DE FUNDACIONES

6.1. DISEÑO DE FUNDACIONES PARA ESTRUCTURAS ALTAS

Se entiende por estructuras altas las definidas en la cláusula 5.06.07E de las


especificaciones técnicas del contrato. Estas estructuras sólo podrán ser fundadas
sobre el horizonte H2, roca diorita, siguiendo el procedimiento definido en la
misma cláusula, ya sea del tipo fundación directa o con anclajes.

6.1.1. FUNDACIÓN DIRECTA EN HORIZONTE H2

 Tensión adm. sello de fund. : adm=35 kgf/cm2


 Porcentaje mín. de área comp. : %Amín=100% (combinaciones ASD 1, 2, 3
y 4 sección 8)
%Amín=80% (combinaciones ASD 5a, 5b,
6a y 6b sección 8)
%Amín=50% (combinaciones ASD 7 y 8
sección 8)
 Factor de seguridad al desl. : FSdesl=según cláus. 5.06.07G de ET

Dada la calidad esperada de la roca, las modelaciones de estructuras podrán


considerar la interacción suelo-estructura como apoyos fijos en el sentido vertical,
debido al bajo nivel de deformaciones esperadas (< 0,08 mm).

6.1.2. ANCLAJES DE FUNDACIÓN

En caso que el Contratista proyecte el diseño de anclajes de fundación para


resistir las tracciones provenientes de la súper-estructura, éstos deben cumplir con
lo siguiente:

 Longitud mínima de anclaje de 3,5 m, desarrollados en roca.


 Angulo del cono teórico de arrancamiento 30°, para verificar su diseño.

Dada las características de anclajes permanentes, los anclajes deben ser


galvanizados (barra, coplas, tuercas, etc.) y tener doble protección superficial
contra la corrosión. Esta doble protección debe ser propuesta por el Contratista y
sometida a aprobación de CELTA.

Además, cabe señalar que los anclajes proyectados, deben cumplir con los
requerimientos de ensayos establecidos en la cláusula 5.07.02G de las
especificaciones técnicas del contrato, durante su construcción.

12 de 392

Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-001

6.1.3. CASO ESPECIALE ESTRUCTURAS ALTAS

Tal como se indica en la cláusula 5.06.7B–SectorA–H1 de las especificaciones


técnicas del contrato, en la zona de emplazamiento del sistema de refrigeración,
bajo la calle interior de la Central indicada en la figura N°5.9 de la misma
especificación, el horizonte H1 (material de relleno, gravas pobremente
graduadas) se encuentra a mayor profundidad que en el sector A. Por este motivo,
en caso que una estructura alta quede fundada una porción en H1 y otra porción
en H2, la solución de fundación debe ser una losa, de manera de traspasar la
mínima carga posible al horizonte H1, debido principalmente a las grandes
diferencias de rigidez entre ambos estratos.
En estos casos se debe analizar los eventuales asentamientos diferenciales que
podrían producirse y limitar el giro.

6.2. DISEÑO DE FUNDACIONES PARA ESTRUCTURAS BAJAS

Se entiende por estructuras bajas las definidas en la cláusula 5.06.07F de las


especificaciones técnicas del contrato. Estas estructuras podrán ser fundadas
directamente sobre el horizonte H1 o H3 (depósitos aluviales), siguiendo el
procedimiento definido en la misma cláusula y los parámetros geotécnicos
descritos en 6.2.1. También se permite que el Contratista opte por fundar en
horizonte H2, en dicho caso los parámetros geotécnicos para el diseño de la
fundación serán los señalados en 6.1.1.

6.2.1. FUNDACIÓN DIRECTA EN HORIZONTE H1 O H3

Tensión adm. sello de fund. : adm=1 kgf/cm2

 Porcentaje mín. de área comp. : %Amín=100% (combinaciones ASD 1, 2, 3


y 4 sección 8)
%Amín=80% (combinaciones ASD 5a, 5b,
6a y 6b sección 8)
%Amín=50% (combinaciones ASD 7 y 8
sección 8)
 Factor de seguridad al desl. : FSdesl=según cláus. 5.06.07G de ET

Sólo se podrán proyectar soluciones de fundaciones rígidas para fundar en estos


horizontes. Controlar asentamientos y giros de fundaciones

13 de 392

Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-001

7. SOLICITACIONES

Cada obra deberá ser diseñada para resistir las combinaciones de cargas
indicadas en la cláusula 8, sin exceder las condiciones de resistencia, tensiones
admisibles en el sello de fundación, estabilidad ni deformabilidad prescritas en
estas bases de diseño.

Para el diseño de las estructuras se deben considerar como mínimo las cargas
definidas en el Standard ASCE/SEI 7, modificado o complementado por lo
indicado en las cláusulas7.1 a 7.8 de estas bases de diseño.

7.1. CARGA MUERTA (D)

Esta carga se refiere al peso propio de la estructura y sus fundaciones. Esta


solicitación considera el peso de todos los materiales de construcción, ya sean
estructurales o no estructurales, dentro de los cuales se puede mencionar muros,
pisos, techos, cielos, escalas, aislamiento térmico, terminaciones, revestimientos y
otros ítems arquitectónicos y estructurales similares, y equipamiento fijo, entre
otros.

Las densidades de los materiales de construcción podrán ser tomadas de los


anexos A y B de la norma chilena NCh1537-2009.

7.2. CARGAS VIVAS (L)

Esta solicitación corresponde a la cargas por la ocupación y uso de una estructura,


como el contenido de estanques, silos, tolvas, ductos, cargas móviles y transitorias
como peso de personas, equipos y herramientas, y otras aglomeraciones de
materiales.

Se considerarán, como mínimo, las siguientes sobrecargas uniformemente


distribuidas:

- Sala de control y de baterías 800 kg/m2


- Bodegas 600 kg/m2
- Oficinas, pasillos, escaleras 400 kg/m2
- Techo no expuesto a tráfico (Lr) 100 kg/m2

De las sobrecargas anteriores; Oficinas, pasillos, escaleras (400 kg/m2) puede ser
reducido en las combinaciones LRFD 3a, 4 y 5 utilizando un factor de mayoración
igual a 0.5, según lo especificado en 9.1.1 a) de la NCh 3171

14 de 392

Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-001

Todos los ductos horizontales o con inclinación menor que 45º, con respecto a la
horizontal, deben ser calculados considerando una altura de material (ceniza)
acumulado igual a 30% de la altura interior del ducto. Para el caso de los silos y
tolvas se deben considerar llenos hasta la máxima altura de control. Con respecto
a la acumulación de material al interior del Absorbedor (SDA) el Contratista deberá
considerar la peor situación posible de ocurrir en el proceso y justificarla. El 100%
de estas acumulaciones de materiales se considerará que está presente
simultáneamente con el sismo.

7.2.1. DENSIDAD MATERIALES

Dentro de las distintas obras y equipos se debe considerar las siguientes


densidades:

Material Densidad [ton/m3]


Ceniza pura 0.8 – 1.0
Ceniza con Cal 0.8 – 1.25
Cal 0.9 – 1.2

Para la verificación estructural se utilizará la mayor densidad del rango


especificado. Para verificar la capacidad volumétrica de los silos o tolvas se
considerará la menor densidad del rango especificado. Para otros materiales se
deberá utilizar lo estipulado en la norma NCh 1537-2009, aplicando el mismo
criterio cuando la norma indique rangos de densidad.

7.3. VIENTO (W)

Esta solicitación se refiere a las cargas que se producen debido al efecto del
viento sobre las estructuras.

La acción del viento es calculada según la norma NCh432Of.1971. Teniendo en


cuenta la ubicación de las obras, donde las construcciones están situadas en
campo abierto ante el mar, se debe utilizar la presión básica indicada en la tabla 1
de la misma normativa.

Además, se considera la exposición de las obras a cima de cerro, por lo que los
valores de la presión básica son incrementados en un 20%.

Las cargas de viento son calculadas en dos direcciones horizontales y


perpendiculares.

15 de 392

Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-001

Cuando se requieran coeficientes no especificados en la norma citada se podrá


utilizar la norma en su versión 2010.

7.4. SISMO (E)

Este estado de carga se refiere a la acción sísmica sobre las estructuras. Las
fuerzas sísmicas deben ser calculadas DE MANERA INDEPENDIENTE en tres
direcciones ortogonales, dos horizontales y una vertical. Cuando existan
direcciones principales claras de la estructura estas acciones deberán ser
aplicadas en esas direcciones principales.

La acción sísmica se evaluara de acuerdo a la metodología definida por la NCh-


2369, con la única excepción que el espectro de diseño a usar deberá ser el
establecido por ENDESA en la ETG-1015.

En aquellos aspectos no cubiertos por las normativas mencionadas anteriormente


esta deberá ser complementada por ejemplo el Euro código en el caso de Silos y
Ductos y la API-650 en el caso de estanques. Debiera agregarse también la norma
neozelandesa citada en la norma NCh-2369.

7.4.1. ACCIÓN SÍSMICA HORIZONTAL

La acción sísmica de las estructuras y sus fundaciones se calcula de acuerdo al


espectro mostrado en la figura 1 de la ETG-1.015 “Diseño Sísmico”, multiplicado
por 0.8, utilizando una aceleración máxima del suelo a=0,4 g. Para ejemplificar la
aplicación del factor de modificación de la respuesta R, según la ETG 1.015, se
presenta a continuación un gráfico con el espectro para razón de amortiguamiento
:=5% , R=1 y R=5.

El factor 0,8 es para llevar el espectro de ENDESA según la ETG-1.015 “Diseño


Sísmico”, a la aceleración máxima del suelo a 0,4g

Todas las estructuras son clasificadas en la categoría sísmica A

16 de 392

Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-001

1.0

0.9 ETG 1.015 ξ=0.05 R=1

0.8 ETG 1.015 ξ=0.05 R=5

0.7

0.6
A(T)/g

0.5

0.4

0.3

0.2

0.1

0.0
0 0.5 1 1.5 2 2.5
T seg

Figura N° 1: Ejemplo de espectro de diseño aplicando factor R=1 y R=5 y razón de


amortiguamiento ξ=5%

En general, no es necesario combinar los efectos debidos a las dos componentes


horizontales de la acción sísmica. Sin embargo, las estructuras que presenten
notorias irregularidades torsionales o que tienen en ambas direcciones marcos
rígidos con columnas comunes a dos líneas resistentes que se intersectan, deben
ser diseñadas para los esfuerzos obtenidos de considerar el 100% de la
solicitación sísmica que actúa en una dirección más los esfuerzos obtenidos de
considerar el 30% de la solicitación sísmica actuando en la dirección ortogonal a la
anterior, y viceversa. Se debe considerar los mayores esfuerzos resultantes de las
dos combinaciones anteriores.

7.4.2. ACCIÓN SÍSMICA EN LA DIRECCIÓN VERTICAL

Se considera que la acción sísmica en la dirección vertical, con coeficiente sísmico


Cv=2/3Ao , con Ao=0.4g, es decir Cv=0.267.
17 de 392

Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-001

7.4.3. AMORTIGUAMIENTO Y FACTOR R.

Los factores de modificación de la respuesta y los coeficientes de


amortiguamiento a utilizar serán los siguientes:

Estructura ξ% R
SDA – casing 2 4
SDA – estructura de soporte 2 4
Silos metálicos - casing 2 3*
Silos metálicos – estructura de soporte 2 3*
Estanque apoyados directamente en fundación 2 4
Ductos - casing 2 3
Ductos – estructura de soporte 2 3
Fundación transformadores de poder 5 3
Edificio Eléctrico / Control (Hormigón Armado) 5 5
Taller de máquinas (estructura metálica) 3 5
Edificios anexos de hormigón 5 5
Estanques en planta de tratamiento de aguas, 2 4
Contenedores de líquidos apoyados sobre el suelo.
Estructuras de soporte menores no arriostradas 2 3
(postes). Soldadas en general.
Pipe rack 3 5
Muro cortafuego 5 4.5

Tabla N°1: Razón de Amortiguamiento ξ y Factor de Modificación de Respuesta R.

 Considera la estructura del tipo “Skirt”, es decir el manto del estanque se


apoya directamente sobre la fundación, en caso de utilizar un Silo Apoyado
sobre columna el factor de modificación de respuesta R puede ser igual a 4.

7.4.4. MÉTODO DE ANÁLISIS

Para el cálculo de los esfuerzos y desplazamientos debido a la acción sísmica


sobre las estructuras se utilizará un análisis del tipo modal espectral.

El análisis debe incluir los suficientes modos de vibrar, de tal forma que se
asegure que la suma de las masas equivalentes, en cada dirección de análisis,
sea igual o superior al 90% de la masa total.

18 de 392

Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-001

Para el cálculo de los esfuerzos y deformaciones sísmicas se realizará una


superposición de los valores máximos modales mediante el método de la
Superposición Cuadrática Completa (CQC), de acuerdo a las siguientes fórmulas:

donde,

S: combinación modal

Si, Sj: valores máximos de las contribuciones de los modos i y j

Cij: coeficiente de acoplamiento entre los modos i y j

: razón de amortiguamiento

Ti, Tj: período de los modos i y j

El efecto de la torsión accidental se debe considerar solo en los niveles que


tengan un diafragma rígido. El efecto de la torsión accidental se puede incluir
considerando posibles variaciones en la distribución del peso propio y sobrecarga.
Si no existen antecedentes para realizar lo anterior, se debe usar la disposición
6.2.8 de NCh433Of.96

19 de 392

Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-001

7.4.5. PORCENTAJE DE MASA SÍSMICA DE LAS CARGAS VIVAS


Para el cálculo de las fuerzas de inercia horizontales debidas al sismo, esta puede
ser reducida utilizando el siguiente porcentaje:

Carga viva de techo sin transito 0%


Carga viva de oficinas, pasillos, escaleras 25%
Material en silos, ductos, SDA 100%

En el caso de la combinaciones en que esté presente el sismo E pero no la carga


viva L, en la masa sísmica no se considerarán aportes de la carga L.

Esto significara evaluar modos y frecuencias para dos situaciones distintas.

La reducción señalada no es aplicable para las fuerzas inerciales verticales.

7.4.6. DEFORMACIONES SÍSMICAS

Según la sección 6.1 de la NCh 2369, cuando el análisis se hace con las
solicitaciones sísmicas reducidas por el factor R, las deformaciones provenientes
de las combinaciones de carga ASD establecidas en 8, deben ser determinadas
de la siguiente forma:

d=d0+R1 dd

en que:
d= Deformación de la combinación sísmica;
d0= Deformación debida a cargas no sísmicas;
R1= Factor que resulta de multiplicar el valor de R por el cuociente Q0/Qmín.,
siempre que Q0/Qmín. sea menor o igual a 1.0. Sin embargo, para el
cuociente Q0/Qmín. no se debe usar un valor inferior a 0.5. En caso que este
cuociente sea mayor a 1.0, se debe usar R1=R;
dd= Deformación calculada con solicitaciones sísmicas reducidas por el factor
R.

Se debe prestar atención a aquellos elementos estructurales especialmente


diseñados para comportamiento dúctil a modo de evitar falla frágil debido a
pandeo local y/o global. Ya que el objetivo es minimizar el daño y tener estructuras
que se puedan reparar fácilmente, la demanda de ductilidad sobre los elementos
se debe considerar menor que la capacidad de ductilidad.

20 de 392

Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-001

7.4.7. DISEÑO PARTICULAR DE FUNDACIONES DE TRANSFORMADORES

Para determinar la carga sísmica se usará el coeficiente sísmico C=0.353 El corte


basal será Qb=C*W, con W igual al peso del transformador más la fundación.

La fuerza de corte basal se distribuirá según la altura descomponiéndola en


fuerzas Fi aplicadas simultáneamente al nivel del centro de masas de cada una de
las partes, todas dirigidas en el mismo sentido en la dirección de análisis. Se
distribuirá el corte basal Qb en proporción a los pesos Wi de las partes
(distribución uniforme), obteniéndose así fuerzas Fi dadas por la ecuación:

WiQb
Fi   CWi
Wi
i

Wi=peso de las partes, es decir, fundación o transformador

Se emplearán los siguientes valores de amortiguamiento  expresados como


porcentaje del amortiguamiento crítico:

Sobre terreno con Vs ≥ 1800 m/s,  = 5%

Sobre terreno con Vs< 1800 m/s,  = 7%

Con Vs = velocidad de propagación de las ondas transversales.

Tanto las fuerzas de corte como los momentos correspondientes serán los que
resulten de la estática al aplicar Fi.

El efecto de la componente vertical del sismo se evaluará usando el coeficiente


sísmico vertical Cv, dado por la relación:

CV  0.6  C

En que C es el coeficiente sísmico horizontal.

Después de diseñada la fundación se recomienda realizar un análisis modal


espectral del conjunto fundación y equipo para validar el diseño sísmico del equipo
completo y verificar sus componentes frágiles contrastando los resultados de las
fuerzas sísmicas de diseño definidas para las componentes del equipo con el
resultado analítico del modelo modal espectral del conjunto.

21 de 392

Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-001

Los transformadores de poder serán anclados a la fundación utilizando el sistema


de cajas de anclaje, consistente en cajas metálicas embebidas en el macizo de
hormigón de la fundación, que alojan a los pernos de anclaje de los equipos tal
que ellos puedan ser removibles.

Los pernos de anclaje que vinculan el chasis de apoyo del equipo con la caja de
anclaje deberán ser dimensionados para resistir la carga sísmica obtenida del
análisis de verificación sísmica realizado al propio equipo aplicando la ETG 1.020
de ENDESA. Por otra parte, la verificación de resistencia de la caja de anclaje y de
las piezas de fijación de la caja a la fundación se realizará considerando la
solicitación sísmica especificada en esta cláusula.

Las juntas de dilatación entre la pileta y las obras circundantes, se sellarán con un
cordón de polietileno y sello de silicona resistente al aceite (Sikaflex 11 FC o
equivalente). Lo anterior permite garantizar la durabilidad del sello estanco de
silicona. El sistema de sello se indica en la figura N° 2.

Figura N° 2: Sistema de sello de pileta

Las dimensiones de las losas de fundación para soportar los transformadores,


deben ser determinadas para asegurar que la losa de fundación permanezca
100% en contacto con el suelo.

22 de 392

Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-001

7.4.8. DISEÑO PARTICULAR DE MUROS CORTAFUEGO

Los esfuerzos sísmicos deberán evaluarse con un factor de reducción R = 4,5.

Se debe considerar además lo siguiente:

 Amortiguamiento: 5%.
 Para el cálculo de la distribución en altura de fuerzas sísmicas horizontales
para las diversas secciones en que se dividirá el muro, se utilizará la
siguiente expresión:

Donde

hi = altura del centro de masas por encima del nivel basal, sección i

Wi = peso de la sección i

Qb = corte basal total de la estructura

Fi = fuerza sísmica horizontal, sección i

 La discretización en altura de masas puntuales para representar al muro


deberá ser consecuente con la obtención de una distribución triangular del
corte sísmico, como se espera de la ecuación que define Fi.

La geometría del muro cortafuego debe cumplir con los siguientes requerimientos:

 El muro debe tener una altura mínima que supere por lo menos en 30 cm el
punto más alto del transformador. En todo caso, la altura del muro no
deberá ser inferior a 1 m sobre el punto más alto del conservador de aceite.
 El muro debe tener una longitud mínima igual al largo del lado de la pileta
de captación de aceite paralela al eje del muro.
 Sobre los muros cortafuegos no se permite la colocación de equipos
eléctricos.

23 de 392

Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-001

7.4.9. DISEÑO PARTICULAR DE ESTANQUES CONTENEDORES DE


LÍQUIDOS APOYADOS EN SUELO

Para todo lo concerniente al diseño de los estanques contenedores de líquidos


apoyados en suelo se debe seguir el diseño especificado en la normativa API650,
más todas las consideraciones especificadas en el punto 11.8 de la NCh2369, con
las siguientes aclaraciones de sus cláusulas:

 11.8 (Filosofía General): Cuando este punto remita al espectro o coeficiente


sísmico (horizontal) del punto 5 de la NCh2369, se deberá utilizar el espectro
de la ETG1015.
 11.8.2: Se utilizará API 650.
 11.8.5: La determinación de las masas hidrodinámicas y los períodos
asociados a los modos de respuesta impulsivo y convectivo se debe hacer
según lo especificado en las normas de diseño API650.
 11.8.8: La aceleración espectral de diseño o coeficiente sísmico del modo
impulsivo para la acción sísmica horizontal debe ser igual al plató del espectro
de la ETG1015 multiplicado por 0.8, para ξ = 0,02 en el caso de estanques de
acero, y ξ = 0,03 en el caso de estanques de hormigón (por ejemplo, para el
caso de acero sería 1.37 * 0.8 / R). La aceleración espectral de diseño o
coeficiente sísmico del modo convectivo para la acción sísmica horizontal debe
ser determinado de acuerdo a la ecuación de la hipérbola de la ETG 1015,
multiplicado por 0.8, considerando una razón de amortiguamiento ξ = 0,005; en
ningún caso este valor será menor que 0,10 Ao/g (0.10*0.4/g).
 11.8.10: No aplica
 11.8.12: No aplica

24 de 392

Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-001

7.5. EFECTOS DE TEMPERATURA (T)

Se deben considerar como mínimo 2 solicitaciones debido al efecto de


temperatura:

7.5.1. TEMPERATURA EXTERIOR (Te)

Es el efecto de temperatura que se produce sobre las estructuras, debido a las


condiciones climáticas de la zona.

Para las estructuras de hormigón se debe considerar una variación de temperatura


de acuerdo a las condiciones locales, pero no menor que ±15 ºC.

Para las estructuras metálicas la variación de temperatura depende de las


condiciones locales, pero no será menor que ±25° C.

7.5.2. TEMPERATURA DE LOS GASES (Tg)

Se debe considerar el efecto de las altas temperaturas del flujo de gases del
proceso. El Contratista deberá considerar un aumento de temperatura no menor
que +180 °C, en todos los elementos que estén en contacto con el flujo de gas.

Las constantes de expansión térmica del acero a utilizar es  = 1.2·10-5 °C-1.

7.6. PRESIÓN DEL FLUIDO (F)

Esta carga se refiere a la presión que genera la circulación de los gases al interior
de los ductos o compartimentos de los equipos. Puede tener valores positivos,
cuando es mayor a la presión atmosférica, o negativos cuando es menor a ella.

Valor de la presión de los gases en las distintas condiciones del proceso,


será de - 400 mm H2O

El caso de fluidos circulando en ductos deberá considerarse las fuerzas que se


generan debido a los cambios de dirección en las singularidades (codos, T, etc.).

7.7. FUERZAS DEBIDAS A EQUIPOS MÓVILES

Estas cargas deben ser consideradas como cargas vivas (L) y se refieren a las
acciones dinámicas provenientes del uso de equipos móviles. De acuerdo con
esta definición se debe incluir bajo este ítem:

25 de 392

Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-001

 Impactos y cargas de origen dinámico en general, aunque se modelen


como acciones estáticas equivalentes.
 Frenajes.

Salvo que el análisis indique fuerzas mayores, se deberán usar como mínimo las
cargas de impacto indicadas en la norma ASCE/SEI 7.

7.8. OTRAS SOLICITACIONES

En el caso de cargas no previstas en la presente especificación, se usarán las


prescritas en normas de reconocido prestigio internacional.

26 de 392

Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-001

8. COMBINACIONES DE CARGA

El diseño por resistencia de obras de hormigón y estructura metálica será hecho


utilizando las combinaciones de carga incluidas en la norma NCh 3171 “Diseño
estructural – Disposiciones generales y combinaciones de carga”, usando el
método de diseño LRFD, cuyas combinaciones se especifican en el punto 9.1 de
dicha norma.

Para el análisis de estabilidad de fundaciones (factor de seguridad al


deslizamiento, porcentaje de área apoyada), verificación de tensiones en el sello
de fundación y cálculo de deformaciones, se usarán las combinaciones de carga
de la norma NCh 3171 de diseño por tensiones admisibles, las cuales se
especifican en el punto 9.2 de dicha norma.

Las combinaciones de carga para LRFD tomarán en cuenta la carga sísmica


especificada en 7.4, por lo que se debe amplificar por el factor 1.4. Para las
combinaciones de carga para ASD la carga sísmica se no debe amplificarse.

Todas las combinaciones deben ser verificadas con el efecto de variación térmica.

Combinaciones de carga LRFD referente a las normas especificadas:


1) 1.4 (D + F + T)
2) 1.2 (D + F + T) + 1.6 L + 0.5 Lr
3a) 1.2 (D + F + T) + 1.6 Lr + L
3b) 1.2 (D + F + T) + 1.6 Lr + 0.8 W
4) 1.2 (D + F + T) + 1.6 W + L + 0.5 Lr
5) 1.2 (D + F + T) + 1.4 E + L
6) 0.9 (D + T) + 1.6 W
7) 0.9 (D + F + T) + 1.4 E

Combinaciones de carga ASD referente a las normas especificadas:


1) (D + F + T)
2) (D + F + T) + L
3) (D + F + T) + Lr
4) (D + F + T) + 0.75 L + 0.75 Lr
5a) (D + F + T) + W
5b) (D + F + T) + E
6a) (D + F + T) + 0.75 W + 0.75 L + 0.75 Lr
6b) (D + F + T) + 0.75 E + 0.75 L
7) 0.6 (D + T) + W
8) 0.6 (D + F + T) + E

27 de 392

Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-001

Siendo:

D: Cargas permanentes
E: Cargas sísmicas, correspondiente a la combinación de dos direcciones
horizontales como se indica en 7.4.1 y la dirección vertical de 7.4.2.
F: Cargas debido a fluidos con presiones bien definidas.
L: Cargas vivas.
Lr: Carga viva de techo sin transito.
T: Cargas por efectos acumulados por variación de temperatura, retracción o
asentamientos diferenciales
W: Cargas de viento

Para el estado de carga T se deben considerar 4 casos:


• T = Tg
• T = ±Te
• T = Tg ± Te
• Considerar T nulo
Tg y Te según lo definido en 7.5.

Las condiciones operativas del proceso, ya sean de temperatura; de presión; de


acumulación de materiales en silos, tolvas o similares, incluidos los fenómenos
transientes, del funcionamiento normal de la central; deberán aplicarse en todas
las combinaciones de carga. Se exceptuarán solamente de lo anterior, en las
combinaciones que incluyen carga sísmica, aquellas solicitaciones que se
interrumpan al iniciarse las aceleraciones basales.

Las cargas de los fenómenos accidentales de proceso que se derivan de la


ocurrencia de un sismo deben aplicarse en las combinaciones LRFD N° 5 y 7 y
ASD N° 5b, 6b y 8.

Para las combinaciones de emergencias se deben considerar adicionalmente


las siguientes combinaciones:

1.2 (D + F + T) + 1.6 L_EM + 0.5 Lr

1.2 (D + F + T) + 1.6 Lr + L_EM

(D + F + T) + L_EM

(D + F + T) + 0.75 L_EM + 0.75 Lr

28 de 392

Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-001

Las cargas de los fenómenos accidentales de proceso que son independientes del
sismo deben aplicarse en las combinaciones LRFD N° 1 y 2 y ASD N° 1 y 2, con
los factores de mayoración de F, T y L, según corresponda.

Para efectos de verificación de estabilidad de fundaciones (factor de seguridad al


deslizamiento, porcentaje de área apoyada), asentamientos y tensiones en el sello
de fundación, se permite que la componente vertical del sismo sea considerada
nula en la combinación ASD número 8), según lo especificado en 12.14.1.2 de
ASCE/SEI 7.

Para efectos de cálculo de deformaciones en las combinaciones ASD que


contienen el estado de carga sísmico (E), éstas se deben determinar considerando
lo descrito en 7.4.6.

Para los casos en que existen ∆T, se consideraran los siguientes estados de
cargas:

 ∆T=+-25ºC (Acero expuesto al ambiente)


 ∆T=+180ºC (carcasa en contacto con gas))
 T1: carga térmica (∆T=+25ºC en caso del acero expuesto al ambiente,
∆T=180ºC en caso de carcasa en contacto con gas)
 T2: carga térmica (∆T=-25ºC en caso del acero expuesto al ambiente,
∆T=180ºC en caso de carcasa en contacto con gas)
 T3: carga térmica (∆T=180ºC en caso de carcasa en contacto con gas)
 T4: carga térmica (∆T=+25ºC en caso del acero expuesto al ambiente)
 T5: carga térmica (∆T=-25ºC en caso del acero expuesto al ambiente)
 Sin temperatura (∆T=0ºC)

29 de 392

Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-001

9. REACCIONES

Las reacciones se presentarán desagregadas por estado de carga sin aplicar los
factores de las combinaciones de carga, tal que se puedan calcular con esos
datos, tanto las combinaciones ASD como LRFD.

10. APOYOS DESLIZANTES, FIJOS, JUNTAS DE EXPANSIÓN Y DE


DILATACIÓN.

En la etapa de diseño básico se definirá la ubicación y descripción de los apoyos


de los equipos en cuanto a si son de tipo fijo rotulado, deslizante o de
empotramiento. En esta etapa se definirá también la posición de las juntas de
expansión.

En caso de apoyos deslizantes, se analizará la magnitud de desplazamientos


máximos y se dispondrá en los diseños de topes y holguras (horizontales y
verticales) que aseguren la estabilidad en caso que, por solicitaciones mayores a
las previstas, los apoyos móviles superen su rango de trabajo.

Para diseñar los apoyos fijos se deberá considerar que en los apoyos móviles no
se ejerce roce que disminuya los esfuerzos de los primeros. Por su parte, para
diseñar los apoyos deslizantes y las partes de estructura asociadas a ellos, se
considerará la solicitación transferida por fuerza de roce.

Las juntas de expansión deben ser diseñadas de tal manera que permitan
desarrollar deformaciones superiores a las provenientes de las combinaciones de
cargas ASD definidas en 8, con la debida consideración del cálculo de
deformaciones por carga sísmica como se indica en 7.4.6.

Debe tenerse especial atención al analizar las direcciones en que pueden ocurrir
los desplazamientos. En el caso de los originados por carga sísmica debe
considerarse que ellos ocurren en cualquier sentido horizontal o vertical e incluso
en sentidos opuestos en estructuras dilatadas entre sí.

Las separaciones entre estructuras deben cumplir con los valores mínimos
indicados en la cláusula 6.2.1 de la NCh 2369.

La separación entre partes de estructuras que se materializan con de juntas de


dilatación y apoyos deslizantes, sólo deben cumplir con los valores mínimos
indicados en la ecuación 6-2 de la cláusula 6.2.1 de la NCh 2369.

30 de 392

Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-001

11. DISEÑO DE OBRAS DE HORMIGÓN

11.1. GENERAL

El diseño de las obras de hormigón se hará de acuerdo con la norma ACI 318-08
"Building Code Requirements for Reinforced Concrete". Además se aplicarán las
modificaciones al ACI 318-08 indicadas en Decreto N° 60 del MINVU ”Aprueba
reglamento que fija los requisitos de diseño y cálculo para el hormigón armado y
deroga decreto nº 118, de 2010”.

Se deberán considerar las disposiciones del capítulo 21 del ACI 318-08 tomando
en cuenta las disposiciones del Decreto N° 60 del MINVU ”Aprueba reglamento
que fija los requisitos de diseño y cálculo para el hormigón armado y deroga
decreto nº 118, de 2010”

Como mínimo se usará hormigón grado H30 de acuerdo a la norma INN NCh 170.
La resistencia especificada a la compresión es la siguiente:

NCh 170 Resistencia especificada a la Resistencia especificada a la


compresión usando una probeta compresión usando una probeta
Grado del cúbica de 20x20cm de acuerdo a cilíndrica de 150mm de alto de
hormigón la NCh 1017 y NCh 1037 acuerdo a la ASTM C39M
H30 30 MPa 25 MPa

Los hormigones a usar deberán ser de gran compacidad, evaluada esencialmente


por condiciones de durabilidad más que por resistencia, debido a su ubicación en
ambiente marino. Para ello las dosificaciones deben considerar:

 Grado del hormigón H30(90)20/(10±2) (resistencia cúbica 300 kgf/cm2


según NCh 170, 10% de fracción defectuosa, tamaño máximo del árido
grueso 20 mm, asentamiento de cono 10±2 cm).
 Cemento Portland puzolánico o Portland Siderúrgico de grado alta
resistencia inicial.
 Razón agua/cementante=0.45 (cementante considera el cemento y
microsílice).
 Microsílice en un porcentaje de uso de 8% del peso del cemento.
 Aditivo superplastificante Viscocrete 5000 CL en un porcentaje de uso de
0,5 % del peso de cemento.

31 de 392

Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-001

El diseño del hormigón considerará una dosificación para obtener un 10 % de


fracción defectuosa.

Se usará acero de refuerzo grado A630-420H (según NCh 204) cuya tensión de
fluencia es 4200 kgf/cm2.

Se deberán considerar los siguientes recubrimientos, medidos desde el borde de


las armaduras:

 Superficie en contacto con agua, tierra o roca : 7 cm


 Superficies no expuestas al agua, tierra o roca : 4 cm

Las barras de refuerzo para hormigón armado deben ser de acero aprobado
para su uso en Chile. Todos los miembros estructurales de una estructura
particular deben ser diseñados y construidos utilizando barras de refuerzo de la
misma calidad

11.2. CONSIDERACIONES ESPECIALES DE DISEÑO DE OBRAS CIVILES

En la Central Térmica Tarapacá se debe tener en especial consideración las


condiciones actuales de los hormigones de las fundaciones. Gran parte de las
partidas de hormigón de la central fueron confeccionadas con agregado pétreo
contaminado con sales de cloruros y sulfatos lo que ocasiona un proceso de
corrosión acelerado en las armaduras de esos hormigones.

Los elementos de hormigón armado contaminados con sales de cloruro presentan


distinto grado de corrosión en sus armaduras, generando diferentes niveles de
agrietamiento de los elementos contaminados. En general presentan mayor
agrietamiento aquellos ubicados en zonas expuestas a mayor temperatura y
humedad, condiciones que favorecen el proceso químico que origina la corrosión
del acero.

El proceso de degradación de los hormigones armados confeccionados con áridos


contaminados continúa en desarrollo y su velocidad de corrosión va en aumento,
ya que el agrietamiento inducido favorece el ingreso de oxígeno y agua,
necesarios para la reacción química que provoca la corrosión.

Para el sistema de desulfurización el Contratista debe determinar todas las


estructuras existentes que deban ser intervenidas. Para ello, se deberá considerar
las condiciones actuales de la central en el proyecto, sin perjudicar su
funcionalidad y operación. El Contratista deberá asumir que todo el hormigón de la
central está contaminado con sales de cloruro y tomar las medidas pertinentes

32 de 392

Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-001

para evitar problemas futuros de corrosión en la interacción entre los hormigones


ya existentes con los nuevos.

Según respuesta n° 2.38 de la serie de preguntas y respuestas, del proceso de


licitación, no se debe utilizar ninguna fundación existente como elemento
constitutivo del proyecto de desulfurizador. Toda fundación proyectada debe
quedar dilatada estructuralmente de las existentes tal que no se transfieran
solicitaciones a éstas últimas. Para evitar la contaminación de los nuevos
hormigones que queden adyacentes a los existentes, se los deberá separa con
láminas de polietileno continuas.

33 de 392

Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-001

12. DISEÑO DE ESTRUCTURAS DE ACERO

12.1. GENERAL

El diseño de las estructuras metálicas deberá cumplir con lo establecido en


"Specification for Structural Steel Buildings" del AISC, última edición 2005.

Los perfiles de plancha plegada deben cumplir con lo indicado en "Specification for
the Design of Cold-Formed Steel Structural Members” del AISI, última edición.

El diseño sísmico de las estructuras metálicas deberá cumplir con lo especificado


en el capítulo 8 y Anexo B de la norma INN NCh 2369. En particular, las cláusulas
siguientes de la norma NCh2369 se considerarán como se indica a continuación.

Cláusula 8.3.6. El esfuerzo sísmico que debe ser menor al 80% de la capacidad
resistente de las diagonales comprimidas, debe considerarse como el esfuerzo
axial que se obtiene de las combinaciones que incluyen la carga sísmica.

Clausula 8.5.2. Las conexiones de las diagonales símicas se deben diseñar para
resistir el 100% e la capacidad en tracción de la sección bruta de estas. Todo
elemento que sea parte del mismo sistema sismo resistente deberá disponer en
sus conexiones una capacidad mayor o igual a la capacidad de la diagonal más
solicitada. Las conexiones de Vigas o elementos horizontales (Vigas puntales) del
sistema de arriostramiento sísmico vertical podrán calcularse considerando el 100
% de su capacidad axial, pero con un límite superior igual al 100% de la capacidad
axial en tracción del arriostramiento o diagonal vertical que controla el diseño de
dicho eje estructural. De cualquier forma dicha viga puntal deberá conectarse al
menos para el 50% de su propia capacidad axial en tracción

El modelamiento de elementos tipo membranas con funciones estructurales como,


silos, casing, tolvas, paneles y similares serán analizados mediante el uso de
elementos finitos.

34 de 392

Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-001

12.2. MATERIALES

12.2.1.ACERO ESTRUCTURAL

Para perfiles y planchas se aceptará el uso de hasta dos calidades de acero por
estructura.

El acero estructural cumplirá con la siguiente norma JIS G 3101 y JIS 3106.

Denominación Fy [MPa] Fu [MPa] E [Mpa]


SS 400 Fy = 235MPa (t <= 40mm) 400 Mpa 200.000
MPa
Fy = 215MPa (40mm <t<=100mm)
SM 490 Fy = 315MPa (t <= 40mm) 490 MPa 200.000
MPa
Fy = 295MPa (40mm <t<=100mm)

Todos los perfiles ángulo deberán ser laminados, otros perfiles podrán ser
soldados, laminados o de plancha plegada.

El acero estructural de perfiles y planchas debe tener como mínimo una tenacidad
de 27 J a 20°C en ensayo de impacto Charpy V-Notch de acuerdo a la norma
ASTM A370, con una frecuencia tipo H, según la norma ASTM A673.

El acero debe cumplir en especial los requisitos impuestos en la NCh 2369 punto
8.2.1, incluyendo los requerimientos de soldabilidad de la NCh 203 anexo A, sin
perjuicio de los otros requerimientos estipulados.

La aceptación del uso de las normas mencionadas no exime al Contratista de la


obligación de presentar los certificados (por colada) de todo material utilizado en el
proyecto, que garanticen que el material suministrado cumple con los normas y
especificaciones técnicas exigidas.

De acuerdo a la cláusula 5.04.05 de las especificaciones técnicas, se debe


considerar para todos los elementos tipo membrana con funciones estructurales
como, silos, casing, tolvas, paneles, ductos y similares, formados por planchas
metálicas, una pérdida de espesor de placas por los siguientes conceptos:

 Todas las planchas metálicas que se encuentren en contacto directo


con flujos de gases deben considerar en el diseño, para efecto de la
resistencia, la pérdida de 1 mm de espesor por efecto de abrasión
 Todas las planchas metálicas que se encuentren hacia el exterior,
deben considerar en el diseño, para efecto de la resistencia, la pérdida
35 de 392

Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-001

de 1 mm de espesor por efecto de corrosión, incluyendo aquéllas


cubiertas por aislación térmica.

El espesor para el diseño por resistencia debe ser considerado como el


espesor nominal menos el espesor de pérdida por corrosión y degaste.

Acero Temperatura Fy MPa E MPa

SS 400 T1=180 °C 204 MPa 193200 MPa

SS 400 T2=50 °C 227 MPa 199412 MPa

Estos valores están de acuerdo a norma ASME 2010 (Table Y-1 and Table
TM-1)

12.2.2.PERNOS DE CONEXIÓN

Los pernos estructurales deben ser de alta resistencia según ASTM A325 o A490
con golilla plana endurecida, según ASTM F436. Alternativamente se permite el
uso del acero KS B 1010 F10T.

En uniones de elementos no estructurales se podrá usar pernos calidad ASTM


A307.

12.2.3.PERNOS DE ANCLAJE

El acero de los pernos de anclaje debe cumplir con la norma ASTM A193 tipo B7,
ASTM A1554, ASTM A36 o JIS G 3101 SS400.

El acero para pernos de anclaje debe tener grano fino y uniforme y tenacidad de
27 Joules a 0°C en ensayo de impacto Charpy V-Notch de acuerdo a la norma
ASTM A370, con una frecuencia tipo H, según la norma ASTM A673.

36 de 392

Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-001

El diseño de la fundación debe considerar que el perno de anclaje se embebe en


el primer hormigón, por lo cual debe usarse plantillas de posicionamiento
firmemente sujetas. Una opción es la instalación de pernos removibles, para lo
cual el sistema de fijación de igual forma debe ser instalado en el primer hormigón
de la fundación. No se acepta diseños de pernos instalados después de
hormigonar la fundación.

12.2.4.SOLDADURA

En las uniones soldadas se debe especificar un electrodo adecuado al tipo de


acero y al tipo de unión, de acuerdo con lo indicado en "Structural Welding Code",
AWS, última edición.

12.3. UNIONES

En general las uniones en taller serán soldadas. Las uniones de terreno serán de
preferencia apernadas. En casos especiales se aceptará soldadura en terreno,
debiéndose prever pernos adicionales para el montaje.

Las uniones con pernos de alta resistencia se diseñarán tipo fricción con
coeficiente de fricción 0.35. Además deberán verificarse como tipo aplastamiento.

El apriete de los pernos se hará de acuerdo a la norma RCSC “Specification for


structural joints using ASTM A325 or A490 bolts”. Los pernos que requieran
pretensión completa serán explícitamente indicados en los planos.

Los pernos de alta resistencia serán de diámetro igual o superior a 16 mm (5/8").


Para evitar problemas durante el montaje no se aceptarán pernos de igual
diámetro y diferente calidad.

Se debe entregar memoria de cálculo de las uniones.

37 de 392

Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-001

12.4. ESBELTECES MÁXIMAS

Las esbelteces máximas que se pueden considerar en el diseño son las


siguientes:

kl/r
 Columnas 1,5π√ (E/Fy)
 Otros elementos en compresión 1,5π√ (E/Fy)
 Elementos en tracción 240
 Arriostramiento que resista carga sísmica 1,5π√ (E/Fy)

Donde:
l: largo real entre arriostramientos
k: coeficiente de longitud efectiva
r: radio de giro

12.5. PERFILES MÍNIMOS

Los perfiles mínimos que se deberán usar en los marcos de las estructuras serán
los siguientes:

Elemento Perfil AISC Perfil Perfiles KS


ICHA
Perfiles W en elementos principales W 8x10 IN H200x100x5.5x8
de marcos. 20x15.3
Perfiles W en columnas W 10x33 IN H200X200X8X12
25x46.6
Angulares dobles usados en 2L 2L L 75x75x6
contravención. 3”x3”x1/4” 75x75x6
Elementos verticales en estructuras L L L 75x75x6
secundarias y colgadores 3”x3”x1/4” 75x75x6

Espesor mínimo de plancha será 6mm.

12.6. DEFORMACIONES MÁXIMAS

Las deformaciones máximas admisibles serán las siguientes:

– Vigas de piso: 1/300 de la luz.


– Vigas de Techo: 1/200 de la luz
38 de 392

Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-001

– Paneles metálicos
 Vertical: 1/240 de la luz.
1/960 de la luz con un máximo de
10mm en el caso de paneles
vidriados.
 Horizontal: 1/180 de la luz.
1/360 de la luz con un máximo de
35mm en el caso de paneles
vidriados.
– Enrejados: 1/700 de la luz.
– Columnas: Según NCh 2369 para cargas
sísmicas o viento.

– Soportes de grúas, rieles y monorrieles:


o Vertical: 1/1000 de la luz, sin considerar
impacto en la nave de turbinas.
o Horizontal: 1/400 de la luz en todos los casos.

Se debe tener presente que para el cálculo de deformaciones en las


combinaciones ASD que contienen el estado de carga sísmico (E), éstas se deben
determinar considerando lo descrito en 7.4.6.

Las deformaciones de las estructuras debidas a cualquier combinación de cargas


deben ser compatibles con la estabilidad y condiciones de apoyo permanente
necesarias para la integridad de los equipos eléctricos y mecánicos.

12.7. PERNOS DE ANCLAJE Y LLAVES DE CORTE

Las columnas sometidas a carga sísmica deben diseñarse con doble placa base
según lo estipulado en el punto 8.6.2 de la norma chilena NCh 2369.

Las llaves de corte se deben disponer en las placas bases de las columnas. Las
llaves de corte deben resistir la totalidad del esfuerzo de corte basal. El hormigón y
las armaduras de los pedestales de las fundaciones deben proporcionar una
resistencia mayor a la de los pernos de anclaje y llaves de corte.

Los pernos de anclaje no deberán soportar esfuerzos de corte.

Anclajes, llaves de corte

La filosofía de diseño en el diseño de anclajes y llaves de corte es asegurar modos


de falla dúctil.

39 de 392

Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-001

Pernos:

Comprobación que la resistencia del hormigón (en pedestal o losa de fundación)


sea superior a la de los pernos. Para esto se chequean los siguientes puntos
(según código ACI 318-08):

- Resistencia del acero de un anclaje en tracción

- Resistencia al arrancamiento del concreto de un anclaje en tracción

- Resistencia a la extracción por deslizamiento de un anclaje en tracción

- Resistencia al desprendimiento lateral del concreto

Llave de corte:

Comprobación de que la resistencia del hormigón (en pedestal o losa de


fundación) sea superior a la de la llave de corte. Para esto se chequean los
siguientes puntos:

- Modo de falla de resistencia a corte

- Modo de falla de resistencia a flexión (global y en ala)

- Modo de falla de aplastamiento del hormigón

- Capacidad del cono de falla del hormigón (según Design Guide #1 de AISC)

13. ESTIPULACIONES DE DISEÑO PARA OTROS MATERIALES O


ESTRUCTURAS

Para estos diseños se utilizarán las normas chilenas, en el caso de ausencia de


ellas, se usarán normas de reconocido prestigio internacional, previa autorización
de ENDESA.

40 de 392

Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-001

ANEXO 1: CRITERIOS DE DISEÑO ESPECIFICOS PARA


ESTANQUES

41 de 392

Revisión F
TOTAL 17 HOJAS
DESIGN CRITERIA FOR TANK
(Incluyendo Portada)

PROPOSITO

Para Revisión
 NOMBRE CONTRATO EPC POR EL SISTEMA DE
PROYECTO DESULFURIZACION DE GASES - FGD - PARA
LA CENTRAL TARAPACÁ Para Aprobación

 NOMBRE FGD CENTRAL TARAPACÁ Para Construcción


SISTEMA
Para Oferta
 N° DOCUMENTO DCTO413-C8-VVT-000-002
Para Información
 TITULO DESIGN CRITERIA FOR TANK

 CLIENTE ENDESA S.A.

F 29-12-2014 JCR VBS NCR Para Aprobación

E 22-12-2014 JCR VBS NCR Para Aprobación

D 25-11-2014 JCR VBS NCR Para Aprobación

C 27-10-2014 JCR VBS NCR Para Aprobación

B 30-09-2014 JCR VBS NCR Para Aprobación

A 24-09-2014 JCR VBS NCR Coordinación Interna - - -

PREP. REV. APR. REV. REV. APR.


Rev
FECHA DESCRIPCION
.
STX HI ENDESA S.A.

PROPIETARIO:

CONTRATISTA:
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-002

DESIGN CRITERIA FOR TANK

Rev. F

43
Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-002

Contents

1 INTRODUCTION
1.1 Location
1.2 Weather
1.3 Scope

2 STRUCTURAL DESIGN CRITERIA


2.1 Design Code and Reference
2.2 Materials
2.3 Structural Analysis and Design Program

3 DESIGN LOADS
3.1 Dead Load
3.2 Live Load
3.3 Thermal Load
3.4 Wind Load
3.5 Earthquake Load
3.6 Load Combination

4 CALCULATION NOTE
4.1 Tank Design

44
Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-002

1. INTRODUCTION
1.1 Location
The Tarapacá Thermal Power Plant (158 MW), henceforth the Power Plant, owned by Compañía
Eléctrica Tarapacá S.A., hereinafter CELTA S.A or CELTA, is located on the I Region of Chile,
approximately 60km south of Iquique, by the coast, on the area known as Punta Patache.

1.2 Weather
Weather conditions in the sector are as follows:
Barometric Pressure(Average): 1,015 millibars
Ambient Temperature: Maximum 31.3℃, Minimum 8℃
Relative Humidity(Mean): 78%

1.3 Scope
This is design criteria for Tank.

45
Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-002

2. STRUCTURAL DESIGN CRITERIA


The structural design criteria in this report were defined according to Technical Specification.

2.1 Design Code and Reference


Code Code & Reference Remarks
Earthquake-Resistant Design of Industrial Structures and
NCh 2369 Seismic Design
Facilities
ETG 1015 General Technical Specifications – Seismic Design Seismic Design
NCh 432 Structural Design – Wind Loads Wind Load
Structural Design – General Dispositions and Combinations
NCh 3171 Load Combination
of Load
ASCE 7-05 Minimum Design Loads for Building and Other Structures Load Combination
AISC 360-05 Specification for Structural Steel Buildings Steel Design
ACI 318-08 Building Code Requirements for Structural Concrete Anchoring to Concrete
API 650 Welded Steel Tanks for Oil Storage TANK Design

2.2 Materials
Tensile Modulus of
Standard Symbol Yield Strength Remarks
Strength Elasticity
Structural Steel /
KS D 3503 235 MPa (t ≤ 40mm)
SS 400 400 MPa 200,000 MPa Anchor Bolt / Duct
JIS G 3101 215 MPa (t > 40mm)
Casing
KS D 3515 315 MPa (t ≤ 40mm)
SS 490 490 MPa 200,000 MPa Structural Steel
JIS G 3106 295 MPa (t > 40mm)
ASTM A36 250 MPa 400 MPa 200,000 MPa Anchor Bolt

Standard Symbol Nominal Tensile Stress Nominal Shear Stress Remarks

KS B 1010 F10T 736 MPa 392 MPa


High Strength Bolt /
Torque Shear Bolt
ASTM A325 620 MPa 330 MPa
ASTM A490 780 MPa 414 MPa

 Friction Coefficent 0.35 : Class A Surface (unpainted clean mill scale steel surface or surface
with Class A coatings blast-cleaned steel and hot-dipped galvanized and roughened surfaces)

46
Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-002

Material properties in operation temperature (180ºC) (ASME 2010U, Y-1, TM-1)

Modulus of
Symbol Yield Strength Tensile Strength Remarks
Elasticity

SS 400 204 MPa 400 MPa 193.200 MPa SA-36

2.3 Structural Analysis and Design Program


Software Program Code & Reference Remarks
3D Static & Dynamic Analysis -
SAP 2000
Member Design

SAFE Foundation Analysis -

47
Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-002

3. DESIGN LOADS

3.1 Dead Load (D)


Dead load is the load due to the permanent weight of all structural and nonstructural components of a
construction, including thermal insulation, ladders and others.

Item Density or Load Remark


7,850 kg/m3
Steel SS 400, SM 490
(=76.98 kN/m3)
50 kg/m2
Grating ARRIGONI ARS-5 33 kg/m2.
(=0.49 kN/m2)
100 kg/m3
Insulation
(=0.98 kN/m3)

3.2 Live Load (L , L_ and Lr)


It shall be included in this load category, the content of tanks, silos, hoppers, ducting, mobile and
transient loads and weight of people, equipment and tools, and other material agglomerations.
Live load is calculated according to Technical Specification.

Item Load Remark


100 kg/m2
Roof not exposed to traffic Lr -
(= 0.98 kN/m2)
Atomizer Feed Tank Density : 1.36 tonf/m3
Lime Slurry Storage Tank Density : 1.15 tonf/m3
Recycle Ash Slurry Storage Tank Density : 1.36 tonf/m3
-
Recycle Ash Slurry Mixing Tank Density : 1.36 tonf/m3
SDA Make-Up Water Tank Density : 1.0 tonf/m3
Seawater Tank Density : 1.023 tonf/m3

* All tanks should be verified for water test condition (Density : 1.0 ton/m3, Height : Full)

48
Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-002

3.3 Thermal Load (T)

3.3.1 External Temperature


Effect of temperature on the structure, due to climatic conditions of the area
Metal structures for temperature variation depends on local conditions, but it will not be less than
±25℃.

3.3.2 Liquid Temperature (Tg, In case of Lime Slurry Storage Tank)


It shall be considered the effect of high temperatures of gas flow, per process. The operation
temperature is 50℃

3.3.3 Strain due to the Temperature

Where,
α = 1.2×10-5 /℃, coefficient of thermal expansion
∆T = ±25℃ (Steel exposed to ambient)
∆T = +50℃ (In case of Lime Slurry Storage Tank)

49
Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-002

3.4 Wind Load (WX, WY)


Wind load is calculated based on NCh 432 Table 1.

Structures located in open country, facing the ocean, or locations under similar conditions, in the
judgment of the Reviewing Authority

Height above the NCh 432 Chapter 6.5


Basic pressure, q Basic pressure, q
ground ×1.2
[kg/m2] [kPa]
[m] [kPa]
0 70 0.69 0.82
4 70 0.69 0.82
7 95 0.93 1.12
10 106 1.04 1.25
15 118 1.16 1.39
20 126 1.24 1.48
30 137 1.34 1.61
40 145 1.42 1.71
50 151 1.48 1.78
75 163 1.60 1.92
100 170 1.67 2.00
150 182 1.78 2.14
200 191 1.87 2.25
300 209 2.05 2.46

50
Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-002

3.5 Earthquake Load (EX, EY, EZ)

3.5.1 Earthquake Load


For all matters relating to the design of ponds of liquid containers supported on floor (Tanks) must
follow the rules specified in API650 design, plus all the considerations specified in section 11.8 of
NCh2369, with the following clarification of its provisions:

• 11.8 (General Philosophy): When this point forward spectrum or (horizontal) seismic coefficient
NCh2369 item 5, you must use the specter of ETG1015.
• 11.8.2: API 650 is used.
• 11.8.5: The determination of the hydrodynamic masses and periods associated with the impulsive
and convective modes of response must be made as specified in API650 design standards.
• 11.8.8: Spectral seismic design acceleration or impulsively coefficient for horizontal seismic action
set should equal the ETG1015 spectrum multiplied by 0.8, for ξ = 0.02 in the case of steel tanks, and
ξ = 0.03 in the case of concrete tanks (for example, in the case of steel would be 1.37 * 0.8 / R).
Spectral or seismic design acceleration mode convective coefficient for horizontal seismic action
should be determined according to the equation of the hyperbola of the ETG 1015, multiplied by 0.8,
whereas a ratio of damping ξ = 0.005; in any case this value cannot be less than 0.10 Ao / g (0.10 *
0.4 / g).

3.5.1.1 Earthquake action for horizontal direction


The acceleration at support level of the structure shall be determined by Midas Analysis.

3.5.1.2 Earthquake action for vertical direction


The vertical earthquake action is considered as following:

According to point 11.8.9 NCh 2369, 2/3 of the impulsive mode coefficient.

3.5.2 Methods of Analysis


In order to compute the forces and displacements in a given structural system when subjected to the
earthquake action, a static analysis shell be performed.

51
Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-002

3.6 Load Combination

3.6.1 Basic Load Case


D Dead Load
T1 Thermal Load (∆T = +25℃ in case of steel exposed to ambient, ∆T = +50℃ in case of Lime
Slurry Storage Tank)
T2 Thermal Load (∆T = -25℃ in case of steel exposed to ambient, ∆T = +50℃ in case of Lime
Slurry Storage Tank)
T3 Thermal Load (∆T = +50℃ in case of Lime Slurry Storage Tank)
T4 Thermal Load (∆T = +25℃ in case of steel exposed to ambient)
T5 Thermal Load (∆T = -25℃ in case of steel exposed to ambient)
L Live Load
Lr Roof live load not exposed to traffic
WX Wind Load X direction
WY Wind Load Y direction
EX Earthquake Load X direction
EY Earthquake Load Y direction
EZ Earthquake Load Vertical direction

3.6.2 ASD Load Combination (for TANK)


The ASD load combinations shall take into account the earthquake load in Technical Specification.
Technical Specification considered a nominal load, so it must be amplified by a factor 1.0.

No. Case Name Description


1 sLCB1 (D + T1)
2 sLCB2 (D + T1) + L
3 sLCB3 (D + T1) + Lr
4 sLCB4 (D + T1) + 0.75L+0.75Lr
5 sLCB5 (D + T1) + WX
6 sLCB6 (D + T1) + WY
7 sLCB7 (D + T1) + EX + EZ
8 sLCB8 (D + T1) + EY + EZ
9 sLCB9 (D + T1) + 0.75WX + 0.75L + 0.75Lr
10 sLCB10 (D + T1) + 0.75WY + 0.75L + 0.75Lr

52
Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-002

11 sLCB11 (D + T1) + 0.75(EX + EZ) + 0.75L


12 sLCB12 (D + T1) + 0.75(EY + EZ) + 0.75L
13 sLCB13 0.6(D+T1) + WX
14 sLCB14 0.6(D+T1) + WY
15 sLCB15 0.6(D + T1) + EX + EZ
16 sLCB16 0.6(D + T1) + EY + EZ
17 sLCB17 (D + T2)
18 sLCB18 (D + T2) + L
19 sLCB19 (D + T2) + Lr
20 sLCB20 (D + T2) + 0.75L+0.75Lr
21 sLCB21 (D + T2) + WX
22 sLCB22 (D + T2) + WY
23 sLCB23 (D + T2) + EX + EZ
24 sLCB24 (D + T2) + EY + EZ
25 sLCB25 (D + T2) + 0.75WX + 0.75L+0.75Lr
26 sLCB26 (D + T2) + 0.75WY + 0.75L+0.75Lr
27 sLCB27 (D + T2) + 0.75(EX + EZ) + 0.75L
28 sLCB28 (D + T2) + 0.75(EY + EZ) + 0.75L
29 sLCB29 0.6(D+T2) + WX
30 sLCB30 0.6(D+T2) + WY
31 sLCB31 0.6(D + T2) + EX + EZ
32 sLCB32 0.6(D + T2) + EY + EZ
33 sLCB33 (D + T3)
34 sLCB34 (D + T3) + L
35 sLCB35 (D + T3) + Lr
36 sLCB36 (D + T3) + 0.75L+0.75Lr
37 sLCB37 (D + T3) + WX
38 sLCB38 (D + T3) + WY
39 sLCB39 (D + T3) + EX + EZ
40 sLCB40 (D + T3) + EY + EZ
41 sLCB41 (D + T3) + 0.75WX + 0.75L + 0.75Lr
42 sLCB42 (D + T3) + 0.75WY + 0.75L + 0.75Lr

53
Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-002

43 sLCB43 (D + T3) + 0.75(EX + EZ) + 0.75L


44 sLCB44 (D + T3) + 0.75(EY + EZ) + 0.75L
45 sLCB45 0.6(D+T3) + WX
46 sLCB46 0.6(D+T3) + WY
47 sLCB47 0.6(D + T3) + EX + EZ
48 sLCB48 0.6(D + T3) + EY + EZ
49 sLCB49 (D + T4)
50 sLCB50 (D + T4) + L
51 sLCB51 (D + T4) + Lr
52 sLCB52 (D + T4) + 0.75L + 0.75Lr
53 sLCB53 (D + T4) + WX
54 sLCB54 (D + T4) + WY
55 sLCB55 (D + T4) + EX + EZ
56 sLCB56 (D + T4) + EY + EZ
57 sLCB57 (D + T4) + 0.75WX + 0.75L + 0.75Lr
58 sLCB58 (D + T4) + 0.75WY + 0.75L + 0.75Lr
59 sLCB59 (D + T4) + 0.75(EX + EZ) + 0.75L
60 sLCB60 (D + T4) + 0.75(EY + EZ) + 0.75L
61 sLCB61 0.6(D+T4) + WX
62 sLCB62 0.6(D+T4) + WY
63 sLCB63 0.6(D + T4) + EX + EZ
64 sLCB64 0.6(D + T4) + EY + EZ
65 sLCB65 (D + T5)
66 sLCB66 (D + T5) + L
67 sLCB67 (D + T5) + Lr
68 sLCB68 (D + T5) + 0.75L + 0.75Lr
69 sLCB69 (D + T5) + WX
70 sLCB70 (D + T5) + WY
71 sLCB71 (D + T5) + EX + EZ
72 sLCB72 (D + T5) + EY + EZ
73 sLCB73 (D + T5) + 0.75WX + 0.75L + 0.75Lr
74 sLCB74 (D + T5) + 0.75WY + 0.75L + 0.75Lr

54
Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-002

75 sLCB75 (D + T5) + 0.75(EX + EZ) + 0.75L


76 sLCB76 (D + T5) + 0.75(EY + EZ) + 0.75L
77 sLCB77 0.6(D+T5) + WX
78 sLCB78 0.6(D+T5) + WY
79 sLCB79 0.6(D + T5) + EX + EZ
80 sLCB80 0.6(D + T5) + EY + EZ
81 sLCB81 D
82 sLCB82 D+L
83 sLCB83 D + Lr
84 sLCB84 D + 0.75L + 0.75Lr
85 sLCB85 D + WX
86 sLCB86 D + WY
87 sLCB87 D + EX + EZ
88 sLCB88 D + EY + EZ
89 sLCB89 D + 0.75WX + 0.75L + 0.75Lr
90 sLCB90 D + 0.75WY + 0.75L + 0.75Lr
91 sLCB91 D + 0.75(EX + EZ) + 0.75L
92 sLCB92 D + 0.75(EY + EZ) + 0.75L
93 sLCB93 0.6D + WX
94 sLCB94 0.6D + WY
95 sLCB95 0.6D + EX + EZ
96 sLCB96 0.6D + EY + EZ

55
Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-002

4. CALCULATION NOTE

56
Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-002

4.1 Tank Design

4.1.1 Design Load


Dead Load, Live Load, Seismic Load, Wind Load

4.1.2 Schematic Drawing

4.1.3 Verification (Only by Hand Calculation according to API 650, ETG1015, NCh 432, ACI318-
08)
1) Thickness of Bottom Plate
- Bottom Plate Thickness ≥ Min. Thickness + Corrosion Allowance
2) Requirement of Wind Stiffener
- H1 = 9.47 x t x √(t/D)3 > H : Stiffener does not required.
3) Roof Rafter Design
- Maximum Rafter Spacing l = 0.6 π
- Minimum Number of Rafter Nmin = (π x D) / l
- Roof Plate Thickness ≥ Min. Thickness + Corrosion Allowance
- Bending Stress of Rafter Mmax / σall < Zi......(OK)
- Displacement δ < L/300......(OK)
4) Design for Wind Load
- Design Wind Load Fw = Max (q × D0 × Hm(NCh 432), 87.76 × (V / 160)2 × D0 × Hm (API650))
- Overturning Moment Mw = Fw x Hm / 2

57
Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-002

- Resistance Moment Rw = 2 / 3 x (W1 x Do / 2)


- Mw < Rw......(OK)
5) Design for Earthquake Load
- Overturning Moment Me = Z × I × [C1 × Ws × Xs + C1 × Wr × Ht + C1 × W1 × X1 + C2 × W2 × X2]
- Shell Compression σc = (wt (1+Av) + 1.273 M / D2 ) / ts
- Allowance Shell Compression Fc = Min (Fc1, Fc2)
Fc1 = 83 × ts / D (If GHD2 / t2 ≥ 44), 83 ts / (2.5D) + 7.5 √(GH) < 0.5 Fty (If GHD2 / t2 < 44 )
Fc2 = 135 Fy x t / D < 0.8 Fy
- σc < Fc......(OK)
6) Anchor Bolt Design
- Design Load Nua = 0.9 x Dead Load / n - 1.4 (Me / D) – 1.4 (V x 2/3) / n
- Steel Strength of Anchor in Tension 0.75 Φ Nsa = 0.75 Φ (Ase x futa) > Nua......(OK)
- Concrete Breakout Strength of Anchor in Tension 0.75 Φ Nsb = 0.75 Φ (ANc / ANco × Ψed,N × Ψc,N ×
Ψcp, N × Nb) > Nua......(OK)
7) Embedded Depth and Width of the Shear Key
- Φ Vn = 0.85 Φ fc A > V / n......(Concrete bearing)
8) Thickness of Shear Key
- treq = √ (ß x q x b2 / 0.75 Fy) (ß : derived by Roak’s Table)
- treq > t ......(OK)
9) Design of Rib Plate
- Height of Rib Plate : 8d of 250mm
- Ta = Ase x fut
- Φ Pn = Φ Ag Fcr > Ta......(OK)
10) Design of Upper Plate
M : Bending Moment due to the anchor bolt full capacity
- Φ Fy Z = Φ Fy u t2 / 4 > M......(OK)
11) Design of Anchor Plate
M : Bending Moment due to the anchor bolt full capacity
- Φ Fy Z = Φ Fy u t2 / 4 > M......(OK)
12) Beam Web Crippling (If necessary)
- ΦRn = Φ 0.8 tw2 [1 + 3(N / d) (tw / tf)1.5] √(E Fyw tf / tw) > Ru......(OK)
13) Beam Web Local Yielding (If necessary)
- ΦRn = (5k + N) Fyw tw > Ru......(OK)

58
Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-001

ANEXO 2: CRITERIOS DE DISEÑO ESPECIFICOS PARA SDA

59 de 392

Revisión F
DESIGN CRITERIA FOR SDA SUPPORT TOTAL 85 HOJAS
STRUCTURE AND CASING (Incluyendo Portada)

PROPOSITO

Para Revisión
 NOMBRE CONTRATO EPC POR EL SISTEMA DE
PROYECTO DESULFURIZACION DE GASES - FGD - PARA
LA CENTRAL TARAPACÁ Para Aprobación

 NOMBRE FGD CENTRAL TARAPACÁ Para Construcción


SISTEMA
Para Oferta
 N° DOCUMENTO DCTO413-C8-VVT-000-003
Para Información
 TITULO DESIGN CRITERIA FOR SDA SUPPORT
STRUCTURE AND CASING

 CLIENTE ENDESA S.A.

F 29-12-2014 JCR VBS NCR Para Aprobación

E 22-12-2014 JCR VBS NCR Para Aprobación

D 25-11-2014 JCR VBS NCR Para Aprobación

C 27-10-2014 JCR VBS NCR Para Aprobación

B 30/09/2014 JCR VBS NCR Para Aprobación

A 24-09-2014 JCR VBS NCR Coordinación Interna - - -

PREP. REV. APR. REV. REV. APR.


Rev
FECHA DESCRIPCION
.
STX HI ENDESA S.A.

PROPIETARIO:

CONTRATISTA:
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-003

DESIGN CRITERIA FOR SDA


SUPPORT STRUCTURE AND CASING

Rev. F

Revisión F 61
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-003

Contents

1 INTRODUCTION
1.1 Location
1.2 Weather
1.3 Scope

2 STRUCTURAL DESIGN CRITERIA


2.1 Design Code and Reference
2.2 Materials
2.3 Structural Analysis and Design Program

3 DESIGN LOADS
3.1 Dead Load
3.2 Live Load
3.3 Thermal Load
3.4 Pressure Load
3.5 Wind Load
3.6 Earthquake Load
3.7 Load Combination

4 STRUCTURAL SYSTEM
4.1 Structural System and Analysis Condition
4.2 Base Plate and Anchor System

5 STRUCTURAL ANALYSIS
5.1 Base Shear and Equivalent Mass
5.2 Natural Vibration Mode
5.3 Support Reaction
5.4 Displacement

Revisión F 62
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-003

6 MEMBER DESIGN
6.1 Column Design
6.2 Beam and Girder Design
6.3 Brace Design
6.4 Connection Design
6.5 Base Plate and Anchor Bolt Design
6.6 Connection between SDA and Structure

7 CASING CALCULATION NOTE


7.1 SDA Casing Design

Revisión F 63
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-003

1. INTRODUCTION
1.1 Location
The Tarapacá Thermal Power Plant (158 MW), henceforth the Power Plant, owned by Compañía
Eléctrica Tarapacá S.A., hereinafter CELTA S.A or CELTA, is located on the I Region of Chile,
approximately 60km south of Iquique, by the coast, on the area known as Punta Patache.

1.2 Weather
Weather conditions in the sector are as follows:
Barometric Pressure(Average): 1,015 millibars
Ambient Temperature: Maximum 31.3℃, Minimum 8℃
Relative Humidity(Mean): 78%

1.3 Scope
This is design criteria for SDA support structure and casing.

Revisión F 64
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-003

2. STRUCTURAL DESIGN CRITERIA


The structural design criteria in this report were defined according to Technical Specification.

2.1 Design Code and Reference


Code Code & Reference Remarks
Earthquake-Resistant Design of Industrial Structures and
NCh 2369 Seismic Design
Facilities
ETG 1015 General Technical Specifications – Seismic Design Seismic Design
NCh 432 Structural Design – Wind Loads Wind Load
Structural Design – General Dispositions and Combinations of
NCh 3171 Load Combination
Load
ASCE 7-05 Minimum Design Loads for Building and Other Structures Load Combination
AISC 360-05 Specification for Structural Steel Buildings Steel Design
Anchoring to
ACI 318-08 Building Code Requirements for Structural Concrete
Concrete
EN 1991-4 Euro code 1 – Actions on Structures – Part4 : Silo and Tanks SDA Design Loads
EN 1993-4-1 Euro code 3 – Design of Steel Structures – Part4 : Silos SDA Design
2010 ASME Boiler & Pressure Vessel Code Section Ⅱ Part
ASME 2010 Material Properties
D : Properties (Metric) Materials

2.2 Materials
Tensile Modulus of
Standard Symbol Yield Strength Remarks
Strength Elasticity
Structural Steel /
KS D 3503 235 MPa (t ≤ 40mm)
SS 400 400 MPa 200,000 MPa Anchor Bolt / SDA
JIS G 3101 215 MPa (t > 40mm)
Casing
KS D 3515 315 MPa (t ≤ 40mm)
SM490 490 MPa 200,000 MPa Structural Steel
JIS G 3106 295 MPa (t > 40mm)
ASTM A36 250 MPa 400 MPa 200,000 MPa Anchor Bolt

Revisión F 65
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-003

Standard Symbol Nominal Tensile Stress Nominal Shear Stress Remarks


KS B 1010 F10T 736 MPa 392 MPa
High Strength Bolt
ASTM A325 620 MPa 330 MPa
/ Torque Shear Bolt
ASTM A490 780 MPa 414 MPa

* Friction Coefficient 0.35 : Class A surface ( unpainted clean mill scale steel surfaces or surfaces with

Class A coatings on blast-cleaned steel and hot-dipped galvanized and roughened surfaces)
Material properties in operation temperature (180℃) (ASME 2010 U, Y-1, TM-1)
Modulus of
Symbol Yield Strength Tensile Strength Remarks
Elasticity
z 204 MPa 400 MPa 193,200 MPa SA-36

The material properties for determine the required strength of element and connection are included
KBC 2009 (Korean Building Code 2009) section 0713.6.2.

In section 0713.6.2 of KBC 2009 (Original)

Revisión F 66
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-003

In section 0713.6.2 of KBC 2009 (Translation)


0713.6.2 Material Properties for determine the required strength of member and connection
(1) When estimate the required strength of each member (member or connection) by the provision of
this section, the required strength should be calculated based on the expected yield strength Ry Fy
of connected member. In here, Fy is the minimum yield strength of connected member and Ry is
the ratio of expected yield strength and minimum yield strength.

(2) The design strength ФRn should be at least the required strength. When estimate the nominal

Strength Rn for fracture and yield state, the expected tensile strength Rt Fu and expected yield
Strength Ry Fy can be used instead of Fu and Fy.
(3) The values of Ry and Rt are in the table 0713.6.1.

<Table 0713.6.1> The values of Ry and Rt for each type of steel

Application Ry Rt
KS SS400, SSC400, SWH400,
KS STK400, STK490, SPSR400, SPSR490, 1.3 1.2
Structural Rolled Shapes STKN400, STKN490
Steel and Cold Formed
Steel KS SM400, SM490, SM520
KS SPAR295, SPAP235, SPAP325, 1.2 1.2
SCW490-CF

Revisión F 67
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-003

KS SHN400, SHN490 1.1 1.1


KS SS400 1.3 1.2
KS SM490, SM490TMC, SM520,
SM520TMC, SM570, SM570TMC, 1.2 1.2
Plate KS SMA400, SMA490, SMA570
KS SN400, SN490 1.1 1.1
HSA800 1.1 1.1

2.3 Structural Analysis and Design Program


Software Program Code & Reference Remarks
3D Static & Dynamic Analysis -
SAP 2000
Member Design

SAFE Foundation Analysis

Revisión F 68
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-003

3. DESIGN LOADS
3.1 Dead Load (D)
Dead load is the load due to the permanent weight of all structural and nonstructural components of a
construction, including thermal insulation, ladders and others.

Item Density or Load Remark


7,850 kg/m 3
Steel SS 400, SM 490
(=76.98 kN/m3)
50 kg/m2
Grating ARRIGONI ARS-5 33 kg/m2.
(=0.49 kN/m2)
100 kg/m3
Insulation -
(=0.98 kN/m3)

3.2 Live Load (L , L_ and Lr)

It shall be included in this load category, the content of tanks, silos, hoppers, ducting, mobile and
transient loads and weight of people, equipment and tools, and other material agglomerations.
Live load is calculated according to Technical Specification.

Item Load Remark


400kg/m2
Offices, Hallways, Stairs (L) -
(= 3.92 kN/m2)
100 kg/m2
Roof not exposed to traffic (Lr) -
(= 0.98 kN/m2)
Density : 0.8 tonf/m3 (for volume) It should not be
1.25 tonf/m3 (for structural design) considered the 0.5
Ash with Lime (L_EM)
Total Volume (Emergency Condition) : Later factor in load
Total Weight (Emergency Condition) : Later combination.

The material Properties of Ash with Lime (according to the EN 1991-4 Eurocode 1 – Actions on
Structures – Part4 : Silo and Tanks)

Revisión F 69
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-003

3.3 Thermal Load (T)

3.3.1 External Temperature (Te)


Effect of temperature on the structure, due to climatic conditions of the area
Metal structures for temperature variation depends on local conditions, but it will not be less than
±25℃.

3.3.2 Gas Temperature (Tg)


It shall be considered the effect of high temperatures of gas flow, per process. The operation
temperature is 180℃

3.3.3 Strain due to the Temperature

Where,
α = 1.2×10-5 /℃, coefficient of thermal expansion
∆T = ±25℃ (Steel exposed to ambient)
∆T = +180℃ (Casing which contacts with gas)

3.4 Pressure Load (F)


The pressure load is a negative pressure which generate inside the SDA. The following pressure load
is used.
- SDA Design Pressure: -400 mmH20 (- 0.040 kg/cm2)

Revisión F 70
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-003

3.5 Wind Load (WX, WY)


Wind load is calculated based on NCh 432 Table 1.

Structures located in open country, facing the ocean, or locations under similar conditions, in the
judgment of the Reviewing Authority

Height above the NCh 432 Chapter 6.5


Basic pressure, q Basic pressure, q
ground ×1.2
[kg/m2] [kPa]
[m] [kPa]
0 70 0.69 0.82
4 70 0.69 0.82
7 95 0.93 1.12
10 106 1.04 1.25
15 118 1.16 1.39
20 126 1.24 1.48
30 137 1.34 1.61
40 145 1.42 1.71
50 151 1.48 1.78
75 163 1.60 1.92
100 170 1.67 2.00
150 182 1.78 2.14
200 191 1.87 2.25
300 209 2.05 2.46

Revisión F 71
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-003

3.6 Earthquake Load (EX, EY, EZ)

3.6.1 Earthquake Load


The total base shear shall be computed from the expression.
V = C X W ≥ 0.12 W
Where,
V Base shear
C Seismic coefficient, obtained directly from the design spectrum.
W Total seismic weight of the structure or system, computed as the sum of dead load of
structure and equipment

3.6.1.1 Earthquake action for horizontal direction


The design spectrum is calculated based on ETG1015 figure 1.
Applied coefficients are as follows:
Ground Acceleration a/g = 0.4
Response Modification Factors: R = 4.0
Equivalent viscous damping: ζ = 0.02

3.6.1.2 Earthquake action for vertical direction


The vertical earthquake shall be considered according to Section 5.5 of NCh 2369 Standard, with
seismic coefficient equal to 2 A0 / 3g.

Revisión F 72
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-003

Coordinates of the corner point for a/g = 0.4

ζ T1 T2 A/g
0.005 0.113 0.451 1.472
0.01 0.115 0.461 1.284
0.02 0.119 0.474 1.096
0.03 0.121 0.485 0.984
0.05 0.125 0.499 0.848
0.07 0.128 0.512 0.756
0.10 0.134 0.535 0.656
0.20 0.148 0.591 0.468
Equation of hyperbolic branch:

(T2<=T<=2.5 s)

3.6.2 Methods of Analysis


In order to compute the forces and displacements in a given structural system when subjected to the

Revisión F 73
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-003

earthquake action, a response spectrum analysis shell be performed.

3.6.3 Number of Modes


The analysis shall include a sufficient number of vibration modes for the sum of equivalent masses in
each analysis direction is equal to or higher than 90% of the total mass.

3.6.4 Mode Superposition


In order to obtain an estimate of the maximum values of any response quantity considered in the
analysis, the maximum values of the corresponding responses computed for the individual mode of
vibration shall be combined with the CQC superposition criterion normally called “Complete Quadratic
Combination”, recommended in Chilean code Section 5.4.4 of NCh 2369.
The following expressions summarize the mode superposition procedure:

Where,
S Modal combination
Si , Sj Maximum values of mode contributions i and j
ζ Damping ratio
Ti, Tj Period of mode i and j

3.6.5 Coupling of earthquake action for Support Structure


For the case of dynamic analysis, the requirements of Section 5.1.2 of Chilean code NCh 2369
regarding the effect of the combination of the seismic horizontal components effect are applicable.
This requires that the modal shape and frequencies have to be analyzed and if they are found to be
coupled without a clear or predominant directional acceleration input shall be performed instead of
two independent analyses. This can be implemented by carrying out two different three dimensional
analyses; in each of them the earthquake action input (acceleration spectrum ordinates) shall be
100% of the Project Specification design spectrum in on direction plus 30% of the Project
Specification design spectrum in the orthogonal direction.

Point 5.1.2 of NCh-2369 clearly indicates that it is not necessary to combine the horizontal
components of the seismic action, ie can be analyzed separately for earthquake acting in both
directions considered analysis and design with the unfavorable situation.

Exceptions to this rule structures that have significant torsional irregularities, for which it requires rigid
diaphragms own buildings. The situation is important to consider in the corner columns orthogonal

Revisión F 74
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-003

building rigid frames that share these corner columns. In cases like this should be at 100% overlap in
a direction analysis 30% of the analyzes in the other direction and the same for the other direction
relative to the first. This exception should be applied to irregular structured buildings preferably those
based on rigid frames.

3.6.6 Seismic Mass Percentage for Live Load


Seismic mass percentages are considered according to Technical Specification.
It shall be considered the following percentage of seismic mass for live load:

Section Seismic Mass Percentage (%)

Area of Normal Use, Floor Live Load 25

Roof without Transit 0

Absorber SDA 100

Revisión F 75
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-003

3.7 Load Combination

3.7.1 Basic Load Case


D Dead Load
F Pressure Load
T1 Thermal Load (∆T = +25℃ in case of steel exposed to ambient, ∆T = +180℃ in case of
casing which contacts with gas)
T2 Thermal Load (∆T = -25℃ in case of steel exposed to ambient, ∆T = +180℃ in case of
casing which contacts with gas)
T3 Thermal Load (∆T = +180℃ in case of casing which contacts with gas)
T4 Thermal Load (∆T = +25℃ in case of steel exposed to ambient)
T5 Thermal Load (∆T = -25℃ in case of steel exposed to ambient)
L Live Load
L_ Ash with Lime Load
Lr Roof live load not exposed to traffic
WX Wind Load X direction
WY Wind Load Y direction
EX Earthquake Load X direction
EY Earthquake Load Y direction
EZ Earthquake Load Vertical direction

3.7.2 LRFD Load Combination (for Anchor System and Foundations)


The LRFD load combinations shall take into account the earthquake load in Technical Specification.
Technical Specification considered a nominal load, so it must be amplified by a factor 1.4. as shown in
the following table

No. Case Name Description


1 uLCB1 1.4(D + F + T1)
2 uLCB2 1.2(D + F + T1) + 1.6L + 1.6L_ + 0.5Lr
3 uLCB3 1.2(D + F + T1) + 0.5L + 1.0L_ + 1.6Lr

4 uLCB4 1.2(D + F + T1) + 1.6Lr + 0.8WX


5 uLCB5 1.2(D + F + T1) + 1.6Lr - 0.8WX

6 uLCB6 1.2(D + F + T1) + 1.6Lr + 0.8WY


7 uLCB7 1.2(D + F + T1) + 1.6Lr - 0.8WY

Revisión F 76
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-003

8 uLCB8 1.2(D + F + T1) + 1.6WX + 0.5L + L_ + 0.5Lr


9 uLCB9 1.2(D + F + T1) - 1.6WX + 0.5L + L_ + 0.5Lr
10 uLCB10 1.2(D + F + T1) + 1.6WY + 0.5L + L_ + 0.5Lr
11 uLCB11 1.2(D + F + T1) - 1.6WY + 0.5L + L_ + 0.5Lr
12 uLCB12 1.2(D + F + T1) + 1.4(1.0EX + 0.3EY + 1.0EZ) + 0.5L + 1.0L_
13 uLCB13 1.2(D + F + T1) + 1.4(1.0EX + 0.3EY - 1.0EZ) + 0.5L + 1.0L_
14 uLCB14 1.2(D + F + T1) + 1.4(1.0EX - 0.3EY + 1.0EZ) + 0.5L + 1.0L_
15 uLCB15 1.2(D + F + T1) + 1.4(1.0EX - 0.3EY - 1.0EZ) + 0.5L + 1.0L_
16 uLCB16 1.2(D + F + T1) - 1.4(1.0EX + 0.3EY + 1.0EZ) + 0.5L + 1.0L_
17 uLCB17 1.2(D + F + T1) - 1.4(1.0EX + 0.3EY - 1.0EZ) + 0.5L + 1.0L_
18 uLCB18 1.2(D + F + T1) - 1.4(1.0EX - 0.3EY + 1.0EZ) + 0.5L + 1.0L_
19 uLCB19 1.2(D + F + T1) - 1.4(1.0EX - 0.3EY - 1.0EZ) + 0.5L + 1.0L_
20 uLCB20 1.2(D + F + T1) + 1.4(0.3EX + 1.0EY + 1.0EZ) + 0.5L + 1.0L_
21 uLCB21 1.2(D + F + T1) + 1.4(0.3EX + 1.0EY - 1.0EZ) + 0.5L + 1.0L_
22 uLCB22 1.2(D + F + T1) + 1.4(0.3EX – 1.0EY + 1.0EZ) + 0.5L + 1.0L_
23 uLCB23 1.2(D + F + T1) + 1.4(0.3EX – 1.0EY - 1.0EZ) + 0.5L + 1.0L_
24 uLCB24 1.2(D + F + T1) - 1.4(0.3EX + 1.0EY + 1.0EZ) + 0.5L + 1.0L_
25 uLCB25 1.2(D + F + T1) - 1.4(0.3EX + 1.0EY - 1.0EZ) + 0.5L + 1.0L_
26 uLCB26 1.2(D + F + T1) - 1.4(0.3EX – 1.0EY + 1.0EZ) + 0.5L + 1.0L_
27 uLCB27 1.2(D + F + T1) - 1.4(0.3EX – 1.0EY - 1.0EZ) + 0.5L + 1.0L_
28 uLCB28 0.9(D + T1) + 1.6WX
29 uLCB29 0.9(D + T1) - 1.6WX
30 uLCB30 0.9(D + T1) + 1.6WY
31 uLCB31 0.9(D + T1) - 1.6WY
32 uLCB32 0.9(D + F + T1) + 1.4(1.0EX + 0.3EY + 1.0EZ)
33 uLCB33 0.9(D + F + T1) + 1.4(1.0EX + 0.3EY - 1.0EZ)
34 uLCB34 0.9(D + F + T1) + 1.4(1.0EX - 0.3EY + 1.0EZ)
35 uLCB35 0.9(D + F + T1) + 1.4(1.0EX - 0.3EY - 1.0EZ)
36 uLCB36 0.9(D + F + T1) - 1.4(1.0EX + 0.3EY + 1.0EZ)
37 uLCB37 0.9(D + F + T1) - 1.4(1.0EX + 0.3EY - 1.0EZ)
38 uLCB38 0.9(D + F + T1) - 1.4(1.0EX - 0.3EY + 1.0EZ)
39 uLCB39 0.9(D + F + T1) - 1.4(1.0EX - 0.3EY - 1.0EZ)
40 uLCB40 0.9(D + F + T1) + 1.4(0.3EX + 1.0EY + 1.0EZ)
41 uLCB41 0.9(D + F + T1) + 1.4(0.3EX + 1.0EY - 1.0EZ)

Revisión F 77
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-003

42 uLCB42 0.9(D + F + T1) + 1.4(0.3EX – 1.0EY + 1.0EZ)


43 uLCB43 0.9(D + F + T1) + 1.4(0.3EX – 1.0EY - 1.0EZ)
44 uLCB44 0.9(D + F + T1) - 1.4(0.3EX + 1.0EY + 1.0EZ)
45 uLCB45 0.9(D + F + T1) - 1.4(0.3EX + 1.0EY - 1.0EZ)
46 uLCB46 0.9(D + F + T1) - 1.4(0.3EX – 1.0EY + 1.0EZ)
47 uLCB47 0.9(D + F + T1) - 1.4(0.3EX – 1.0EY - 1.0EZ)
48 uLCB48 1.4(D + F + T2)
49 uLCB49 1.2(D + F + T2) + 1.6L + 1.6L_ + 0.5Lr
50 uLCB50 1.2(D + F + T2) + 0.5L + 1.0L_ + 1.6Lr

51 uLCB51 1.2(D + F + T2) + 1.6Lr + 0.8WX


52 uLCB52 1.2(D + F + T2) + 1.6Lr - 0.8WX

53 uLCB53 1.2(D + F + T2) + 1.6Lr + 0.8WY


54 uLCB54 1.2(D + F + T2) + 1.6Lr - 0.8WY
55 uLCB55 1.2(D + F + T2) + 1.6WX + 0.5L + L_ + 0.5Lr
56 uLCB56 1.2(D + F + T2) - 1.6WX + 0.5L + L_ + 0.5Lr
57 uLCB57 1.2(D + F + T2) + 1.6WY + 0.5L + L_ + 0.5Lr
58 uLCB58 1.2(D + F + T2) - 1.6WY + 0.5L + L_ + 0.5Lr
59 uLCB59 1.2(D + F + T2) + 1.4(1.0EX + 0.3EY + 1.0EZ) + 0.5L + L_
60 uLCB60 1.2(D + F + T2) + 1.4(1.0EX + 0.3EY - 1.0EZ) + 0.5L + L_
61 uLCB61 1.2(D + F + T2) + 1.4(1.0EX - 0.3EY + 1.0EZ) + 0.5L + L_
62 uLCB62 1.2(D + F + T2) + 1.4(1.0EX - 0.3EY - 1.0EZ) + 0.5L + L_
63 uLCB63 1.2(D + F + T2) - 1.4(1.0EX + 0.3EY + 1.0EZ) + 0.5L + L_
64 uLCB64 1.2(D + F + T2) - 1.4(1.0EX + 0.3EY - 1.0EZ) + 0.5L + L_
65 uLCB65 1.2(D + F + T2) - 1.4(1.0EX - 0.3EY + 1.0EZ) + 0.5L + L_
66 uLCB66 1.2(D + F + T2) - 1.4(1.0EX - 0.3EY - 1.0EZ) + 0.5L + L_
67 uLCB67 1.2(D + F + T2) + 1.4(0.3EX + 1.0EY + 1.0EZ) + 0.5L + L_
68 uLCB68 1.2(D + F + T2) + 1.4(0.3EX + 1.0EY - 1.0EZ) + 0.5L + L_
69 uLCB69 1.2(D + F + T2) + 1.4(0.3EX – 1.0EY + 1.0EZ) + 0.5L + L_
70 uLCB70 1.2(D + F + T2) + 1.4(0.3EX – 1.0EY - 1.0EZ) + 0.5L + L_
71 uLCB71 1.2(D + F + T2) - 1.4(0.3EX + 1.0EY + 1.0EZ) + 0.5L + L_
72 uLCB72 1.2(D + F + T2) - 1.4(0.3EX + 1.0EY - 1.0EZ) + 0.5L + L_
73 uLCB73 1.2(D + F + T2) - 1.4(0.3EX – 1.0EY + 1.0EZ) + 0.5L + L_
74 uLCB74 1.2(D + F + T2) - 1.4(0.3EX – 1.0EY - 1.0EZ) + 0.5L + L_

Revisión F 78
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-003

75 uLCB75 0.9(D + T2) + 1.6WX


76 uLCB76 0.9(D + T2) - 1.6WX
77 uLCB77 0.9(D + T2) + 1.6WY
78 uLCB78 0.9(D + T2) - 1.6WY
79 uLCB79 0.9(D + F + T2) + 1.4(1.0EX + 0.3EY + 1.0EZ)
80 uLCB80 0.9(D + F + T2) + 1.4(1.0EX + 0.3EY - 1.0EZ)
81 uLCB81 0.9(D + F + T2) + 1.4(1.0EX - 0.3EY + 1.0EZ)
82 uLCB82 0.9(D + F + T2) + 1.4(1.0EX - 0.3EY - 1.0EZ)
83 uLCB83 0.9(D + F + T2) - 1.4(1.0EX + 0.3EY + 1.0EZ)
84 uLCB84 0.9(D + F + T2) - 1.4(1.0EX + 0.3EY - 1.0EZ)
85 uLCB85 0.9(D + F + T2) - 1.4(1.0EX - 0.3EY + 1.0EZ)
86 uLCB86 0.9(D + F + T2) - 1.4(1.0EX - 0.3EY - 1.0EZ)
87 uLCB87 0.9(D + F + T2) + 1.4(0.3EX + 1.0EY + 1.0EZ)
88 uLCB88 0.9(D + F + T2) + 1.4(0.3EX + 1.0EY - 1.0EZ)
89 uLCB89 0.9(D + F + T2) + 1.4(0.3EX – 1.0EY + 1.0EZ)
90 uLCB90 0.9(D + F + T2) + 1.4(0.3EX – 1.0EY - 1.0EZ)
91 uLCB91 0.9(D + F + T2) - 1.4(0.3EX + 1.0EY + 1.0EZ)
92 uLCB92 0.9(D + F + T2) - 1.4(0.3EX + 1.0EY - 1.0EZ)
93 uLCB93 0.9(D + F + T2) - 1.4(0.3EX – 1.0EY + 1.0EZ)
94 uLCB94 0.9(D + F + T2) - 1.4(0.3EX – 1.0EY - 1.0EZ)
95 uLCB95 1.4(D + F + T3)
96 uLCB96 1.2(D + F + T3) + 1.6L + 1.6L_ + 0.5Lr
97 uLCB97 1.2(D + F + T3) + 0.5L + 1.0L_ + 1.6Lr

98 uLCB98 1.2(D + F + T3) + 1.6Lr + 0.8WX


99 uLCB99 1.2(D + F + T3) + 1.6Lr - 0.8WX

100 uLCB100 1.2(D + F + T3) + 1.6Lr + 0.8WY


101 uLCB101 1.2(D + F + T3) + 1.6Lr - 0.8WY
102 uLCB102 1.2(D + F + T3) + 1.6WX + 0.5L + L_+ 0.5Lr
103 uLCB103 1.2(D + F + T3) - 1.6WX + 0.5L + L_ + 0.5Lr
104 uLCB104 1.2(D + F + T3) + 1.6WY + 0.5L + L_ + 0.5Lr
105 uLCB105 1.2(D + F + T3) - 1.6WY + 0.5L + L_ + 0.5Lr
106 uLCB106 1.2(D + F + T3) + 1.4(1.0EX + 0.3EY + 1.0EZ) + 0.5L + L_
107 uLCB107 1.2(D + F + T3) + 1.4(1.0EX + 0.3EY - 1.0EZ) + 0.5L + L_

Revisión F 79
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-003

108 uLCB108 1.2(D + F + T3) + 1.4(1.0EX - 0.3EY + 1.0EZ) + 0.5L + L_


109 uLCB109 1.2(D + F + T3) + 1.4(1.0EX - 0.3EY - 1.0EZ) + 0.5L + L_
110 uLCB110 1.2(D + F + T3) - 1.4(1.0EX + 0.3EY + 1.0EZ) + 0.5L + L_
111 uLCB111 1.2(D + F + T3) - 1.4(1.0EX + 0.3EY - 1.0EZ) + 0.5L + L_
112 uLCB112 1.2(D + F + T3) - 1.4(1.0EX - 0.3EY + 1.0EZ) + 0.5L + L_
113 uLCB113 1.2(D + F + T3) - 1.4(1.0EX - 0.3EY - 1.0EZ) + 0.5L + L_
114 uLCB114 1.2(D + F + T3) + 1.4(0.3EX + 1.0EY + 1.0EZ) + 0.5L + L_
115 uLCB115 1.2(D + F + T3) + 1.4(0.3EX + 1.0EY - 1.0EZ) + 0.5L + L_
116 uLCB116 1.2(D + F + T3) + 1.4(0.3EX – 1.0EY + 1.0EZ) + 0.5L + L_
117 uLCB117 1.2(D + F + T3) + 1.4(0.3EX – 1.0EY - 1.0EZ) + 0.5L + L_
118 uLCB118 1.2(D + F + T3) - 1.4(0.3EX + 1.0EY + 1.0EZ) + 0.5L + L_
119 uLCB119 1.2(D + F + T3) - 1.4(0.3EX + 1.0EY - 1.0EZ) + 0.5L + L_
120 uLCB120 1.2(D + F + T3) - 1.4(0.3EX – 1.0EY + 1.0EZ) + 0.5L + L_
121 uLCB121 1.2(D + F + T3) - 1.4(0.3EX – 1.0EY - 1.0EZ) + 0.5L + L_
122 uLCB122 0.9(D + T3) + 1.6WX
123 uLCB123 0.9(D + T3) - 1.6WX
124 uLCB124 0.9(D + T3) + 1.6WY
125 uLCB125 0.9(D + T3) - 1.6WY
126 uLCB126 0.9(D + F + T3) + 1.4(1.0EX + 0.3EY + 1.0EZ)
127 uLCB127 0.9(D + F + T3) + 1.4(1.0EX + 0.3EY - 1.0EZ)
128 uLCB128 0.9(D + F + T3) + 1.4(1.0EX - 0.3EY + 1.0EZ)
129 uLCB129 0.9(D + F + T3) + 1.4(1.0EX - 0.3EY - 1.0EZ)
130 uLCB130 0.9(D + F + T3) - 1.4(1.0EX + 0.3EY + 1.0EZ)
131 uLCB131 0.9(D + F + T3) - 1.4(1.0EX + 0.3EY - 1.0EZ)
132 uLCB132 0.9(D + F + T3) - 1.4(1.0EX - 0.3EY + 1.0EZ)
133 uLCB133 0.9(D + F + T3) - 1.4(1.0EX - 0.3EY - 1.0EZ)
134 uLCB134 0.9(D + F + T3) + 1.4(0.3EX + 1.0EY + 1.0EZ)
135 uLCB135 0.9(D + F + T3) + 1.4(0.3EX + 1.0EY - 1.0EZ)
136 uLCB136 0.9(D + F + T3) + 1.4(0.3EX – 1.0EY + 1.0EZ)
137 uLCB137 0.9(D + F + T3) + 1.4(0.3EX – 1.0EY - 1.0EZ)
138 uLCB138 0.9(D + F + T3) - 1.4(0.3EX + 1.0EY + 1.0EZ)
139 uLCB139 0.9(D + F + T3) - 1.4(0.3EX + 1.0EY - 1.0EZ)
140 uLCB140 0.9(D + F + T3) - 1.4(0.3EX – 1.0EY + 1.0EZ)
141 uLCB141 0.9(D + F + T3) - 1.4(0.3EX – 1.0EY - 1.0EZ)

Revisión F 80
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-003

142 uLCB142 1.4(D + F + T4)


143 uLCB143 1.2(D + F + T4) + 1.6L + 1.6L_ + 0.5Lr
144 uLCB144 1.2(D + F + T4) + 0.5L + 1.0L_ + 1.6Lr

145 uLCB145 1.2(D + F + T4) + 1.6Lr + 0.8WX


146 uLCB146 1.2(D + F + T4) + 1.6Lr - 0.8WX

147 uLCB147 1.2(D + F + T4) + 1.6Lr + 0.8WY


148 uLCB148 1.2(D + F + T4) + 1.6Lr - 0.8WY
149 uLCB149 1.2(D + F + T4) + 1.6WX + 0.5L + L_ + 0.5Lr
150 uLCB150 1.2(D + F + T4) - 1.6WX + 0.5L + L_ + 0.5Lr
151 uLCB151 1.2(D + F + T4) + 1.6WY + 0.5L + L_ + 0.5Lr
152 uLCB152 1.2(D + F + T4) - 1.6WY + 0.5L + L_ + 0.5Lr
153 uLCB153 1.2(D + F + T4) + 1.4(1.0EX + 0.3EY + 1.0EZ) + 0.5L + L_
154 uLCB154 1.2(D + F + T4) + 1.4(1.0EX + 0.3EY - 1.0EZ) + 0.5L + L_
155 uLCB155 1.2(D + F + T4) + 1.4(1.0EX - 0.3EY + 1.0EZ) + 0.5L + L_
156 uLCB156 1.2(D + F + T4) + 1.4(1.0EX - 0.3EY - 1.0EZ) + 0.5L + L_
157 uLCB157 1.2(D + F + T4) - 1.4(1.0EX + 0.3EY + 1.0EZ) + 0.5L + L_
158 uLCB158 1.2(D + F + T4) - 1.4(1.0EX + 0.3EY - 1.0EZ) + 0.5L + L_
159 uLCB159 1.2(D + F + T4) - 1.4(1.0EX - 0.3EY + 1.0EZ) + 0.5L + L_
160 uLCB160 1.2(D + F + T4) - 1.4(1.0EX - 0.3EY - 1.0EZ) + 0.5L + L_
161 uLCB161 1.2(D + F + T4) + 1.4(0.3EX + 1.0EY + 1.0EZ) + 0.5L + L_
162 uLCB162 1.2(D + F + T4) + 1.4(0.3EX + 1.0EY - 1.0EZ) + 0.5L + L_
163 uLCB163 1.2(D + F + T4) + 1.4(0.3EX – 1.0EY + 1.0EZ) + 0.5L + L_
164 uLCB164 1.2(D + F + T4) + 1.4(0.3EX – 1.0EY - 1.0EZ) + 0.5L + L_
165 uLCB165 1.2(D + F + T4) - 1.4(0.3EX + 1.0EY + 1.0EZ) + 0.5L + L_
166 uLCB166 1.2(D + F + T4) - 1.4(0.3EX + 1.0EY - 1.0EZ) + 0.5L + L_
167 uLCB167 1.2(D + F + T4) - 1.4(0.3EX – 1.0EY + 1.0EZ) + 0.5L + L_
168 uLCB168 1.2(D + F + T4) - 1.4(0.3EX – 1.0EY - 1.0EZ) + 0.5L + L_
169 uLCB169 0.9(D + T4) + 1.6WX
170 uLCB170 0.9(D + T4) - 1.6WX
171 uLCB171 0.9(D + T4) + 1.6WY
172 uLCB172 0.9(D + T4) - 1.6WY
173 uLCB173 0.9(D + F + T4) + 1.4(1.0EX + 0.3EY + 1.0EZ)
174 uLCB174 0.9(D + F + T4) + 1.4(1.0EX + 0.3EY - 1.0EZ)

Revisión F 81
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-003

175 uLCB175 0.9(D + F + T4) + 1.4(1.0EX - 0.3EY + 1.0EZ)


176 uLCB176 0.9(D + F + T4) + 1.4(1.0EX - 0.3EY - 1.0EZ)
177 uLCB177 0.9(D + F + T4) - 1.4(1.0EX + 0.3EY + 1.0EZ)
178 uLCB178 0.9(D + F + T4) - 1.4(1.0EX + 0.3EY - 1.0EZ)
179 uLCB179 0.9(D + F + T4) - 1.4(1.0EX - 0.3EY + 1.0EZ)
180 uLCB180 0.9(D + F + T4) - 1.4(1.0EX - 0.3EY - 1.0EZ)
181 uLCB181 0.9(D + F + T4) + 1.4(0.3EX + 1.0EY + 1.0EZ)
182 uLCB182 0.9(D + F + T4) + 1.4(0.3EX + 1.0EY - 1.0EZ)
183 uLCB183 0.9(D + F + T4) + 1.4(0.3EX – 1.0EY + 1.0EZ)
184 uLCB184 0.9(D + F + T4) + 1.4(0.3EX – 1.0EY - 1.0EZ)
185 uLCB185 0.9(D + F + T4) - 1.4(0.3EX + 1.0EY + 1.0EZ)
186 uLCB186 0.9(D + F + T4) - 1.4(0.3EX + 1.0EY - 1.0EZ)
187 uLCB187 0.9(D + F + T4) - 1.4(0.3EX – 1.0EY + 1.0EZ)
188 uLCB188 0.9(D + F + T4) - 1.4(0.3EX – 1.0EY - 1.0EZ)
189 uLCB189 1.4(D + F + T5)
190 uLCB190 1.2(D + F + T5) + 1.6L + 1.6L_ + 0.5Lr
191 uLCB191 1.2(D + F + T5) + 0.5L + 1.0L_ + 1.6Lr

192 uLCB192 1.2(D + F + T5) + 1.6Lr + 0.8WX


193 uLCB193 1.2(D + F + T5) + 1.6Lr - 0.8WX

194 uLCB194 1.2(D + F + T5) + 1.6Lr + 0.8WY


195 uLCB195 1.2(D + F + T5) + 1.6Lr - 0.8WY
196 uLCB196 1.2(D + F + T5) + 1.6WX + 0.5L + L_ + 0.5Lr
197 uLCB197 1.2(D + F + T5) - 1.6WX + 0.5L + L_ + 0.5Lr
198 uLCB198 1.2(D + F + T5) + 1.6WY + 0.5L + L_ + 0.5Lr
199 uLCB199 1.2(D + F + T5) - 1.6WY + 0.5L + L_ + 0.5Lr
200 uLCB200 1.2(D + F + T5) + 1.4(1.0EX + 0.3EY + 1.0EZ) + 0.5L + L_
201 uLCB201 1.2(D + F + T5) + 1.4(1.0EX + 0.3EY - 1.0EZ) + 0.5L + L_
202 uLCB202 1.2(D + F + T5) + 1.4(1.0EX - 0.3EY + 1.0EZ) + 0.5L + L_
203 uLCB203 1.2(D + F + T5) + 1.4(1.0EX - 0.3EY - 1.0EZ) + 0.5L + L_
204 uLCB204 1.2(D + F + T5) - 1.4(1.0EX + 0.3EY + 1.0EZ) + 0.5L + L_
205 uLCB205 1.2(D + F + T5) - 1.4(1.0EX + 0.3EY - 1.0EZ) + 0.5L + L_
206 uLCB206 1.2(D + F + T5) - 1.4(1.0EX - 0.3EY + 1.0EZ) + 0.5L + L_
207 uLCB207 1.2(D + F + T5) - 1.4(1.0EX - 0.3EY - 1.0EZ) + 0.5L + L_

Revisión F 82
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-003

208 uLCB208 1.2(D + F + T5) + 1.4(0.3EX + 1.0EY + 1.0EZ) + 0.5L + L_


209 uLCB209 1.2(D + F + T5) + 1.4(0.3EX + 1.0EY - 1.0EZ) + 0.5L + L_
210 uLCB210 1.2(D + F + T5) + 1.4(0.3EX – 1.0EY + 1.0EZ) + 0.5L + L_
211 uLCB211 1.2(D + F + T5) + 1.4(0.3EX – 1.0EY - 1.0EZ) + 0.5L + L_
212 uLCB212 1.2(D + F + T5) - 1.4(0.3EX + 1.0EY + 1.0EZ) + 0.5L + L_
213 uLCB213 1.2(D + F + T5) - 1.4(0.3EX + 1.0EY - 1.0EZ) + 0.5L + L_
214 uLCB214 1.2(D + F + T5) - 1.4(0.3EX – 1.0EY + 1.0EZ) + 0.5L + L_
215 uLCB215 1.2(D + F + T5) - 1.4(0.3EX – 1.0EY - 1.0EZ) + 0.5L + L_
216 uLCB216 0.9(D + T5) + 1.6WX
217 uLCB217 0.9(D + T5) - 1.6WX
218 uLCB218 0.9(D + T5) + 1.6WY
219 uLCB219 0.9(D + T5) - 1.6WY
220 uLCB220 0.9(D + F + T5) + 1.4(1.0EX + 0.3EY + 1.0EZ)
221 uLCB221 0.9(D + F + T5) + 1.4(1.0EX + 0.3EY - 1.0EZ)
222 uLCB222 0.9(D + F + T5) + 1.4(1.0EX - 0.3EY + 1.0EZ)
223 uLCB223 0.9(D + F + T5) + 1.4(1.0EX - 0.3EY - 1.0EZ)
224 uLCB224 0.9(D + F + T5) - 1.4(1.0EX + 0.3EY + 1.0EZ)
225 uLCB225 0.9(D + F + T5) - 1.4(1.0EX + 0.3EY - 1.0EZ)
226 uLCB226 0.9(D + F + T5) - 1.4(1.0EX - 0.3EY + 1.0EZ)
227 uLCB227 0.9(D + F + T5) - 1.4(1.0EX - 0.3EY - 1.0EZ)
228 uLCB228 0.9(D + F + T5) + 1.4(0.3EX + 1.0EY + 1.0EZ)
229 uLCB229 0.9(D + F + T5) + 1.4(0.3EX + 1.0EY - 1.0EZ)
230 uLCB230 0.9(D + F + T5) + 1.4(0.3EX – 1.0EY + 1.0EZ)
231 uLCB231 0.9(D + F + T5) + 1.4(0.3EX – 1.0EY - 1.0EZ)
232 uLCB232 0.9(D + F + T5) - 1.4(0.3EX + 1.0EY + 1.0EZ)
233 uLCB233 0.9(D + F + T5) - 1.4(0.3EX + 1.0EY - 1.0EZ)
234 uLCB234 0.9(D + F + T5) - 1.4(0.3EX – 1.0EY + 1.0EZ)
235 uLCB235 0.9(D + F + T5) - 1.4(0.3EX – 1.0EY - 1.0EZ)
236 uLCB236 1.4(D + F)
237 uLCB237 1.2(D + F) + 1.6L + 1.6L_ + 0.5Lr
238 uLCB238 1.2(D + F) + 0.5L + 1.0L_ + 1.6Lr

239 uLCB239 1.2(D + F) + 1.6Lr + 0.8WX


240 uLCB240 1.2(D + F) + 1.6Lr - 0.8WX

Revisión F 83
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-003

241 uLCB241 1.2(D + F) + 1.6Lr + 0.8WY


242 uLCB242 1.2(D + F) + 1.6Lr - 0.8WY
243 uLCB243 1.2(D + F) + 1.6WX + 0.5L + L_ + 0.5Lr
244 uLCB244 1.2(D + F) - 1.6WX + 0.5L + L_ + 0.5Lr
245 uLCB245 1.2(D + F) + 1.6WY + 0.5L + L_ + 0.5Lr
246 uLCB246 1.2(D + F) - 1.6WY + 0.5L + L_ + 0.5Lr
247 uLCB247 1.2(D + F) + 1.4(1.0EX + 0.3EY + 1.0EZ) + 0.5L + L_
248 uLCB248 1.2(D + F) + 1.4(1.0EX + 0.3EY - 1.0EZ) + 0.5L + L_
249 uLCB249 1.2(D + F) + 1.4(1.0EX - 0.3EY + 1.0EZ) + 0.5L + L_
250 uLCB250 1.2(D + F) + 1.4(1.0EX - 0.3EY - 1.0EZ) + 0.5L + L_
251 uLCB251 1.2(D + F) - 1.4(1.0EX + 0.3EY + 1.0EZ) + 0.5L + L_
252 uLCB252 1.2(D + F) - 1.4(1.0EX + 0.3EY - 1.0EZ) + 0.5L + L_
253 uLCB253 1.2(D + F) - 1.4(1.0EX - 0.3EY + 1.0EZ) + 0.5L + L_
254 uLCB254 1.2(D + F) - 1.4(1.0EX - 0.3EY - 1.0EZ) + 0.5L + L_
255 uLCB255 1.2(D + F) + 1.4(0.3EX + 1.0EY + 1.0EZ) + 0.5L + L_
256 uLCB256 1.2(D + F) + 1.4(0.3EX + 1.0EY - 1.0EZ) + 0.5L + L_
257 uLCB257 1.2(D + F) + 1.4(0.3EX – 1.0EY + 1.0EZ) + 0.5L + L_
258 uLCB258 1.2(D + F) + 1.4(0.3EX – 1.0EY - 1.0EZ) + 0.5L + L_
259 uLCB259 1.2(D + F) - 1.4(0.3EX + 1.0EY + 1.0EZ) + 0.5L + L_
260 uLCB260 1.2(D + F) - 1.4(0.3EX + 1.0EY - 1.0EZ) + 0.5L + L_
261 uLCB261 1.2(D + F) - 1.4(0.3EX – 1.0EY + 1.0EZ) + 0.5L + L_
262 uLCB262 1.2(D + F) - 1.4(0.3EX – 1.0EY - 1.0EZ) + 0.5L + L_
263 uLCB263 0.9(D) + 1.6WX
264 uLCB264 0.9(D) - 1.6WX
265 uLCB265 0.9(D) + 1.6WY
266 uLCB266 0.9(D) - 1.6WY
267 uLCB267 0.9(D + F) + 1.4(1.0EX + 0.3EY + 1.0EZ)
268 uLCB268 0.9(D + F) + 1.4(1.0EX + 0.3EY - 1.0EZ)
269 uLCB269 0.9(D + F) + 1.4(1.0EX - 0.3EY + 1.0EZ)
270 uLCB270 0.9(D + F) + 1.4(1.0EX - 0.3EY - 1.0EZ)
271 uLCB271 0.9(D + F) - 1.4(1.0EX + 0.3EY + 1.0EZ)
272 uLCB272 0.9(D + F) - 1.4(1.0EX + 0.3EY - 1.0EZ)
273 uLCB273 0.9(D + F) - 1.4(1.0EX - 0.3EY + 1.0EZ)
274 uLCB274 0.9(D + F) - 1.4(1.0EX - 0.3EY - 1.0EZ)

Revisión F 84
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-003

275 uLCB275 0.9(D + F) + 1.4(0.3EX + 1.0EY + 1.0EZ)


276 uLCB276 0.9(D + F) + 1.4(0.3EX + 1.0EY - 1.0EZ)
277 uLCB277 0.9(D + F) + 1.4(0.3EX – 1.0EY + 1.0EZ)
278 uLCB278 0.9(D + F) + 1.4(0.3EX – 1.0EY - 1.0EZ)
279 uLCB279 0.9(D + F) - 1.4(0.3EX + 1.0EY + 1.0EZ)
280 uLCB280 0.9(D + F) - 1.4(0.3EX + 1.0EY - 1.0EZ)
281 uLCB281 0.9(D + F) - 1.4(0.3EX – 1.0EY + 1.0EZ)
282 uLCB282 0.9(D + F) - 1.4(0.3EX – 1.0EY - 1.0EZ)
283 uLCB283 1.4(D + T1)
284 uLCB284 1.2(D + T1) + 1.6L + 1.6L_ + 0.5Lr
285 uLCB285 1.2(D + T1) + 0.5L + 1.0L_ + 1.6Lr
286 uLCB286 1.2(D + T1) + 1.6Lr + 0.8WX
287 uLCB287 1.2(D + T1) + 1.6Lr - 0.8WX
288 uLCB288 1.2(D + T1) + 1.6Lr + 0.8WY
289 uLCB289 1.2(D + T1) + 1.6Lr - 0.8WY
290 uLCB290 1.2(D + T1) + 1.6WX + 0.5L + L_ + 0.5Lr
291 uLCB291 1.2(D + T1) - 1.6WX + 0.5L + L_ + 0.5Lr
292 uLCB292 1.2(D + T1) + 1.6WY + 0.5L + L_ + 0.5Lr
293 uLCB293 1.2(D + T1) - 1.6WY + 0.5L + L_ + 0.5Lr
294 uLCB294 1.2(D + T1) + 1.4(1.0EX + 0.3EY + 1.0EZ) + 0.5L + 1.0L_
295 uLCB295 1.2(D + T1) + 1.4(1.0EX + 0.3EY - 1.0EZ) + 0.5L + 1.0L_
296 uLCB296 1.2(D + T1) + 1.4(1.0EX - 0.3EY + 1.0EZ) + 0.5L + 1.0L_
297 uLCB297 1.2(D + T1) + 1.4(1.0EX - 0.3EY - 1.0EZ) + 0.5L + 1.0L_
298 uLCB298 1.2(D + T1) - 1.4(1.0EX + 0.3EY + 1.0EZ) + 0.5L + 1.0L_
299 uLCB299 1.2(D + T1) - 1.4(1.0EX + 0.3EY - 1.0EZ) + 0.5L + 1.0L_
300 uLCB300 1.2(D + T1) - 1.4(1.0EX - 0.3EY + 1.0EZ) + 0.5L + 1.0L_
301 uLCB301 1.2(D + T1) - 1.4(1.0EX - 0.3EY - 1.0EZ) + 0.5L + 1.0L_
302 uLCB302 1.2(D + T1) + 1.4(0.3EX + 1.0EY + 1.0EZ) + 0.5L + 1.0L_
303 uLCB303 1.2(D + T1) + 1.4(0.3EX + 1.0EY - 1.0EZ) + 0.5L + 1.0L_
304 uLCB304 1.2(D + T1) + 1.4(0.3EX – 1.0EY + 1.0EZ) + 0.5L + 1.0L_
305 uLCB305 1.2(D + T1) + 1.4(0.3EX – 1.0EY - 1.0EZ) + 0.5L + 1.0L_
306 uLCB306 1.2(D + T1) - 1.4(0.3EX + 1.0EY + 1.0EZ) + 0.5L + 1.0L_
307 uLCB307 1.2(D + T1) - 1.4(0.3EX + 1.0EY - 1.0EZ) + 0.5L + 1.0L_

Revisión F 85
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-003

308 uLCB308 1.2(D + T1) - 1.4(0.3EX – 1.0EY + 1.0EZ) + 0.5L + 1.0L_


309 uLCB309 1.2(D + T1) - 1.4(0.3EX – 1.0EY - 1.0EZ) + 0.5L + 1.0L_
310 uLCB310 0.9(D + T1) + 1.4(1.0EX + 0.3EY + 1.0EZ)
311 uLCB311 0.9(D + T1) + 1.4(1.0EX + 0.3EY - 1.0EZ)
312 uLCB312 0.9(D + T1) + 1.4(1.0EX - 0.3EY + 1.0EZ)
313 uLCB313 0.9(D + T1) + 1.4(1.0EX - 0.3EY - 1.0EZ)
314 uLCB314 0.9(D + T1) - 1.4(1.0EX + 0.3EY + 1.0EZ)
315 uLCB315 0.9(D + T1) - 1.4(1.0EX + 0.3EY - 1.0EZ)
316 uLCB316 0.9(D + T1) - 1.4(1.0EX - 0.3EY + 1.0EZ)
317 uLCB317 0.9(D + T1) - 1.4(1.0EX - 0.3EY - 1.0EZ)
318 uLCB318 0.9(D + T1) + 1.4(0.3EX + 1.0EY + 1.0EZ)
319 uLCB319 0.9(D + T1) + 1.4(0.3EX + 1.0EY - 1.0EZ)
320 uLCB320 0.9(D + T1) + 1.4(0.3EX – 1.0EY + 1.0EZ)
321 uLCB321 0.9(D + T1) + 1.4(0.3EX – 1.0EY - 1.0EZ)
322 uLCB322 0.9(D + T1) - 1.4(0.3EX + 1.0EY + 1.0EZ)
323 uLCB323 0.9(D + T1) - 1.4(0.3EX + 1.0EY - 1.0EZ)
324 uLCB324 0.9(D + T1) - 1.4(0.3EX – 1.0EY + 1.0EZ)
325 uLCB325 0.9(D + T1) - 1.4(0.3EX – 1.0EY - 1.0EZ)
326 uLCB326 1.4(D + T2)
327 uLCB327 1.2(D + T2) + 1.6L + 1.6L_ + 0.5Lr
328 uLCB328 1.2(D + T2) + 0.5L + 1.0L_ + 1.6Lr
329 uLCB329 1.2(D + T2) + 1.6Lr + 0.8WX
330 uLCB330 1.2(D + T2) + 1.6Lr - 0.8WX
331 uLCB331 1.2(D + T2) + 1.6Lr + 0.8WY
332 uLCB332 1.2(D + T2) + 1.6Lr - 0.8WY
333 uLCB333 1.2(D + T2) + 1.6WX + 0.5L + L_ + 0.5Lr
334 uLCB334 1.2(D + T2) - 1.6WX + 0.5L + L_ + 0.5Lr
335 uLCB335 1.2(D + T2) + 1.6WY + 0.5L + L_ + 0.5Lr
336 uLCB336 1.2(D + T2) - 1.6WY + 0.5L + L_ + 0.5Lr
337 uLCB337 1.2(D + T2) + 1.4(1.0EX + 0.3EY + 1.0EZ) + 0.5L + L_
338 uLCB338 1.2(D + T2) + 1.4(1.0EX + 0.3EY - 1.0EZ) + 0.5L + L_
339 uLCB339 1.2(D + T2) + 1.4(1.0EX - 0.3EY + 1.0EZ) + 0.5L + L_
340 uLCB340 1.2(D + T2) + 1.4(1.0EX - 0.3EY - 1.0EZ) + 0.5L + L_

Revisión F 86
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-003

341 uLCB341 1.2(D + T2) - 1.4(1.0EX + 0.3EY + 1.0EZ) + 0.5L + L_


342 uLCB342 1.2(D + T2) - 1.4(1.0EX + 0.3EY - 1.0EZ) + 0.5L + L_
343 uLCB343 1.2(D + T2) - 1.4(1.0EX - 0.3EY + 1.0EZ) + 0.5L + L_
344 uLCB344 1.2(D + T2) - 1.4(1.0EX - 0.3EY - 1.0EZ) + 0.5L + L_
345 uLCB345 1.2(D + T2) + 1.4(0.3EX + 1.0EY + 1.0EZ) + 0.5L + L_
346 uLCB346 1.2(D + T2) + 1.4(0.3EX + 1.0EY - 1.0EZ) + 0.5L + L_
347 uLCB347 1.2(D + T2) + 1.4(0.3EX – 1.0EY + 1.0EZ) + 0.5L + L_
348 uLCB348 1.2(D + T2) + 1.4(0.3EX – 1.0EY - 1.0EZ) + 0.5L + L_
349 uLCB349 1.2(D + T2) - 1.4(0.3EX + 1.0EY + 1.0EZ) + 0.5L + L_
350 uLCB350 1.2(D + T2) - 1.4(0.3EX + 1.0EY - 1.0EZ) + 0.5L + L_
351 uLCB351 1.2(D + T2) - 1.4(0.3EX – 1.0EY + 1.0EZ) + 0.5L + L_
352 uLCB352 1.2(D + T2) - 1.4(0.3EX – 1.0EY - 1.0EZ)
353 uLCB353 0.9(D + T2) + 1.4(1.0EX + 0.3EY + 1.0EZ)
354 uLCB354 0.9(D + T2) + 1.4(1.0EX + 0.3EY - 1.0EZ)
355 uLCB355 0.9(D + T2) + 1.4(1.0EX - 0.3EY + 1.0EZ)
356 uLCB356 0.9(D + T2) + 1.4(1.0EX - 0.3EY - 1.0EZ)
357 uLCB357 0.9(D + T2) - 1.4(1.0EX + 0.3EY + 1.0EZ)
358 uLCB358 0.9(D + T2) - 1.4(1.0EX + 0.3EY - 1.0EZ)
359 uLCB359 0.9(D + T2) - 1.4(1.0EX - 0.3EY + 1.0EZ)
360 uLCB360 0.9(D + T2) - 1.4(1.0EX - 0.3EY - 1.0EZ)
361 uLCB361 0.9(D + T2) + 1.4(0.3EX + 1.0EY + 1.0EZ)
362 uLCB362 0.9(D + T2) + 1.4(0.3EX + 1.0EY - 1.0EZ)
363 uLCB363 0.9(D + T2) + 1.4(0.3EX – 1.0EY + 1.0EZ)
364 uLCB364 0.9(D + T2) + 1.4(0.3EX – 1.0EY - 1.0EZ)
365 uLCB365 0.9(D + T2) - 1.4(0.3EX + 1.0EY + 1.0EZ)
366 uLCB366 0.9(D + T2) - 1.4(0.3EX + 1.0EY - 1.0EZ)
367 uLCB367 0.9(D + T2) - 1.4(0.3EX – 1.0EY + 1.0EZ)
368 uLCB368 0.9(D + T2) - 1.4(0.3EX – 1.0EY - 1.0EZ)
369 uLCB369 1.4(D + T3)
370 uLCB370 1.2(D + T3) + 1.6L + 1.6L_ + 0.5Lr
371 uLCB371 1.2(D + T3) + 0.5L + 1.0L_ + 1.6Lr
372 uLCB372 1.2(D + T3) + 1.6Lr + 0.8WX
373 uLCB373 1.2(D + T3) + 1.6Lr - 0.8WX

Revisión F 87
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-003

374 uLCB374 1.2(D + T3) + 1.6Lr + 0.8WY


375 uLCB375 1.2(D + T3) + 1.6Lr - 0.8WY
376 uLCB376 1.2(D + T3) + 1.6WX + 0.5L + L_+ 0.5Lr
377 uLCB377 1.2(D + T3) - 1.6WX + 0.5L + L_ + 0.5Lr
378 uLCB378 1.2(D + T3) + 1.6WY + 0.5L + L_ + 0.5Lr
379 uLCB379 1.2(D + T3) - 1.6WY + 0.5L + L_ + 0.5Lr
380 uLCB380 1.2(D + T3) + 1.4(1.0EX + 0.3EY + 1.0EZ) + 0.5L + L_
381 uLCB381 1.2(D + T3) + 1.4(1.0EX + 0.3EY - 1.0EZ) + 0.5L + L_
382 uLCB382 1.2(D + T3) + 1.4(1.0EX - 0.3EY + 1.0EZ) + 0.5L + L_
383 uLCB383 1.2(D + T3) + 1.4(1.0EX - 0.3EY - 1.0EZ) + 0.5L + L_
384 uLCB384 1.2(D + T3) - 1.4(1.0EX + 0.3EY + 1.0EZ) + 0.5L + L_
385 uLCB385 1.2(D + T3) - 1.4(1.0EX + 0.3EY - 1.0EZ) + 0.5L + L_
386 uLCB386 1.2(D + T3) - 1.4(1.0EX - 0.3EY + 1.0EZ) + 0.5L + L_
387 uLCB387 1.2(D + T3) - 1.4(1.0EX - 0.3EY - 1.0EZ) + 0.5L + L_
388 uLCB388 1.2(D + T3) + 1.4(0.3EX + 1.0EY + 1.0EZ) + 0.5L + L_
389 uLCB389 1.2(D + T3) + 1.4(0.3EX + 1.0EY - 1.0EZ) + 0.5L + L_
390 uLCB390 1.2(D + T3) + 1.4(0.3EX – 1.0EY + 1.0EZ) + 0.5L + L_
391 uLCB391 1.2(D + T3) + 1.4(0.3EX – 1.0EY - 1.0EZ) + 0.5L + L_
392 uLCB392 1.2(D + T3) - 1.4(0.3EX + 1.0EY + 1.0EZ) + 0.5L + L_
393 uLCB393 1.2(D + T3) - 1.4(0.3EX + 1.0EY - 1.0EZ) + 0.5L + L_
394 uLCB394 1.2(D + T3) - 1.4(0.3EX – 1.0EY + 1.0EZ) + 0.5L + L_
395 uLCB395 1.2(D + T3) - 1.4(0.3EX – 1.0EY - 1.0EZ) + 0.5L + L_
396 uLCB396 0.9(D + T3) + 1.4(1.0EX + 0.3EY + 1.0EZ)
397 uLCB397 0.9(D + T3) + 1.4(1.0EX + 0.3EY - 1.0EZ)
398 uLCB398 0.9(D + T3) + 1.4(1.0EX - 0.3EY + 1.0EZ)
399 uLCB399 0.9(D + T3) + 1.4(1.0EX - 0.3EY - 1.0EZ)
400 uLCB400 0.9(D + T3) - 1.4(1.0EX + 0.3EY + 1.0EZ)
401 uLCB401 0.9(D + T3) - 1.4(1.0EX + 0.3EY - 1.0EZ)
402 uLCB402 0.9(D + T3) - 1.4(1.0EX - 0.3EY + 1.0EZ)
403 uLCB403 0.9(D + T3) - 1.4(1.0EX - 0.3EY - 1.0EZ)
404 uLCB404 0.9(D + T3) + 1.4(0.3EX + 1.0EY + 1.0EZ)
405 uLCB405 0.9(D + T3) + 1.4(0.3EX + 1.0EY - 1.0EZ)
406 uLCB406 0.9(D + T3) + 1.4(0.3EX – 1.0EY + 1.0EZ)
407 uLCB407 0.9(D + T3) + 1.4(0.3EX – 1.0EY - 1.0EZ)

Revisión F 88
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-003

408 uLCB408 0.9(D + T3) - 1.4(0.3EX + 1.0EY + 1.0EZ)


409 uLCB409 0.9(D + T3) - 1.4(0.3EX + 1.0EY - 1.0EZ)
410 uLCB410 0.9(D + T3) - 1.4(0.3EX – 1.0EY + 1.0EZ)
411 uLCB411 0.9(D + T3) - 1.4(0.3EX – 1.0EY - 1.0EZ)
412 uLCB412 1.4(D + T4)
413 uLCB413 1.2(D + T4) + 1.6L + 1.6L_ + 0.5Lr
414 uLCB414 1.2(D + T4) + 0.5L + 1.0L_ + 1.6Lr
415 uLCB415 1.2(D + T4) + 1.6Lr + 0.8WX
416 uLCB416 1.2(D + T4) + 1.6Lr - 0.8WX
417 uLCB417 1.2(D + T4) + 1.6Lr + 0.8WY
418 uLCB418 1.2(D + T4) + 1.6Lr - 0.8WY
419 uLCB419 1.2(D + T4) + 1.6WX + 0.5L + L_ + 0.5Lr
420 uLCB420 1.2(D + T4) - 1.6WX + 0.5L + L_ + 0.5Lr
421 uLCB421 1.2(D + T4) + 1.6WY + 0.5L + L_ + 0.5Lr
422 uLCB422 1.2(D + T4) - 1.6WY + 0.5L + L_ + 0.5Lr
423 uLCB423 1.2(D + T4) + 1.4(1.0EX + 0.3EY + 1.0EZ) + 0.5L + L_
424 uLCB424 1.2(D + T4) + 1.4(1.0EX + 0.3EY - 1.0EZ) + 0.5L + L_
425 uLCB425 1.2(D + T4) + 1.4(1.0EX - 0.3EY + 1.0EZ) + 0.5L + L_
426 uLCB426 1.2(D + T4) + 1.4(1.0EX - 0.3EY - 1.0EZ) + 0.5L + L_
427 uLCB427 1.2(D + T4) - 1.4(1.0EX + 0.3EY + 1.0EZ) + 0.5L + L_
428 uLCB428 1.2(D + T4) - 1.4(1.0EX + 0.3EY - 1.0EZ) + 0.5L + L_
429 uLCB429 1.2(D + T4) - 1.4(1.0EX - 0.3EY + 1.0EZ) + 0.5L + L_
430 uLCB430 1.2(D + T4) - 1.4(1.0EX - 0.3EY - 1.0EZ) + 0.5L + L_
431 uLCB431 1.2(D + T4) + 1.4(0.3EX + 1.0EY + 1.0EZ) + 0.5L + L_
432 uLCB432 1.2(D + T4) + 1.4(0.3EX + 1.0EY - 1.0EZ) + 0.5L + L_
433 uLCB433 1.2(D + T4) + 1.4(0.3EX – 1.0EY + 1.0EZ) + 0.5L + L_
434 uLCB434 1.2(D + T4) + 1.4(0.3EX – 1.0EY - 1.0EZ) + 0.5L + L_
435 uLCB435 1.2(D + T4) - 1.4(0.3EX + 1.0EY + 1.0EZ) + 0.5L + L_
436 uLCB436 1.2(D + T4) - 1.4(0.3EX + 1.0EY - 1.0EZ) + 0.5L + L_
437 uLCB437 1.2(D + T4) - 1.4(0.3EX – 1.0EY + 1.0EZ) + 0.5L + L_
438 uLCB438 1.2(D + T4) - 1.4(0.3EX – 1.0EY - 1.0EZ) + 0.5L + L_
439 uLCB439 0.9(D + T4) + 1.4(1.0EX + 0.3EY + 1.0EZ)
440 uLCB440 0.9(D + T4) + 1.4(1.0EX + 0.3EY - 1.0EZ)

Revisión F 89
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-003

441 uLCB441 0.9(D + T4) + 1.4(1.0EX - 0.3EY + 1.0EZ)


442 uLCB442 0.9(D + T4) + 1.4(1.0EX - 0.3EY - 1.0EZ)
443 uLCB443 0.9(D + T4) - 1.4(1.0EX + 0.3EY + 1.0EZ)
444 uLCB444 0.9(D + T4) - 1.4(1.0EX + 0.3EY - 1.0EZ)
445 uLCB445 0.9(D + T4) - 1.4(1.0EX - 0.3EY + 1.0EZ)
446 uLCB446 0.9(D + T4) - 1.4(1.0EX - 0.3EY - 1.0EZ)
447 uLCB447 0.9(D + T4) + 1.4(0.3EX + 1.0EY + 1.0EZ)
448 uLCB448 0.9(D + T4) + 1.4(0.3EX + 1.0EY - 1.0EZ)
449 uLCB449 0.9(D + T4) + 1.4(0.3EX – 1.0EY + 1.0EZ)
450 uLCB450 0.9(D + T4) + 1.4(0.3EX – 1.0EY - 1.0EZ)
451 uLCB451 0.9(D + T4) - 1.4(0.3EX + 1.0EY + 1.0EZ)
452 uLCB452 0.9(D + T4) - 1.4(0.3EX + 1.0EY - 1.0EZ)
453 uLCB453 0.9(D + T4) - 1.4(0.3EX – 1.0EY + 1.0EZ)
454 uLCB454 0.9(D + T4) - 1.4(0.3EX – 1.0EY - 1.0EZ)
455 uLCB455 1.4(D + T5)
456 uLCB456 1.2(D + T5) + 1.6L + 1.6L_ + 0.5Lr
457 uLCB457 1.2(D + T5) + 0.5L + 1.0L_ + 1.6Lr
458 uLCB458 1.2(D + T5) + 1.6Lr + 0.8WX
459 uLCB459 1.2(D + T5) + 1.6Lr - 0.8WX
460 uLCB460 1.2(D + T5) + 1.6Lr + 0.8WY
461 uLCB461 1.2(D + T5) + 1.6Lr - 0.8WY
462 uLCB462 1.2(D + T5) + 1.6WX + 0.5L + L_ + 0.5Lr
463 uLCB463 1.2(D + T5) - 1.6WX + 0.5L + L_ + 0.5Lr
464 uLCB464 1.2(D + T5) + 1.6WY + 0.5L + L_ + 0.5Lr
465 uLCB465 1.2(D + T5) - 1.6WY + 0.5L + L_ + 0.5Lr
466 uLCB466 1.2(D + T5) + 1.4(1.0EX + 0.3EY + 1.0EZ) + 0.5L + L_
467 uLCB467 1.2(D + T5) + 1.4(1.0EX + 0.3EY - 1.0EZ) + 0.5L + L_
468 uLCB468 1.2(D + T5) + 1.4(1.0EX - 0.3EY + 1.0EZ) + 0.5L + L_
469 uLCB469 1.2(D + T5) + 1.4(1.0EX - 0.3EY - 1.0EZ) + 0.5L + L_
470 uLCB470 1.2(D + T5) - 1.4(1.0EX + 0.3EY + 1.0EZ) + 0.5L + L_
471 uLCB471 1.2(D + T5) - 1.4(1.0EX + 0.3EY - 1.0EZ) + 0.5L + L_
472 uLCB472 1.2(D + T5) - 1.4(1.0EX - 0.3EY + 1.0EZ) + 0.5L + L_
473 uLCB473 1.2(D + T5) - 1.4(1.0EX - 0.3EY - 1.0EZ) + 0.5L + L_

Revisión F 90
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-003

474 uLCB474 1.2(D + T5) + 1.4(0.3EX + 1.0EY + 1.0EZ) + 0.5L + L_


475 uLCB475 1.2(D + T5) + 1.4(0.3EX + 1.0EY - 1.0EZ) + 0.5L + L_
476 uLCB476 1.2(D + T5) + 1.4(0.3EX – 1.0EY + 1.0EZ) + 0.5L + L_
477 uLCB477 1.2(D + T5) + 1.4(0.3EX – 1.0EY - 1.0EZ) + 0.5L + L_
478 uLCB478 1.2(D + T5) - 1.4(0.3EX + 1.0EY + 1.0EZ) + 0.5L + L_
479 uLCB479 1.2(D + T5) - 1.4(0.3EX + 1.0EY - 1.0EZ) + 0.5L + L_
480 uLCB480 1.2(D + T5) - 1.4(0.3EX – 1.0EY + 1.0EZ) + 0.5L + L_
481 uLCB481 1.2(D + T5) - 1.4(0.3EX – 1.0EY - 1.0EZ) + 0.5L + L_
482 uLCB482 0.9(D + T5) + 1.4(1.0EX + 0.3EY + 1.0EZ)
483 uLCB483 0.9(D + T5) + 1.4(1.0EX + 0.3EY - 1.0EZ)
484 uLCB484 0.9(D + T5) + 1.4(1.0EX - 0.3EY + 1.0EZ)
485 uLCB485 0.9(D + T5) + 1.4(1.0EX - 0.3EY - 1.0EZ)
486 uLCB486 0.9(D + T5) - 1.4(1.0EX + 0.3EY + 1.0EZ)
487 uLCB487 0.9(D + T5) - 1.4(1.0EX + 0.3EY - 1.0EZ)
488 uLCB488 0.9(D + T5) - 1.4(1.0EX - 0.3EY + 1.0EZ)
489 uLCB489 0.9(D + T5) - 1.4(1.0EX - 0.3EY - 1.0EZ)
490 uLCB490 0.9(D + T5) + 1.4(0.3EX + 1.0EY + 1.0EZ)
491 uLCB491 0.9(D + T5) + 1.4(0.3EX + 1.0EY - 1.0EZ)
492 uLCB492 0.9(D + T5) + 1.4(0.3EX – 1.0EY + 1.0EZ)
493 uLCB493 0.9(D + T5) + 1.4(0.3EX – 1.0EY - 1.0EZ)
494 uLCB494 0.9(D + T5) - 1.4(0.3EX + 1.0EY + 1.0EZ)
495 uLCB495 0.9(D + T5) - 1.4(0.3EX + 1.0EY - 1.0EZ)
496 uLCB496 0.9(D + T5) - 1.4(0.3EX – 1.0EY + 1.0EZ)
497 uLCB497 0.9(D + T5) - 1.4(0.3EX – 1.0EY - 1.0EZ)
498 uLCB498 1.4D
499 uLCB499 1.2D + 1.6L + 1.6L_ + 0.5Lr
500 uLCB500 1.2D + 0.5L + 1.0L_ + 1.6Lr
501 uLCB501 1.2D + 1.6Lr + 0.8WX
502 uLCB502 1.2D + 1.6Lr - 0.8WX
503 uLCB503 1.2D + 1.6Lr + 0.8WY
504 uLCB504 1.2D + 1.6Lr - 0.8WY
505 uLCB505 1.2D + 1.6WX + 0.5L + L_ + 0.5Lr
506 uLCB506 1.2D - 1.6WX + 0.5L + L_ + 0.5Lr

Revisión F 91
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-003

507 uLCB507 1.2D + 1.6WY + 0.5L + L_ + 0.5Lr


508 uLCB508 1.2D - 1.6WY + 0.5L + L_ + 0.5Lr
509 uLCB509 1.2D + 1.4(1.0EX + 0.3EY + 1.0EZ) + 0.5L + L_
510 uLCB510 1.2D + 1.4(1.0EX + 0.3EY - 1.0EZ) + 0.5L + L_
511 uLCB511 1.2D + 1.4(1.0EX - 0.3EY + 1.0EZ) + 0.5L + L_
512 uLCB512 1.2D + 1.4(1.0EX - 0.3EY - 1.0EZ) + 0.5L + L_
513 uLCB513 1.2D - 1.4(1.0EX + 0.3EY + 1.0EZ) + 0.5L + L_
514 uLCB514 1.2D - 1.4(1.0EX + 0.3EY - 1.0EZ) + 0.5L + L_
515 uLCB515 1.2D - 1.4(1.0EX - 0.3EY + 1.0EZ) + 0.5L + L_
516 uLCB516 1.2D - 1.4(1.0EX - 0.3EY - 1.0EZ) + 0.5L + L_
517 uLCB517 1.2D + 1.4(0.3EX + 1.0EY + 1.0EZ) + 0.5L + L_
518 uLCB518 1.2D + 1.4(0.3EX + 1.0EY - 1.0EZ) + 0.5L + L_
519 uLCB519 1.2D + 1.4(0.3EX – 1.0EY + 1.0EZ) + 0.5L + L_
520 uLCB520 1.2D + 1.4(0.3EX – 1.0EY - 1.0EZ) + 0.5L + L_
521 uLCB521 1.2D - 1.4(0.3EX + 1.0EY + 1.0EZ) + 0.5L + L_
522 uLCB522 1.2D - 1.4(0.3EX + 1.0EY - 1.0EZ) + 0.5L + L_
523 uLCB523 1.2D - 1.4(0.3EX – 1.0EY + 1.0EZ) + 0.5L + L_
524 uLCB524 1.2D - 1.4(0.3EX – 1.0EY - 1.0EZ) + 0.5L + L_
525 uLCB525 0.9D + 1.4(1.0EX + 0.3EY + 1.0EZ)
526 uLCB526 0.9D + 1.4(1.0EX + 0.3EY - 1.0EZ)
527 uLCB527 0.9D + 1.4(1.0EX - 0.3EY + 1.0EZ)
528 uLCB528 0.9D + 1.4(1.0EX - 0.3EY - 1.0EZ)
529 uLCB529 0.9D - 1.4(1.0EX + 0.3EY + 1.0EZ)
530 uLCB530 0.9D - 1.4(1.0EX + 0.3EY - 1.0EZ)
531 uLCB531 0.9D - 1.4(1.0EX - 0.3EY + 1.0EZ)
532 uLCB532 0.9D - 1.4(1.0EX - 0.3EY - 1.0EZ)
533 uLCB533 0.9D + 1.4(0.3EX + 1.0EY + 1.0EZ)
534 uLCB534 0.9D + 1.4(0.3EX + 1.0EY - 1.0EZ)
535 uLCB535 0.9D + 1.4(0.3EX – 1.0EY + 1.0EZ)
536 uLCB536 0.9D + 1.4(0.3EX – 1.0EY - 1.0EZ)
537 uLCB537 0.9D - 1.4(0.3EX + 1.0EY + 1.0EZ)
538 uLCB538 0.9D - 1.4(0.3EX + 1.0EY - 1.0EZ)
539 uLCB539 0.9D - 1.4(0.3EX – 1.0EY + 1.0EZ)
540 uLCB540 0.9D - 1.4(0.3EX – 1.0EY - 1.0EZ)

Revisión F 92
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-003

3.7.3 ASD Load Combination (for SDA Casing and Structure)


The ASD load combinations shall take into account the earthquake load in Technical Specification.
Technical Specification considered a nominal load, so it must be amplified by a factor 1.0.

No. Case Name Description


1 sLCB1 (D + F + T1)
2  sLCB2 (D + F + T1) + L + L_
3  sLCB3 (D + F + T1) + Lr
4  sLCB4 (D + F + T1) + 0.75L + 0.75L_ + 0.75Lr
5  sLCB5 (D + F + T1) + WX
6  sLCB6 (D + F + T1) - WX
7  sLCB7 (D + F + T1) + WY
8  sLCB8 (D + F + T1) - WY
9  sLCB9 (D + F + T1) + EX + 0.3EY + EZ
10  sLCB10 (D + F + T1) + EX + 0.3EY - EZ
11  sLCB11 (D + F + T1) + EX - 0.3EY + EZ
12  sLCB12 (D + F + T1) + EX - 0.3EY - EZ
13  sLCB13 (D + F + T1) - EX + 0.3EY + EZ
14  sLCB14 (D + F + T1) - EX + 0.3EY - EZ
15  sLCB15 (D + F + T1) - EX - 0.3EY + EZ
16  sLCB16 (D + F + T1) - EX - 0.3EY - EZ
17  sLCB17 (D + F + T1) + 0.3EX - EY + EZ
18  sLCB18 (D + F + T1) + 0.3EX + EY - EZ
19  sLCB19 (D + F + T1) + 0.3EX - EY + EZ
20  sLCB20 (D + F + T1) + 0.3EX - EY - EZ
21  sLCB21 (D + F + T1) – 0.3EX + EY + EZ
22  sLCB22 (D + F + T1) – 0.3EX + EY - EZ
23  sLCB23 (D + F + T1) – 0.3EX - EY + EZ
24  sLCB24 (D + F + T1) – 0.3EX - EY - EZ
25  sLCB25 (D + F + T1) + 0.75WX + 0.75L+ 0.75L_ + 0.75Lr
26  sLCB26 (D + F + T1) - 0.75WX + 0.75L+ 0.75L_ + 0.75Lr

Revisión F 93
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-003

27  sLCB27 (D + F + T1) + 0.75WY + 0.75L+ 0.75L_ + 0.75Lr


28  sLCB28 (D + F + T1) - 0.75WY + 0.75L+ 0.75L_ + 0.75Lr
29  sLCB29 (D + F + T1) + 0.75(EX + 0.3EY + EZ) + 0.75L+ 0.75L_
30  sLCB30 (D + F + T1) + 0.75(EX + 0.3EY - EZ) + 0.75L+ 0.75L_
31  sLCB31 (D + F + T1) + 0.75(EX - 0.3EY + EZ) + 0.75L+ 0.75L_
32  sLCB32 (D + F + T1) + 0.75(EX - 0.3EY - EZ) + 0.75L+ 0.75L_
33  sLCB33 (D + F + T1) + 0.75(-EX + 0.3EY + EZ) + 0.75L+ 0.75L_
34  sLCB34 (D + F + T1) + 0.75(-EX + 0.3EY - EZ) + 0.75L+ 0.75L_
35  sLCB35 (D + F + T1) + 0.75(-EX - 0.3EY + EZ) + 0.75L+ 0.75L_
36  sLCB36 (D + F + T1) + 0.75(-EX - 0.3EY - EZ) + 0.75L+ 0.75L_
37  sLCB37 (D + F + T1) + 0.75(0.3EX + EY + EZ) + 0.75L+ 0.75L_
38  sLCB38 (D + F + T1) + 0.75(0.3EX + EY - EZ) + 0.75L+ 0.75L_
39  sLCB39 (D + F + T1) + 0.75(0.3EX - EY + EZ) + 0.75L+ 0.75L_
40  sLCB40 (D + F + T1) + 0.75(0.3EX - EY - EZ) + 0.75L+ 0.75L_
41  sLCB41 (D + F + T1) + 0.75(-0.3EX + EY + EZ) + 0.75L+ 0.75L_
42  sLCB42 (D + F + T1) + 0.75(-0.3EX + EY - EZ) + 0.75L+ 0.75L_
43  sLCB43 (D + F + T1) + 0.75(-0.3EX - EY + EZ) + 0.75L+ 0.75L_
44  sLCB44 (D + F + T1) + 0.75(-0.3EX - EY - EZ) + 0.75L+ 0.75L_
45  sLCB45 0.6(D+ T1) + WX
46  sLCB46 0.6(D+ T1) - WY
47  sLCB47 0.6(D+ T1) + WY
48  sLCB48 0.6(D+ T1) - WY
49  sLCB49 0.6(D + F + T1) + EX + 0.3EY + EZ
50  sLCB50 0.6(D + F + T1) + EX + 0.3EY - EZ
51  sLCB51 0.6(D + F + T1) + EX - 0.3EY + EZ
52  sLCB52 0.6(D + F + T1) + EX - 0.3EY - EZ
53  sLCB53 0.6(D + F + T1) - EX + 0.3EY + EZ
54  sLCB54 0.6(D + F + T1) - EX + 0.3EY - EZ
55  sLCB55 0.6(D + F + T1) - EX - 0.3EY + EZ
56  sLCB56 0.6(D + F + T1) - EX - 0.3EY - EZ

Revisión F 94
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-003

57  sLCB57 0.6(D + F + T1) + 0.3EX + EY + EZ

58  sLCB58 0.6(D + F + T1) + 0.3EX + EY - EZ

59  sLCB59 0.6(D + F + T1) + 0.3EX - EY + EZ

60  sLCB60 0.6(D + F + T1) + 0.3EX - EY - EZ

61  sLCB61 0.6(D + F + T1) - 0.3EX + EY + EZ

62  sLCB62 0.6(D + F + T1) - 0.3EX + EY - EZ

63  sLCB63 0.6(D + F + T1) - 0.3EX - EY + EZ

64  sLCB64 0.6(D + F + T1) - 0.3EX - EY - EZ

65  sLCB65 (D + F + T2)


66  sLCB66 (D + F + T2) + L + L_
67  sLCB67 (D + F + T2) + Lr
68  sLCB68 (D + F + T2) + 0.75L + 0.75L_ + 0.75Lr
69  sLCB69 (D + F + T2) + WX
70  sLCB70 (D + F + T2) - WX
71  sLCB71 (D + F + T2) + WY
72  sLCB72 (D + F + T2) - WY
73  sLCB73 (D + F + T2) + EX + 0.3EY + EZ
74  sLCB74 (D + F + T2) + EX + 0.3EY - EZ
75  sLCB75 (D + F + T2) + EX - 0.3EY + EZ
76  sLCB76 (D + F + T2) + EX - 0.3EY - EZ
77  sLCB77 (D + F + T2) - EX + 0.3EY + EZ
78  sLCB78 (D + F + T2) - EX + 0.3EY - EZ
79  sLCB79 (D + F + T2) - EX - 0.3EY + EZ
80  sLCB80 (D + F + T2) - EX - 0.3EY - EZ
81  sLCB81 (D + F + T2) + 0.3EX + EY + EZ
82  sLCB82 (D + F + T2) + 0.3EX + EY - EZ
83  sLCB83 (D + F + T2) + 0.3EX - EY + EZ
84  sLCB84 (D + F + T2) + 0.3EX - EY – EZ
85  sLCB85 (D + F + T2) - 0.3EX + EY + EZ
86  sLCB86 (D + F + T2) - 0.3EX + EY - EZ

Revisión F 95
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-003

87  sLCB87 (D + F + T2) - 0.3EX - EY + EZ


88  sLCB88 (D + F + T2) - 0.3EX - EY – EZ
89  sLCB89 (D + F + T2) + 0.75WX + 0.75L+ 0.75L_ + 0.75Lr
90  sLCB90 (D + F + T2) - 0.75WX + 0.75L+ 0.75L_ + 0.75Lr
91  sLCB91 (D + F + T2) + 0.75WY + 0.75L+ 0.75L_ + 0.75Lr
92  sLCB92 (D + F + T2) - 0.75WY + 0.75L+ 0.75L_ + 0.75Lr
93  sLCB93 (D + F + T2) + 0.75(EX + 0.3EY + EZ) + 0.75L+ 0.75L_
94  sLCB94 (D + F + T2) + 0.75(EX + 0.3EY - EZ) + 0.75L+ 0.75L_
95  sLCB95 (D + F + T2) + 0.75(EX - 0.3EY + EZ) + 0.75L+ 0.75L_
96  sLCB96 (D + F + T2) + 0.75(EX - 0.3EY - EZ) + 0.75L+ 0.75L_
97  sLCB97 (D + F + T2) + 0.75(-EX + 0.3EY + EZ) + 0.75L+ 0.75L_
98  sLCB98 (D + F + T2) + 0.75(-EX + 0.3EY - EZ) + 0.75L+ 0.75L_
99  sLCB99 (D + F + T2) + 0.75(-EX - 0.3EY + EZ) + 0.75L+ 0.75L_
100  sLCB100 (D + F + T2) + 0.75(-EX - 0.3EY - EZ) + 0.75L+ 0.75L_
101  sLCB101 (D + F + T2) + 0.75(0.3EX + EY + EZ) + 0.75L+ 0.75L_
102  sLCB102 (D + F + T2) + 0.75(0.3EX + EY - EZ) + 0.75L+ 0.75L_
103  sLCB103 (D + F + T2) + 0.75(0.3EX - EY + EZ) + 0.75L+ 0.75L_
104  sLCB104 (D + F + T2) + 0.75(0.3EX - EY - EZ) + 0.75L+ 0.75L_
105  sLCB105 (D + F + T2) + 0.75(-0.3EX + EY + EZ) + 0.75L+ 0.75L_
106  sLCB106 (D + F + T2) + 0.75(-0.3EX + EY - EZ) + 0.75L+ 0.75L_
107  sLCB107 (D + F + T2) + 0.75(-0.3EX - EY + EZ) + 0.75L+ 0.75L_
108  sLCB108 (D + F + T2) + 0.75(-0.3EX - EY - EZ) + 0.75L+ 0.75L_
109  sLCB109 0.6(D+ T2) + WX
110  sLCB110 0.6(D+ T2) - WY
111  sLCB111 0.6(D+ T2) + WY
112  sLCB112 0.6(D+ T2) - WY
113  sLCB113 0.6(D + F + T2) + EX + 0.3EY + EZ
114  sLCB114 0.6(D + F + T2) + EX + 0.3EY - EZ
115  sLCB115 0.6(D + F + T2) + EX - 0.3EY + EZ
116  sLCB116 0.6(D + F + T2) + EX - 0.3EY – EZ

Revisión F 96
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-003

117  sLCB117 0.6(D + F + T2) - EX + 0.3EY + EZ


118  sLCB118 0.6(D + F + T2) - EX + 0.3EY - EZ
119  sLCB119 0.6(D + F + T2) - EX - 0.3EY + EZ
120  sLCB120 0.6(D + F + T2) - EX - 0.3EY – EZ
121  sLCB121 0.6(D + F + T2) + 0.3EX + EY + EZ
122  sLCB122 0.6(D + F + T2) + 0.3EX + EY - EZ
123  sLCB123 0.6(D + F + T2) + 0.3EX - EY + EZ
124  sLCB124 0.6(D + F + T2) + 0.3EX - EY – EZ
125  sLCB125 0.6(D + F + T2) - 0.3EX + EY + EZ
126  sLCB126 0.6(D + F + T2) - 0.3EX + EY - EZ
127  sLCB127 0.6(D + F + T2) - 0.3EX - EY + EZ
128  sLCB128 0.6(D + F + T2) - 0.3EX - EY – EZ
129  sLCB129 (D + F + T3)
130  sLCB130 (D + F + T3) + L + L_
131  sLCB131 (D + F + T3) + Lr
132  sLCB132 (D + F + T3) + 0.75L + 0.75L_ + 0.75Lr
133  sLCB133 (D + F + T3) + WX
134  sLCB134 (D + F + T3) - WX
135  sLCB135 (D + F + T3) + WY
136  sLCB136 (D + F + T3) - WY
137  sLCB137 (D + F + T3) + EX + 0.3EY + EZ
138  sLCB138 (D + F + T3) + EX + 0.3EY - EZ
139  sLCB139 (D + F + T3) + EX - 0.3EY + EZ
140  sLCB140 (D + F + T3) + EX - 0.3EY – EZ
141  sLCB141 (D + F + T3) - EX + 0.3EY + EZ
142  sLCB142 (D + F + T3) - EX + 0.3EY - EZ
143  sLCB143 (D + F + T3) - EX - 0.3EY + EZ
144  sLCB144 (D + F + T3) - EX - 0.3EY – EZ
145  sLCB145 (D + F + T3) + 0.3EX + EY + EZ
146  sLCB146 (D + F + T3) + 0.3EX + EY - EZ

Revisión F 97
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-003

147  sLCB147 (D + F + T3) + 0.3EX - EY + EZ


148  sLCB148 (D + F + T3) + 0.3EX - EY – EZ
149  sLCB149 (D + F + T3) - 0.3EX + EY + EZ
150  sLCB150 (D + F + T3) - 0.3EX + EY - EZ
151  sLCB151 (D + F + T3) - 0.3EX - EY + EZ
152  sLCB152 (D + F + T3) - 0.3EX - EY - EZ
153  sLCB153 (D + F + T3) + 0.75WX + 0.75L+ 0.75L_ + 0.75Lr
154  sLCB154 (D + F + T3) - 0.75WX + 0.75L+ 0.75L_ + 0.75Lr
155  sLCB155 (D + F + T3) + 0.75WY + 0.75L+ 0.75L_ + 0.75Lr
156  sLCB156 (D + F + T3) - 0.75WY + 0.75L+ 0.75L_ + 0.75Lr
157  sLCB157 (D + F + T3) + 0.75(EX + 0.3EY + EZ) + 0.75L+ 0.75L_
158  sLCB158 (D + F + T3) + 0.75(EX + 0.3EY - EZ) + 0.75L+ 0.75L_
159  sLCB159 (D + F + T3) + 0.75(EX - 0.3EY + EZ) + 0.75L+ 0.75L_
160  sLCB160 (D + F + T3) + 0.75(EX - 0.3EY - EZ) + 0.75L+ 0.75L_
161  sLCB161 (D + F + T3) + 0.75(-EX + 0.3EY + EZ) + 0.75L+ 0.75L_
162  sLCB162 (D + F + T3) + 0.75(-EX + 0.3EY - EZ) + 0.75L+ 0.75L_
163  sLCB163 (D + F + T3) + 0.75(-EX - 0.3EY + EZ) + 0.75L+ 0.75L_
164  sLCB164 (D + F + T3) + 0.75(-EX - 0.3EY - EZ) + 0.75L+ 0.75L_
165  sLCB165 (D + F + T3) + 0.75(0.3EX + EY + EZ) + 0.75L+ 0.75L_
166  sLCB166 (D + F + T3) + 0.75(0.3EX + EY - EZ) + 0.75L+ 0.75L_
167  sLCB167 (D + F + T3) + 0.75(0.3EX - EY + EZ) + 0.75L+ 0.75L_
168  sLCB168 (D + F + T3) + 0.75(0.3EX - EY - EZ) + 0.75L+ 0.75L_
169  sLCB169 (D + F + T3) + 0.75(-0.3EX + EY + EZ) + 0.75L+ 0.75L_
170  sLCB170 (D + F + T3) + 0.75(-0.3EX + EY - EZ) + 0.75L+ 0.75L_
171  sLCB171 (D + F + T3) + 0.75(-0.3EX - EY + EZ) + 0.75L+ 0.75L_
172  sLCB172 (D + F + T3) + 0.75(-0.3EX - EY - EZ) + 0.75L+ 0.75L_
173  sLCB173 0.6(D+ T3) + WX
174  sLCB174 0.6(D+ T3) - WY
175  sLCB175 0.6(D+ T3) + WY
176  sLCB176 0.6(D+ T3) - WY

Revisión F 98
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-003

177  sLCB177 0.6(D + F + T3) + EX + 0.3EY + EZ


178  sLCB178 0.6(D + F + T3) + EX + 0.3EY - EZ
179  sLCB179 0.6(D + F + T3) + EX - 0.3EY + EZ
180  sLCB180 0.6(D + F + T3) + EX - 0.3EY - EZ
181  sLCB181 0.6(D + F + T3) + EX + 0.3EY + EZ
182  sLCB182 0.6(D + F + T3) - EX + 0.3EY - EZ
183  sLCB183 0.6(D + F + T3) - EX - 0.3EY + EZ
184  sLCB184 0.6(D + F + T3) - EX - 0.3EY - EZ
185  sLCB185 0.6(D + F + T3) + 0.3EX + EY + EZ
186  sLCB186 0.6(D + F + T3) + 0.3EX + EY - EZ

187  sLCB187 0.6(D + F + T3) + 0.3EX - EY + EZ


188  sLCB188 0.6(D + F + T3) + 0.3EX - EY - EZ

189  sLCB189 0.6(D + F + T3) - 0.3EX + EY + EZ


190  sLCB190 0.6(D + F + T3) - 0.3EX + EY - EZ

191  sLCB191 0.6(D + F + T3) - 0.3EX - EY + EZ


192  sLCB192 0.6(D + F + T3) - 0.3EX - EY - EZ

193  sLCB193 (D + F + T4)


194  sLCB194 (D + F + T4) + L + L_
195  sLCB195 (D + F + T4) + Lr
196  sLCB196 (D + F + T4) + 0.75L + 0.75L_ + 0.75Lr
197  sLCB197 (D + F + T4) + WX
198  sLCB198 (D + F + T4) - WX
199  sLCB199 (D + F + T4) + WY
200  sLCB200 (D + F + T4) - WY
201  sLCB201 (D + F + T4) + EX + 0.3EY + EZ
202  sLCB202 (D + F + T4) + EX + 0.3EY - EZ
203  sLCB203 (D + F + T4) + EX - 0.3EY + EZ
204  sLCB204 (D + F + T4) + EX - 0.3EY - EZ
205  sLCB205 (D + F + T4) - EX + 0.3EY + EZ
206  sLCB206 (D + F + T4) - EX + 0.3EY - EZ

Revisión F 99
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-003

207  sLCB207 (D + F + T4) - EX - 0.3EY + EZ


208  sLCB208 (D + F + T4) - EX - 0.3EY - EZ
209  sLCB209 (D + F + T4) + 0.3EX + EY + EZ
210  sLCB210 (D + F + T4) + 0.3EX + EY - EZ
211  sLCB211 (D + F + T4) + 0.3EX - EY + EZ
212  sLCB212 (D + F + T4) + 0.3EX - EY – EZ
213  sLCB213 (D + F + T4) - 0.3EX + EY + EZ
214  sLCB214 (D + F + T4) - 0.3EX + EY - EZ
215  sLCB215 (D + F + T4) - 0.3EX - EY + EZ
216  sLCB216 (D + F + T4) - 0.3EX - EY – EZ
217  sLCB217 (D + F + T4) + 0.75WX + 0.75L+ 0.75L_ + 0.75Lr
218  sLCB218 (D + F + T4) - 0.75WX + 0.75L+ 0.75L_ + 0.75Lr
219  sLCB219 (D + F + T4) + 0.75WY + 0.75L+ 0.75L_ + 0.75Lr
220  sLCB220 (D + F + T4) - 0.75WY + 0.75L+ 0.75L_ + 0.75Lr
221  sLCB221 (D + F + T4) + 0.75(EX + 0.3EY + EZ) + 0.75L+ 0.75L_
222  sLCB222 (D + F + T4) + 0.75(EX + 0.3EY - EZ) + 0.75L+ 0.75L_
223  sLCB223 (D + F + T4) + 0.75(EX - 0.3EY + EZ) + 0.75L+ 0.75L_
224  sLCB224 (D + F + T4) + 0.75(EX - 0.3EY - EZ) + 0.75L+ 0.75L_
225  sLCB225 (D + F + T4) + 0.75(-EX + 0.3EY + EZ) + 0.75L+ 0.75L_
226  sLCB226 (D + F + T4) + 0.75(-EX + 0.3EY - EZ) + 0.75L+ 0.75L_
227  sLCB227 (D + F + T4) + 0.75(-EX - 0.3EY + EZ) + 0.75L+ 0.75L_
228  sLCB228 (D + F + T4) + 0.75(-EX - 0.3EY - EZ) + 0.75L+ 0.75L_
229  sLCB229 (D + F + T4) + 0.75(0.3EX + EY + EZ) + 0.75L+ 0.75L_
230  sLCB230 (D + F + T4) + 0.75(0.3EX + EY - EZ) + 0.75L+ 0.75L_
231  sLCB231 (D + F + T4) + 0.75(0.3EX - EY + EZ) + 0.75L+ 0.75L_
232  sLCB232 (D + F + T4) + 0.75(0.3EX - EY - EZ) + 0.75L+ 0.75L_
233  sLCB233 (D + F + T4) + 0.75(-0.3EX + EY + EZ) + 0.75L+ 0.75L_
234  sLCB234 (D + F + T4) + 0.75(-0.3EX + EY - EZ) + 0.75L+ 0.75L_
235  sLCB235 (D + F + T4) + 0.75(-0.3EX - EY + EZ) + 0.75L+ 0.75L_
236  sLCB236 (D + F + T4) + 0.75(-0.3EX - EY - EZ) + 0.75L+ 0.75L_

Revisión F 100
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-003

237  sLCB237 0.6(D+ T4) + WX


238  sLCB238 0.6(D+ T4) - WY
239  sLCB239 0.6(D+ T4) + WY
240  sLCB240 0.6(D+ T4) - WY
241  sLCB241 0.6(D + F + T4) + EX + 0.3EY + EZ
242  sLCB242 0.6(D + F + T4) + EX + 0.3EY - EZ
243  sLCB243 0.6(D + F + T4) + EX - 0.3EY + EZ
244  sLCB244 0.6(D + F + T4) + EX - 0.3EY - EZ
245  sLCB245 0.6(D + F + T4) - EX + 0.3EY + EZ
246  sLCB246 0.6(D + F + T4) - EX + 0.3EY - EZ
247  sLCB247 0.6(D + F + T4) - EX - 0.3EY + EZ
248  sLCB248 0.6(D + F + T4) - EX - 0.3EY - EZ
249  sLCB249 0.6(D + F + T4) + 0.3EX + EY + EZ
250  sLCB250 0.6(D + F + T4) + 0.3EX + EY - EZ

251  sLCB251 0.6(D + F + T4) + 0.3EX - EY + EZ


252  sLCB252 0.6(D + F + T4) + 0.3EX - EY - EZ

253  sLCB253 0.6(D + F + T4) - 0.3EX + EY + EZ


254  sLCB254 0.6(D + F + T4) - 0.3EX + EY - EZ

255  sLCB255 0.6(D + F + T4) - 0.3EX - EY + EZ


256  sLCB256 0.6(D + F + T4) - 0.3EX - EY - EZ

257  sLCB257 (D + F + T5)


258  sLCB258 (D + F + T5) + L + L_
259  sLCB259 (D + F + T5) + Lr
260  sLCB260 (D + F + T5) + 0.75L + 0.75L_ + 0.75Lr
261  sLCB261 (D + F + T5) + WX
262  sLCB262 (D + F + T5) - WX
263  sLCB263 (D + F + T5) + WY
264  sLCB264 (D + F + T5) - WY
265  sLCB265 (D + F + T5) + EX + 0.3EY + EZ
266  sLCB266 (D + F + T5) + EX + 0.3EY - EZ

Revisión F 101
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-003

267  sLCB267 (D + F + T5) + EX - 0.3EY + EZ


268  sLCB268 (D + F + T5) + EX - 0.3EY - EZ
269  sLCB269 (D + F + T5) - EX + 0.3EY + EZ
270  sLCB270 (D + F + T5) - EX + 0.3EY - EZ
271  sLCB271 (D + F + T5) - EX - 0.3EY + EZ
272  sLCB272 (D + F + T5) - EX - 0.3EY - EZ
273  sLCB273 (D + F + T5) + 0.3EX + EY + EZ
274  sLCB274 (D + F + T5) + 0.3EX + EY - EZ
275  sLCB275 (D + F + T5) + 0.3EX - EY + EZ
276  sLCB276 (D + F + T5) + 0.3EX - EY - EZ
277  sLCB277 (D + F + T5) - 0.3EX + EY + EZ
278  sLCB278 (D + F + T5) - 0.3EX + EY - EZ
279  sLCB279 (D + F + T5) - 0.3EX - EY + EZ
280  sLCB280 (D + F + T5) - 0.3EX - EY - EZ
281  sLCB281 (D + F + T5) + 0.75WX + 0.75L+ 0.75L_ + 0.75Lr
282  sLCB282 (D + F + T5) - 0.75WX + 0.75L+ 0.75L_ + 0.75Lr
283  sLCB283 (D + F + T5) + 0.75WY + 0.75L+ 0.75L_ + 0.75Lr
284  sLCB284 (D + F + T5) - 0.75WY + 0.75L+ 0.75L_ + 0.75Lr
285  sLCB285 (D + F + T5) + 0.75(EX + 0.3EY + EZ) + 0.75L+ 0.75L_
286  sLCB286 (D + F + T5) + 0.75(EX + 0.3EY - EZ) + 0.75L+ 0.75L_
287  sLCB287 (D + F + T5) + 0.75(EX - 0.3EY + EZ) + 0.75L+ 0.75L_
288  sLCB288 (D + F + T5) + 0.75(EX - 0.3EY - EZ) + 0.75L+ 0.75L_
289  sLCB289 (D + F + T5) + 0.75(-EX + 0.3EY + EZ) + 0.75L+ 0.75L_
290  sLCB290 (D + F + T5) + 0.75(-EX + 0.3EY - EZ) + 0.75L+ 0.75L_
291  sLCB291 (D + F + T5) + 0.75(-EX - 0.3EY + EZ) + 0.75L+ 0.75L_
292  sLCB292 (D + F + T5) + 0.75(-EX - 0.3EY - EZ) + 0.75L+ 0.75L_
293  sLCB293 (D + F + T5) + 0.75(0.3EX + EY + EZ) + 0.75L+ 0.75L_
294  sLCB294 (D + F + T5) + 0.75(0.3EX + EY - EZ) + 0.75L+ 0.75L_
295  sLCB295 (D + F + T5) + 0.75(0.3EX - EY + EZ) + 0.75L+ 0.75L_
296  sLCB296 (D + F + T5) + 0.75(0.3EX - EY - EZ) + 0.75L+ 0.75L_

Revisión F 102
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-003

297  sLCB297 (D + F + T5) + 0.75(-0.3EX + EY + EZ) + 0.75L+ 0.75L_


298  sLCB298 (D + F + T5) + 0.75(-0.3EX + EY - EZ) + 0.75L+ 0.75L_
299  sLCB299 (D + F + T5) + 0.75(-0.3EX - EY + EZ) + 0.75L+ 0.75L_
300  sLCB300 (D + F + T5) + 0.75(-0.3EX - EY - EZ) + 0.75L+ 0.75L_
301  sLCB301 0.6(D+ T5) + WX
302  sLCB302 0.6(D+ T5) - WY
303  sLCB303 0.6(D+ T5) + WY
304  sLCB304 0.6(D+ T5) - WY
305  sLCB305 0.6(D + F + T5) + EX + 0.3EY + EZ
306  sLCB306 0.6(D + F + T5) + EX + 0.3EY - EZ
307  sLCB307 0.6(D + F + T5) + EX - 0.3EY + EZ
308  sLCB308 0.6(D + F + T5) + EX - 0.3EY - EZ
309  sLCB309 0.6(D + F + T5) - EX + 0.3EY + EZ
310  sLCB310 0.6(D + F + T5) - EX + 0.3EY - EZ
311  sLCB311 0.6(D + F + T5) - EX - 0.3EY + EZ
312  sLCB312 0.6(D + F + T5) - EX - 0.3EY - EZ
313  sLCB313 0.6(D + F + T5) + 0.3EX + EY + EZ
314  sLCB314 0.6(D + F + T5) + 0.3EX + EY - EZ

315  sLCB315 0.6(D + F + T5) + 0.3EX - EY + EZ


316  sLCB316 0.6(D + F + T5) + 0.3EX - EY – EZ

317  sLCB317 0.6(D + F + T5) - 0.3EX + EY + EZ


318  sLCB318 0.6(D + F + T5) - 0.3EX + EY - EZ

319  sLCB319 0.6(D + F + T5) - 0.3EX - EY + EZ


320  sLCB320 0.6(D + F + T5) - 0.3EX - EY – EZ

321  sLCB321 (D + F)
322  sLCB322 (D + F) + L + L_
323  sLCB323 (D + F) + Lr
324  sLCB324 (D + F) + 0.75L + 0.75L_ + 0.75Lr
325  sLCB325 (D + F) + WX
326  sLCB326 (D + F) - WX

Revisión F 103
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-003

327  sLCB327 (D + F) + WY
328  sLCB328 (D + F) - WY
329  sLCB329 (D + F) + EX + 0.3EY + EZ
330  sLCB330 (D + F) + EX + 0.3EY – EZ
331  sLCB331 (D + F) + EX - 0.3EY + EZ
332  sLCB332 (D + F) + EX - 0.3EY – EZ
333  sLCB333 (D + F) - EX + 0.3EY + EZ
334  sLCB334 (D + F) - EX + 0.3EY – EZ
335  sLCB335 (D + F) - EX - 0.3EY + EZ
336  sLCB336 (D + F) - EX - 0.3EY – EZ
337  sLCB337 (D + F) + 0.3EX + EY + EZ
338  sLCB338 (D + F) + 0.3EX + EY – EZ
339  sLCB339 (D + F) + 0.3EX - EY + EZ
340  sLCB340 (D + F) + 0.3EX - EY – EZ
341  sLCB341 (D + F) - 0.3EX + EY + EZ
342  sLCB342 (D + F) - 0.3EX + EY – EZ
343  sLCB343 (D + F) - 0.3EX - EY + EZ
344  sLCB344 (D + F) - 0.3EX - EY – EZ
345  sLCB345 (D + F) + 0.75WX + 0.75L+ 0.75L_ + 0.75Lr
346  sLCB346 (D + F) - 0.75WX + 0.75L+ 0.75L_ + 0.75Lr
347  sLCB347 (D + F) + 0.75WY + 0.75L+ 0.75L_ + 0.75Lr
348  sLCB348 (D + F) - 0.75WY + 0.75L+ 0.75L_ + 0.75Lr
349  sLCB349 (D + F) + 0.75(EX + 0.3EY + EZ) + 0.75L+ 0.75L_
350  sLCB350 (D + F) + 0.75(EX + 0.3EY - EZ) + 0.75L+ 0.75L_
351  sLCB351 (D + F) + 0.75(EX - 0.3EY + EZ) + 0.75L+ 0.75L_
352  sLCB352 (D + F) + 0.75(EX - 0.3EY - EZ) + 0.75L+ 0.75L_
353  sLCB353 (D + F) + 0.75(-EX + 0.3EY + EZ) + 0.75L+ 0.75L_
354  sLCB354 (D + F) + 0.75(-EX + 0.3EY - EZ) + 0.75L+ 0.75L_
355  sLCB355 (D + F) + 0.75(-EX - 0.3EY + EZ) + 0.75L+ 0.75L_
356  sLCB356 (D + F) + 0.75(-EX - 0.3EY - EZ) + 0.75L+ 0.75L_

Revisión F 104
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-003

357  sLCB357 (D + F) + 0.75(0.3EX + EY + EZ) + 0.75L+ 0.75L_


358  sLCB358 (D + F) + 0.75(0.3EX + EY - EZ) + 0.75L+ 0.75L_
359  sLCB359 (D + F) + 0.75(0.3EX - EY + EZ) + 0.75L+ 0.75L_
360  sLCB360 (D + F) + 0.75(0.3EX - EY - EZ) + 0.75L+ 0.75L_
361  sLCB361 (D + F) + 0.75(-0.3EX + EY + EZ) + 0.75L+ 0.75L_
362  sLCB362 (D + F) + 0.75(-0.3EX + EY - EZ) + 0.75L+ 0.75L_
363  sLCB363 (D + F) + 0.75(-0.3EX - EY + EZ) + 0.75L+ 0.75L_
364  sLCB364 (D + F) + 0.75(-0.3EX - EY - EZ) + 0.75L+ 0.75L_
365  sLCB365 0.6(D) + WX
366  sLCB366 0.6(D) - WY
367  sLCB367 0.6(D) + WY
368  sLCB368 0.6(D) - WY
369  sLCB369 0.6(D + F) + EX + 0.3EY + EZ
370  sLCB370 0.6(D + F) + EX + 0.3EY - EZ
371  sLCB371 0.6(D + F) + EX - 0.3EY + EZ
372  sLCB372 0.6(D + F) + EX - 0.3EY - EZ
373  sLCB373 0.6(D + F) - EX + 0.3EY + EZ
374  sLCB374 0.6(D + F) - EX + 0.3EY - EZ
375  sLCB375 0.6(D + F) - EX - 0.3EY + EZ
376  sLCB376 0.6(D + F) - EX - 0.3EY - EZ
377  sLCB377 0.6(D + F) + 0.3EX + EY + EZ
378  sLCB378 0.6(D + F) + 0.3EX + EY - EZ
379  sLCB379 0.6(D + F) + 0.3EX - EY + EZ
380  sLCB380 0.6(D + F) + 0.3EX - EY - EZ
381  sLCB381 0.6(D + F) - 0.3EX + EY + EZ
382  sLCB382 0.6(D + F) - 0.3EX + EY - EZ
383  sLCB383 0.6(D + F) - 0.3EX - EY + EZ
384  sLCB384 0.6(D + F) - 0.3EX - EY - EZ
385  sLCB385 (D + T1)
386  sLCB386 (D + T1) + L + L_

Revisión F 105
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-003

387  sLCB387 (D + T1) + Lr


388  sLCB388 (D + T1) + 0.75L + 0.75L_ + 0.75Lr
389  sLCB389 (D + T1) + WX
390  sLCB390 (D + T1) - WX
391  sLCB391 (D + T1) + WY
392  sLCB392 (D + T1) - WY
393  sLCB393 (D + T1) + EX + 0.3EY + EZ
394  sLCB394 (D + T1) + EX + 0.3EY - EZ
395  sLCB395 (D + T1) + EX - 0.3EY + EZ
396  sLCB396 (D + T1) + EX - 0.3EY - EZ
397  sLCB397 (D + T1) - EX + 0.3EY + EZ
398  sLCB398 (D + T1) - EX + 0.3EY - EZ
399  sLCB399 (D + T1) - EX - 0.3EY + EZ
400  sLCB400 (D + T1) - EX - 0.3EY - EZ
401  sLCB401 (D + T1) + 0.3EX + EY + EZ
402  sLCB402 (D + T1) + 0.3EX + EY - EZ
403  sLCB403 (D + T1) + 0.3EX - EY + EZ
404  sLCB404 (D + T1) + 0.3EX - EY - EZ
405  sLCB405 (D + T1) - 0.3EX + EY + EZ
406  sLCB406 (D + T1) - 0.3EX + EY - EZ
407  sLCB407 (D + T1) - 0.3EX - EY + EZ
408  sLCB408 (D + T1) - 0.3EX - EY - EZ
409  sLCB409 (D + T1) + 0.75WX + 0.75L+ 0.75L_ + 0.75Lr
410  sLCB410 (D + T1) - 0.75WX + 0.75L+ 0.75L_ + 0.75Lr
411  sLCB411 (D + T1) + 0.75WY + 0.75L+ 0.75L_ + 0.75Lr
412  sLCB412 (D + T1) - 0.75WY + 0.75L+ 0.75L_ + 0.75Lr
413  sLCB413 (D + T1) + 0.75(EX + 0.3EY + EZ) + 0.75L+ 0.75L_
414  sLCB414 (D + T1) + 0.75(EX + 0.3EY - EZ) + 0.75L+ 0.75L_
415  sLCB415 (D + T1) + 0.75(EX - 0.3EY + EZ) + 0.75L+ 0.75L_
416  sLCB416 (D + T1) + 0.75(EX - 0.3EY - EZ) + 0.75L+ 0.75L_

Revisión F 106
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-003

417  sLCB417 (D + T1) + 0.75(-EX + 0.3EY + EZ) + 0.75L+ 0.75L_


418  sLCB418 (D + T1) + 0.75(-EX + 0.3EY - EZ) + 0.75L+ 0.75L_
419  sLCB419 (D + T1) + 0.75(-EX - 0.3EY + EZ) + 0.75L+ 0.75L_
420  sLCB420 (D + T1) + 0.75(-EX - 0.3EY - EZ) + 0.75L+ 0.75L_
421  sLCB421 (D + T1) + 0.75(0.3EX + EY + EZ) + 0.75L+ 0.75L_
422  sLCB422 (D + T1) + 0.75(0.3EX + EY - EZ) + 0.75L+ 0.75L_
423  sLCB423 (D + T1) + 0.75(0.3EX - EY + EZ) + 0.75L+ 0.75L_
424  sLCB424 (D + T1) + 0.75(0.3EX - EY - EZ) + 0.75L+ 0.75L_
425  sLCB425 (D + T1) + 0.75(-0.3EX + EY + EZ) + 0.75L+ 0.75L_
426  sLCB426 (D + T1) + 0.75(-0.3EX + EY - EZ) + 0.75L+ 0.75L_
427  sLCB427 (D + T1) + 0.75(-0.3EX - EY + EZ) + 0.75L+ 0.75L_
428  sLCB428 (D + T1) + 0.75(-0.3EX - EY - EZ) + 0.75L+ 0.75L_
429  sLCB429 0.6(D + T1) + EX + 0.3EY + EZ
430  sLCB430 0.6(D + T1) + EX + 0.3EY – EZ
431  sLCB431 0.6(D + T1) + EX - 0.3EY + EZ
432  sLCB432 0.6(D + T1) + EX - 0.3EY - EZ
433  sLCB433 0.6(D + T1) - EX + 0.3EY + EZ
434  sLCB434 0.6(D + T1) - EX + 0.3EY – EZ
435  sLCB435 0.6(D + T1) - EX - 0.3EY + EZ
436  sLCB436 0.6(D + T1) - EX - 0.3EY - EZ
437  sLCB437 0.6(D + T1) + 0.3EX + EY + EZ
438  sLCB438 0.6(D + T1) + 0.3EX + EY - EZ

439  sLCB439 0.6(D + T1) + 0.3EX - EY + EZ


440  sLCB440 0.6(D + T1) + 0.3EX - EY - EZ

441  sLCB441 0.6(D + T1) - 0.3EX + EY + EZ


442  sLCB442 0.6(D + T1) - 0.3EX + EY - EZ

443  sLCB443 0.6(D + T1) - 0.3EX - EY + EZ


444  sLCB444 0.6(D + T1) - 0.3EX - EY - EZ

445  sLCB445 (D + T2)


446  sLCB446 (D + T2) + L + L_

Revisión F 107
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-003

447  sLCB447 (D + T2) + Lr


448  sLCB448 (D + T2) + 0.75L + 0.75L_ + 0.75Lr
449  sLCB449 (D + T2) + WX
450  sLCB450 (D + T2) - WX
451  sLCB451 (D + T2) + WY
452  sLCB452 (D + T2) - WY
453  sLCB453 (D + T2) + EX + 0.3EY + EZ
454  sLCB454 (D + T2) + EX + 0.3EY - EZ
455  sLCB455 (D + T2) + EX - 0.3EY + EZ
456  sLCB456 (D + T2) + EX - 0.3EY - EZ
457  sLCB457 (D + T2) - EX + 0.3EY + EZ
458  sLCB458 (D + T2) - EX + 0.3EY - EZ
459  sLCB459 (D + T2) - EX - 0.3EY + EZ
460  sLCB460 (D + T2) - EX - 0.3EY - EZ
461  sLCB461 (D + T2) + 0.3EX + EY + EZ
462  sLCB462 (D + T2) + 0.3EX + EY - EZ
463  sLCB463 (D + T2) + 0.3EX - EY + EZ
464  sLCB464 (D + T2) + 0.3EX - EY - EZ
465  sLCB465 (D + T2) - 0.3EX + EY + EZ
466  sLCB466 (D + T2) - 0.3EX + EY - EZ
467  sLCB467 (D + T2) - 0.3EX - EY + EZ
468  sLCB468 (D + T2) - 0.3EX - EY - EZ
469  sLCB469 (D + T2) + 0.75WX + 0.75L+ 0.75L_ + 0.75Lr
470  sLCB470 (D + T2) - 0.75WX + 0.75L+ 0.75L_ + 0.75Lr
471  sLCB471 (D + T2) + 0.75WY + 0.75L+ 0.75L_ + 0.75Lr
472  sLCB472 (D + T2) - 0.75WY + 0.75L+ 0.75L_ + 0.75Lr
473  sLCB473 (D + T2) + 0.75(EX + 0.3EY + EZ) + 0.75L+ 0.75L_
474  sLCB474 (D + T2) + 0.75(EX + 0.3EY - EZ) + 0.75L+ 0.75L_
475  sLCB475 (D + T2) + 0.75(EX – 0.3EY + EZ) + 0.75L+ 0.75L_
476  sLCB476 (D + T2) + 0.75(EX – 0.3EY - EZ) + 0.75L+ 0.75L_

Revisión F 108
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-003

477  sLCB477 (D + T2) + 0.75(-EX + 0.3EY + EZ) + 0.75L+ 0.75L_


478  sLCB478 (D + T2) + 0.75(-EX + 0.3EY - EZ) + 0.75L+ 0.75L_
479  sLCB479 (D + T2) + 0.75(-EX – 0.3EY + EZ) + 0.75L+ 0.75L_
480  sLCB480 (D + T2) + 0.75(-EX – 0.3EY - EZ) + 0.75L+ 0.75L_
481  sLCB481 (D + T2) + 0.75(0.3EX + EY + EZ) + 0.75L+ 0.75L_
482  sLCB482 (D + T2) + 0.75(0.3EX + EY - EZ) + 0.75L+ 0.75L_
483  sLCB483 (D + T2) + 0.75(0.3EX - EY + EZ) + 0.75L+ 0.75L_
484  sLCB484 (D + T2) + 0.75(0.3EX - EY - EZ) + 0.75L+ 0.75L_
485  sLCB485 (D + T2) + 0.75(-0.3EX + EY + EZ) + 0.75L+ 0.75L_
486  sLCB486 (D + T2) + 0.75(-0.3EX + EY - EZ) + 0.75L+ 0.75L_
487  sLCB487 (D + T2) + 0.75(-0.3EX - EY + EZ) + 0.75L+ 0.75L_
488  sLCB488 (D + T2) + 0.75(-0.3EX - EY - EZ) + 0.75L+ 0.75L_
489  sLCB489 0.6(D + T2) + EX + 0.3EY + EZ
490  sLCB490 0.6(D + T2) + EX + 0.3EY - EZ
491  sLCB491 0.6(D + T2) + EX - 0.3EY + EZ
492  sLCB492 0.6(D + T2) + EX - 0.3EY - EZ
493  sLCB493 0.6(D + T2) - EX + 0.3EY + EZ
494  sLCB494 0.6(D + T2) - EX + 0.3EY - EZ
495  sLCB495 0.6(D + T2) - EX - 0.3EY + EZ
496  sLCB496 0.6(D + T2) - EX - 0.3EY - EZ
497  sLCB497 0.6(D + T2) + 0.3EX + EY + EZ
498  sLCB498 0.6(D + T2) + 0.3EX + EY - EZ

499  sLCB499 0.6(D + T2) + 0.3EX - EY + EZ


500  sLCB500 0.6(D + T2) + 0.3EX - EY - EZ

501  sLCB501 0.6(D + T2) - 0.3EX + EY + EZ


502  sLCB502 0.6(D + T2) - 0.3EX + EY - EZ

503  sLCB503 0.6(D + T2) - 0.3EX - EY + EZ


504  sLCB504 0.6(D + T2) - 0.3EX - EY - EZ

505  sLCB505 (D + T3)


506  sLCB506 (D + T3) + L + L_

Revisión F 109
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-003

507  sLCB507 (D + T3) + Lr


508  sLCB508 (D + T3) + 0.75L + 0.75L_ + 0.75Lr
509  sLCB509 (D + T3) + WX
510  sLCB510 (D + T3) - WX
511  sLCB511 (D + T3) + WY
512  sLCB512 (D + T3) - WY
513  sLCB513 (D + T3) + EX + 0.3EY + EZ
514  sLCB514 (D + T3) + EX + 0.3EY - EZ
515  sLCB515 (D + T3) + EX - 0.3EY + EZ
516  sLCB516 (D + T3) + EX - 0.3EY - EZ
517  sLCB517 (D + T3) - EX + 0.3EY + EZ
518  sLCB518 (D + T3) - EX + 0.3EY - EZ
519  sLCB519 (D + T3) - EX - 0.3EY + EZ
520  sLCB520 (D + T3) - EX - 0.3EY - EZ
521  sLCB521 (D + T3) + 0.3EX + EY + EZ
522  sLCB522 (D + T3) + 0.3EX + EY - EZ
523  sLCB523 (D + T3) + 0.3EX - EY + EZ
524  sLCB524 (D + T3) + 0.3EX - EY - EZ
525  sLCB525 (D + T3) - 0.3EX + EY + EZ
526  sLCB526 (D + T3) - 0.3EX + EY - EZ
527  sLCB527 (D + T3) - 0.3EX - EY + EZ
528  sLCB528 (D + T3) - 0.3EX - EY - EZ
529  sLCB529 (D + T3) + 0.75WX + 0.75L+ 0.75L_ + 0.75Lr
530  sLCB530 (D + T3) - 0.75WX + 0.75L+ 0.75L_ + 0.75Lr
531  sLCB531 (D + T3) + 0.75WY + 0.75L+ 0.75L_ + 0.75Lr
532  sLCB532 (D + T3) - 0.75WY + 0.75L+ 0.75L_ + 0.75Lr
533  sLCB533 (D + T3) + 0.75(EX + 0.3EY + EZ) + 0.75L+ 0.75L_
534  sLCB534 (D + T3) + 0.75(EX + 0.3EY - EZ) + 0.75L+ 0.75L_
535  sLCB535 (D + T3) + 0.75(EX - 0.3EY + EZ) + 0.75L+ 0.75L_
536  sLCB536 (D + T3) + 0.75(EX - 0.3EY - EZ) + 0.75L+ 0.75L_

Revisión F 110
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-003

537  sLCB537 (D + T3) + 0.75(-EX + 0.3EY + EZ) + 0.75L+ 0.75L_


538  sLCB538 (D + T3) + 0.75(-EX + 0.3EY - EZ) + 0.75L+ 0.75L_
539  sLCB539 (D + T3) + 0.75(-EX - 0.3EY + EZ) + 0.75L+ 0.75L_
540  sLCB540 (D + T3) + 0.75(-EX - 0.3EY - EZ) + 0.75L+ 0.75L_
541  sLCB541 (D + T3) + 0.75(0.3EX + EY + EZ) + 0.75L+ 0.75L_
542  sLCB542 (D + T3) + 0.75(0.3EX + EY - EZ) + 0.75L+ 0.75L_
543  sLCB543 (D + T3) + 0.75(0.3EX - EY + EZ) + 0.75L+ 0.75L_
544  sLCB544 (D + T3) + 0.75(0.3EX - EY - EZ) + 0.75L+ 0.75L_
545  sLCB545 (D + T3) + 0.75(-0.3EX + EY + EZ) + 0.75L+ 0.75L_
546  sLCB546 (D + T3) + 0.75(-0.3EX + EY - EZ) + 0.75L+ 0.75L_
547  sLCB547 (D + T3) + 0.75(-0.3EX - EY + EZ) + 0.75L+ 0.75L_
548  sLCB548 (D + T3) + 0.75(-0.3EX - EY - EZ) + 0.75L+ 0.75L_
549  sLCB549 0.6(D + T3) + EX + 0.3EY + EZ
550  sLCB550 0.6(D + T3) + EX + 0.3EY - EZ
551  sLCB551 0.6(D + T3) + EX - 0.3EY + EZ
552  sLCB552 0.6(D + T3) + EX - 0.3EY - EZ
553  sLCB553 0.6(D + T3) - EX + 0.3EY + EZ
554  sLCB554 0.6(D + T3) - EX + 0.3EY - EZ
555  sLCB555 0.6(D + T3) - EX - 0.3EY + EZ
556  sLCB556 0.6(D + T3) - EX - 0.3EY - EZ
557  sLCB557 0.6(D + T3) + 0.3EX + EY + EZ
558  sLCB558 0.6(D + T3) + 0.3EX + EY - EZ

559  sLCB559 0.6(D + T3) + 0.3EX - EY + EZ


560  sLCB560 0.6(D + T3) + 0.3EX - EY - EZ

561  sLCB561 0.6(D + T3) - 0.3EX + EY + EZ


562  sLCB562 0.6(D + T3) - 0.3EX + EY - EZ

563  sLCB563 0.6(D + T3) - 0.3EX - EY + EZ


564  sLCB564 0.6(D + T3) - 0.3EX - EY - EZ

565  sLCB565 (D + T4)


566  sLCB566 (D + T4) + L + L_

Revisión F 111
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-003

567  sLCB567 (D + T4) + Lr


568  sLCB568 (D + T4) + 0.75L + 0.75L_ + 0.75Lr
569  sLCB569 (D + T4) + WX
570  sLCB570 (D + T4) - WX
571  sLCB571 (D + T4) + WY
572  sLCB572 (D + T4) - WY
573  sLCB573 (D + T4) + EX + 0.3EY + EZ
574  sLCB574 (D + T4) + EX + 0.3EY - EZ
575  sLCB575 (D + T4) + EX - 0.3EY + EZ
576  sLCB576 (D + T4) + EX - 0.3EY - EZ
577  sLCB577 (D + T4) - EX + 0.3EY + EZ
578  sLCB578 (D + T4) - EX + 0.3EY - EZ
579  sLCB579 (D + T4) - EX - 0.3EY + EZ
580  sLCB580 (D + T4) - EX - 0.3EY - EZ
581  sLCB581 (D + T4) + 0.3EX + EY + EZ
582  sLCB582 (D + T4) + 0.3EX + EY - EZ
583  sLCB583 (D + T4) + 0.3EX - EY + EZ
584  sLCB584 (D + T4) + 0.3EX - EY - EZ
585  sLCB585 (D + T4) - 0.3EX + EY + EZ
586  sLCB586 (D + T4) - 0.3EX + EY - EZ
587  sLCB587 (D + T4) - 0.3EX - EY + EZ
588  sLCB588 (D + T4) - 0.3EX - EY - EZ
589  sLCB589 (D + T4) + 0.75WX + 0.75L+ 0.75L_ + 0.75Lr
590  sLCB590 (D + T4) - 0.75WX + 0.75L+ 0.75L_ + 0.75Lr
591  sLCB591 (D + T4) + 0.75WY + 0.75L+ 0.75L_ + 0.75Lr
592  sLCB592 (D + T4) - 0.75WY + 0.75L+ 0.75L_ + 0.75Lr
593  sLCB593 (D + T4) + 0.75(EX + 0.3EY + EZ) + 0.75L+ 0.75L_
594  sLCB594 (D + T4) + 0.75(EX + 0.3EY - EZ) + 0.75L+ 0.75L_
595  sLCB595 (D + T4) + 0.75(EX - 0.3EY + EZ) + 0.75L+ 0.75L_
596  sLCB596 (D + T4) + 0.75(EX - 0.3EY - EZ) + 0.75L+ 0.75L_

Revisión F 112
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-003

597  sLCB597 (D + T4) + 0.75(-EX + 0.3EY + EZ) + 0.75L+ 0.75L_


598  sLCB598 (D + T4) + 0.75(-EX + 0.3EY - EZ) + 0.75L+ 0.75L_
599  sLCB599 (D + T4) + 0.75(-EX - 0.3EY + EZ) + 0.75L+ 0.75L_
600  sLCB600 (D + T4) + 0.75(-EX - 0.3EY - EZ) + 0.75L+ 0.75L_
601  sLCB601 (D + T4) + 0.75(0.3EX + EY + EZ) + 0.75L+ 0.75L_
602  sLCB602 (D + T4) + 0.75(0.3EX + EY - EZ) + 0.75L+ 0.75L_
603  sLCB603 (D + T4) + 0.75(0.3EX - EY + EZ) + 0.75L+ 0.75L_
604  sLCB604 (D + T4) + 0.75(0.3EX - EY - EZ) + 0.75L+ 0.75L_
605  sLCB605 (D + T4) + 0.75(-0.3EX + EY + EZ) + 0.75L+ 0.75L_
606  sLCB606 (D + T4) + 0.75(-0.3EX + EY - EZ) + 0.75L+ 0.75L_
607  sLCB607 (D + T4) + 0.75(-0.3EX - EY + EZ) + 0.75L+ 0.75L_
608  sLCB608 (D + T4) + 0.75(-0.3EX - EY - EZ) + 0.75L+ 0.75L_
609  sLCB609 0.6(D + T4) + EX + 0.3EY + EZ
610  sLCB610 0.6(D + T4) + EX + 0.3EY - EZ
611  sLCB611 0.6(D + T4) + EX - 0.3EY + EZ
612  sLCB612 0.6(D + T4) + EX - 0.3EY - EZ
613  sLCB613 0.6(D + T4) - EX + 0.3EY + EZ
614  sLCB614 0.6(D + T4) - EX + 0.3EY - EZ
615  sLCB615 0.6(D + T4) - EX - 0.3EY + EZ
616  sLCB616 0.6(D + T4) - EX - 0.3EY - EZ
617  sLCB617 0.6(D + T4) + 0.3EX + EY + EZ
618  sLCB618 0.6(D + T4) + 0.3EX + EY - EZ

619  sLCB619 0.6(D + T4) + 0.3EX - EY + EZ


620  sLCB620 0.6(D + T4) + 0.3EX - EY - EZ

621  sLCB621 0.6(D + T4) - 0.3EX + EY + EZ


622  sLCB622 0.6(D + T4) - 0.3EX + EY - EZ

623  sLCB623 0.6(D + T4) - 0.3EX - EY + EZ


624  sLCB624 0.6(D + T4) - 0.3EX - EY - EZ

625  sLCB625 (D + T5)


626  sLCB626 (D + T5) + L + L_

Revisión F 113
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-003

627  sLCB627 (D + T5) + Lr


628  sLCB628 (D + T5) + 0.75L + 0.75L_ + 0.75Lr
629  sLCB629 (D + T5) + WX
630  sLCB630 (D + T5) - WX
631  sLCB631 (D + T5) + WY
632  sLCB632 (D + T5) - WY
633  sLCB633 (D + T5) + EX + 0.3EY + EZ
634  sLCB634 (D + T5) + EX + 0.3EY - EZ
635  sLCB635 (D + T5) + EX - 0.3EY + EZ
636  sLCB636 (D + T5) + EX - 0.3EY - EZ
637  sLCB637 (D + T5) - EX + 0.3EY + EZ
638  sLCB638 (D + T5) - EX + 0.3EY - EZ
639  sLCB639 (D + T5) - EX - 0.3EY + EZ
640  sLCB640 (D + T5) - EX - 0.3EY - EZ
641  sLCB641 (D + T5) + 0.3EX + EY + EZ
642  sLCB642 (D + T5) + 0.3EX + EY - EZ
643  sLCB643 (D + T5) + 0.3EX - EY + EZ
644  sLCB644 (D + T5) + 0.3EX - EY - EZ
645  sLCB645 (D + T5) - 0.3EX + EY + EZ
646  sLCB646 (D + T5) - 0.3EX + EY - EZ
647  sLCB647 (D + T5) - 0.3EX - EY + EZ
648  sLCB648 (D + T5) - 0.3EX - EY - EZ
649  sLCB649 (D + T5) + 0.75WX + 0.75L+ 0.75L_ + 0.75Lr
650  sLCB650 (D + T5) - 0.75WX + 0.75L+ 0.75L_ + 0.75Lr
651  sLCB651 (D + T5) + 0.75WY + 0.75L+ 0.75L_ + 0.75Lr
652  sLCB652 (D + T5) - 0.75WY + 0.75L+ 0.75L_ + 0.75Lr
653  sLCB653 (D + T5) + 0.75(EX + 0.3EY + EZ) + 0.75L+ 0.75L_
654  sLCB654 (D + T5) + 0.75(EX + 0.3EY - EZ) + 0.75L+ 0.75L_
655  sLCB655 (D + T5) + 0.75(EX - 0.3EY + EZ) + 0.75L+ 0.75L_
656  sLCB656 (D + T5) + 0.75(EX - 0.3EY - EZ) + 0.75L+ 0.75L_

Revisión F 114
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-003

657  sLCB657 (D + T5) + 0.75(-EX + 0.3EY + EZ) + 0.75L+ 0.75L_


658  sLCB658 (D + T5) + 0.75(-EX + 0.3EY - EZ) + 0.75L+ 0.75L_
659  sLCB659 (D + T5) + 0.75(-EX - 0.3EY + EZ) + 0.75L+ 0.75L_
660  sLCB660 (D + T5) + 0.75(-EX - 0.3EY - EZ) + 0.75L+ 0.75L_
661  sLCB661 (D + T5) + 0.75(0.3EX + EY + EZ) + 0.75L+ 0.75L_
662  sLCB662 (D + T5) + 0.75(0.3EX + EY - EZ) + 0.75L+ 0.75L_
663  sLCB663 (D + T5) + 0.75(0.3EX - EY + EZ) + 0.75L+ 0.75L_
664  sLCB664 (D + T5) + 0.75(0.3EX - EY - EZ) + 0.75L+ 0.75L_
665  sLCB665 (D + T5) + 0.75(-0.3EX + EY + EZ) + 0.75L+ 0.75L_
666  sLCB666 (D + T5) + 0.75(-0.3EX + EY - EZ) + 0.75L+ 0.75L_
667  sLCB667 (D + T5) + 0.75(-0.3EX - EY + EZ) + 0.75L+ 0.75L_
668  sLCB668 (D + T5) + 0.75(-0.3EX - EY - EZ) + 0.75L+ 0.75L_
669  sLCB669 0.6(D + T5) + EX + 0.3EY + EZ
670  sLCB670 0.6(D + T5) + EX + 0.3EY - EZ
671  sLCB671 0.6(D + T5) + EX - 0.3EY + EZ
672  sLCB672 0.6(D + T5) + EX - 0.3EY - EZ
673  sLCB673 0.6(D + T5) - EX + 0.3EY + EZ
674  sLCB674 0.6(D + T5) - EX + 0.3EY - EZ
675  sLCB675 0.6(D + T5) - EX - 0.3EY + EZ
676  sLCB676 0.6(D + T5) - EX - 0.3EY - EZ
677  sLCB677 0.6(D + T5) + 0.3EX + EY + EZ
678  sLCB678 0.6(D + T5) + 0.3EX + EY - EZ

679  sLCB679 0.6(D + T5) + 0.3EX - EY + EZ


680  sLCB680 0.6(D + T5) + 0.3EX - EY - EZ

681  sLCB681 0.6(D + T5) - 0.3EX + EY + EZ


682  sLCB682 0.6(D + T5) - 0.3EX + EY - EZ

683  sLCB683 0.6(D + T5) - 0.3EX - EY + EZ


684  sLCB684 0.6(D + T5) - 0.3EX - EY - EZ

685  sLCB685 (D)


686  sLCB686 (D) + L + L_

Revisión F 115
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-003

687  sLCB687 (D) + Lr


688  sLCB688 (D) + 0.75L + 0.75L_ + 0.75Lr
689  sLCB689 (D) + WX
690  sLCB690 (D) - WX
691  sLCB691 (D) + WY
692  sLCB692 (D) - WY
693  sLCB693 (D) + EX + 0.3EY + EZ
694  sLCB694 (D) + EX + 0.3EY - EZ
695  sLCB695 (D) + EX - 0.3EY + EZ
696  sLCB696 (D) + EX - 0.3EY - EZ
697  sLCB697 (D) - EX + 0.3EY + EZ
698  sLCB698 (D) - EX + 0.3EY - EZ
699  sLCB699 (D) - EX - 0.3EY + EZ
700  sLCB700 (D) - EX - 0.3EY - EZ
701  sLCB701 (D) + 0.3EX + EY + EZ
702  sLCB702 (D) + 0.3EX + EY - EZ
703  sLCB703 (D) + 0.3EX - EY + EZ
704  sLCB704 (D) + 0.3EX - EY - EZ
705  sLCB705 (D) - 0.3EX + EY + EZ
706  sLCB706 (D) - 0.3EX + EY - EZ
707  sLCB707 (D) - 0.3EX - EY + EZ
708  sLCB708 (D) - 0.3EX - EY - EZ
709  sLCB709 (D) + 0.75WX + 0.75L+ 0.75L_ + 0.75Lr
710  sLCB710 (D) - 0.75WX + 0.75L+ 0.75L_ + 0.75Lr
711  sLCB711 (D) + 0.75WY + 0.75L+ 0.75L_ + 0.75Lr
712  sLCB712 (D) - 0.75WY + 0.75L+ 0.75L_ + 0.75Lr
713  sLCB713 (D) + 0.75(EX + 0.3EY + EZ) + 0.75L+ 0.75L_
714  sLCB714 (D) + 0.75(EX + 0.3EY - EZ) + 0.75L+ 0.75L_
715  sLCB715 (D) + 0.75(EX - 0.3EY + EZ) + 0.75L+ 0.75L_
716  sLCB716 (D) + 0.75(EX - 0.3EY - EZ) + 0.75L+ 0.75L_

Revisión F 116
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-003

717  sLCB717 (D) + 0.75(-EX + 0.3EY + EZ) + 0.75L+ 0.75L_


718  sLCB718 (D) + 0.75(-EX + 0.3EY - EZ) + 0.75L+ 0.75L_
719  sLCB719 (D) + 0.75(-EX - 0.3EY + EZ) + 0.75L+ 0.75L_
720  sLCB720 (D) + 0.75(-EX - 0.3EY - EZ) + 0.75L+ 0.75L_
721  sLCB721 (D) + 0.75(0.3EX + EY + EZ) + 0.75L+ 0.75L_
722  sLCB722 (D) + 0.75(0.3EX + EY - EZ) + 0.75L+ 0.75L_
723  sLCB723 (D) + 0.75(0.3EX - EY + EZ) + 0.75L+ 0.75L_
724  sLCB724 (D) + 0.75(0.3EX - EY - EZ) + 0.75L+ 0.75L_
725  sLCB725 (D) + 0.75(-0.3EX + EY + EZ) + 0.75L+ 0.75L_
726  sLCB726 (D) + 0.75(-0.3EX + EY - EZ) + 0.75L+ 0.75L_
727  sLCB727 (D) + 0.75(-0.3EX - EY + EZ) + 0.75L+ 0.75L_
728  sLCB728 (D) + 0.75(-0.3EX - EY - EZ) + 0.75L+ 0.75L_
729  sLCB729 0.6(D) + EX + 0.3EY + EZ
730  sLCB730 0.6(D) + EX + 0.3EY - EZ
731  sLCB731 0.6(D) + EX - 0.3EY + EZ
732  sLCB732 0.6(D) + EX - 0.3EY - EZ
733  sLCB733 0.6(D) - EX + 0.3EY + EZ
734  sLCB734 0.6(D) - EX + 0.3EY - EZ
735  sLCB735 0.6(D) - EX - 0.3EY + EZ
736  sLCB736 0.6(D) - EX - 0.3EY - EZ
737  sLCB737 0.6(D) + 0.3EX + EY + EZ
738  sLCB738 0.6(D) + 0.3EX + EY - EZ

739  sLCB739 0.6(D) + 0.3EX - EY + EZ


740  sLCB740 0.6(D) + 0.3EX - EY - EZ

741  sLCB741 0.6(D) - 0.3EX + EY + EZ


742  sLCB742 0.6(D) - 0.3EX + EY - EZ

743  sLCB743 0.6(D) - 0.3EX - EY + EZ


744  sLCB744 0.6(D) - 0.3EX - EY - EZ

Note: Due the Silo's double symmetry, it's not necessary to consider the seismic 30% combination
rule for the plate allowable stresses checking.
Note 2: It's allowed to not consider the seismic 30% combination for structure and foundations design,
if a more detailed seismic directionality analysis show that this effect is irrelevant.

Revisión F 117
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-003

4. STRUCTURAL SYSTEM
4.1 Structural System and Analysis Condition
The seismic force-resisting system is Concentrically Braced Frame (CBF). A braced frame is
subjected primarily to axial forces.
Structural analysis program use SAP2000. It’s performed to analyze three dimension structural
systems for checking serviceability of this structure on lateral load, designing column, beam and
brace.
4.1.1 Boundary Conditions

The boundary condition of column at ground level will be defined as a pinned connection in all the
Concetrical Braced Frames Structures.

If Necessary to define a Moment Frame Structure to Comply the Process Requirements, the boundary
condition of column at ground level will be defines as a semi-rigid moment connection in both
horizontal translational degrees of freedoms.

The semi – rigid condition is defined as a rotational spring with an associated rotational stiffness
according to the base plate and anchor bolts configuration, in order to determine this value it will be
necessary to build a detailed model of the column base and the anchor configuration.

4.1.2 Connection Condition between SDA and Structure


If the relative displacement at the sliding support due to earthquake loading is larger than the
available gap of bolt hole, the analysis model should be modified only for earthquake load case as
fixed support.

4.1.3 Structural Element


- One dimensional element for steel structure modeling purposes as follows:
Korea Standard Section
Material = Steel KS D 3503 : SS400, Steel KS D 3515 : SM490

Revisión F 118
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-003

- Shell element for SDA casing modeling purposes as follows:


Material = Steel KS D 3503 : SS400 (See section 2.2)

Revisión F 119
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-003

Revisión F 120
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-003

4.2 Base Plate and Anchor System

Column reaction resulting from the structural analysis shall be used for the design of base plates and
anchor bolts. Column base plate and anchor bolts shall be designed as per ACI 318-08 and AISC
360-05.
Base plate is made to transfer the column loads and moments to the footings and foundations. Anchor
rods are designed to provide the required resistance to loads which result from load combination
stipulated in Section 3.7.
The requirement that anchor bolts of columns shall have a projection of at least eight diameters and
no less than 250 mm measured from the base plates (according to Section 8.6.2 of NCh 2369),
provides adequate anchor bolts length to eventually allow for yielding of the anchor bolt under severe
earthquake loading.

Typical Detail of Column Base in Figure A.1 of NCh 2369 of 2003

Revisión F 121
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-003

5. STRUCTURAL ANALYSIS
5.1 Base Shear and Equivalent Mass

These results are calculated by the analysis model for earthquake load.
If the base shear force is lower than the minimum base shear (0.12 X total weight), the scale-up factor
(12% of total weight / base shear) should be applied for earthquake load according to the Section
5.4.5 of NCh 2369 of 2003.

5.1.1 Mass Distribution


The self-weight is converted into masses automatically in SAP2000 program.
Seismic mass percentages are considered according to Technical Specification.
It shall be considered the following percentage of seismic mass for live load:

Section Seismic Mass Percentage (%)

Area of Normal Use, Floor Live Load 25

Roof without Transit 0

Absorber SDA 100

5.2 Natural Vibration Mode


These results are calculated by the analysis model. The analysis shall include a sufficient number of
vibration modes for the sum of equivalent masses in each analysis direction is equal to or higher than
90% of the total mass.

5.3 Support Reaction


These results are calculated by the analysis model in three directions.

Since the earthquake load was computed trough a Response Spectrum Analysis, its reactions are
absolute values. In order to design the foundations of this structure it is necessary to assign the sign
for each reaction according to the predominant modal shapes in the respective direction.

Revisión F 122
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-003

5.4 Displacement

5.4.1 Displacement due to the Earthquake Load

The displacement for earthquake load can verified according to the Section 6.1 and 6.3.
d = d0 + R1dd
Where,
d = Seismic Deformation
dd = Deformation due to non-seismic service loads
R1 = Factor resulting from multiplying the R factor derived from Table 5.6 of NCh 2369 of 2003 by the
quotient Q0/Qmin provided that Q0/Qmin ne lower or equal to 1.0. However, for the quotient
Q0/Qmin a value under 0.5 shall not be used. If this quotient is higher than 1.0, R1 =R shall be
used.

The maximum seismic deformation for other structures is below:


dmax = 0.015 h
Where,
h = Height between floors of between two points located on the same vertical.

5.4.2 Separation between Structures

The separation between structures is calculated based on section 6.2 of NCh 2369. The purpose of
preventing impacts between adjoining structures, their separation shall be bigger than the highest of
the following values:

1) S = ((R1i ddi)2 + (R1j ddj)2)1/2 + d0i + d0j


2) S = 0.002 (hi + hj)
3) 30mm

Where, ddi, ddj : Deformation calculated with R-factor reduced earthquake load of the structures i and j
d0i, d0j : Deformation due to non-seismic service loads
R1i ,R1j : Response modification factors R1 used for the design of the structures i and j
hi, hj : Height at the considered level of the structures I and j measured from their respective
base levels

Revisión F 123
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-003

6. MEMBER DESIGN
The design of steel structures shall comply with “Earthquake-Resistant Design of Industrial Structures
and Facilities NCh 2369” and “Specification for Structural Steel Buildings AISC 360-05”.
The maximum slenderness can be considered in the design:

Element kl / r

Columns 1.5π√(E/Fy)
Other Elements in Compression 1.5π√(E/Fy)
Element in Traction 240
Bracing Resisting Seismic Load 1.5π√(E/Fy)

Member design was checked about all members of column, beam and brace and so on. On this
report, attached calculation note is about what the worst case of the load combination cases each
member.

Revisión F 124
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-003

6.1 Column Design

6.1.1 Design Load


Load from LRFD Combination
- Pr : Maximum Axial Force
- Mr : Maximum Bending Moment
- Vr : Maximum Shear Force

6.1.2 Schematic Drawing

6.1.3 Verification (AISC360-05, NCh 2369)


1) Slenderness Ratio
- KL / r < 1.5π√(E/Fy)......(OK)
2) Seismic Width-Thickness
- λf = bf / 2tf < λps (for flange)......(OK)
- λw = h / tw < λps (for web)......(OK)
3) Axial Strength
- Pr / Pc < 1.0......(OK)
4) Bending Strength
- Mrx / Mcx < 1.0......(OK)
- Mry / Mcy < 1.0......(OK)
5) Combined Strength (Compression + Bending)
- For Pr / Pc ≥ 0.2 => Rmax = Pr / Pc + 8/9 X (Mrx / Mcx + Mry / Mcy) < 1.0......(OK)
- For Pr / Pc < 0.2 => Rmax = Pr / 2Pc + (Mrx / Mcx + Mry / Mcy) < 1.0......(OK)
6) Shear Strength
- Vrx / Vcx < 1.0......(OK)
- Vry / Vcy < 1.0......(OK)

Revisión F 125
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-003

Where,
λps : Limiting Width-Thickness Ratio
Pc : Design Compressive Strength
Mc : Design Flexural Strength
Vc : Design Shear Strength

Revisión F 126
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-003

6.2 Beam and Girder Design

6.2.1 Design Load


Load from LRFD Combination
- Pr : Maximum Axial Force
- Mr : Maximum Bending Moment
- Vr : Maximum Shear Force

6.2.2 Schematic Drawing

6.2.3 Verification (AISC360-05, NCh 2369)


1) Slenderness Ratio
- KL / r < 1.5π√(E/Fy)......(OK)
2) Seismic Width-Thickness
- λf = bf / 2tf < λps (for flange)......(OK)
- λw = h / tw < λps (for web)......(OK)
3) Axial Strength
- Pr / Pc < 1.0......(OK)
4) Bending Strength
- Mrx / Mcx < 1.0......(OK)
- Mry / Mcy < 1.0......(OK)
5) Combined Strength (Compression + Bending)
- For Pr / Pc ≥ 0.2 => Rmax = Pr / Pc + 8/9 X (Mrx / Mcx + Mry / Mcy) < 1.0......(OK)
- For Pr / Pc < 0.2 => Rmax = Pr / 2Pc + (Mrx / Mcx + Mry / Mcy) < 1.0......(OK)
6) Shear Strength
- Vrx / Vcx < 1.0......(OK)
- Vry / Vcy < 1.0......(OK)

Revisión F 127
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-003

Where,
λps : Limiting Width-Thickness Ratio
Pc : Design Compressive Strength
Mc : Design Flexural Strength
Vc : Design Shear Strength

Revisión F 128
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-003

6.3 Brace Design

6.3.1 Design Load


Load from LRFD Combination
- Pr : Maximum Axial Force
- Mr : Maximum Bending Moment
- Vr : Maximum Shear Force

6.3.2 Schematic Drawing

6.3.3 Verification (AISC360-05, NCh 2369)


1) Slenderness Ratio
- KL / r < 1.5π√(E/Fy)......(OK)
2) Seismic Width-Thickness
- λf = bf / 2tf < λps (for flange)......(OK)
- λw = h / tw < λps (for web)......(OK)
3) Axial Strength
- Pr / Pc < 0.8......(OK)
4) Bending Strength
- Mrx / Mcx < 0.8......(OK)
- Mry / Mcy < 0.8......(OK)
5) Combined Strength (Compression + Bending)
- For Pr / Pc ≥ 0.2 => Rmax = Pr / Pc + 8/9 X (Mrx / Mcx + Mry / Mcy) < 0.8......(OK)
- For Pr / Pc < 0.2 => Rmax = Pr / 2Pc + (Mrx / Mcx + Mry / Mcy) < 0.8......(OK)
6) Shear Strength
- Vrx / Vcx < 0.8......(OK)
- Vry / Vcy < 0.8......(OK)

Revisión F 129
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-003

Where,
λps : Limiting Width-Thickness Ratio
Pc : Design Compressive Strength
Mc : Design Flexural Strength
Vc : Design Shear Strength

Revisión F 130
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-003

6.4 Connection Design

6.4.1 Column Splice

6.4.1.1 Design Load


Full Capacity of Column
- Pu : Maximum Axial Force (= Φ Fy Ag)
- Mu : Maximum Bending Moment (= Φ Fy Zx)
- Vu : Maximum Shear Force (= 0.6 Φ Fy Aw)
- Tu : Maximum Tensile Force at Flange (=Mu / Arm of Column)

6.4.1.2 Schematic Drawing

6.4.1.3 Verification (AISC360-05)


1) Bolt Strength
- Shear Strength ΦRn1 = Φ Ns Fn Ab
- Bearing Strength at Bolt Holes ΦRn2 = Min (Φ 1.2 Lc t Fu, Φ 2.4 d t Fu)
- Slip-Critical Connections ΦRn3 = Φ μ Du hsc Tb Ns
- ΦRn = Min (ΦRn1, ΦRn2, ΦRn3)
- Pu / ΦRn < Number of Bolt......(OK)
- Vu / ΦRn < Number of Bolt......(OK)
- Tu / ΦRn < Number of Bolt......(OK)
2) Web Splice Plate Verification
- Shear Yielding Φ 0.6 Fy Ag ≥ Vu......(OK)

Revisión F 131
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-003

- Shear Rupture Φ 0.6 Fu Anv ≥ Vu......(OK)


3) Flange Splice Plate Verification
- Tensile Yielding Φ Fy Ag ≥ Tu......(OK)
- Tensile Rupture Φ Fu Ae ≥ Tu......(OK)

Revisión F 132
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-003

6.4.2 Beam Connection

6.4.2.1 Design Load


1) Special Earthquake Load Combination
- Ru1 is determined due to the 1.2D + 0.5L + ΩE
2) 0.5 X Full Capacity for Shear
- Ru2 = 0.5 Φ 0.6 Fy Aw Cv
3) Ru = Max (Ru1, Ru2)
4) If the load from brace are transferred to the girder and beam directly, the connection would be
designed by full capacity of brace.

6.4.2.2 Schematic Drawing

6.4.2.3 Verification (AISC360-05)


1) Bolt Strength
- Shear Strength ΦRn1 = Φ Ns Fn Ab
- Bearing Strength at Bolt Holes ΦRn2 = Min (Φ 1.2 Lc t Fu, Φ 2.4 d t Fu)
- Slip-Critical Connections ΦRn3 = Φ μ Du hsc Tb Ns
- ΦRn = Min (ΦRn1, ΦRn2, ΦRn3)
- Ru / ΦRn < Number of Bolt......(OK)
2) Web Splice Plate Verification
- Shear Yielding Φ 0.6 Fy Ag ≥ Ru......(OK)
- Shear Rupture Φ 0.6 Fu Anv ≥ Ru......(OK)
3) Block Shear Rupture Verification
- Φ (0.6 Fu Anv + Ubs Fu Ant) ≥ Ru......(OK)
- Φ (0.6 Fy Agv + Ubs Fu Ant) ≥ Ru......(OK)

Revisión F 133
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-003

6.4.3 Brace to Gusset Connection

6.4.3.1 Design Load


Full Capacity of Brace
- Tu : Maximum Tensile Force (= Ry Fy Ag)
- Pu : Maximum Compressive Force (= 1.1 Ry Pn)
- Ruw : Force in Web
- Ruf : Force in Flange

6.4.3.2 Schematic Drawing


In case of H-Shape Brace In case of Channel Brace

6.4.3.3 Verification in case of H-Shape Brace (AISC360-05)


1) Bolt Strength
- Shear Strength ΦRn1 = Φ Ns Fn Ab
- Bearing Strength at Bolt Holes ΦRn2 = Min(Φ 1.2 Lc t Fu, Φ 2.4 d t Fu)
- Slip-Critical Connections ΦRn3 = Φ μ Du hsc Tb Ns
- ΦRn = Min(ΦRn1, ΦRn2, ΦRn3)
- Ruf / ΦRn < Number of Bolt......(OK)
- Ruw / ΦRn < Number of Bolt......(OK)

Revisión F 134
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-003

2) Tension Capacity of the Angles


- Tension Yielding Φ Fy Ag ≥ Ruf / 2......(OK)
Φ Fy Ag ≥ Ruw......(OK)
- Tension Rupture Φ Fu Ae ≥ Ruf / 2......(OK)
Φ Fu Ae ≥ Ruw......(OK)
3) Block Shear Rupture Verification of the Angles
- Φ (0.6 Rt Fu Anv + Ubs Rt Fu Ant) ≥ Ruf / 2......(OK)
- Φ (0.6 Ry Fy Agv + Ubs Rt Fu Ant) ≥ Ruf / 2......(OK)
- Φ (0.6 Rt Fu Anv + Ubs Rt Fu Ant) ≥ Rw......(OK)
- Φ (0.6 Ry Fy Agv + Ubs Rt Fu Ant) ≥ Rw......(OK)

6.4.3.4 Verification in case of Channel Brace (AISC360-05)


1) Bolt Strength
- Shear Strength ΦRn1 = Φ Ns Fn Ab
- Bearing Strength at Bolt Holes ΦRn2 = Min(Φ 1.2 Lc t Fu, Φ 2.4 d t Fu)
- Slip-Critical Connections ΦRn3 = Φ μ Du hsc Tb Ns
- ΦRn = Min(ΦRn1, ΦRn2, ΦRn3)
- Tu / ΦRn < Number of Bolt......(OK)
2) Net Section Fracture
- Φt Rt Fu Ae ≥ Tu......(OK)
3) Block Shear Rupture Verification of the Angles
- Φ (0.6 Rt Fu Anv + Ubs Rt Fu Ant) ≥ Tu......(OK)
- Φ (0.6 Ry Fy Agv + Ubs Rt Fu Ant) ≥ Tu......(OK)

Revisión F 135
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-003

6.4.4 Gusset Plate Design

6.4.4.1 Design Load


Full Capacity of Brace
- Tu : Maximum Tensile Force (= Ry Fy Ag)
- Pu : Maximum Compressive Force (= 1.1 Ry Pn)

6.4.4.2 Schematic Drawing


Concept Drawing Design Force of Gusset Plate

Whitmore Section of Gusset Plate

6.4.4.3 Verification (AISC360-05)


1) Design the Weld at the Gusset-Column Interface

Revisión F 136
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-003

- fv = Huc / 2β
- fa = Vuc / 2β
- fb = 0
- fpeak = √[fv2 + (fa + fb)2]
- favg = (1/2) × {√[(fa - fb)2 + fv2] +√[(fa + fb)2+ fv2]}
- fr = 1.25 X favg (If fpeak / favg < 1.25)
- fr = fpeak (If fpeak / favg ≥ 1.25)
- s ≥ fr / (0.7 (0.9) (0.6) Fy (2))......(OK)
- tmin (=2 (0.9) (0.6) Fy 0.7s / (0.75 (0.6) Fu) < thickness of gusset plate......(OK)
2) Yielding of Gusset Plate
- ΦRn (=Φ Fy t) > MAX.(fv,fa)......(OK)
3) Column Web Yielding
- ΦRn (=Φ Fy tw) > fr......(OK)
4) Column Web Crippling
- ΦRn = Φ 0.8 tw2 [1 + 3(N / d) (tw / tf)1.5] √(E Fyw tf / tw) > Huc......(OK)
5) Design the Weld at the Gusset-Beam Interface (In Tension and Compression)
- fv = Hub / 2α
- fa = Vub / 2α
- fb = Mub / Sw (Sw = (2α)2 / 6)
- fpeak = √[fv2 + (fa + fb)2]
- favg = (1/2) × {√[(fa - fb)2 + fv2] +√[(fa + fb)2+ fv2]}
- fr = 1.25 X favg (If fpeak / favg < 1.25)
- fr = fpeak (If fpeak / favg ≥ 1.25)
- s ≥ fr / (0.7 (0.9) (0.6) Fy (2))......(OK)
- tmin (=2 (0.9) (0.6) Fy 0.7s / (0.75 (0.6) Fu) < thickness of gusset plate......(OK)
6) Yielding of Gusset Plate
- ΦRn (=Φ Fy t) > MAX.(fv,fa)......(OK)
7) Beam Web Yielding
- ΦRn (=Φ Fy tw) > fr......(OK)
8) Beam Web Local Yielding (if the brace connection is located in center of girder)
- ft = fa + fb
- fc = fa – fb
- Lt = [ft / (ft + tc)] / Lg
- Ru = (1/2) Lt ft
- ΦRn = (5k + N) Fyw tw

Revisión F 137
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-003

- Ru < ΦRn......(OK)
9) Beam Web Crippling
- Ru = [Mub / (N2 / 4)] (N / 2) + Vub = 2Mub / N + Vub
- ΦRn = Φ 0.4 tw2 [1 + 3(N / d) (tw / tf)1.5] √(E Fyw tf / tw) (N/d ≤ 0.2)
- ΦRn = Φ 0.4 tw2 [1 + (4N / d - 0.2) (tw / tf)1.5] √(E Fyw tf / tw) (N/d > 0.2)
- Ru < ΦRn......(OK)
10) Beam Web Crippling (if the brace connection is located in center of girder)
- Ru = (1/2) (Lg - Lt) fc
- ΦRn = Φ 0.8 tw2 [1 + 3(N / d) (tw / tf)1.5] √(E Fyw tf / tw)
- Ru < ΦRn......(OK)
11) Compression Buckling of Gusset Plate
- Φc Fcr Ag > Pu......(OK) (The Ag should be considered whitmore section)
12) Tensile Yielding of Gusset Plate
- Φt Fy Ag > Tu X Ratio of Resisting Bolt......(OK) (The Ag should be considered whitmore section)

Revisión F 138
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-003

6.5 Base Plate and Anchor Bolt Design

6.5.1 Design Load


Load from LRFD Combination
- Pu : Maximum Compressive Force
- Tu : Maximum Tensile Force
- Mu : Maximum Bending Moment
- Vu : Maximum Shear Force

6.5.2 Schematic Drawing

6.5.3 Verification (AISC360-05, ACI318-08)


1) Bearing Stress of Base Plate
- Fp = 0.85 Φ fc √(A2 / A1)
- fp = Pu (1+6e / (N or B)) / A (In case of e < (N or B) / 6)
- fp < Fp......(OK)
2) Thickness of Base Plate
- t1 = √ (ß x fp x u2 / 1.5 Fy) (ß : derived by Roak’s Table)
- t2 = √ (ß x fp x (B / 2)2 / 1.5 Fy) (ß : derived by Roak’s Table)
- t > Max.(t1,t2) ......(OK)
3) Embedded Depth and Width of the Shear Key
- Φ Vn = 0.85 Φ fc A > Vu......(OK)
4) Thickness of Shear Key
- treq = √ (ß x fp x Max(W/2-t/2, d+G)2 / 1.5 Fy) (ß : derived by Roak’s Table)
- treq > t ......(OK)

Revisión F 139
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-003

5) Bearing Strength of the Concrete


- Fp = 0.85 Φ fc √(A2 / A1)
- fp = Vu / (W X d)
- fp < Fp......(OK)
6) Anchor Bolt Verification
- Tension Strength : 0.75 Φ Nn = 0.75 Φ n Ase Fut > Tu......(OK)
- Tb = (Tu / 2 + (Mbuilt-in / (d-d’)) / Number of Bolt
- Ase,req = Tu / (0.75 Φ Tb) < Ase......(OK)
- Concrete Breakout Strength : Ncb = ANc / ANco x ψed,N x ψc,N x ψcp,N x Nb > Tu......(OK)
7) Design of Rib Plate
- Height of Rib Plate : 8d of 250mm
- Ru : Reaction due to the anchor bolt full capacity
- Φ Pn = Φ Ag Fcr > Ru......(OK)
- fa : Axial Stress due to the concrete pressure
- Fc > fa......(OK)
8) Design of Upper Plate
M : Bending Moment due to the anchor bolt full capacity
- Φ Fy Z = Φ Fy u t2 / 4 > M......(OK)
9) Design of Anchor Plate
M : Bending Moment due to the anchor bolt full capacity
- Φ Fy Z = Φ Fy u t2 / 4 > M......(OK)

Revisión F 140
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-003

6.6 Connection between SDA and Structure

6.6.1 Design Load


Load from LRFD Combination
- Pu : Maximum Compressive Force
- Tu : Maximum Tensile Force
- Vu : Maximum Shear Force

6.6.2 Schematic Drawing

6.6.3 Verification (AISC360-05, NCh 2369)


1) Bolt Strength
- Shear Strength ΦRn1 = Φ Ns Fnv Ab
- Bearing Strength at Bolt Holes ΦRn2 = Min (Φ 1.0 Lc t Fu, Φ 2.0 d t Fu)
- ΦRn = Min (ΦRn1, ΦRn2)
- Vu / ΦRn < (1/2) X Number of Bolt......(OK)
- Tension Capacity ΦTn1 = Φ Fnt Ab
- Combined Tension and Shear Capacity ΦTn2 = {1.3 Fnt – (Fnt / Φ Fnv) fv} Ab
- ΦTn = Min (ΦTn1, ΦTn2)
- Tu / ΦTn < (1/2) X Number of Bolt......(OK)
2) Gap Size of Bolt Hole
- by temperature : δ = α (∆T) DSDA < Gap Size......(OK)
- If the relative displacement at the sliding support due to earthquake loading is larger than the

Revisión F 141
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-003

available gap of bolt hole, the analysis model should be modified only for earthquake load case as
fixed support.
3) Bearing Strength of Sliding Pad
- 0.9 fc A > Pu......(OK)
4) Beam Web Crippling
- ΦRn = Φ 0.8 tw2 [1 + 3(N / d) (tw / tf)1.5] √(E Fyw tf / tw) > Pu......(OK)
5) Beam Web Local Yielding
- ΦRn = (5k + N) Fyw tw > Pu......(OK)

Revisión F 142
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-003

7. CASING CALCULATION NOTE

Revisión F 143
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-003

7.1 SDA Casing Design

7.1.1 Design Load


Load from ASD Combination

7.1.2 Schematic Drawing

7.1.3 Verification (NCh 2369, EN 1991-4, EN 1993-4-1)


1) Effective Stress
- σe < 0.6 x Fy......(OK) (σe derived by analysis modeling)
2) Combined Compressive Stress
- σcr = 135 Fy x t / D < 0.8 Fy
- σc < σcr......(OK) (σc derived by analysis modeling)

Revisión F 144
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-001

ANEXO 3: CRITERIOS DE DISEÑO ESPECIFICOS PARA PIPE


RACK

145 de 392

Revisión F
DESIGN CRITERIA FOR PIPE RACK TOTAL 49 HOJAS
SUPPORT STRUCTURE (Incluyendo Portada)

PROPOSITO

Para Revisión
 NOMBRE CONTRATO EPC POR EL SISTEMA DE
PROYECTO DESULFURIZACION DE GASES - FGD - PARA
LA CENTRAL TARAPACÁ Para Aprobación

 NOMBRE FGD CENTRAL TARAPACÁ Para Construcción


SISTEMA
Para Oferta
 N° DOCUMENTO DCTO413-C8-VVT-000-004
Para Información
 TITULO DESIGN CRITERIA FOR PIPE RACK
SUPPORT STRUCTURE

 CLIENTE ENDESA S.A.

F 29-12-2014 JCR VBS NCR Para Aprobación

E 22-12-2014 JCR VBS NCR Para Aprobación

D 25-11-2014 JCR VBS NCR Para Aprobación

C 27-10-2014 JCR VBS NCR Para Aprobación

B 30-09-2014 JCR VBS NCR Para Aprobación

A 24-09-2014 JCR VBS NCR Coordinación Interna - - -

PREP. REV. APR. REV. REV. APR.


Rev
FECHA DESCRIPCION
.
STX HI ENDESA S.A.

PROPIETARIO:

CONTRATISTA:
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-004

DESIGN CRITERIA FOR PIPERACK


SUPPORT STRUCTURE

Rev. F

Revisión F 147
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-004

Contents

1 INTRODUCTION
1.1 Location
1.2 Weather
1.3 Scope

2 STRUCTURAL DESIGN CRITERIA


2.1 Design Code and Reference
2.2 Materials
2.3 Structural Analysis and Design Program

3 DESIGN LOADS
3.1 Dead Load
3.2 Live Load
3.3 Thermal Load
3.4 Wind Load
3.5 Earthquake Load
3.6 Load Combination

4 STRUCTURAL SYSTEM
4.1 Structural System and Analysis Condition
4.2 Base Plate and Anchor System

5 STRUCTURAL ANALYSIS
5.1 Base Shear and Equivalent Mass
5.2 Natural Vibration Mode
5.3 Support Reaction
5.4 Displacement

Revisión F 148
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-004

6 MEMBER DESIGN
6.1 Column Design
6.2 Beam and Girder Design
6.3 Brace Design
6.4 Connection Design
6.5 Base Plate and Anchor Bolt Design

Revisión F 149
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-004

1. INTRODUCTION
1.1 Location
The Tarapacá Thermal Power Plant (158 MW), henceforth the Power Plant, owned by Compañía Eléctrica
Tarapacá S.A., hereinafter CELTA S.A or CELTA, is located on the I Region of Chile, approximately 60km
south of Iquique, by the coast, on the area known as Punta Patache.

1.2 Weather
Weather conditions in the sector are as follows:
Barometric Pressure(Average): 1,015 millibars
Ambient Temperature: Maximum 31.3℃, Minimum 8℃
Relative Humidity(Mean): 78%

1.3 Scope
This is design criteria for pipe rack support structure.

Revisión F 150
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-004

2. STRUCTURAL DESIGN CRITERIA


The structural design criteria in this report were calculated according to Technical Specification.

2.1 Design Code and Reference


Code Code & Reference Remarks
Earthquake-Resistant Design of Industrial Structures and
NCh 2369 Seismic Design
Facilities
ETG 1015 General Technical Specifications – Seismic Design Seismic Design
NCh 432 Structural Design – Wind Loads Wind Load
Structural Design – General Dispositions and Combinations
NCh 3171 Load Combination
of Load
ASCE 7-05 Minimum Design Loads for Building and Other Structures Load Combination
AISC 360-05 Specification for Structural Steel Buildings Steel Design
ACI 318-08 Building Code Requirements for Structural Concrete Anchoring to Concrete

2.2 Materials
Tensile Modulus of
Standard Symbol Yield Strength Remarks
Strength Elasticity
KS D 3503 235 MPa (t ≤ 40mm) Structural Steel /
SS 400 400 MPa 200,000 MPa
JIS G 3101 215 MPa (t > 40mm) Anchor Bolt
KS D 3515 315 MPa (t ≤ 40mm)
SM490 490 MPa 200,000 MPa Structural Steel
JIS G 3106 295 MPa (t > 40mm)
ASTM A36 250 MPa 400 MPa 200,000 MPa Anchor Bolt

Standard Symbol Nominal Tensile Stress Nominal Shear Stress Remarks


KS B 1010 F10T 736 MPa 392 MPa
High Strength Bolt
ASTM A325 620 MPa 330 MPa
/ Torque Shear Bolt
ASTM A490 780 MPa 414 MPa

* Friction Coefficient 0.35 : Class A surface ( unpainted clean mill scale steel surfaces or surfaces with
Class A coatings on blast-cleaned steel and hot-dipped galvanized and roughened surfaces)

Revisión F 151
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-004

Material properties in operation temperature (180℃) (ASME 2010 U, Y-1, TM-1)

Modulus of
Symbol Yield Strength Tensile Strength Remarks
Elasticity
SS 400 204 MPa 400 MPa 193,200 MPa SA-36

The material properties for determine the required strength of element and connection are included KBC
2009 (Korean Building Code 2009) section 0713.6.2.

In section 0713.6.2 of KBC 2009 (Original)

Revisión F 152
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-004

In section 0713.6.2 of KBC 2009 (Translation)


0713.6.2 Material Properties for determine the required strength of member and connection
(1) When estimate the required strength of each member (member or connection) by the provision of
this section, the required strength should be calculated based on the expected yield strength Ry Fy
of connected member. In here, Fy is the minimum yield strength of connected member and Ry is the
ratio of expected yield strength and minimum yield strength.

(2) The design strength ФRn should be at least the required strength. When estimate the nominal

Strength Rn for fracture and yield state, the expected tensile strength Rt Fu and expected yield
Strength Ry Fy can be used instead of Fu and Fy.
(3) The values of Ry and Rt are in the table 0713.6.1.

<Table 0713.6.1> The values of Ry and Rt for each type of steel

Application Ry Rt
KS SS400, SSC400, SWH400,
Structural Rolled Shapes KS STK400, STK490, SPSR400, SPSR490, 1.3 1.2
Steel and Cold Formed STKN400, STKN490
Steel
KS SM400, SM490, SM520 1.2 1.2

Revisión F 153
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-004

KS SPAR295, SPAP235, SPAP325,


SCW490-CF
KS SHN400, SHN490 1.1 1.1
KS SS400 1.3 1.2
KS SM490, SM490TMC, SM520,
SM520TMC, SM570, SM570TMC, 1.2 1.2
Plate KS SMA400, SMA490, SMA570
KS SN400, SN490 1.1 1.1
HSA800 1.1 1.1

2.3 Structural Analysis and Design Program


Software Program Code & Reference Remarks
3D Static & Dynamic Analysis -
SAP 2000
Member Design

SAFE Foundation Analysis -

Revisión F 154
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-004

3. DESIGN LOADS
3.1 Dead Load (D)
Dead load is the load due to the permanent weight of all structural and nonstructural components of a
construction, including thermal insulation, ladders and others.

Item Density or Load Remark


7,850 kg/m3
Steel SS 400, SM 490
(=76.98 kN/m3)
50 kg/m2
Grating ARRIGONI ARS-5 33 kg/m2.
(=0.49 kN/m2)

3.2 Live Load (L , L_ and Lr)

It shall be included in this load category, the content of tanks, silos, hoppers, ducting, mobile and transient
loads and weight of people, equipment and tools, and other material agglomerations.
Live load is calculated according to Technical Specification.

Item Load Remark


2
400kg/m
Offices, Hallways, Stairs -
(= 3.92 kN/m2)

3.3 Thermal Load (T)

3.3.1 External Temperature


Effect of temperature on the structure, due to climatic conditions of the area
Metal structures for temperature variation depends on local conditions, but it will not be less than ±25℃.

3.3.2 Strain due to the Temperature

Where,
α = 1.2×10-5 /℃, coefficient of thermal expansion
∆T = ±25℃ (Steel exposed to ambient)

Revisión F 155
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-004

3.4 Wind Load (WX, WY)


Wind load is calculated based on NCh 432 Table 1.

Structures located in open country, facing the ocean, or locations under similar conditions, in the
judgment of the Reviewing Authority

Height above the NCh 432 Chapter 6.5


Basic pressure, q Basic pressure, q
ground ×1.2
[kg/m2] [kPa]
[m] [kPa]
0 70 0.69 0.82
4 70 0.69 0.82
7 95 0.93 1.12
10 106 1.04 1.25
15 118 1.16 1.39
20 126 1.24 1.48
30 137 1.34 1.61
40 145 1.42 1.71
50 151 1.48 1.78
75 163 1.60 1.92
100 170 1.67 2.00
150 182 1.78 2.14
200 191 1.87 2.25
300 209 2.05 2.46

Revisión F 156
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-004

3.5 Earthquake Load (EX, EY, EZ)

3.5.1 Earthquake Load


The total base shear shall be computed from the expression.
V = C X W ≥ 0.12 W
Where,
V Base shear
C Seismic coefficient, obtained directly from the design spectrum.
W Total seismic weight of the structure or system, computed as the sum of dead load of structure
and equipment

3.5.1.1 Earthquake action for horizontal direction


The design spectrum is calculated based on ETG1015 figure 1.
Applied coefficients are as follows:
Ground Acceleration a/g = 0.4
Response Modification Factors: R = 5.0
Equivalent viscous damping: ζ = 0.03

3.5.1.2 Earthquake action for vertical direction


The vertical earthquake shall be considered according to Section 5.5 of NCh 2369 Standard, with seismic
coefficient equal to 2 A0 / 3g.

Revisión F 157
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-004

Coordinates of the corner point for a/g = 0.4

ζ T1 T2 A/g
0.005 0.113 0.451 1.472
0.01 0.115 0.461 1.284
0.02 0.119 0.474 1.096
0.03 0.121 0.485 0.984
0.05 0.125 0.499 0.848
0.07 0.128 0.512 0.756
0.10 0.134 0.535 0.656
0.20 0.148 0.591 0.468
Equation of hyperbolic branch:

Revisión F 158
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-004

(T2<=T<=2.5 s)

3.5.2 Methods of Analysis


In order to compute the forces and displacements in a given structural system when subjected to the
earthquake action, a response spectrum analysis shell be performed.

3.5.3 Number of Modes


The analysis shall include a sufficient number of vibration modes for the sum of equivalent masses in
each analysis direction is equal to or higher than 90% of the total mass.

3.5.4 Mode Superposition


In order to obtain an estimate of the maximum values of any response quantity considered in the analysis,
the maximum values of the corresponding responses computed for the individual mode of vibration shall
be combined with the CQC superposition criterion normally called “Complete Quadratic Combination”,
recommended in Chilean code Section 5.4.4 of NCh 2369.
The following expressions summarize the mode superposition procedure:

Where,
S Modal combination
Si, Sj Maximum values of mode contributions i and j
ζ Damping ratio
Ti, Tj Period of mode i and j

Revisión F 159
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-004

3.5.5 Coupling of earthquake action for Support Structure


For the case of dynamic analysis, the requirements of Section 5.1.2 of Chilean code NCh 2369 regarding
the effect of the combination of the seismic horizontal components effect are applicable. This requires that
the modal shape and frequencies have to be analyzed and if they are found to be coupled without a clear
or predominant directional acceleration input shall be performed instead of two independent analyses.
This can be implemented by carrying out two different three dimensional analyses; in each of them the
earthquake action input (acceleration spectrum ordinates) shall be 100% of the Project Specification
design spectrum in on direction plus 30% of the Project Specification design spectrum in the orthogonal
direction.

Point 5.1.2 of NCh-2369 clearly indicates that it is not necessary to combine the horizontal components of
the seismic action, ie can be analyzed separately for earthquake acting in both directions considered
analysis and design with the unfavorable situation.
Exceptions to this rule structures that have significant torsional irregularities, for which it requires rigid
diaphragms own buildings. The situation is important to consider in the corner columns orthogonal
building rigid frames that share these corner columns. In cases like this should be at 100% overlap in a
direction analysis 30% of the analyzes in the other direction and the same for the other direction relative
to the first. This exception should be applied to irregular structured buildings preferably those based on
rigid frames.

Revisión F 160
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-004

3.6 Load Combination

3.6.1 Basic Load Case


D Dead Load
T1 Thermal Load (∆T = +25C, in case of steel exposed to ambient)
T2 Thermal Load (∆T = -25℃, in case of steel exposed to ambient)
L Live Load
Lr Roof live load not exposed to traffic
WX Wind Load X direction
WY Wind Load Y direction
EX Earthquake Load X direction
EY Earthquake Load Y direction
EZ Earthquake Load Vertical direction

3.6.2 LRFD Load Combination (For Anchor System and Foundations)


The LRFD load combinations shall take into account the earthquake load in Technical Specification.
Technical Specification considered a nominal load, so it must be amplified by a factor 1.4, as indicated in
the following table.

No. Case Name Description


1 uLCB1 1.4(D + T1)
2 uLCB2 1.2(D + T1) + 1.6L + 0.5Lr
3 uLCB3 1.2(D + T1) + 1.6Lr + 0.5L
4 uLCB4 1.2(D + T1) + 1.6Lr + 0.8WX
5 uLCB5 1.2(D + T1) + 1.6Lr - 0.8WX
6 uLCB6 1.2(D + T1) + 1.6Lr + 0.8WY
7 uLCB7 1.2(D + T1) + 1.6Lr - 0.8WY
8 uLCB8 1.2(D + T1) + 1.6WX + 0.5L + 0.5Lr
9 uLCB9 1.2(D + T1) - 1.6WX + 0.5L + 0.5Lr
10 uLCB10 1.2(D + T1) + 1.6WY + 0.5L + 0.5Lr
11 uLCB11 1.2(D + T1) - 1.6WY + 0.5L + 0.5Lr
12 uLCB12 1.2(D + T1) + 1.4(1.0EX + 0.3EY + 1.0EZ) + 0.5L
13 uLCB13 1.2(D + T1) + 1.4(1.0EX + 0.3EY - 1.0EZ) + 0.5L

Revisión F 161
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-004

14 uLCB14 1.2(D + T1) + 1.4(1.0EX - 0.3EY + 1.0EZ) + 0.5L


15 uLCB15 1.2(D + T1) + 1.4(1.0EX - 0.3EY - 1.0EZ) + 0.5L
16 uLCB16 1.2(D + T1) - 1.4(1.0EX + 0.3EY + 1.0EZ) + 0.5L
17 uLCB17 1.2(D + T1) - 1.4(1.0EX + 0.3EY - 1.0EZ) + 0.5L
18 uLCB18 1.2(D + T1) - 1.4(1.0EX - 0.3EY + 1.0EZ) + 0.5L
19 uLCB19 1.2(D + T1) - 1.4(1.0EX - 0.3EY - 1.0EZ) + 0.5L
20 uLCB20 1.2(D + T1) + 1.4(0.3EX + 1.0EY + 1.0EZ) + 0.5L
21 uLCB21 1.2(D + T1) + 1.4(0.3EX + 1.0EY - 1.0EZ) + 0.5L
22 uLCB22 1.2(D + T1) + 1.4(0.3EX – 1.0EY + 1.0EZ) + 0.5L
23 uLCB23 1.2(D + T1) + 1.4(0.3EX – 1.0EY - 1.0EZ) + 0.5L
24 uLCB24 1.2(D + T1) - 1.4(0.3EX + 1.0EY + 1.0EZ) + 0.5L
25 uLCB25 1.2(D + T1) - 1.4(0.3EX + 1.0EY - 1.0EZ) + 0.5L
26 uLCB26 1.2(D + T1) - 1.4(0.3EX – 1.0EY + 1.0EZ) + 0.5L
27 uLCB27 1.2(D + T1) - 1.4(0.3EX – 1.0EY - 1.0EZ) + 0.5L
28 uLCB28 0.9(D + T1) + 1.6WX
29 uLCB29 0.9(D + T1) - 1.6WX
30 uLCB30 0.9(D + T1) + 1.6WY
31 uLCB31 0.9(D + T1) - 1.6WY
32 uLCB32 0.9(D + T1) + 1.4(1.0EX + 0.3EY + 1.0EZ)
33 uLCB33 0.9(D + T1) + 1.4(1.0EX + 0.3EY - 1.0EZ)
34 uLCB34 0.9(D + T1) + 1.4(1.0EX - 0.3EY + 1.0EZ)
35 uLCB35 0.9(D + T1) + 1.4(1.0EX - 0.3EY - 1.0EZ)
36 uLCB36 0.9(D + T1) - 1.4(1.0EX + 0.3EY + 1.0EZ)
37 uLCB37 0.9(D + T1) - 1.4(1.0EX + 0.3EY - 1.0EZ)
38 uLCB38 0.9(D + T1) - 1.4(1.0EX - 0.3EY + 1.0EZ)
39 uLCB39 0.9(D + T1) - 1.4(1.0EX - 0.3EY - 1.0EZ)
40 uLCB40 0.9(D + T1) + 1.4(0.3EX + 1.0EY + 1.0EZ)
41 uLCB41 0.9(D + T1) + 1.4(0.3EX + 1.0EY - 1.0EZ)
42 uLCB42 0.9(D + T1) + 1.4(0.3EX – 1.0EY + 1.0EZ)
43 uLCB43 0.9(D + T1) + 1.4(0.3EX – 1.0EY - 1.0EZ)
44 uLCB44 0.9(D + T1) - 1.4(0.3EX + 1.0EY + 1.0EZ)

Revisión F 162
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-004

45 uLCB45 0.9(D + T1) - 1.4(0.3EX + 1.0EY - 1.0EZ)


46 uLCB46 0.9(D + T1) - 1.4(0.3EX – 1.0EY + 1.0EZ)
47 uLCB47 0.9(D + T1) - 1.4(0.3EX – 1.0EY - 1.0EZ)
48 uLCB48 1.4(D + T2)
49 uLCB49 1.2(D + T2) + 1.6L + 0.5Lr
50 uLCB50 1.2(D + T2) + 1.6Lr + 0.5L
51 uLCB51 1.2(D + T2) + 1.6Lr + 0.8WX
52 uLCB52 1.2(D + T2) + 1.6Lr - 0.8WX
53 uLCB53 1.2(D + T2) + 1.6Lr + 0.8WY
54 uLCB54 1.2(D + T2) + 1.6Lr - 0.8WY
55 uLCB55 1.2(D + T2) + 1.6WX + 0.5L + 0.5Lr
56 uLCB56 1.2(D + T2) - 1.6WX + 0.5L + 0.5Lr
57 uLCB57 1.2(D + T2) + 1.6WY + 0.5L + 0.5Lr
58 uLCB58 1.2(D + T2) - 1.6WY + 0.5L + 0.5Lr
59 uLCB59 1.2(D + T2) + 1.4(1.0EX + 0.3EY + 1.0EZ) + 0.5L
60 uLCB60 1.2(D + T2) + 1.4(1.0EX + 0.3EY - 1.0EZ) + 0.5L
61 uLCB61 1.2(D + T2) + 1.4(1.0EX - 0.3EY + 1.0EZ) + 0.5L
62 uLCB62 1.2(D + T2) + 1.4(1.0EX - 0.3EY - 1.0EZ) + 0.5L
63 uLCB63 1.2(D + T2) - 1.4(1.0EX + 0.3EY + 1.0EZ) + 0.5L
64 uLCB64 1.2(D + T2) - 1.4(1.0EX + 0.3EY - 1.0EZ) + 0.5L
65 uLCB65 1.2(D + T2) - 1.4(1.0EX - 0.3EY + 1.0EZ) + 0.5L
66 uLCB66 1.2(D + T2) - 1.4(1.0EX - 0.3EY - 1.0EZ) + 0.5L
67 uLCB67 1.2(D + T2) + 1.4(0.3EX + 1.0EY + 1.0EZ) + 0.5L
68 uLCB68 1.2(D + T2) + 1.4(0.3EX + 1.0EY - 1.0EZ) + 0.5L
69 uLCB69 1.2(D + T2) + 1.4(0.3EX – 1.0EY + 1.0EZ) + 0.5L
70 uLCB70 1.2(D + T2) + 1.4(0.3EX – 1.0EY - 1.0EZ) + 0.5L
71 uLCB71 1.2(D + T2) - 1.4(0.3EX + 1.0EY + 1.0EZ) + 0.5L
72 uLCB72 1.2(D + T2) - 1.4(0.3EX + 1.0EY - 1.0EZ) + 0.5L
73 uLCB73 1.2(D + T2) - 1.4(0.3EX – 1.0EY + 1.0EZ) + 0.5L
74 uLCB74 1.2(D + T2) - 1.4(0.3EX – 1.0EY - 1.0EZ) + 0.5L
75 uLCB75 0.9(D + T2) + 1.6WX

Revisión F 163
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-004

76 uLCB76 0.9(D + T2) - 1.6WX


77 uLCB77 0.9(D + T2) + 1.6WY
78 uLCB78 0.9(D + T2) - 1.6WY
79 uLCB79 0.9(D + T2) + 1.4(1.0EX + 0.3EY + 1.0EZ)
80 uLCB80 0.9(D + T2) + 1.4(1.0EX + 0.3EY - 1.0EZ)
81 uLCB81 0.9(D + T2) + 1.4(1.0EX - 0.3EY + 1.0EZ)
82 uLCB82 0.9(D + T2) + 1.4(1.0EX - 0.3EY - 1.0EZ)
83 uLCB83 0.9(D + T2) - 1.4(1.0EX + 0.3EY + 1.0EZ)
84 uLCB84 0.9(D + T2) - 1.4(1.0EX + 0.3EY - 1.0EZ)
85 uLCB85 0.9(D + T2) - 1.4(1.0EX - 0.3EY + 1.0EZ)
86 uLCB86 0.9(D + T2) - 1.4(1.0EX - 0.3EY - 1.0EZ)
87 uLCB87 0.9(D + T2) + 1.4(0.3EX + 1.0EY + 1.0EZ)
88 uLCB88 0.9(D + T2) + 1.4(0.3EX + 1.0EY - 1.0EZ)
89 uLCB89 0.9(D + T2) + 1.4(0.3EX – 1.0EY + 1.0EZ)
90 uLCB90 0.9(D + T2) + 1.4(0.3EX – 1.0EY - 1.0EZ)
91 uLCB91 0.9(D + T2) - 1.4(0.3EX + 1.0EY + 1.0EZ)
92 uLCB92 0.9(D + T2) - 1.4(0.3EX + 1.0EY - 1.0EZ)
93 uLCB93 0.9(D + T2) - 1.4(0.3EX – 1.0EY + 1.0EZ)
94 uLCB94 0.9(D + T2) - 1.4(0.3EX – 1.0EY - 1.0EZ)
95 uLCB95 1.4D
96 uLCB96 1.2D + 1.6L + 0.5Lr
97 uLCB97 1.2D + 1.6Lr + 0.5L
98 uLCB98 1.2D + 1.6Lr + 0.8WX
99 uLCB99 1.2D + 1.6Lr - 0.8WX
100 uLCB100 1.2D + 1.6Lr + 0.8WY
101 uLCB101 1.2D + 1.6Lr - 0.8WY
102 uLCB102 1.2D + 1.6WX + 0.5L + 0.5Lr
103 uLCB103 1.2D - 1.6WX + 0.5L + 0.5Lr
104 uLCB104 1.2D + 1.6WY + 0.5L + 0.5Lr
105 uLCB105 1.2D - 1.6WY + 0.5L + 0.5Lr
106 uLCB106 1.2D + 1.4(1.0EX + 0.3EY + 1.0EZ) + 0.5L

Revisión F 164
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-004

107 uLCB107 1.2D + 1.4(1.0EX + 0.3EY - 1.0EZ) + 0.5L


108 uLCB108 1.2D + 1.4(1.0EX - 0.3EY + 1.0EZ) + 0.5L
109 uLCB109 1.2D + 1.4(1.0EX - 0.3EY - 1.0EZ) + 0.5L
110 uLCB110 1.2D - 1.4(1.0EX + 0.3EY + 1.0EZ) + 0.5L
111 uLCB111 1.2D - 1.4(1.0EX + 0.3EY - 1.0EZ) + 0.5L
112 uLCB112 1.2D - 1.4(1.0EX - 0.3EY + 1.0EZ) + 0.5L
113 uLCB113 1.2D - 1.4(1.0EX - 0.3EY - 1.0EZ) + 0.5L
114 uLCB114 1.2D + 1.4(0.3EX + 1.0EY + 1.0EZ) + 0.5L
115 uLCB115 1.2D + 1.4(0.3EX + 1.0EY - 1.0EZ) + 0.5L
116 uLCB116 1.2D + 1.4(0.3EX – 1.0EY + 1.0EZ) + 0.5L
117 uLCB117 1.2D + 1.4(0.3EX – 1.0EY - 1.0EZ) + 0.5L
118 uLCB118 1.2D - 1.4(0.3EX + 1.0EY + 1.0EZ) + 0.5L
119 uLCB119 1.2D - 1.4(0.3EX + 1.0EY - 1.0EZ) + 0.5L
120 uLCB120 1.2D - 1.4(0.3EX – 1.0EY + 1.0EZ) + 0.5L
121 uLCB121 1.2D - 1.4(0.3EX – 1.0EY - 1.0EZ) + 0.5L
122 uLCB122 0.9D + 1.6WX
123 uLCB123 0.9D - 1.6WX
124 uLCB124 0.9D + 1.6WY
125 uLCB125 0.9D - 1.6WY
126 uLCB126 0.9D + 1.4(1.0EX + 0.3EY + 1.0EZ)
127 uLCB127 0.9D + 1.4(1.0EX + 0.3EY - 1.0EZ)
128 uLCB128 0.9D + 1.4(1.0EX - 0.3EY + 1.0EZ)
129 uLCB129 0.9D + 1.4(1.0EX - 0.3EY - 1.0EZ)
130 uLCB130 0.9D - 1.4(1.0EX + 0.3EY + 1.0EZ)
131 uLCB131 0.9D - 1.4(1.0EX + 0.3EY - 1.0EZ)
132 uLCB132 0.9D - 1.4(1.0EX - 0.3EY + 1.0EZ)
133 uLCB133 0.9D - 1.4(1.0EX - 0.3EY - 1.0EZ)
134 uLCB134 0.9D + 1.4(0.3EX + 1.0EY + 1.0EZ)
135 uLCB135 0.9D + 1.4(0.3EX + 1.0EY - 1.0EZ)
136 uLCB136 0.9D + 1.4(0.3EX – 1.0EY + 1.0EZ)
137 uLCB137 0.9D + 1.4(0.3EX – 1.0EY - 1.0EZ)

Revisión F 165
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-004

138 uLCB138 0.9D - 1.4(0.3EX + 1.0EY + 1.0EZ)


139 uLCB139 0.9D - 1.4(0.3EX + 1.0EY - 1.0EZ)
140 uLCB140 0.9D - 1.4(0.3EX – 1.0EY + 1.0EZ)
141 uLCB141 0.9D - 1.4(0.3EX – 1.0EY - 1.0EZ)

3.7.3 ASD Load Combination (For Structure)


The AUD load combinationu uhall take into account the earthquake load in Technical Specification.
Technical Upecification conuidered a nominal load, uo it muut be amplified by a factor 1.0.

No. Caue Name Deucription


1 sLCB1 (D + T1)
2 sLCB2 (D + T1) + L
3 sLCB3 (D + T1) + Lr
4 sLCB4 (D + T1) + 0.75L + 0.75Lr
5 sLCB5 (D + T1) + WX
6 sLCB6 (D + T1) - WX
7 sLCB7 (D + T1) + WY
8 sLCB8 (D + T1) - WY
9 sLCB9 (D + T1) + EX + 0.3EY + EZ
10 sLCB10 (D + T1) + EX + 0.3EY - EZ
11 sLCB11 (D + T1) + EX - 0.3EY + EZ
12 sLCB12 (D + T1) + EX - 0.3EY - EZ
13 sLCB13 (D + T1) - EX + 0.3EY + EZ
14 sLCB14 (D + T1) - EX + 0.3EY - EZ
15 sLCB15 (D + T1) - EX - 0.3EY + EZ
16 sLCB16 (D + T1) - EX - 0.3EY - EZ
17 sLCB17 (D + T1) + 0.3EX + EY + EZ
18 sLCB18 (D + T1) + 0.3EX + EY - EZ
19 sLCB19 (D + T1) + 0.3EX - EY + EZ
20 sLCB20 (D + T1) + 0.3EX - EY - EZ
21 sLCB21 (D + T1) - 0.3EX + EY + EZ

Revisión F 166
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-004

22 sLCB22 (D + T1) - 0.3EX + EY - EZ


23 sLCB23 (D + T1) - 0.3EX - EY + EZ
24 sLCB24 (D + T1) - 0.3EX - EY - EZ
25 sLCB25 (D + T1) + 0.75WX + 0.75L + 0.75Lr
26 sLCB26 (D + T1) - 0.75WX + 0.75L + 0.75Lr
27 sLCB27 (D + T1) + 0.75WY + 0.75L + 0.75Lr
28 sLCB28 (D + T1) - 0.75WY + 0.75L + 0.75Lr
29 sLCB29 (D + T1) + 0.75[EX + 0.3EY + EZ] + 0.75L
30 sLCB30 (D + T1) + 0.75[EX + 0.3EY – EZ] + 0.75L
31 sLCB31 (D + T1) + 0.75[EX - 0.3EY + EZ] + 0.75L
32 sLCB32 (D + T1) + 0.75[EX - 0.3EY – EZ] + 0.75L
33 sLCB33 (D + T1) - 0.75[EX + 0.3EY + EZ] + 0.75L
34 sLCB34 (D + T1) - 0.75[EX + 0.3EY – EZ] + 0.75L
35 sLCB35 (D + T1) - 0.75[EX - 0.3EY + EZ] + 0.75L
36 sLCB36 (D + T1) - 0.75[EX - 0.3EY – EZ] + 0.75L
37 sLCB37 (D + T1) + 0.75[0.3EX + EY + EZ] + 0.75L
38 sLCB38 (D + T1) + 0.75[0.3EX + EY – EZ] + 0.75L
39 sLCB39 (D + T1) + 0.75[0.3EX - EY + EZ] + 0.75L
40 sLCB40 (D + T1) + 0.75[0.3EX - EY – EZ] + 0.75L
41 sLCB41 (D + T1) - 0.75[0.3EX + EY + EZ] + 0.75L
42 sLCB42 (D + T1) - 0.75[0.3EX + EY – EZ] + 0.75L
43 sLCB43 (D + T1) - 0.75[0.3EX - EY + EZ] + 0.75L
44 sLCB44 (D + T1) - 0.75[0.3EX - EY – EZ] + 0.75L
45 sLCB45 0.6(D + T1) + WX
46 sLCB46 0.6 (D + T1) - WX
47 sLCB47 0.6 (D + T1) + WY
48 sLCB48 0.6 (D + T1) - WY
49 sLCB49 0.6 (D + T1) + EX + 0.3EY + EZ
50 sLCB50 0.6 (D + T1) + EX + 0.3EY - EZ
51 sLCB51 0.6 (D + T1) + EX - 0.3EY + EZ
52 sLCB52 0.6 (D + T1) + EX - 0.3EY - EZ

Revisión F 167
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-004

53 sLCB53 0.6 (D + T1) - EX + 0.3EY + EZ


54 sLCB54 0.6 (D + T1) - EX + 0.3EY - EZ
55 sLCB55 0.6 (D + T1) - EX - 0.3EY + EZ
56 sLCB56 0.6 (D + T1) - EX - 0.3EY - EZ
57 sLCB57 0.6 (D + T1) + 0.3EX + EY + EZ
58 sLCB58 0.6 (D + T1) + 0.3EX + EY - EZ
59 sLCB59 0.6 (D + T1) + 0.3EX - EY + EZ
60 sLCB60 0.6 (D + T1) + 0.3EX - EY - EZ
61 sLCB61 0.6 (D + T1) - 0.3EX + EY + EZ
62 sLCB62 0.6 (D + T1) - 0.3EX + EY - EZ
63 sLCB63 0.6 (D + T1) - 0.3EX - EY + EZ
64 sLCB64 0.6 (D + T1) - 0.3EX - EY - EZ
65 sLCB65 (D + T2)
66 sLCB66 (D + T2) + L
67 sLCB67 (D + T2) + Lr
68 sLCB68 (D + T2) + 0.75L + 0.75Lr
69 sLCB69 (D + T2) + WX
70 sLCB70 (D + T2) - WX
71 sLCB71 (D + T2) + WY
72 sLCB72 (D + T2) - WY
73 sLCB73 (D + T2) + EX + 0.3EY + EZ
74 sLCB74 (D + T2) + EX + 0.3EY - EZ
75 sLCB75 (D + T2) + EX - 0.3EY + EZ
76 sLCB76 (D + T2) + EX - 0.3EY - EZ
77 sLCB77 (D + T2) - EX + 0.3EY + EZ
78 sLCB78 (D + T2) - EX + 0.3EY - EZ
79 sLCB79 (D + T2) - EX - 0.3EY + EZ
80 sLCB80 (D + T2) - EX - 0.3EY - EZ
81 sLCB81 (D + T2) + 0.3EX + EY + EZ
82 sLCB82 (D + T2) + 0.3EX + EY - EZ
83 sLCB83 (D + T2) + 0.3EX - EY + EZ

Revisión F 168
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-004

84 sLCB84 (D + T2) + 0.3EX - EY - EZ


85 sLCB85 (D + T2) - 0.3EX + EY + EZ
86 sLCB86 (D + T2) - 0.3EX + EY - EZ
87 sLCB87 (D + T2) - 0.3EX - EY + EZ
88 sLCB88 (D + T2) - 0.3EX - EY - EZ
89 sLCB89 (D + T2) + 0.75WX + 0.75L + 0.75Lr
90 sLCB90 (D + T2) - 0.75WX + 0.75L + 0.75Lr
91 sLCB91 (D + T2) + 0.75WY + 0.75L + 0.75Lr
92 sLCB92 (D + T2) - 0.75WY + 0.75L + 0.75Lr
93 sLCB93 (D + T2) + 0.75[EX + 0.3EY + EZ] + 0.75L
94 sLCB94 (D + T2) + 0.75[EX + 0.3EY – EZ] + 0.75L
95 sLCB95 (D + T2) + 0.75[EX - 0.3EY + EZ] + 0.75L
96 sLCB96 (D + T2) + 0.75[EX - 0.3EY – EZ] + 0.75L
97 sLCB97 (D + T2) - 0.75[EX + 0.3EY + EZ] + 0.75L
98 sLCB98 (D + T2) - 0.75[EX + 0.3EY – EZ] + 0.75L
99 sLCB99 (D + T2) - 0.75[EX - 0.3EY + EZ] + 0.75L
100 sLCB100 (D + T2) - 0.75[EX - 0.3EY – EZ] + 0.75L
101 sLCB101 (D + T2) + 0.75[0.3EX + EY + EZ] + 0.75L
102 sLCB102 (D + T2) + 0.75[0.3EX + EY – EZ] + 0.75L
103 sLCB103 (D + T2) + 0.75[0.3EX - EY + EZ] + 0.75L
104 sLCB104 (D + T2) + 0.75[0.3EX - EY – EZ] + 0.75L
105 sLCB105 (D + T2) - 0.75[0.3EX + EY + EZ] + 0.75L
106 sLCB106 (D + T2) - 0.75[0.3EX + EY – EZ] + 0.75L
107 sLCB107 (D + T2) - 0.75[0.3EX - EY + EZ] + 0.75L
108 sLCB108 (D + T2) - 0.75[0.3EX - EY – EZ] + 0.75L
109 sLCB109 0.6(D + T2) + WX
110 sLCB110 0.6 (D + T2) - WX
111 sLCB111 0.6 (D + T2) + WY
112 sLCB112 0.6 (D + T2) - WY
113 sLCB113 0.6 (D + T2) + EX + 0.3EY + EZ
114 sLCB114 0.6 (D + T2) + EX + 0.3EY - EZ

Revisión F 169
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-004

115 sLCB115 0.6 (D + T2) + EX - 0.3EY + EZ


116 sLCB116 0.6 (D + T2) + EX - 0.3EY - EZ
117 sLCB117 0.6 (D + T2) - EX + 0.3EY + EZ
118 sLCB118 0.6 (D + T2) - EX + 0.3EY - EZ
119 sLCB119 0.6 (D + T2) - EX - 0.3EY + EZ
120 sLCB120 0.6 (D + T2) - EX - 0.3EY - EZ
121 sLCB121 0.6 (D + T2) + 0.3EX + EY + EZ
122 sLCB122 0.6 (D + T2) + 0.3EX + EY - EZ
123 sLCB123 0.6 (D + T2) + 0.3EX - EY + EZ
124 sLCB124 0.6 (D + T2) + 0.3EX - EY - EZ
125 sLCB125 0.6 (D + T2) - 0.3EX + EY + EZ
126 sLCB126 0.6 (D + T2) - 0.3EX + EY - EZ
127 sLCB127 0.6 (D + T2) - 0.3EX - EY + EZ
128 sLCB128 0.6 (D + T2) - 0.3EX - EY - EZ
129 sLCB129 D
130 sLCB130 D+L
131 sLCB131 D + Lr
132 sLCB132 D + 0.75L + 0.75Lr
133 sLCB133 D + WX
134 sLCB134 D - WX
135 sLCB135 D + WY
136 sLCB136 D - WY
137 sLCB137 D + EX + 0.3EY + EZ
138 sLCB138 D + EX + 0.3EY - EZ
139 sLCB139 D + EX - 0.3EY + EZ
140 sLCB140 D + EX - 0.3EY - EZ
141 sLCB141 D - EX + 0.3EY + EZ
142 sLCB142 D - EX + 0.3EY - EZ
143 sLCB143 D - EX - 0.3EY + EZ
144 sLCB144 D - EX - 0.3EY - EZ
145 sLCB145 D + 0.3EX + EY + EZ

Revisión F 170
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-004

146 sLCB146 D + 0.3EX + EY - EZ


147 sLCB147 D + 0.3EX - EY + EZ
148 sLCB148 D + 0.3EX - EY - EZ
149 sLCB149 D - 0.3EX + EY + EZ
150 sLCB150 D - 0.3EX + EY - EZ
151 sLCB151 D - 0.3EX - EY + EZ
152 sLCB152 D - 0.3EX - EY - EZ
153 sLCB153 D + 0.75WX + 0.75L + 0.75Lr
154 sLCB154 D - 0.75WX + 0.75L + 0.75Lr
155 sLCB155 D + 0.75WY + 0.75L + 0.75Lr
156 sLCB156 D - 0.75WY + 0.75L + 0.75Lr
157 sLCB157 D + 0.75[EX + 0.3EY + EZ] + 0.75L
158 sLCB158 D + 0.75[EX + 0.3EY – EZ] + 0.75L
159 sLCB159 D + 0.75[EX - 0.3EY + EZ] + 0.75L
160 sLCB160 D + 0.75[EX - 0.3EY – EZ] + 0.75L
161 sLCB161 D - 0.75[EX + 0.3EY + EZ] + 0.75L
162 sLCB162 D - 0.75[EX + 0.3EY – EZ] + 0.75L
163 sLCB163 D - 0.75[EX - 0.3EY + EZ] + 0.75L
164 sLCB164 D - 0.75[EX - 0.3EY – EZ] + 0.75L
165 sLCB165 D + 0.75[0.3EX + EY + EZ] + 0.75L
166 sLCB166 D + 0.75[0.3EX + EY – EZ] + 0.75L
167 sLCB167 D + 0.75[0.3EX - EY + EZ] + 0.75L
168 sLCB168 D + 0.75[0.3EX - EY – EZ] + 0.75L
169 sLCB169 D - 0.75[0.3EX + EY + EZ] + 0.75L
170 sLCB170 D - 0.75[0.3EX + EY – EZ] + 0.75L
171 sLCB171 D - 0.75[0.3EX - EY + EZ] + 0.75L
172 sLCB172 D - 0.75[0.3EX - EY – EZ] + 0.75L
173 sLCB173 0.6D + WX
174 sLCB174 0.6 D - WX
175 sLCB175 0.6 D + WY
176 sLCB176 0.6 D - WY

Revisión F 171
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-004

177 sLCB177 0.6 D + EX + 0.3EY + EZ


178 sLCB178 0.6 D + EX + 0.3EY - EZ
179 sLCB179 0.6 D + EX - 0.3EY + EZ
180 sLCB180 0.6 D + EX - 0.3EY - EZ
181 sLCB181 0.6 D - EX + 0.3EY + EZ
182 sLCB182 0.6 D - EX + 0.3EY - EZ
183 sLCB183 0.6 D - EX - 0.3EY + EZ
184 sLCB184 0.6 D - EX - 0.3EY - EZ
185 sLCB185 0.6 D + 0.3EX + EY + EZ
186 sLCB186 0.6 D + 0.3EX + EY - EZ
187 sLCB187 0.6 D + 0.3EX - EY + EZ
188 sLCB188 0.6 D + 0.3EX - EY - EZ
189 sLCB189 0.6 D - 0.3EX + EY + EZ
190 sLCB190 0.6 D - 0.3EX + EY - EZ
191 sLCB191 0.6 D - 0.3EX - EY + EZ
192 sLCB192 0.6 D - 0.3EX - EY - EZ

Revisión F 172
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-004

4. STRUCTURAL SYSTEM
4.1 Structural System and Analysis Condition
The seismic force-resisting system is Concentrically Braced Frame (CBF). A braced frame is subjected
primarily to axial forces.
Structural analysis program use SAP2000. It’s performed to analyze three dimension structural systems
for checking serviceability of this structure on lateral load, designing column, beam and brace.

4.1.1 Boundary Conditions


The boundary condition of column at ground level will be defined as a pinned connection in all the
Concetrical Braced Frames Structures.

If Necessary to define a Moment Frame Structure to Comply the Process Requirements, the boundary
condition of column at ground level will be defines as a semi-rigid moment connection in both horizontal
translational degrees of freedoms.

The semi – rigid condition is defined as a rotational spring with an associated rotational stiffness
according to the base plate and anchor bolts configuration, in order to determine this value it will be
necessary to build a detailed model of the column base and the anchor configuration.

4.1.2 Structural Element


- One dimensional element for steel structure modeling purposes as follows:
Korea Standard Section
Material = Steel KS D 3503 : SS400, Steel KS D 3515 : SM490

Revisión F 173
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-004

4.2 Base Plate and Anchor System


Column reaction resulting from the structural analysis shall be used for the design of base plates and
anchor bolts. Column base plate and anchor bolts shall be designed as per ACI 318-08 and AISC 360-05.
Base plate is made to transfer the column loads and moments to the footings and foundations. Anchor
rods are designed to provide the required resistance to loads which result from load combination
stipulated in Section 3.7.
The requirement that anchor bolts of columns shall have a projection of at least eight diameters and no
less than 250 mm measured from the base plates (according to Section 8.6.2 of NCh 2369), provides
adequate anchor bolts length to eventually allow for yielding of the anchor bolt under severe earthquake
loading.

Revisión F 174
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-004

Typical Detail of Column Base in Figure A.1 of NCh 2369 of 2003

Revisión F 175
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-004

5. STRUCTURAL ANALYSIS
5.1 Base Shear and Equivalent Mass
These results are calculated by the analysis model for earthquake load.
If the base shear force is lower than the minimum base shear (0.12 X total weight), the scale-up factor
(12% of total weight / base shear) should be applied for earthquake load according to the Section 5.4.5 of
NCh 2369 of 2003.

5.1.1 Mass Distribution


The self-weight is converted into masses automatically in SAP2000 program.
Seismic mass percentages are considered according to Technical Specification.
It shall be considered the following percentage of seismic mass for live load:

Section Seismic Mass Percentage (%)

Area of Normal Use, Floor Live Load 25

5.2 Natural Vibration Mode


These results are calculated by the analysis model. The analysis shall include a sufficient number of
vibration modes for the sum of equivalent masses in each analysis direction is equal to or higher than
90% of the total mass.

5.3 Support Reaction


These results are calculated by the analysis model in three directions.

Since the earthquake load was computed trough a Response Spectrum Analysis, its reactions are
absolute values. In order to design the foundations of this structure it is necessary to assign the sign for
each reaction according to the predominant modal shapes in the respective direction.

Revisión F 176
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-004

5.4 Displacement

5.4.1 Displacement due to the Earthquake Load

The displacement for earthquake load can verified according to the Section 6.1 and 6.3.
d = d0 + R1dd
Where,
d = Seismic Deformation
dd = Deformation due to non-seismic service loads
R1 = Factor resulting from multiplying the R factor derived from Table 5.6 of NCh 2369 of 2003 by the
quotient Q0/Qmin provided that Q0/Qmin ne lower or equal to 1.0. However, for the quotient Q0/Qmin a
value under 0.5 shall not be used. If this quotient is higher than 1.0, R1 =R shall be used.

The maximum seismic deformation for other structures is below:


dmax = 0.015 h
Where,
h = Height between floors of between two points located on the same vertical.

5.4.2 Separation between Structures

The separation between structures is calculated based on section 6.2 of NCh 2369. The purpose of
preventing impacts between adjoining structures, their separation shall be bigger than the highest of the
following values:

1) S = ((R1i ddi)2 + (R1j ddj)2)1/2 + d0i + d0j


2) S = 0.002 (hi + hj)
3) 30mm

Where, ddi, ddj : Deformation calculated with R-factor reduced earthquake load of the structures i and j
d0i, d0j : Deformation due to non-seismic service loads
R1i ,R1j : Response modification factors R1 used for the design of the structures i and j
hi, hj : Height at the considered level of the structures I and j measured from their respective base
levels

Revisión F 177
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-004

6. MEMBER DESIGN
The design of steel structures shall comply with “Earthquake-Resistant Design of Industrial Structures and
Facilities NCh 2369” and “Specification for Structural Steel Buildings AISC 360-05”.
The maximum slenderness can be considered in the design:

Element kl / r

Columns 1.5π√(E/Fy)
Other Elements in Compression 1.5π√(E/Fy)
Element in Traction 240
Bracing Resisting Seismic Load 1.5π√(E/Fy)

Member design was checked about all members of column, beam and brace and so on. On this report,
attached calculation note is about what the worst case of the load combination cases each member.

Revisión F 178
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-004

6.1 Column Design

6.1.1 Design Load


Load from LRFD Combination
- Pr : Maximum Axial Force
- Mr : Maximum Bending Moment
- Vr : Maximum Shear Force

6.1.2 Schematic Drawing

6.1.3 Verification (AISC360-05, NCh 2369)


1) Slenderness Ratio
- KL / r < 1.5π√(E/Fy)......(OK)
2) Seismic Width-Thickness
- λf = bf / 2tf < λps (for flange)......(OK)
- λw = h / tw < λps (for web)......(OK)
3) Axial Strength
- Pr / Pc < 1.0......(OK)
4) Bending Strength
- Mrx / Mcx < 1.0......(OK)
- Mry / Mcy < 1.0......(OK)
5) Combined Strength (Compression + Bending)
- For Pr / Pc ≥ 0.2 => Rmax = Pr / Pc + 8/9 X (Mrx / Mcx + Mry / Mcy) < 1.0......(OK)
- For Pr / Pc < 0.2 => Rmax = Pr / 2Pc + (Mrx / Mcx + Mry / Mcy) < 1.0......(OK)
6) Shear Strength

Revisión F 179
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-004

- Vrx / Vcx < 1.0......(OK)


- Vry / Vcy < 1.0......(OK)

Where,
λps : Limiting Width-Thickness Ratio
Pc : Design Compressive Strength
Mc : Design Flexural Strength
Vc : Design Shear Strength

Revisión F 180
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-004

6.2 Beam and Girder Design

6.2.1 Design Load


Load from LRFD Combination
- Pr : Maximum Axial Force
- Mr : Maximum Bending Moment
- Vr : Maximum Shear Force

6.2.2 Schematic Drawing

6.2.3 Verification (AISC360-05, NCh 2369)


1) Slenderness Ratio
- KL / r < 1.5π√(E/Fy)......(OK)
2) Seismic Width-Thickness
- λf = bf / 2tf < λps (for flange)......(OK)
- λw = h / tw < λps (for web)......(OK)
3) Axial Strength
- Pr / Pc < 1.0......(OK)
4) Bending Strength
- Mrx / Mcx < 1.0......(OK)
- Mry / Mcy < 1.0......(OK)
5) Combined Strength (Compression + Bending)
- For Pr / Pc ≥ 0.2 => Rmax = Pr / Pc + 8/9 X (Mrx / Mcx + Mry / Mcy) < 1.0......(OK)
- For Pr / Pc < 0.2 => Rmax = Pr / 2Pc + (Mrx / Mcx + Mry / Mcy) < 1.0......(OK)
6) Shear Strength

Revisión F 181
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-004

- Vrx / Vcx < 1.0......(OK)


- Vry / Vcy < 1.0......(OK)

Where,
λps : Limiting Width-Thickness Ratio
Pc : Design Compressive Strength
Mc : Design Flexural Strength
Vc : Design Shear Strength

Revisión F 182
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-004

6.3 Brace Design

6.3.1 Design Load


Load from LRFD Combination
- Pr : Maximum Axial Force
- Mr : Maximum Bending Moment
- Vr : Maximum Shear Force

6.3.2 Schematic Drawing

6.3.3 Verification (AISC360-05, NCh 2369)


1) Slenderness Ratio
- KL / r < 1.5π√(E/Fy)......(OK)
2) Seismic Width-Thickness
- λf = bf / 2tf < λps (for flange)......(OK)
- λw = h / tw < λps (for web)......(OK)
3) Axial Strength
- Pr / Pc < 0.8......(OK)
4) Bending Strength
- Mrx / Mcx < 0.8......(OK)
- Mry / Mcy < 0.8......(OK)
5) Combined Strength (Compression + Bending)
- For Pr / Pc ≥ 0.2 => Rmax = Pr / Pc + 8/9 X (Mrx / Mcx + Mry / Mcy) < 0.8......(OK)
- For Pr / Pc < 0.2 => Rmax = Pr / 2Pc + (Mrx / Mcx + Mry / Mcy) < 0.8......(OK)
6) Shear Strength

Revisión F 183
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-004

- Vrx / Vcx < 0.8......(OK)


- Vry / Vcy < 0.8......(OK)

Where,
λps : Limiting Width-Thickness Ratio
Pc : Design Compressive Strength
Mc : Design Flexural Strength
Vc : Design Shear Strength

Revisión F 184
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-004

6.4 Connection Design

6.4.1 Column Splice

6.4.1.1 Design Load


Full Capacity of Column
- Pu : Maximum Axial Force (= Φ Fy Ag)
- Mu : Maximum Bending Moment (= Φ Fy Zx)
- Vu : Maximum Shear Force (= 0.6 Φ Fy Aw)
- Tu : Maximum Tensile Force at Flange (=Mu / Arm of Column)

6.4.1.2 Schematic Drawing

6.4.1.3 Verification (AISC360-05)


1) Bolt Strength
- Shear Strength ΦRn1 = Φ Ns Fn Ab
- Bearing Strength at Bolt Holes ΦRn2 = Min (Φ 1.2 Lc t Fu, Φ 2.4 d t Fu)
- Slip-Critical Connections ΦRn3 = Φ μ Du hsc Tb Ns
- ΦRn = Min (ΦRn1, ΦRn2, ΦRn3)
- Pu / ΦRn < Number of Bolt......(OK)
- Vu / ΦRn < Number of Bolt......(OK)

Revisión F 185
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-004

- Tu / ΦRn < Number of Bolt......(OK)


2) Web Splice Plate Verification
- Shear Yielding Φ 0.6 Fy Ag ≥ Vu......(OK)
- Shear Rupture Φ 0.6 Fu Anv ≥ Vu......(OK)
3) Flange Splice Plate Verification
- Tensile Yielding Φ Fy Ag ≥ Tu......(OK)
- Tensile Rupture Φ Fu Ae ≥ Tu......(OK)

Revisión F 186
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-004

6.4.2 Beam Connection

6.4.2.1 Design Load


1) Special Earthquake Load Combination
- Ru1 is determined due to the 1.2D + 0.5L + ΩE
2) 0.5 X Full Capacity for Shear
- Ru2 = 0.5 Φ 0.6 Fy Aw Cv
3) Ru = Max (Ru1, Ru2)
4) If the load from brace are transferred to the girder and beam directly, the connection would be
designed by full capacity of brace.

6.4.2.2 Schematic Drawing

6.4.2.3 Verification (AISC360-05)


1) Bolt Strength
- Shear Strength ΦRn1 = Φ Ns Fn Ab
- Bearing Strength at Bolt Holes ΦRn2 = Min (Φ 1.2 Lc t Fu, Φ 2.4 d t Fu)
- Slip-Critical Connections ΦRn3 = Φ μ Du hsc Tb Ns
- ΦRn = Min (ΦRn1, ΦRn2, ΦRn3)
- Ru / ΦRn < Number of Bolt......(OK)
2) Web Splice Plate Verification
- Shear Yielding Φ 0.6 Fy Ag ≥ Ru......(OK)
- Shear Rupture Φ 0.6 Fu Anv ≥ Ru......(OK)
3) Block Shear Rupture Verification
- Φ (0.6 Fu Anv + Ubs Fu Ant) ≥ Ru......(OK)
- Φ (0.6 Fy Agv + Ubs Fu Ant) ≥ Ru......(OK)

Revisión F 187
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-004

.4.3 Brace to Gusset Connection

6.4.3.1 Design Load


Full Capacity of Brace
- Tu : Maximum Tensile Force (= Ry Fy Ag)
- Pu : Maximum Compressive Force (= 1.1 Ry Pn)
- Ruw : Force in Web
- Ruf : Force in Flange

6.4.3.2 Schematic Drawing


In case of H-Shape Brace In case of Channel Brace

6.4.3.3 Verification in case of H-Shape Brace (AISC360-05)


1) Bolt Strength
- Shear Strength ΦRn1 = Φ Ns Fn Ab
- Bearing Strength at Bolt Holes ΦRn2 = Min(Φ 1.2 Lc t Fu, Φ 2.4 d t Fu)
- Slip-Critical Connections ΦRn3 = Φ μ Du hsc Tb Ns
- ΦRn = Min(ΦRn1, ΦRn2, ΦRn3)

Revisión F 188
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-004

- Ruf / ΦRn < Number of Bolt......(OK)


- Ruw / ΦRn < Number of Bolt......(OK)

2) Tension Capacity of the Angles


- Tension Yielding Φ Fy Ag ≥ Ruf / 2......(OK)
Φ Fy Ag ≥ Ruw......(OK)
- Tension Rupture Φ Fu Ae ≥ Ruf / 2......(OK)
Φ Fu Ae ≥ Ruw......(OK)
3) Block Shear Rupture Verification of the Angles
- Φ (0.6 Rt Fu Anv + Ubs Rt Fu Ant) ≥ Ruf / 2......(OK)
- Φ (0.6 Ry Fy Agv + Ubs Rt Fu Ant) ≥ Ruf / 2......(OK)
- Φ (0.6 Rt Fu Anv + Ubs Rt Fu Ant) ≥ Rw......(OK)
- Φ (0.6 Ry Fy Agv + Ubs Rt Fu Ant) ≥ Rw......(OK)

6.4.3.4 Verification in case of Channel Brace (AISC360-05)


1) Bolt Strength
- Shear Strength ΦRn1 = Φ Ns Fn Ab
- Bearing Strength at Bolt Holes ΦRn2 = Min(Φ 1.2 Lc t Fu, Φ 2.4 d t Fu)
- Slip-Critical Connections ΦRn3 = Φ μ Du hsc Tb Ns
- ΦRn = Min(ΦRn1, ΦRn2, ΦRn3)
- Tu / ΦRn < Number of Bolt......(OK)
2) Net Section Fracture
- Φt Rt Fu Ae ≥ Tu......(OK)
3) Block Shear Rupture Verification of the Angles
- Φ (0.6 Rt Fu Anv + Ubs Rt Fu Ant) ≥ Tu......(OK)
- Φ (0.6 Ry Fy Agv + Ubs Rt Fu Ant) ≥ Tu......(OK)

Revisión F 189
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-004

6.4.4 Gusset Plate Design

6.4.4.1 Design Load


Full Capacity of Brace
- Tu : Maximum Tensile Force (= Ry Fy Ag)
- Pu : Maximum Compressive Force (= 1.1 Ry Pn)

6.4.4.2 Schematic Drawing


Concept Drawing Design Force of Gusset Plate

Whitmore Section of Gusset Plate

Revisión F 190
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-004

6.4.4.3 Verification (AISC360-05)


1) Design the Weld at the Gusset-Column Interface
- fv = Huc / 2β
- fa = Vuc / 2β
- fb = 0
- fpeak = √[fv2 + (fa + fb)2]
- favg = (1/2) × {√[(fa - fb)2 + fv2] +√[(fa + fb)2+ fv2]}
- fr = 1.25 X favg (If fpeak / favg < 1.25)
- fr = fpeak (If fpeak / favg ≥ 1.25)
- s ≥ fr / (0.7 (0.9) (0.6) Fy (2))......(OK)
- tmin (=2 (0.9) (0.6) Fy 0.7s / (0.75 (0.6) Fu) < thickness of gusset plate......(OK)
2) Yielding of Gusset Plate
- ΦRn (=Φ Fy t) > MAX.(fv,fa)......(OK)
3) Column Web Yielding
- ΦRn (=Φ Fy tw) > fr......(OK)
4) Column Web Crippling
- ΦRn = Φ 0.8 tw2 [1 + 3(N / d) (tw / tf)1.5] √(E Fyw tf / tw) > Huc......(OK)
5) Design the Weld at the Gusset-Beam Interface (In Tension and Compression)
- fv = Hub / 2α
- fa = Vub / 2α
- fb = Mub / Sw (Sw = (2α)2 / 6)
- fpeak = √[fv2 + (fa + fb)2]
- favg = (1/2) × {√[(fa - fb)2 + fv2] +√[(fa + fb)2+ fv2]}
- fr = 1.25 X favg (If fpeak / favg < 1.25)
- fr = fpeak (If fpeak / favg ≥ 1.25)
- s ≥ fr / (0.7 (0.9) (0.6) Fy (2))......(OK)
- tmin (=2 (0.9) (0.6) Fy 0.7s / (0.75 (0.6) Fu) < thickness of gusset plate......(OK)
6) Yielding of Gusset Plate
- ΦRn (=Φ Fy t) > MAX.(fv,fa)......(OK)
7) Beam Web Yielding
- ΦRn (=Φ Fy tw) > fr......(OK)
8) Beam Web Local Yielding (if the brace connection is located in center of girder)

Revisión F 191
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-004

- ft = fa + fb
- fc = fa – fb
- Lt = [ft / (ft + tc)] / Lg
- Ru = (1/2) Lt ft
- ΦRn = (5k + N) Fyw tw
- Ru < ΦRn......(OK)
9) Beam Web Crippling
- Ru = [Mub / (N2 / 4)] (N / 2) + Vub = 2Mub / N + Vub
- ΦRn = Φ 0.4 tw2 [1 + 3(N / d) (tw / tf)1.5] √(E Fyw tf / tw) (N/d ≤ 0.2)
- ΦRn = Φ 0.4 tw2 [1 + (4N / d - 0.2) (tw / tf)1.5] √(E Fyw tf / tw) (N/d > 0.2)
- Ru < ΦRn......(OK)
10) Beam Web Crippling (if the brace connection is located in center of girder)
- Ru = (1/2) (Lg - Lt) fc
- ΦRn = Φ 0.8 tw2 [1 + 3(N / d) (tw / tf)1.5] √(E Fyw tf / tw)
- Ru < ΦRn......(OK)
11) Compression Buckling of Gusset Plate
- Φc Fcr Ag > Pu......(OK) (The Ag should be considered whitmore section)
12) Tensile Yielding of Gusset Plate
- Φt Fy Ag > Tu X Ratio of Resisting Bolt......(OK) (The Ag should be considered whitmore section)

Revisión F 192
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-004

6.5 Base Plate and Anchor Bolt Design

6.5.1 Design Load


Load from LRFD Combination
- Pu : Maximum Compressive Force
- Tu : Maximum Tensile Force
- Mu : Maximum Bending Moment
- Vu : Maximum Shear Force

6.5.2 Schematic Drawing

6.5.3 Verification (AISC360-05, ACI318-08)


1) Bearing Stress of Base Plate
- Fp = 0.85 Φ fc √(A2 / A1)
- fp = Pu (1+6e / (N or B)) / A (In case of e < (N or B) / 6)
- fp < Fp......(OK)
2) Thickness of Base Plate
- t1 = √ (ß x fp x u2 / 1.5 Fy) (ß : derived by Roak’s Table)
- t2 = √ (ß x fp x (B / 2)2 / 1.5 Fy) (ß : derived by Roak’s Table)
- t > Max.(t1,t2) ......(OK)
3) Embedded Depth and Width of the Shear Key
- Φ Vn = 0.85 Φ fc A > Vu......(OK)

Revisión F 193
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-004

4) Thickness of Shear Key


- treq = √ (ß x fp x Max(W/2-t/2, d+G)2 / 1.5 Fy) (ß : derived by Roak’s Table)
- treq > t ......(OK)
5) Bearing Strength of the Concrete
- Fp = 0.85 Φ fc √(A2 / A1)
- fp = Vu / (W X d)
- fp < Fp......(OK)
6) Anchor Bolt Verification
- Tension Strength : 0.75 Φ Nn = 0.75 Φ n Ase Fut > Tu......(OK)
- Tb = (Tu / 2 + (Mbuilt-in / (d-d’)) / Number of Bolt
- Ase,req = Tu / (0.75 Φ Tb) < Ase......(OK)
- Concrete Breakout Strength : Ncb = ANc / ANco x ψed,N x ψc,N x ψcp,N x Nb > Tu......(OK)
7) Design of Rib Plate
- Height of Rib Plate : 8d of 250mm
- Ru : Reaction due to the anchor bolt full capacity
- Φ Pn = Φ Ag Fcr > Ru......(OK)
- fa : Axial Stress due to the concrete pressure
- Fc > fa......(OK)
8) Design of Upper Plate
M : Bending Moment due to the anchor bolt full capacity
- Φ Fy Z = Φ Fy u t2 / 4 > M......(OK)
9) Design of Anchor Plate
M : Bending Moment due to the anchor bolt full capacity
- Φ Fy Z = Φ Fy u t2 / 4 > M......(OK)

Revisión F 194
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-001

ANEXO 4: CRITERIOS DE DISEÑO ESPECIFICOS SILO DE CAL Y


CENIZAS RECICLADAS

195 de 392

Revisión F
DESIGN CRITERIA FOR LIME STORAGE, TOTAL 51 HOJAS
RECYCLE ASH STORAGE SILO (Incluyendo Portada)

PROPOSITO

Para Revisión
 NOMBRE CONTRATO EPC POR EL SISTEMA DE
PROYECTO DESULFURIZACION DE GASES - FGD - PARA
LA CENTRAL TARAPACÁ Para Aprobación

 NOMBRE FGD CENTRAL TARAPACÁ Para Construcción


SISTEMA
Para Oferta
 N° DOCUMENTO DCTO413-C8-VVT-000-005
Para Información
 TITULO DESIGN CRITERIA FOR LIME STORAGE,
RECYCLE ASH STORAGE SILO SUPPORT
STRUCTURE AND CASING

 CLIENTE ENDESA S.A.

F 29-12-2014 JCR VBS NCR Para Aprobación

E 22-12-2014 JCR VBS NCR Para Aprobación

D 25-11-2014 JCR VBS NCR Para Aprobación

C 27-10-2014 JCR VBS NCR Para Aprobación

B 30-09-2014 JCR VBS NCR Para Aprobación

A 24-09-2014 JCR VBS NCR Coordinación Interna - - -

PREP. REV. APR. REV. REV. APR.


Rev
FECHA DESCRIPCION
.
STX HI ENDESA S.A.

PROPIETARIO:

CONTRATISTA:
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-005

DESIGN CRITERIA FOR LIME STORAGE,


RECYCLE ASH STORAGE SILO

Rev. F

Revisión F 197
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-005

Contents
1 INTRODUCTION
1.1 Location
1.2 Weather
1.3 Scope

2 STRUCTURAL DESIGN CRITERIA


2.1 Design Code and Reference
2.2 Materials
2.3 Structural Analysis and Design Program

3 DESIGN LOADS
3.1 Dead Load
3.2 Live Load
3.3 Thermal Load
3.4 Wind Load
3.5 Earthquake Load
3.6 Load Combination

4 STRUCTURAL SYSTEM
4.1 Structural System and Analysis Condition
4.2 Base Plate and Anchor System

5 STRUCTURAL ANALYSIS
5.1 Base Shear and Equivalent Mass
5.2 Natural Vibration Mode
5.3 Support Reaction
5.4 Displacement

6 MEMBER DESIGN
6.1 Column Design
6.2 Beam and Girder Design
6.3 Brace Design

Revisión F 198
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-005

6.4 Connection Design


6.5 Base Plate and Anchor Bolt Design
6.6 Connection between SILO and Structure

7 CASING CALCULATION NOTE


7.1 SILO Casing Design

Revisión F 199
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-005

1. INTRODUCTION
1.1 Location
The Tarapacá Thermal Power Plant (158 MW), henceforth the Power Plant, owned by Compañía
Eléctrica Tarapacá S.A., hereinafter CELTA S.A or CELTA, is located on the I Region of Chile,
approximately 60km south of Iquique, by the coast, on the area known as Punta Patache.

1.2 Weather
Weather conditions in the sector are as follows:
Barometric Pressure(Average): 1,015 millibars
Ambient Temperature: Maximum 31.3℃, Minimum 8℃
Relative Humidity(Mean): 78%

1.3 Scope
This is design criteria for Lime Storage, Recycle Ash Storage Silo support structure and casing.

Revisión F 200
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-005

2. STRUCTURAL DESIGN CRITERIA


The structural design criteria in this report were calculated according to Technical Specification.

2.1 Design Code and Reference


Code Code & Reference Remarks
Earthquake-Resistant Design of Industrial Structures
NCh 2369 Seismic Design
and Facilities
ETG 1015 General Technical Specifications – Seismic Design Seismic Design
NCh 432 Structural Design – Wind Loads Wind Load
Structural Design – General Dispositions and
NCh 3171 Load Combination
Combinations of Load
Minimum Design Loads for Building and Other
ASCE 7-05 Load Combination
Structures
AISC 360-05 Specification for Structural Steel Buildings Steel Design
ACI 318-08 Building Code Requirements for Structural Concrete Anchoring to Concrete
Eurocode 1 – Actions on Structures – Part4 : Silo and
EN 1991-4 SILO Design Loads
Tanks
EN 1993-4-1 Eurocode 3 – Design of Steel Structures – Part4 : Silos SILO Design
API 650 Welded Steel Tanks for Oil Storage TANK Design

2.2 Materials
Tensile Modulus of
Standard Symbol Yield Strength Remarks
Strength Elasticity
Structural Steel /
KS D 3503 235 MPa (t ≤ 40mm)
SS 400 400 MPa 200,000 MPa Anchor Bolt / SILO
JIS G 3101 215 MPa (t > 40mm)
Casing
KS D 3515 315 MPa (t ≤ 40mm)
SM490 490 MPa 200,000 MPa Structural Steel
JIS G 3106 295 MPa (t > 40mm)
ASTM A36 250 MPa 400 MPa 200,000 MPa Anchor Bolt

Standard Symbol Nominal Tensile Stress Nominal Shear Stress Remarks


KS B 1010 F10T 736 MPa 392 MPa
High Strength Bolt
ASTM A325 620 MPa 330 MPa
/ Torque Shear Bolt
ASTM A490 780 MPa 414 MPa

* Friction Coefficient 0.35 : Class A surface ( unpainted clean mill scale steel surfaces or surfaces with
Class A coatings on blast-cleaned steel and hot-dipped galvanized and roughened surfaces)

Revisión F 201
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-005

Material properties in operation temperature (180℃) (ASME 2010 U, Y-1, TM-1)


Modulus of
Symbol Yield Strength Tensile Strength Remarks
Elasticity
SS 400 204 MPa 400 MPa 193,200 MPa SA-36

The material properties for determine the required strength of element and connection are included
KBC 2009 (Korean Building Code 2009) section 0713.6.2.

In section 0713.6.2 of KBC 2009 (Original)

Revisión F 202
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-005

In section 0713.6.2 of KBC 2009 (Translation)


0713.6.2 Material Properties for determine the required strength of member and connection
(1) When estimate the required strength of each member (member or connection) by the provision of
this section, the required strength should be calculated based on the expected yield strength Ry Fy
of connected member. In here, Fy is the minimum yield strength of connected member and Ry is
the ratio of expected yield strength and minimum yield strength.

(2) The design strength ФRn should be at least the required strength. When estimate the nominal

Strength Rn for fracture and yield state, the expected tensile strength Rt Fu and expected yield
Strength Ry Fy can be used instead of Fu and Fy.
(3) The values of Ry and Rt are in the table 0713.6.1.

<Table 0713.6.1> The values of Ry and Rt for each type of steel

Application Ry Rt
KS SS400, SSC400, SWH400,
KS STK400, STK490, SPSR400, SPSR490, 1.3 1.2
STKN400, STKN490
Structural Rolled Shapes
Steel and Cold Formed KS SM400, SM490, SM520
Steel KS SPAR295, SPAP235, SPAP325, 1.2 1.2
SCW490-CF
KS SHN400, SHN490 1.1 1.1
KS SS400 1.3 1.2
KS SM490, SM490TMC, SM520,
SM520TMC, SM570, SM570TMC, 1.2 1.2
Plate KS SMA400, SMA490, SMA570
KS SN400, SN490 1.1 1.1
HSA800 1.1 1.1

2.3 Structural Analysis and Design Program


Software Program Code & Reference Remarks
3D Static & Dynamic Analysis -
SAP 2000
Member Design

SAFE For design the foundations -

Revisión F 203
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-005

3. DESIGN LOADS
3.1 Dead Load (D)
Dead load is the load due to the permanent weight of all structural and nonstructural components of a
construction, including thermal insulation, ladders and others.

Item Density or Load Remark


7,850 kg/m3
Steel SS 400, SM 490
(=76.98 kN/m3)
50 kg/m2
Grating ARRIGONI ARS-5 33 kg/m2.
(=0.49 kN/m2)
100 kg/m3
Insulation -
(=0.98 kN/m3)

3.2 Live Load (L , L_ and Lr)


It shall be included in this load category, the content of tanks, silos, hoppers, ducting, mobile and
transient loads and weight of people, equipment and tools, and other material agglomerations.
Live load is calculated according to Technical Specification.

Item Load Remark


400kg/m2
Offices, Hallways, Stairs (L) -
(= 3.92 kN/m2)
Roof not exposed to traffic 100 kg/m2
-
(Lr) (= 0.98 kN/m2)
Density : 0.9 tonf/m3 (for volume)
1.2 tonf/m3 (for structural design) It should not be
Lime Total Volume (Design Condition) : Later considered the 0.5
(L_, Lime Storage Silo) Total Weight (Design Condition) : Later factor in load
Total Volume (Emergency Condition) : Later combination.
Total Weight (Emergency Condition) : Later
Density : 0.8 tonf/m3 (for volume)
1.25 tonf/m3 (for structural design) It should not be
Ash with Lime
Total Volume (Design Condition) : Later considered the 0.5
(L_, Recycle Ash Storage
Total Weight (Design Condition) : Later factor in load
Silo)
Total Volume (Emergency Condition) : Later combination.
Total Weight (Emergency Condition) : Later

Revisión F 204
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-005

The material Properties of Lime and Ash with Lime (according to the EN 1991-4 Eurocode 1 – Actions
on Structures – Part4: Silo and Tanks)

3.3 Thermal Load (T)

3.3.1 External Temperature


Effect of temperature on the structure, due to climatic conditions of the area
Metal structures for temperature variation depends on local conditions, but it will not be less than
±25℃.

3.3.2 Strain due to the Temperature

Where,
α = 1.2×10-5 /℃, coefficient of thermal expansion
∆T = ±25℃

Revisión F 205
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-005

3.4 Wind Load (WX, WY)

Wind load is calculated based on NCh 432 Table 1.

Structures located in open country, facing the ocean, or locations under similar conditions, in the
judgment of the Reviewing Authority

Height above the NCh 432 Chapter 6.5


Basic pressure, q Basic pressure, q
ground ×1.2
[kg/m2] [kPa]
[m] [kPa]
0 70 0.69 0.82
4 70 0.69 0.82
7 95 0.93 1.12
10 106 1.04 1.25
15 118 1.16 1.39
20 126 1.24 1.48
30 137 1.34 1.61
40 145 1.42 1.71
50 151 1.48 1.78
75 163 1.60 1.92
100 170 1.67 2.00
150 182 1.78 2.14
200 191 1.87 2.25
300 209 2.05 2.46

Revisión F 206
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-005

3.5 Earthquake Load (EX, EY, EZ)

3.5.1 Earthquake Load


The total base shear shall be computed from the expression.
V = C X W ≥ 0.12 W
Where,
V Base shear
C Seismic coefficient, obtained directly from the design spectrum.
W Total seismic weight of the structure or system, computed as the sum of dead load of
structure and equipment

3.5.1.1 Earthquake action for horizontal direction


The design spectrum is calculated based on ETG1015 figure 1.
Applied coefficients are as follows:
Ground Acceleration a/g = 0.4
Response Modification Factors: R = 3.0
Equivalent viscous damping: ζ = 0.02

3.5.1.2 Earthquake action for vertical direction


The vertical earthquake shall be considered according to Section 5.5 of NCh 2369 Standard, with
seismic coefficient equal to 2 A0 / 3g.

Revisión F 207
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-005

Coordinates of the corner point for a/g = 0.4

ζ T1 T2 A/g
0.005 0.113 0.451 1.472
0.01 0.115 0.461 1.284
0.02 0.119 0.474 1.096
0.03 0.121 0.485 0.984
0.05 0.125 0.499 0.848
0.07 0.128 0.512 0.756
0.10 0.134 0.535 0.656
0.20 0.148 0.591 0.468
Equation of hyperbolic branch:

(T2<=T<=2.5 s)

3.5.2 Methods of Analysis


In order to compute the forces and displacements in a given structural system when subjected to the
earthquake action, a response spectrum analysis shell be performed.

Revisión F 208
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-005

3.5.3 Number of Modes


The analysis shall include a sufficient number of vibration modes for the sum of equivalent masses in
each analysis direction is equal to or higher than 90% of the total mass.

3.5.4 Mode Superposition


In order to obtain an estimate of the maximum values of any response quantity considered in the
analysis, the maximum values of the corresponding responses computed for the individual mode of
vibration shall be combined with the CQC superposition criterion normally called “Complete Quadratic
Combination”, recommended in Chilean code Section 5.4.4 of NCh 2369.
The following expressions summarize the mode superposition procedure:

Where,
S Modal combination
Si , Sj Maximum values of mode contributions i and j
ζ Damping ratio
Ti, Tj Period of mode i and j

3.5.5 Coupling of earthquake action for Support Structure


For the case of dynamic analysis, the requirements of Section 5.1.2 of Chilean code NCh 2369
regarding the effect of the combination of the seismic horizontal components effect are applicable.
This requires that the modal shape and frequencies have to be analyzed and if they are found to be
coupled without a clear or predominant directional acceleration input shall be performed instead of
two independent analyses. This can be implemented by carrying out two different three dimensional
analyses; in each of them the earthquake action input (acceleration spectrum ordinates) shall be
100% of the Project Specification design spectrum in on direction plus 30% of the Project
Specification design spectrum in the orthogonal direction.

Point 5.1.2 of NCh-2369 clearly indicates that it is not necessary to combine the horizontal
components of the seismic action, ie can be analyzed separately for earthquake acting in both
directions considered analysis and design with the unfavorable situation.

Exceptions to this rule structures that have significant torsional irregularities, for which it requires rigid
diaphragms own buildings. The situation is important to consider in the corner columns orthogonal
building rigid frames that share these corner columns. In cases like this should be at 100% overlap in

Revisión F 209
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-005

a direction analysis 30% of the analyzes in the other direction and the same for the other direction
relative to the first. This exception should be applied to irregular structured buildings preferably those
based on rigid frames.

3.5.6 Seismic Mass Percentage for Live Load


Seismic mass percentages are considered according to Technical Specification.
It shall be considered the following percentage of seismic mass for live load:

Section Seismic Mass Percentage (%)

Area of Normal Use, Floor Live Load 25

Roof without Transit 0

Silos 100

Revisión F 210
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-005

3.6 Load Combination

3.6.1 Basic Load Case


D Dead Load
T1 Thermal Load (∆T = +25℃, in case of steel exposed to ambient)
T2 Thermal Load (∆T = -25℃, in case of steel exposed to ambient)
L Live Load
L_1 Lime Load and Ash with Lime Load
Lr Roof live load not exposed to traffic
WX Wind Load X direction
WY Wind Load Y direction
EX Earthquake Load X direction
EY Earthquake Load Y direction
EZ Earthquake Load Vertical direction
L_EM Emergency Load

3.6.2 LRFD Load Combination (for Anchor System and Foundations)


The LRFD load combinations shall take into account the earthquake load in Technical Specification.
Technical Specification considered a nominal load, so it must be amplified by a factor 1.4. as shown in
the following table

No. Case Name Description


1 uLCB1 1.4(D + T1)
2 uLCB2 1.2(D + T1) + 1.6L + 1.6L_+ 0.5Lr
3  uLCB3 1.2(D + T1) + 0.5L + 1.6Lr + L_
4  uLCB4 1.2(D + T1) + 1.6Lr + 0.8WX
5  uLCB5 1.2(D + T1) + 1.6Lr - 0.8WX
6  uLCB6 1.2(D + T1) + 1.6Lr + 0.8WY
7  uLCB7 1.2(D + T1) + 1.6Lr - 0.8WY
8  uLCB8 1.2(D + T1) + 1.6WX + 0.5L + 1.0L_ + 0.5Lr
9  uLCB9 1.2(D + T1) - 1.6WX + 0.5L + 1.0L_ + 0.5Lr
10  uLCB10 1.2(D + T1) + 1.6WY + 0.5L + 1.0L_ + 0.5Lr
11  uLCB11 1.2(D + T1) - 1.6WY + 0.5L + 1.0L_ + 0.5Lr
12  uLCB12 1.2(D + T1) + 1.4(1.0EX + 1.0EZ) + 0.5L + 1.0L_

Revisión F 211
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-005

13  uLCB13 1.2(D + T1) + 1.4(1.0EX - 1.0EZ) + 0.5L + 1.0L_


14  uLCB14 1.2(D + T1) + 1.4(-1.0EX + 1.0EZ) + 0.5L + 1.0L_
15  uLCB15 1.2(D + T1) + 1.4(-1.0EX - 1.0EZ) + 0.5L + 1.0L_
16  uLCB16 1.2(D + T1) + 1.4(1.0EY + 1.0EZ) + 0.5L + 1.0L_
17  uLCB17 1.2(D + T1) + 1.4(1.0EY - 1.0EZ) + 0.5L + 1.0L_
18  uLCB18 1.2(D + T1) + 1.4(-1.0EY + 1.0EZ) + 0.5L + 1.0L_
19  uLCB19 1.2(D + T1) + 1.4(-1.0EY - 1.0EZ) + 0.5L + 1.0L_
20  uLCB20 0.9(D + T1) + 1.6WX
21  uLCB21 0.9(D + T1) - 1.6WX
22  uLCB22 0.9(D + T1) + 1.6WY
23  uLCB23 0.9(D + T1) - 1.6WY
24  uLCB24 0.9(D + T1) + 1.4(1.0EX + 1.0EZ)
25  uLCB25 0.9(D + T1) + 1.4(1.0EX - 1.0EZ)
26  uLCB26 0.9(D + T1) + 1.4(-1.0EX + 1.0EZ)
27  uLCB27 0.9(D + T1) + 1.4(-1.0EX - 1.0EZ)
28  uLCB28 0.9(D + T1) + 1.4(1.0EY + 1.0EZ)
29  uLCB29 0.9(D + T1) + 1.4(1.0EY - 1.0EZ)
30  uLCB30 0.9(D + T1) + 1.4(-1.0EY + 1.0EZ)
31  uLCB31 0.9(D + T1) + 1.4(-1.0EY - 1.0EZ)
32  uLCB32 1.2(D + T1) + 1.6L + 1.6(L_EM) + 0.5Lr
33  uLCB33 1.2(D + T1) + 1.0(L_EM) + 1.6Lr + 0.5L
34  uLCB34 1.4(D + T2)
35  uLCB35 1.2(D + T2) + 1.6L + 1.6L_+ 0.5Lr
36  uLCB36 1.2(D + T2) + 0.5L + 1.6Lr + L_
37  uLCB37 1.2(D + T2) + 1.6Lr + 0.8WX
38  uLCB38 1.2(D + T2) + 1.6Lr - 0.8WX
39  uLCB39 1.2(D + T2) + 1.6Lr + 0.8WY
40  uLCB40 1.2(D + T2) + 1.6Lr - 0.8WY
41  uLCB41 1.2(D + T2) + 1.6WX + 0.5L + 1.0L_ + 0.5Lr
42  uLCB42 1.2(D + T2) - 1.6WX + 0.5L + 1.0L_ + 0.5Lr
43  uLCB43 1.2(D + T2) + 1.6WY + 0.5L + 1.0L_ + 0.5Lr

Revisión F 212
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-005

44  uLCB44 1.2(D + T2) - 1.6WY + 0.5L + 1.0L_ + 0.5Lr


45  uLCB45 1.2(D + T2) + 1.4(1.0EX + 1.0EZ) + 0.5L + 1.0L_
46  uLCB46 1.2(D + T2) + 1.4(1.0EX - 1.0EZ) + 0.5L + 1.0L_
47  uLCB47 1.2(D + T2) + 1.4(-1.0EX + 1.0EZ) + 0.5L + 1.0L_
48  uLCB48 1.2(D + T2) + 1.4(-1.0EX - 1.0EZ) + 0.5L + 1.0L_
49  uLCB49 1.2(D + T2) + 1.4(1.0EY + 1.0EZ) + 0.5L + 1.0L_
50  uLCB50 1.2(D + T2) + 1.4(1.0EY - 1.0EZ) + 0.5L + 1.0L_
51  uLCB51 1.2(D + T2) + 1.4(-1.0EY + 1.0EZ) + 0.5L + 1.0L_
52  uLCB52 1.2(D + T2) + 1.4(-1.0EY - 1.0EZ) + 0.5L + 1.0L_
53  uLCB53 0.9(D + T2) + 1.6WX
54  uLCB54 0.9(D + T2) - 1.6WX
55  uLCB55 0.9(D + T2) + 1.6WY
56  uLCB56 0.9(D + T2) - 1.6WY
57  uLCB57 0.9(D + T2) + 1.4(1.0EX + 1.0EZ)
58  uLCB58 0.9(D + T2) + 1.4(1.0EX - 1.0EZ)
59  uLCB59 0.9(D + T2) + 1.4(-1.0EX + 1.0EZ)
60  uLCB60 0.9(D + T2) + 1.4(-1.0EX - 1.0EZ)
61  uLCB61 0.9(D + T2) + 1.4(1.0EY + 1.0EZ)
62  uLCB62 0.9(D + T2) + 1.4(1.0EY - 1.0EZ)
63  uLCB63 0.9(D + T2) + 1.4(-1.0EY + 1.0EZ)
64  uLCB64 0.9(D + T2) + 1.4(-1.0EY - 1.0EZ)
65  uLCB65 1.2(D + T2) + 1.6L + 1.6(L_EM) + 0.5Lr
66  uLCB66 1.2(D + T2) + 1.0(L_EM) + 1.6Lr + 0.5L
67  uLCB67 1.4D
68  uLCB68 1.2D + 1.6L + 1.6L_+ 0.5Lr
69  uLCB69 1.2D + 0.5L + 1.6Lr + L_
70  uLCB70 1.2D + 1.6Lr + 0.8WX
71  uLCB71 1.2D + 1.6Lr - 0.8WX
72  uLCB72 1.2D + 1.6Lr + 0.8WY
73  uLCB73 1.2D + 1.6Lr - 0.8WY
74  uLCB74 1.2D + 1.6WX + 0.5L + 1.0L_ + 0.5Lr

Revisión F 213
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-005

75  uLCB75 1.2D - 1.6WX + 0.5L + 1.0L_ + 0.5Lr


76  uLCB76 1.2D + 1.6WY + 0.5L + 1.0L_ + 0.5Lr
77  uLCB77 1.2D - 1.6WY + 0.5L + 1.0L_ + 0.5Lr
78  uLCB78 1.2D + 1.4(1.0EX + 1.0EZ) + 0.5L + 1.0L_
79  uLCB79 1.2D + 1.4(1.0EX - 1.0EZ) + 0.5L + 1.0L_
80  uLCB80 1.2D + 1.4(-1.0EX + 1.0EZ) + 0.5L + 1.0L_
81  uLCB81 1.2D + 1.4(-1.0EX - 1.0EZ) + 0.5L + 1.0L_
82  uLCB82 1.2D + 1.4(1.0EY + 1.0EZ) + 0.5L + 1.0L_
83  uLCB83 1.2D + 1.4(1.0EY - 1.0EZ) + 0.5L + 1.0L_
84  uLCB84 1.2D + 1.4(-1.0EY + 1.0EZ) + 0.5L + 1.0L_
85  uLCB85 1.2D + 1.4(-1.0EY - 1.0EZ) + 0.5L + 1.0L_
86  uLCB86 0.9D + 1.6WX
87  uLCB87 0.9D - 1.6WX
88  uLCB88 0.9D + 1.6WY
89  uLCB89 0.9D - 1.6WY
90  uLCB90 0.9D + 1.4(1.0EX + 1.0EZ)
91  uLCB91 0.9D + 1.4(1.0EX - 1.0EZ)
92  uLCB92 0.9D + 1.4(-1.0EX + 1.0EZ)
93  uLCB93 0.9D + 1.4(-1.0EX - 1.0EZ)
94  uLCB94 0.9D + 1.4(1.0EY + 1.0EZ)
95  uLCB95 0.9D + 1.4(1.0EY - 1.0EZ)
96  uLCB96 0.9D + 1.4(-1.0EY + 1.0EZ)
97  uLCB97 0.9D + 1.4(-1.0EY - 1.0EZ)
98  uLCB98 1.2D + 1.6L + 1.6(L_EM) + 0.5Lr
99  uLCB99 1.2D + 1.0(L_EM) + 1.6Lr + 0.5L

Revisión F 214
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-005

3.6.3 ASD Load Combination (for SILO Casing and Platforms Structures)
The ASD load combinations shall take into account the earthquake load in Technical Specification.
Technical Specification considered a nominal load, so it must be amplified by a factor 1.0.

No. Case Name Description


1 sLCB1 (D + T1)
2  sLCB2 (D + T1) + L + L_
3  sLCB3 (D + T1) + Lr
4  sLCB4 (D + T1) + 0.75L + 0.75L_ + 0.75Lr
5  sLCB5 (D + T1) + WX
6  sLCB6 (D + T1) - WX
7  sLCB7 (D + T1) + WY
8  sLCB8 (D + T1) - WY
9  sLCB9 (D + T1) + EX + EZ
10  sLCB10 (D + T1) + EX - EZ
11  sLCB11 (D + T1) - EX + EZ
12  sLCB12 (D + T1) - EX - EZ
13  sLCB13 (D + T1) + EY + EZ
14  sLCB14 (D + T1) + EY - EZ
15  sLCB15 (D + T1) - EY+ EZ
16  sLCB16 (D + T1) - EY - EZ
17  sLCB17 (D + T1) + 0.75WX + 0.75L + 0.75L_ + 0.75Lr
18  sLCB18 (D + T1) - 0.75WX + 0.75L + 0.75L_ + 0.75Lr
19  sLCB19 (D + T1) + 0.75WY + 0.75L + 0.75L_ + 0.75Lr
20  sLCB20 (D + T1) - 0.75WY + 0.75L + 0.75L_ + 0.75Lr
21  sLCB21 (D + T1) + 0.75(EX + EZ) + 0.75L + 0.75L_
22  sLCB22 (D + T1) + 0.75(EX - EZ) + 0.75L + 0.75L_
23  sLCB23 (D + T1) + 0.75(-EX + EZ) + 0.75L + 0.75L_
24  sLCB24 (D + T1) + 0.75(-EX - EZ) + 0.75L + 0.75L_
25  sLCB25 (D + T1) + 0.75(EY + EZ) + 0.75L + 0.75L_
26  sLCB26 (D + T1) + 0.75(EY - EZ) + 0.75L + 0.75L_
27  sLCB27 (D + T1) + 0.75(-EY + EZ) + 0.75L + 0.75L_

Revisión F 215
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-005

28  sLCB28 (D + T1) + 0.75(-EY - EZ) + 0.75L + 0.75L_


29  sLCB29 0.6(D + T1) + WX
30  sLCB30 0.6(D + T1) - WX
31  sLCB31 0.6(D + T1) + WY
32  sLCB32 0.6(D + T1) - WY
33  sLCB33 0.6(D + T1) + EX + EZ
34  sLCB34 0.6(D + T1) + EX - EZ
35  sLCB35 0.6(D + T1) - EX + EZ
36  sLCB36 0.6(D + T1) - EX - EZ
37  sLCB37 0.6(D + T1) + EY + EZ
38  sLCB38 0.6(D + T1) + EY - EZ
39  sLCB39 0.6(D + T1) - EY + EZ
40  sLCB40 0.6(D + T1) - EY - EZ
41  sLCB41 (D + T1) + L + L_EM
42  sLCB42 (D + T1) + 0.75L + 0.75L_EM + 0.75Lr
43  sLCB43 (D + T2)
44  sLCB44 (D + T2) + L + L_
45  sLCB45 (D + T2) + Lr
46  sLCB46 (D + T2) + 0.75L + 0.75L_ + 0.75Lr
47  sLCB47 (D + T2) + WX
48  sLCB48 (D + T2) - WX
49  sLCB49 (D + T2) + WY
50  sLCB50 (D + T2) - WY
51  sLCB51 (D + T2) + EX + EZ
52  sLCB52 (D + T2) + EX - EZ
53  sLCB53 (D + T2) - EX + EZ
54  sLCB54 (D + T2) - EX - EZ
55  sLCB55 (D + T2) + EY + EZ
56  sLCB56 (D + T2) + EY - EZ
57  sLCB57 (D + T2) - EY + EZ
58  sLCB58 (D + T2) - EY - EZ

Revisión F 216
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-005

59  sLCB59 (D + T2) + 0.75WX + 0.75L + 0.75L_ + 0.75Lr


60  sLCB60 (D + T2) - 0.75WX + 0.75L + 0.75L_ + 0.75Lr
61  sLCB61 (D + T2) + 0.75WY + 0.75L + 0.75L_ + 0.75Lr
62  sLCB62 (D + T2) - 0.75WY + 0.75L + 0.75L_ + 0.75Lr
63  sLCB63 (D + T2) + 0.75(EX + EZ) + 0.75L + 0.75L_
64  sLCB64 (D + T2) + 0.75(EX - EZ) + 0.75L + 0.75L_
65  sLCB65 (D + T2) + 0.75(-EX + EZ) + 0.75L + 0.75L_
66  sLCB66 (D + T2) + 0.75(-EX - EZ) + 0.75L + 0.75L_
67  sLCB67 (D + T2) + 0.75(EY + EZ) + 0.75L + 0.75L_
68  sLCB68 (D + T2) + 0.75(EY - EZ) + 0.75L + 0.75L_
69  sLCB69 (D + T2) + 0.75(-EY + EZ) + 0.75L + 0.75L_
70  sLCB70 (D + T2) + 0.75(-EY - EZ) + 0.75L + 0.75L_
71  sLCB71 0.6(D + T2) + WX
72  sLCB72 0.6(D + T2) - WX
73  sLCB73 0.6(D + T2) + WY
74  sLCB74 0.6(D + T2) - WY
75  sLCB75 0.6(D + T2) + EX + EZ
76  sLCB76 0.6(D + T2) + EX - EZ
77  sLCB77 0.6(D + T2) - EX + EZ
78  sLCB78 0.6(D + T2) - EX - EZ
79  sLCB79 0.6(D + T2) + EY + EZ
80  sLCB80 0.6(D + T2) + EY - EZ
81  sLCB81 0.6(D + T2) - EY + EZ
82  sLCB82 0.6(D + T2) - EY - EZ
83  sLCB83 (D + T2) + L + L_EM
84  sLCB84 (D + T2) + 0.75L + 0.75L_EM + 0.75Lr
85  sLCB85 D
86  sLCB86 D + L + L_
87  sLCB87 D + Lr
88  sLCB88 D + 0.75L + 0.75L_ + 0.75Lr
89  sLCB89 D + WX

Revisión F 217
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-005

90  sLCB90 D - WX
91  sLCB91 D + WY
92  sLCB92 D - WY
93  sLCB93 D + EX + EZ
94  sLCB94 D + EX - EZ
95  sLCB95 D - EX + EZ
96  sLCB96 D - EX - EZ
97  sLCB97 D + EY + EZ
98  sLCB98 D + EY - EZ
99  sLCB99 D – EY + EZ
100  sLCB100 D - EY - EZ
101  sLCB101 D + 0.75WX + 0.75L + 0.75L_ + 0.75Lr
102  sLCB102 D - 0.75WX + 0.75L + 0.75L_ + 0.75Lr
103  sLCB103 D + 0.75WY + 0.75L + 0.75L_ + 0.75Lr
104  sLCB104 D - 0.75WY + 0.75L + 0.75L_ + 0.75Lr
105  sLCB105 D + 0.75(EX + EZ) + 0.75L + 0.75L_
106  sLCB106 D + 0.75(EX - EZ) + 0.75L + 0.75L_
107  sLCB107 D + 0.75(-EX + EZ) + 0.75L + 0.75L_
108  sLCB108 D + 0.75(-EX - EZ) + 0.75L + 0.75L_
109  sLCB109 D + 0.75(EY + EZ) + 0.75L + 0.75L_
110  sLCB110 D + 0.75(EY - EZ) + 0.75L + 0.75L_
111  sLCB111 D + 0.75(-EY + EZ) + 0.75L + 0.75L_
112  sLCB112 D + 0.75(-EY - EZ) + 0.75L + 0.75L_
113  sLCB113 0.6D + WX
114  sLCB114 0.6D - WX
115  sLCB115 0.6D + WY
116  sLCB116 0.6D - WY
117  sLCB117 0.6D + EX + EZ
118  sLCB118 0.6D + EX - EZ
119  sLCB119 0.6D - EX + EZ
120  sLCB120 0.6D - EX - EZ

Revisión F 218
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-005

121  sLCB121 0.6D + EY + EZ


122  sLCB122 0.6D + EY - EZ
123  sLCB123 0.6D – EY + EZ
124  sLCB124 0.6D - EY - EZ
125  sLCB125 D + L + L_EM
126  sLCB126 D + 0.75L + 0.75L_EM + 0.75Lr

Revisión F 219
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-005

4 STRUCTURAL SYSTEM

4.1 Structural System and Analysis Condition


The seismic force-resisting system is Concentrically Braced Frame (CBF). A braced frame is
subjected primarily to axial forces.
Structural analysis program use SAP 2000. It’s performed to analyze three dimension structural
systems for checking serviceability of this structure on lateral load, designing column, beam and
brace.
4.1.1 Boundary Conditions
The boundary condition of column at ground level will be defined as a pinned connection in all the
Concetrical Braced Frames Structures.

If Necessary to define a Moment Frame Structure to Comply the Process Requirements, the boundary
condition of column at ground level will be defines as a semi-rigid moment connection in both
horizontal translational degrees of freedoms.

The semi – rigid condition is defined as a rotational spring with an associated rotational stiffness
according to the base plate and anchor bolts configuration, in order to determine this value it will be
necessary to build a detailed model of the column base and the anchor configuration.

4.1.2 Connection Condition between Silo Casing and Structure

The connection between Silo and it Support Structure will be a sliding support with the gap length
defined according to the Thermal Loads displacements.

After that, the gap length will be checked for the earthquake loads displacements, if these
displacements are larger than the gap length the entire seismic load of the Casing will be transferred
to the support structure so the structure must be design as if the connection with de Silo were a fixed
(Non Sliding) connection.

4.1.3 Structural Element


- One dimensional element for steel structure modeling purposes as follows:
Korea Standard Section
Material = Steel KS D 3503 : SS400, Steel KS D 3515 : SM490

Revisión F 220
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-005

- Shell element for SILO casing modeling purposes as follows:


Material = Steel KS D 3503 : SS400 (See section 2.2)

Revisión F 221
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-005

Revisión F 222
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-005

4.2 Base Plate and Anchor System

Column reaction resulting from the structural analysis shall be used for the design of base plates and
anchor bolts. Column base plate and anchor bolts shall be designed as per ACI 318-08 and AISC
360-05.
Base plate is made to transfer the column loads and moments to the footings and foundations. Anchor
rods are designed to provide the required resistance to loads which result from load combination
stipulated in Section 3.7.
The requirement that anchor bolts of columns shall have a projection of at least eight diameters and
no less than 250 mm measured from the base plates (according to Section 8.6.2 of NCh 2369),
provides adequate anchor bolts length to eventually allow for yielding of the anchor bolt under severe
earthquake loading.

Typical Detail of Column Base in Figure A.1 of NCh 2369 of 2003

Revisión F 223
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-005

5. STRUCTURAL ANALYSIS
5.1 Base Shear and Equivalent Mass
These results are calculated by the analysis model for earthquake load.
If the base shear force is lower than the minimum base shear (0.12 X total weight), the scale-up factor
(12% of total weight / base shear) should be applied for earthquake load according to the Section
5.4.5 of NCh 2369 of 2003.

5.1.1 Mass Distribution


The self-weight is converted into masses automatically in SAP2000 program.
Seismic mass percentages are considered according to Technical Specification.
It shall be considered the following percentage of seismic mass for live load:

Section Seismic Mass Percentage (%)

Area of Normal Use, Floor Live Load 25

Roof without Transit 0

Silos 100

5.2 Natural Vibration Mode


These results are calculated by the analysis model. The analysis shall include a sufficient number of
vibration modes for the sum of equivalent masses in each analysis direction is equal to or higher than
90% of the total mass.

5.3 Support Reaction


These results are calculated by the analysis model in three directions.

Since the earthquake load was computed trough a Response Spectrum Analysis, its reactions are
absolute values. In order to design the foundations of this structure it is necessary to assign the sign
for each reaction according to the predominant modal shapes in the respective direction.

Revisión F 224
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-005

5.4 Displacement

5.4.1 Displacement due to the Earthquake Load

The displacement for earthquake load can verified according to the Section 6.1 and 6.3.
d = d0 + R1dd
Where,
d = Seismic Deformation
dd = Deformation due to non-seismic service loads
R1 = Factor resulting from multiplying the R factor derived from Table 5.6 of NCh 2369 of 2003 by the
quotient Q0/Qmin provided that Q0/Qmin ne lower or equal to 1.0. However, for the quotient
Q0/Qmin a value under 0.5 shall not be used. If this quotient is higher than 1.0, R1 =R shall be
used.

The maximum seismic deformation for other structures is below:


dmax = 0.015 h
Where,
h = Height between floors of between two points located on the same vertical.

5.4.2 Separation between Structures

The separation between structures is calculated based on section 6.2 of NCh 2369. The purpose of
preventing impacts between adjoining structures, their separation shall be bigger than the highest of
the following values:

1) S = ((R1i ddi)2 + (R1j ddj)2)1/2 + d0i + d0j


2) S = 0.002 (hi + hj)
3) 30mm

Where, ddi, ddj : Deformation calculated with R-factor reduced earthquake load of the structures i and j
d0i, d0j : Deformation due to non-seismic service loads
R1i ,R1j : Response modification factors R1 used for the design of the structures i and j
hi, hj : Height at the considered level of the structures I and j measured from their respective
base levels

Revisión F 225
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-005

6. MEMBER DESIGN
The design of steel structures shall comply with “Earthquake-Resistant Design of Industrial Structures
and Facilities NCh 2369” and “Specification for Structural Steel Buildings AISC 360-05”.
The maximum slenderness can be considered in the design:

Element kl / r

Columns 1.5π√(E/Fy)
Other Elements in Compression 1.5π√(E/Fy)
Element in Traction 240
Bracing Resisting Seismic Load 1.5π√(E/Fy)

Member design was checked about all members of column, beam and brace and so on. On this
report, attached calculation note is about what the worst case of the load combination cases each
member.

Revisión F 226
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-005

6.1 Column Design

6.1.1 Design Load


Load from LRFD Combination
- Pr : Maximum Axial Force
- Mr : Maximum Bending Moment
- Vr : Maximum Shear Force

6.1.2 Schematic Drawing

6.1.3 Verification (AISC360-05, NCh 2369)


1) Slenderness Ratio
- KL / r < 1.5π√(E/Fy)......(OK)
2) Seismic Width-Thickness
- λf = bf / 2tf < λps (for flange)......(OK)
- λw = h / tw < λps (for web)......(OK)
3) Axial Strength
- Pr / Pc < 1.0......(OK)
4) Bending Strength
- Mrx / Mcx < 1.0......(OK)
- Mry / Mcy < 1.0......(OK)
5) Combined Strength (Compression + Bending)
- For Pr / Pc ≥ 0.2 => Rmax = Pr / Pc + 8/9 X (Mrx / Mcx + Mry / Mcy) < 1.0......(OK)
- For Pr / Pc < 0.2 => Rmax = Pr / 2Pc + (Mrx / Mcx + Mry / Mcy) < 1.0......(OK)
6) Shear Strength
- Vrx / Vcx < 1.0......(OK)
- Vry / Vcy < 1.0......(OK)

Revisión F 227
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-005

Where,
λps : Limiting Width-Thickness Ratio
Pc : Design Compressive Strength
Mc : Design Flexural Strength
Vc : Design Shear Strength

Revisión F 228
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-005

6.2 Beam and Girder Design

6.2.1 Design Load


Load from LRFD Combination
- Pr : Maximum Axial Force
- Mr : Maximum Bending Moment
- Vr : Maximum Shear Force

6.2.2 Schematic Drawing

6.2.3 Verification (AISC360-05, NCh 2369)


1) Slenderness Ratio
- KL / r < 1.5π√(E/Fy)......(OK)
2) Seismic Width-Thickness
- λf = bf / 2tf < λps (for flange)......(OK)
- λw = h / tw < λps (for web)......(OK)
3) Axial Strength
- Pr / Pc < 1.0......(OK)
4) Bending Strength
- Mrx / Mcx < 1.0......(OK)
- Mry / Mcy < 1.0......(OK)
5) Combined Strength (Compression + Bending)
- For Pr / Pc ≥ 0.2 => Rmax = Pr / Pc + 8/9 X (Mrx / Mcx + Mry / Mcy) < 1.0......(OK)
- For Pr / Pc < 0.2 => Rmax = Pr / 2Pc + (Mrx / Mcx + Mry / Mcy) < 1.0......(OK)
6) Shear Strength
- Vrx / Vcx < 1.0......(OK)
- Vry / Vcy < 1.0......(OK)

Revisión F 229
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-005

Where,
λps : Limiting Width-Thickness Ratio
Pc : Design Compressive Strength
Mc : Design Flexural Strength
Vc : Design Shear Strength

Revisión F 230
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-005

6.3 Brace Design

6.3.1 Design Load


Load from LRFD Combination
- Pr : Maximum Axial Force
- Mr : Maximum Bending Moment
- Vr : Maximum Shear Force

6.3.2 Schematic Drawing

6.3.3 Verification (AISC360-05, NCh 2369)


1) Slenderness Ratio
- KL / r < 1.5π√(E/Fy)......(OK)
2) Seismic Width-Thickness
- λf = bf / 2tf < λps (for flange)......(OK)
- λw = h / tw < λps (for web)......(OK)
3) Axial Strength
- Pr / Pc < 0.8......(OK)
4) Bending Strength
- Mrx / Mcx < 0.8......(OK)
- Mry / Mcy < 0.8......(OK)
5) Combined Strength (Compression + Bending)
- For Pr / Pc ≥ 0.2 => Rmax = Pr / Pc + 8/9 X (Mrx / Mcx + Mry / Mcy) < 0.8......(OK)
- For Pr / Pc < 0.2 => Rmax = Pr / 2Pc + (Mrx / Mcx + Mry / Mcy) < 0.8......(OK)
6) Shear Strength
- Vrx / Vcx < 0.8......(OK)
- Vry / Vcy < 0.8......(OK)

Revisión F 231
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-005

Where,
λps : Limiting Width-Thickness Ratio
Pc : Design Compressive Strength
Mc : Design Flexural Strength
Vc : Design Shear Strength

Revisión F 232
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-005

6.4 Connection Design

6.4.1 Column Splice

6.4.1.1 Design Load


Full Capacity of Column
- Pu : Maximum Axial Force (= Φ Fy Ag)
- Mu : Maximum Bending Moment (= Φ Fy Zx)
- Vu : Maximum Shear Force (= 0.6 Φ Fy Aw)
- Tu : Maximum Tensile Force at Flange (=Mu / Arm of Column)

6.4.1.2 Schematic Drawing

6.4.1.3 Verification (AISC360-05)


1) Bolt Strength
- Shear Strength ΦRn1 = Φ Ns Fn Ab
- Bearing Strength at Bolt Holes ΦRn2 = Min (Φ 1.2 Lc t Fu, Φ 2.4 d t Fu)
- Slip-Critical Connections ΦRn3 = Φ μ Du hsc Tb Ns
- ΦRn = Min (ΦRn1, ΦRn2, ΦRn3)
- Pu / ΦRn < Number of Bolt......(OK)
- Vu / ΦRn < Number of Bolt......(OK)
- Tu / ΦRn < Number of Bolt......(OK)
2) Web Splice Plate Verification
- Shear Yielding Φ 0.6 Fy Ag ≥ Vu......(OK)

Revisión F 233
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-005

- Shear Rupture Φ 0.6 Fu Anv ≥ Vu......(OK)


3) Flange Splice Plate Verification
- Tensile Yielding Φ Fy Ag ≥ Tu......(OK)
- Tensile Rupture Φ Fu Ae ≥ Tu......(OK)

Revisión F 234
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-005

6.4.2 Beam Connection

6.4.2.1 Design Load


1) Special Earthquake Load Combination
- Ru1 is determined due to the 1.2D + 0.5L + ΩE
2) 0.5 X Full Capacity for Shear
- Ru2 = 0.5 Φ 0.6 Fy Aw Cv
3) Ru = Max (Ru1, Ru2)
4) If the load from brace are transferred to the girder and beam directly, the connection would be
designed by full capacity of brace.

6.4.2.2 Schematic Drawing

6.4.2.3 Verification (AISC360-05)


1) Bolt Strength
- Shear Strength ΦRn1 = Φ Ns Fn Ab
- Bearing Strength at Bolt Holes ΦRn2 = Min (Φ 1.2 Lc t Fu, Φ 2.4 d t Fu)
- Slip-Critical Connections ΦRn3 = Φ μ Du hsc Tb Ns
- ΦRn = Min (ΦRn1, ΦRn2, ΦRn3)
- Ru / ΦRn < Number of Bolt......(OK)
2) Web Splice Plate Verification
- Shear Yielding Φ 0.6 Fy Ag ≥ Ru......(OK)
- Shear Rupture Φ 0.6 Fu Anv ≥ Ru......(OK)
3) Block Shear Rupture Verification
- Φ (0.6 Fu Anv + Ubs Fu Ant) ≥ Ru......(OK)
- Φ (0.6 Fy Agv + Ubs Fu Ant) ≥ Ru......(OK)

Revisión F 235
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-005

6.4.3 Brace to Gusset Connection

6.4.3.1 Design Load


Full Capacity of Brace
- Tu : Maximum Tensile Force (= Ry Fy Ag)
- Pu : Maximum Compressive Force (= 1.1 Ry Pn)
- Ruw : Force in Web
- Ruf : Force in Flange

6.4.3.2 Schematic Drawing


In case of H-Shape Brace In case of Channel Brace

6.4.3.3 Verification in case of H-Shape Brace (AISC360-05)


1) Bolt Strength
- Shear Strength ΦRn1 = Φ Ns Fn Ab
- Bearing Strength at Bolt Holes ΦRn2 = Min(Φ 1.2 Lc t Fu, Φ 2.4 d t Fu)
- Slip-Critical Connections ΦRn3 = Φ μ Du hsc Tb Ns
- ΦRn = Min(ΦRn1, ΦRn2, ΦRn3)
- Ruf / ΦRn < Number of Bolt......(OK)
- Ruw / ΦRn < Number of Bolt......(OK)

Revisión F 236
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-005

2) Tension Capacity of the Angles


- Tension Yielding Φ Fy Ag ≥ Ruf / 2......(OK)
Φ Fy Ag ≥ Ruw......(OK)
- Tension Rupture Φ Fu Ae ≥ Ruf / 2......(OK)
Φ Fu Ae ≥ Ruw......(OK)
3) Block Shear Rupture Verification of the Angles
- Φ (0.6 Rt Fu Anv + Ubs Rt Fu Ant) ≥ Ruf / 2......(OK)
- Φ (0.6 Ry Fy Agv + Ubs Rt Fu Ant) ≥ Ruf / 2......(OK)
- Φ (0.6 Rt Fu Anv + Ubs Rt Fu Ant) ≥ Rw......(OK)
- Φ (0.6 Ry Fy Agv + Ubs Rt Fu Ant) ≥ Rw......(OK)

6.4.3.4 Verification in case of Channel Brace (AISC360-05)


1) Bolt Strength
- Shear Strength ΦRn1 = Φ Ns Fn Ab
- Bearing Strength at Bolt Holes ΦRn2 = Min(Φ 1.2 Lc t Fu, Φ 2.4 d t Fu)
- Slip-Critical Connections ΦRn3 = Φ μ Du hsc Tb Ns
- ΦRn = Min(ΦRn1, ΦRn2, ΦRn3)
- Tu / ΦRn < Number of Bolt......(OK)
2) Net Section Fracture
- Φt Rt Fu Ae ≥ Tu......(OK)
3) Block Shear Rupture Verification of the Angles
- Φ (0.6 Rt Fu Anv + Ubs Rt Fu Ant) ≥ Tu......(OK)
- Φ (0.6 Ry Fy Agv + Ubs Rt Fu Ant) ≥ Tu......(OK)

Revisión F 237
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-005

6.4.4 Gusset Plate Design

6.4.4.1 Design Load


Full Capacity of Brace
- Tu : Maximum Tensile Force (= Ry Fy Ag)
- Pu : Maximum Compressive Force (= 1.1 Ry Pn)

6.4.4.2 Schematic Drawing


Concept Drawing Design Force of Gusset Plate

Whitmore Section of Gusset Plate

6.4.4.3 Verification (AISC360-05)


1) Design the Weld at the Gusset-Column Interface
- fv = Huc / 2β

Revisión F 238
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-005

- fa = Vuc / 2β
- fb = 0
- fpeak = √[fv2 + (fa + fb)2]
- favg = (1/2) × {√[(fa - fb)2 + fv2] +√[(fa + fb)2+ fv2]}
- fr = 1.25 X favg (If fpeak / favg < 1.25)
- fr = fpeak (If fpeak / favg ≥ 1.25)
- s ≥ fr / (0.7 (0.9) (0.6) Fy (2))......(OK)
- tmin (=2 (0.9) (0.6) Fy 0.7s / (0.75 (0.6) Fu) < thickness of gusset plate......(OK)
2) Yielding of Gusset Plate
- ΦRn (=Φ Fy t) > MAX.(fv,fa)......(OK)
3) Column Web Yielding
- ΦRn (=Φ Fy tw) > fr......(OK)
4) Column Web Crippling
- ΦRn = Φ 0.8 tw2 [1 + 3(N / d) (tw / tf)1.5] √(E Fyw tf / tw) > Huc......(OK)
5) Design the Weld at the Gusset-Beam Interface (In Tension and Compression)
- fv = Hub / 2α
- fa = Vub / 2α
- fb = Mub / Sw (Sw = (2α)2 / 6)
- fpeak = √[fv2 + (fa + fb)2]
- favg = (1/2) × {√[(fa - fb)2 + fv2] +√[(fa + fb)2+ fv2]}
- fr = 1.25 X favg (If fpeak / favg < 1.25)
- fr = fpeak (If fpeak / favg ≥ 1.25)
- s ≥ fr / (0.7 (0.9) (0.6) Fy (2))......(OK)
- tmin (=2 (0.9) (0.6) Fy 0.7s / (0.75 (0.6) Fu) < thickness of gusset plate......(OK)
6) Yielding of Gusset Plate
- ΦRn (=Φ Fy t) > MAX.(fv,fa)......(OK)
7) Beam Web Yielding
- ΦRn (=Φ Fy tw) > fr......(OK)
8) Beam Web Local Yielding (if the brace connection is located in center of girder)
- ft = fa + fb
- fc = fa – fb
- Lt = [ft / (ft + tc)] / Lg
- Ru = (1/2) Lt ft
- ΦRn = (5k + N) Fyw tw
- Ru < ΦRn......(OK)

Revisión F 239
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-005

9) Beam Web Crippling


- Ru = [Mub / (N2 / 4)] (N / 2) + Vub = 2Mub / N + Vub
- ΦRn = Φ 0.4 tw2 [1 + 3(N / d) (tw / tf)1.5] √(E Fyw tf / tw) (N/d ≤ 0.2)
- ΦRn = Φ 0.4 tw2 [1 + (4N / d - 0.2) (tw / tf)1.5] √(E Fyw tf / tw) (N/d > 0.2)
- Ru < ΦRn......(OK)
10) Beam Web Crippling (if the brace connection is located in center of girder)
- Ru = (1/2) (Lg - Lt) fc
- ΦRn = Φ 0.8 tw2 [1 + 3(N / d) (tw / tf)1.5] √(E Fyw tf / tw)
- Ru < ΦRn......(OK)
11) Compression Buckling of Gusset Plate
- Φc Fcr Ag > Pu......(OK) (The Ag should be considered whitmore section)
12) Tensile Yielding of Gusset Plate
- Φt Fy Ag > Tu X Ratio of Resisting Bolt......(OK) (The Ag should be considered whitmore section)

Revisión F 240
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-005

6.5 Base Plate and Anchor Bolt Design

6.5.1 Design Load


Load from LRFD Combination
- Pu : Maximum Compressive Force
- Tu : Maximum Tensile Force
- Mu : Maximum Bending Moment
- Vu : Maximum Shear Force

6.5.2 Schematic Drawing

6.5.3 Verification (AISC360-05, ACI318-08)


1) Bearing Stress of Base Plate
- Fp = 0.85 Φ fc √(A2 / A1)
- fp = Pu (1+6e / (N or B)) / A (In case of e < (N or B) / 6)
- fp < Fp......(OK)
2) Thickness of Base Plate
- t1 = √ (ß x fp x u2 / 1.5 Fy) (ß : derived by Roak’s Table)
- t2 = √ (ß x fp x (B / 2)2 / 1.5 Fy) (ß : derived by Roak’s Table)
- t > Max.(t1,t2) ......(OK)
3) Embedded Depth and Width of the Shear Key
- Φ Vn = 0.85 Φ fc A > Vu......(OK)
4) Thickness of Shear Key
- treq = √ (ß x fp x Max(W/2-t/2, d+G)2 / 1.5 Fy) (ß : derived by Roak’s Table)
- treq > t ......(OK)

Revisión F 241
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-005

5) Bearing Strength of the Concrete


- Fp = 0.85 Φ fc √(A2 / A1)
- fp = Vu / (W X d)
- fp < Fp......(OK)
6) Anchor Bolt Verification
- Tension Strength : 0.75 Φ Nn = 0.75 Φ n Ase Fut > Tu......(OK)
- Tb = (Tu / 2 + (Mbuilt-in / (d-d’)) / Number of Bolt
- Ase,req = Tu / (0.75 Φ Tb) < Ase......(OK)
- Concrete Breakout Strength : Ncb = ANc / ANco x ψed,N x ψc,N x ψcp,N x Nb > Tu......(OK)
7) Design of Rib Plate
- Height of Rib Plate : 8d of 250mm
- Ru : Reaction due to the anchor bolt full capacity
- Φ Pn = Φ Ag Fcr > Ru......(OK)
- fa : Axial Stress due to the concrete pressure
- Fc > fa......(OK)
8) Design of Upper Plate
M : Bending Moment due to the anchor bolt full capacity
- Φ Fy Z = Φ Fy u t2 / 4 > M......(OK)
9) Design of Anchor Plate
M : Bending Moment due to the anchor bolt full capacity
- Φ Fy Z = Φ Fy u t2 / 4 > M......(OK)

Revisión F 242
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-005

6.6 Connection between SILO and Structure

6.6.1 Design Load


Load from LRFD Combination
- Pu : Maximum Compressive Force
- Tu : Maximum Tensile Force
- Vu : Maximum Shear Force

6.6.2 Schematic Drawing

6.6.3 Verification (AISC360-05, NCh 2369)


1) Bolt Strength
- Shear Strength ΦRn1 = Φ Ns Fnv Ab
- Bearing Strength at Bolt Holes ΦRn2 = Min (Φ 1.0 Lc t Fu, Φ 2.0 d t Fu)
- ΦRn = Min (ΦRn1, ΦRn2)
- Vu / ΦRn < (1/2) X Number of Bolt......(OK)
- Tension Capacity ΦTn1 = Φ Fnt Ab
- Combined Tension and Shear Capacity ΦTn2 = {1.3 Fnt – (Fnt / Φ Fnv) fv} Ab
- ΦTn = Min (ΦTn1, ΦTn2)
- Tu / ΦTn < (1/2) X Number of Bolt......(OK)
2) Gap Size of Bolt Hole
- by temperature : δ = α (∆T) DSILO < Gap Size......(OK)
- If the relative displacement at the sliding support due to earthquake loading is larger than the

Revisión F 243
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-005

available gap of bolt hole, the analysis model should be modified only for earthquake load case as
fixed support.
3) Bearing Strength of Sliding Pad
- 0.9 fc A > Pu......(OK)
4) Beam Web Crippling
- ΦRn = Φ 0.8 tw2 [1 + 3(N / d) (tw / tf)1.5] √(E Fyw tf / tw) > Pu......(OK)
5) Beam Web Local Yielding
- ΦRn = (5k + N) Fyw tw > Pu......(OK)

Revisión F 244
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-005

7. CASING CALCULATION NOTE

Revisión F 245
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-005

7.1 SILO Casing Design

7.1.1 Design Load


Load from ASD Combination

7.1.2 Schematic Drawing

7.1.3 Verification (NCh 2369, EN 1991-4, EN 1993-4-1)


1) Effective Stress
- σe < 0.6 x Fy......(OK) (σe derived by analysis modeling)
2) Combined Compressive Stress
- σcr = 135 Fy x t / D < 0.8 Fy
- σc < σcr......(OK) (σc derived by analysis modeling)
3) Design of Transition Junctions and Supporting Ring Girders
- σ < 0.6 x Fy......(OK) (σ derived by analysis modeling, σe method Von Misses)

Revisión F 246
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-001

ANEXO 5: CRITERIOS DE DISEÑO ESPECIFICOS PARA FLY ASH


SILO

247 de 392

Revisión F
DESIGN CRITERIA FOR FLY ASH SILO TOTAL 55 HOJAS
SUPPORT STRUCTURE AND CASING (Incluyendo Portada)

PROPOSITO

Para Revisión
 NOMBRE CONTRATO EPC POR EL SISTEMA DE
PROYECTO DESULFURIZACION DE GASES - FGD - PARA
LA CENTRAL TARAPACÁ Para Aprobación

 NOMBRE FGD CENTRAL TARAPACÁ Para Construcción


SISTEMA
Para Oferta
 N° DOCUMENTO DCTO413-C8-VVT-000-006
Para Información
 TITULO DESIGN CRITERIA FOR FLY ASH SILO
SUPPORT STRUCTURE AND CASING

 CLIENTE ENDESA S.A.

F 29-12-2014 JCR VBS NCR Para Aprobación

E 22-12-2014 JCR VBS NCR Para Aprobación

D 25-11-2014 JCR VBS NCR Para Aprobación

C 27-10-2014 JCR VBS NCR Para Aprobación

B 30-09-2014 JCR VBS NCR Para Aprobación

A 24-09-2014 JCR VBS NCR Coordinación Interna - - -

PREP. REV. APR. REV. REV. APR.


Rev
FECHA DESCRIPCION
.
STX HI ENDESA S.A.

PROPIETARIO:

CONTRATISTA:
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-006

DESIGN CRITERIA FOR FLY ASH SILO


SUPPORT STRUCTURE AND CASING

Rev. F

Revisión F 249
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-006

Contents

1 INTRODUCTION
1.1 Location
1.2 Weather
1.3 Scope

2 STRUCTURAL DESIGN CRITERIA


2.1 Design Code and Reference
2.2 Materials
2.3 Structural Analysis and Design Program

3 DESIGN LOADS
3.1 Dead Load
3.2 Live Load
3.3 Thermal Load
3.4 Wind Load
3.5 Earthquake Load
3.6 Load Combination

4 STRUCTURAL SYSTEM
4.1 Structural System and Analysis Condition
4.2 Base Plate and Anchor System

5 STRUCTURAL ANALYSIS
5.1 Base Shear and Equivalent Mass
5.2 Natural Vibration Mode
5.3 Support Reaction
5.4 Displacement

Revisión F 250
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-006

6 MEMBER DESIGN
6.1 Column Design
6.2 Beam and Girder Design
6.3 Brace Design
6.4 Connection Design
6.5 Base Plate and Anchor Bolt Design
6.6 Connection between SILO and Structure

7 CASING CALCULATION NOTE


7.1 SILO Casing Design

Revisión F 251
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-006

1. INTRODUCTION
1.1 Location
The Tarapacá Thermal Power Plant (158 MW), henceforth the Power Plant, owned by Compañía
Eléctrica Tarapacá S.A., hereinafter CELTA S.A or CELTA, is located on the I Region of Chile,
approximately 60km south of Iquique, by the coast, on the area known as Punta Patache.

1.2 Weather
Weather conditions in the sector are as follows:
Barometric Pressure(Average): 1,015 millibars
Ambient Temperature: Maximum 31.3℃, Minimum 8℃
Relative Humidity(Mean): 78%

1.3 Scope
This is design criteria for Fly Ash Silo support structure and casing.

Revisión F 252
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-006

2. STRUCTURAL DESIGN CRITERIA


The structural design criteria in this report were calculated according to Technical Specification.

2.1 Design Code and Reference


Code Code & Reference Remarks
Earthquake-Resistant Design of Industrial Structures and
NCh 2369 Seismic Design
Facilities
ETG 1015 General Technical Specifications – Seismic Design Seismic Design
NCh 432 Structural Design – Wind Loads Wind Load
Structural Design – General Dispositions and Combinations
NCh 3171 Load Combination
of Load
ASCE 7-05 Minimum Design Loads for Building and Other Structures Load Combination
AISC 360-05 Specification for Structural Steel Buildings Steel Design
ACI 318-08 Building Code Requirements for Structural Concrete Anchoring to Concrete
EN 1991-4 Eurocode 1 – Actions on Structures – Part4 : Silo and Tanks SILO Design Loads
EN 1993-4-1 Eurocode 3 – Design of Steel Structures – Part4 : Silos SILO Design

2.2 Materials
Tensile Modulus of
Standard Symbol Yield Strength Remarks
Strength Elasticity
Structural Steel /
KS D 3503 235 MPa (t ≤ 40mm)
SS 400 400 MPa 200,000 MPa Anchor Bolt / SILO
JIS G 3101 215 MPa (t > 40mm)
Casing
KS D 3515 315 MPa (t ≤ 40mm)
SM490 490 MPa 200,000 MPa Structural Steel
JIS G 3106 295 MPa (t > 40mm)
ASTM A36 250 MPa 400 MPa 200,000 MPa Anchor Bolt

Standard Symbol Nominal Tensile Stress Nominal Shear Stress Remarks


KS B 1010 F10T 736 MPa 392 MPa
High Strength Bolt
ASTM A325 620 MPa 330 MPa
/ Torque Shear Bolt
ASTM A490 780 MPa 414 MPa

* Friction Coefficient 0.35 : Class A surface ( unpainted clean mill scale steel surfaces or surfaces with
Class A coatings on blast-cleaned steel and hot-dipped galvanized and roughened surfaces)
Material properties in operation temperature (180℃) (ASME 2010 U, Y-1, TM-1)

Revisión F 253
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-006

Modulus of
Symbol Yield Strength Tensile Strength Remarks
Elasticity
SS 400 204 MPa 400 MPa 193,200 MPa SA-36

The material properties for determine the required strength of element and connection are included
KBC 2009 (Korean Building Code 2009) section 0713.6.2.

In section 0713.6.2 of KBC 2009 (Original)

Revisión F 254
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-006

In section 0713.6.2 of KBC 2009 (Translation)


0713.6.2 Material Properties for determine the required strength of member and connection
(1) When estimate the required strength of each member (member or connection) by the provision of
this section, the required strength should be calculated based on the expected yield strength Ry Fy
of connected member. In here, Fy is the minimum yield strength of connected member and Ry is
the ratio of expected yield strength and minimum yield strength.

(2) The design strength ФRn should be at least the required strength. When estimate the nominal

Strength Rn for fracture and yield state, the expected tensile strength Rt Fu and expected yield
Strength Ry Fy can be used instead of Fu and Fy.
(3) The values of Ry and Rt are in the table 0713.6.1.

<Table 0713.6.1> The values of Ry and Rt for each type of steel

Application Ry Rt
KS SS400, SSC400, SWH400,
KS STK400, STK490, SPSR400, SPSR490, 1.3 1.2
STKN400, STKN490
Structural Rolled Shapes
Steel and Cold Formed KS SM400, SM490, SM520
Steel KS SPAR295, SPAP235, SPAP325, 1.2 1.2
SCW490-CF
KS SHN400, SHN490 1.1 1.1
KS SS400 1.3 1.2
KS SM490, SM490TMC, SM520,
SM520TMC, SM570, SM570TMC, 1.2 1.2
Plate KS SMA400, SMA490, SMA570
KS SN400, SN490 1.1 1.1
HSA800 1.1 1.1

2.3 Structural Analysis and Design Program


Software Program Code & Reference Remarks
3D Static & Dynamic Analysis -
SAP 2000
Member Design

SAFE Foundation Analysis -

Revisión F 255
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-006

3. DESIGN LOADS
3.1 Dead Load (D)
Dead load is the load due to the permanent weight of all structural and nonstructural components of a
construction, including thermal insulation, ladders and others.

Item Density or Load Remark


7,850 kg/m3
Steel SS 400, SM 490
(=76.98 kN/m3)
50 kg/m2
Grating ARRIGONI ARS-5 33 kg/m2.
(=0.49 kN/m2)
100 kg/m3
Insulation -
(=0.98 kN/m3)

3.2 Live Load (L , L_ and Lr)


It shall be included in this load category, the content of tanks, silos, hoppers, ducting, mobile and
transient loads and weight of people, equipment and tools, and other material agglomerations.
Live load is calculated according to Technical Specification.

Item Load Remark


400kg/m2
Offices, Hallways, Stairs (L) -
(= 3.92 kN/m2)
Roof not exposed to traffic 100 kg/m2
-
(Lr) (= 0.98 kN/m2)
Density : 0.8 tonf/m3 (for volume)
1.25 tonf/m3 (for structural design) It should not be
Total Volume (Design Condition) : Later considered the 0.5
Ash with Lime (L_)
Total Weight (Design Condition) : Later factor in load
Total Volume (Emergency Condition) : Later combination.
Total Weight (Emergency Condition) : Later

The material Properties of Ash with Lime (according to the EN 1991-4 Eurocode 1 – Actions on
Structures – Part4 : Silo and Tanks)

Revisión F 256
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-006

3.3 Thermal Load (T)

3.3.1 External Temperature


Effect of temperature on the structure, due to climatic conditions of the area
Metal structures for temperature variation depends on local conditions, but it will not be less than
±25℃.

3.3.2 Strain due to the Temperature

Where,
α = 1.2×10-5 /℃, coefficient of thermal expansion
∆T = ±25℃ (Steel exposed o ambient)

Revisión F 257
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-006

3.4 Wind Load (WX, WY)


Wind load is calculated based on NCh 432 Table 1.

Structures located in open country, facing the ocean, or locations under similar conditions, in the
judgment of the Reviewing Authority

Height above the NCh 432 Chapter 6.5


Basic pressure, q Basic pressure, q
ground ×1.2
[kg/m2] [kPa]
[m] [kPa]
0 70 0.69 0.82
4 70 0.69 0.82
7 95 0.93 1.12
10 106 1.04 1.25
15 118 1.16 1.39
20 126 1.24 1.48
30 137 1.34 1.61
40 145 1.42 1.71
50 151 1.48 1.78
75 163 1.60 1.92
100 170 1.67 2.00
150 182 1.78 2.14
200 191 1.87 2.25
300 209 2.05 2.46

Revisión F 258
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-006

3.5 Earthquake Load (EX, EY, EZ)

3.5.1 Earthquake Load


The total base shear shall be computed from the expression.
V = C X W ≥ 0.12 W
Where,
V Base shear
C Seismic coefficient, obtained directly from the design spectrum.
W Total seismic weight of the structure or system, computed as the sum of dead load of
structure and equipment

3.5.1.1 Earthquake action for horizontal direction


The design spectrum is calculated based on ETG1015 figure 1.
Applied coefficients are as follows:
Ground Acceleration a/g = 0.4
Response Modification Factors: R = 4.0
Equivalent viscous damping: ζ = 0.02

3.5.1.2 Earthquake action for vertical direction


The vertical earthquake shall be considered according to Section 5.5 of NCh 2369 Standard, with
seismic coefficient equal to 2 A0 / 3g.

Revisión F 259
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-006

Coordinates of the corner point for a/g = 0.4

ζ T1 T2 A/g
0.005 0.113 0.451 1.472
0.01 0.115 0.461 1.284
0.02 0.119 0.474 1.096
0.03 0.121 0.485 0.984
0.05 0.125 0.499 0.848
0.07 0.128 0.512 0.756
0.10 0.134 0.535 0.656
0.20 0.148 0.591 0.468
Equation of hyperbolic branch:

(T2<=T<=2.5 s)

3.5.2 Methods of Analysis

Revisión F 260
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-006

In order to compute the forces and displacements in a given structural system when subjected to the
earthquake action, a response spectrum analysis shell be performed.

3.5.3 Number of Modes


The analysis shall include a sufficient number of vibration modes for the sum of equivalent masses in
each analysis direction is equal to or higher than 90% of the total mass.

3.5.4 Mode Superposition


In order to obtain an estimate of the maximum values of any response quantity considered in the
analysis, the maximum values of the corresponding responses computed for the individual mode of
vibration shall be combined with the CQC superposition criterion normally called “Complete Quadratic
Combination”, recommended in Chilean code Section 5.4.4 of NCh 2369.
The following expressions summarize the mode superposition procedure:

Where,
S Modal combination
Si , Sj Maximum values of mode contributions i and j
ζ Damping ratio
Ti, Tj Period of mode i and j

3.5.5 Coupling of earthquake action for Support Structure


For the case of dynamic analysis, the requirements of Section 5.1.2 of Chilean code NCh 2369
regarding the effect of the combination of the seismic horizontal components effect are applicable.
This requires that the modal shape and frequencies have to be analyzed and if they are found to be
coupled without a clear or predominant directional acceleration input shall be performed instead of
two independent analyses. This can be implemented by carrying out two different three dimensional
analyses; in each of them the earthquake action input (acceleration spectrum ordinates) shall be
100% of the Project Specification design spectrum in on direction plus 30% of the Project
Specification design spectrum in the orthogonal direction.

Point 5.1.2 of NCh-2369 clearly indicates that it is not necessary to combine the horizontal
components of the seismic action, ie can be analyzed separately for earthquake acting in both
directions considered analysis and design with the unfavorable situation.
Exceptions to this rule structures that have significant torsional irregularities, for which it requires rigid
diaphragms own buildings. The situation is important to consider in the corner columns orthogonal

Revisión F 261
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-006

building rigid frames that share these corner columns. In cases like this should be at 100% overlap in
a direction analysis 30% of the analyzes in the other direction and the same for the other direction
relative to the first. This exception should be applied to irregular structured buildings preferably those
based on rigid frames.

3.5.6 Seismic Mass Percentage for Live Load


Seismic mass percentages are considered according to Technical Specification.
It shall be considered the following percentage of seismic mass for live load:

Section Seismic Mass Percentage (%)

Area of Normal Use, Floor Live Load 25

Roof without Transit 0

Silos 100

Revisión F 262
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-006

3.6 Load Combination

3.6.1 Basic Load Case


D Dead Load
T1 Thermal Load (∆T = +25℃, in case of steel exposed to ambient)
T2 Thermal Load (∆T = -25℃, in case of steel exposed to ambient)
L Live Load
L_1 Ash with Lime Load
Lr Roof live load not exposed to traffic
WX Wind Load X direction
WY Wind Load Y direction
EX Earthquake Load X direction
EY Earthquake Load Y direction
EZ Earthquake Load Vertical direction
L_EM Emergency Load

3.6.2 LRFD Load Combination (for Anchor System and Foundations)


The LRFD load combinations shall take into account the earthquake load in Technical Specification.
Technical Specification considered a nominal load, so it must be amplified by a factor 1.4. as shown in
the following table

No. Case Name Description


1 uLCB1 1.4(D + T1)
2 uLCB2 1.2(D + T1) + 1.6L + 1.6L_ + 0.5Lr
3  uLCB3 1.2(D + T1) + 0.5L + 1.0L_ + 1.6Lr
4  uLCB4 1.2(D + T1) + 1.6Lr + 0.8WX
5  uLCB5 1.2(D + T1) + 1.6Lr - 0.8WX
6  uLCB6 1.2(D + T1) + 1.6Lr + 0.8WY
7  uLCB7 1.2(D + T1) + 1.6Lr - 0.8WY
8  uLCB8 1.2(D + T1) + 1.6WX + 0.5L + 1.0L_ + 0.5Lr
9  uLCB9 1.2(D + T1) - 1.6WX + 0.5L + 1.0L_+ 0.5Lr
10  uLCB10 1.2(D + T1) + 1.6WY + 0.5L + 1.0L_+ 0.5Lr
11  uLCB11 1.2(D + T1) - 1.6WY + 0.5L + 1.0L_+ 0.5Lr
12  uLCB12 1.2(D + T1) + 1.4(1.0EX + 0.3EY + 1.0EZ) + 0.5L + 1.0L_

Revisión F 263
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-006

13  uLCB13 1.2(D + T1) + 1.4(1.0EX + 0.3EY - 1.0EZ) + 0.5L + 1.0L_


14  uLCB14 1.2(D + T1) + 1.4(1.0EX - 0.3EY + 1.0EZ) + 0.5L + 1.0L_
15  uLCB15 1.2(D + T1) + 1.4(1.0EX - 0.3EY - 1.0EZ) + 0.5L + 1.0L_
16  uLCB16 1.2(D + T1) - 1.4(1.0EX + 0.3EY + 1.0EZ) + 0.5L + 1.0L_
17  uLCB17 1.2(D + T1) - 1.4(1.0EX + 0.3EY - 1.0EZ) + 0.5L + 1.0L_
18  uLCB18 1.2(D + T1) - 1.4(1.0EX - 0.3EY + 1.0EZ) + 0.5L + 1.0L_
19  uLCB19 1.2(D + T1) - 1.4(1.0EX - 0.3EY - 1.0EZ) + 0.5L + 1.0L_
20  uLCB20 1.2(D + T1) + 1.4(0.3EX + 1.0EY + 1.0EZ) + 0.5L + 1.0L_
21  uLCB21 1.2(D + T1) + 1.4(0.3EX + 1.0EY - 1.0EZ) + 0.5L + 1.0L_
22  uLCB22 1.2(D + T1) + 1.4(0.3EX – 1.0EY + 1.0EZ) + 0.5L + 1.0L_
23  uLCB23 1.2(D + T1) + 1.4(0.3EX – 1.0EY - 1.0EZ) + 0.5L + 1.0L_
24  uLCB24 1.2(D + T1) - 1.4(0.3EX + 1.0EY + 1.0EZ) + 0.5L + 1.0L_
25  uLCB25 1.2(D + T1) - 1.4(0.3EX + 1.0EY - 1.0EZ) + 0.5L + 1.0L_
26  uLCB26 1.2(D + T1) - 1.4(0.3EX – 1.0EY + 1.0EZ) + 0.5L + 1.0L_
27  uLCB27 1.2(D + T1) - 1.4(0.3EX – 1.0EY - 1.0EZ) + 0.5L + 1.0L_
28  uLCB28 0.9(D + T1) + 1.6WX
29  uLCB29 0.9(D + T1) - 1.6WX
30  uLCB30 0.9(D + T1) + 1.6WY
31  uLCB31 0.9(D + T1) - 1.6WY
32  uLCB32 0.9(D + T1) + 1.4(1.0EX + 0.3EY + 1.0EZ)
33  uLCB33 0.9(D + T1) + 1.4(1.0EX + 0.3EY - 1.0EZ)
34  uLCB34 0.9(D + T1) + 1.4(1.0EX - 0.3EY + 1.0EZ)
35  uLCB35 0.9(D + T1) + 1.4(1.0EX - 0.3EY - 1.0EZ)
36  uLCB36 0.9(D + T1) - 1.4(1.0EX + 0.3EY + 1.0EZ)
37  uLCB37 0.9(D + T1) - 1.4(1.0EX + 0.3EY - 1.0EZ)
38  uLCB38 0.9(D + T1) - 1.4(1.0EX - 0.3EY + 1.0EZ)
39  uLCB39 0.9(D + T1) - 1.4(1.0EX - 0.3EY - 1.0EZ)
40  uLCB40 0.9(D + T1) + 1.4(0.3EX + 1.0EY + 1.0EZ)
41  uLCB41 0.9(D + T1) + 1.4(0.3EX + 1.0EY - 1.0EZ)
42  uLCB42 0.9(D + T1) + 1.4(0.3EX – 1.0EY + 1.0EZ)

Revisión F 264
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-006

43  uLCB43 0.9(D + T1) + 1.4(0.3EX – 1.0EY - 1.0EZ)


44  uLCB44 0.9(D + T1) - 1.4(0.3EX + 1.0EY + 1.0EZ)
45  uLCB45 0.9(D + T1) - 1.4(0.3EX + 1.0EY - 1.0EZ)
46  uLCB46 0.9(D + T1) - 1.4(0.3EX – 1.0EY + 1.0EZ)
47  uLCB47 0.9(D + T1) - 1.4(0.3EX – 1.0EY - 1.0EZ)
48  uLCB48 1.2(D + T1) + 1.6L + 1.6(L_EM) + 0.5Lr
49  uLCB49 1.2(D + T1) + 1.0(L_EM) + 1.6Lr + 0.5L
50  uLCB50 1.4(D + T2)
51  uLCB51 1.2(D + T2) + 1.6L + 1.6L_ + 0.5Lr
52  uLCB52 1.2(D + T2) + 0.5L + 1.0L_ + 1.6Lr
53  uLCB53 1.2(D + T2) + 1.6Lr + 0.8WX
54  uLCB54 1.2(D + T2) + 1.6Lr - 0.8WX
55  uLCB55 1.2(D + T2) + 1.6Lr + 0.8WY
56  uLCB56 1.2(D + T2) + 1.6Lr - 0.8WY
57  uLCB57 1.2(D + T2) + 1.6WX + 0.5L + 1.0L_ + 0.5Lr
58  uLCB58 1.2(D + T2) - 1.6WX + 0.5L + 1.0L_+ 0.5Lr
59  uLCB59 1.2(D + T2) + 1.6WY + 0.5L + 1.0L_+ 0.5Lr
60  uLCB60 1.2(D + T2) - 1.6WY + 0.5L + 1.0L_+ 0.5Lr
61  uLCB61 1.2(D + T2) + 1.4(1.0EX + 0.3EY + 1.0EZ) + 0.5L + 1.0L_
62  uLCB62 1.2(D + T2) + 1.4(1.0EX + 0.3EY - 1.0EZ) + 0.5L + 1.0L_
63  uLCB63 1.2(D + T2) + 1.4(1.0EX - 0.3EY + 1.0EZ) + 0.5L + 1.0L_
64  uLCB64 1.2(D + T2) + 1.4(1.0EX - 0.3EY - 1.0EZ) + 0.5L + 1.0L_
65  uLCB65 1.2(D + T2) - 1.4(1.0EX + 0.3EY + 1.0EZ) + 0.5L + 1.0L_
66  uLCB66 1.2(D + T2) - 1.4(1.0EX + 0.3EY - 1.0EZ) + 0.5L + 1.0L_
67  uLCB67 1.2(D + T2) - 1.4(1.0EX - 0.3EY + 1.0EZ) + 0.5L + 1.0L_
68  uLCB68 1.2(D + T2) - 1.4(1.0EX - 0.3EY - 1.0EZ) + 0.5L + 1.0L_
69  uLCB69 1.2(D + T2) + 1.4(0.3EX + 1.0EY + 1.0EZ) + 0.5L + 1.0L_
70  uLCB70 1.2(D + T2) + 1.4(0.3EX + 1.0EY - 1.0EZ) + 0.5L + 1.0L_
71  uLCB71 1.2(D + T2) + 1.4(0.3EX – 1.0EY + 1.0EZ) + 0.5L + 1.0L_
72  uLCB72 1.2(D + T2) + 1.4(0.3EX – 1.0EY - 1.0EZ) + 0.5L + 1.0L_

Revisión F 265
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-006

73  uLCB73 1.2(D + T2) - 1.4(0.3EX + 1.0EY + 1.0EZ) + 0.5L + 1.0L_


74  uLCB74 1.2(D + T2) - 1.4(0.3EX + 1.0EY - 1.0EZ) + 0.5L + 1.0L_
75  uLCB75 1.2(D + T2) - 1.4(0.3EX – 1.0EY + 1.0EZ) + 0.5L + 1.0L_
76  uLCB76 1.2(D + T2) - 1.4(0.3EX – 1.0EY - 1.0EZ) + 0.5L + 1.0L_
77  uLCB77 0.9(D + T2) + 1.6WX
78  uLCB78 0.9(D + T2) - 1.6WX
79  uLCB79 0.9(D + T2) + 1.6WY
80  uLCB80 0.9(D + T2) - 1.6WY
81  uLCB81 0.9(D + T2) + 1.4(1.0EX + 0.3EY + 1.0EZ)
82  uLCB82 0.9(D + T2) + 1.4(1.0EX + 0.3EY - 1.0EZ)
83  uLCB83 0.9(D + T2) + 1.4(1.0EX - 0.3EY + 1.0EZ)
84  uLCB84 0.9(D + T2) + 1.4(1.0EX - 0.3EY - 1.0EZ)
85  uLCB85 0.9(D + T2) - 1.4(1.0EX + 0.3EY + 1.0EZ)
86  uLCB86 0.9(D + T2) - 1.4(1.0EX + 0.3EY - 1.0EZ)
87  uLCB87 0.9(D + T2) - 1.4(1.0EX - 0.3EY + 1.0EZ)
88  uLCB88 0.9(D + T2) - 1.4(1.0EX - 0.3EY - 1.0EZ)
89  uLCB89 0.9(D + T2) + 1.4(0.3EX + 1.0EY + 1.0EZ)
90  uLCB90 0.9(D + T2) + 1.4(0.3EX + 1.0EY - 1.0EZ)
91  uLCB91 0.9(D + T2) + 1.4(0.3EX – 1.0EY + 1.0EZ)
92  uLCB92 0.9(D + T2) + 1.4(0.3EX – 1.0EY - 1.0EZ)
93  uLCB93 0.9(D + T2) - 1.4(0.3EX + 1.0EY + 1.0EZ)
94  uLCB94 0.9(D + T2) - 1.4(0.3EX + 1.0EY - 1.0EZ)
95  uLCB95 0.9(D + T2) - 1.4(0.3EX – 1.0EY + 1.0EZ)
96  uLCB96 0.9(D + T2) - 1.4(0.3EX – 1.0EY - 1.0EZ)
97  uLCB97 1.2(D + T2) + 1.6L + 1.6(L_EM) + 0.5Lr
98  uLCB98 1.2(D + T2) + 1.0(L_EM) + 1.6Lr + 0.5L
99  uLCB99 1.4D
100  uLCB100 1.2D + 1.6L + 1.6L_ + 0.5Lr
101  uLCB101 1.2D + 0.5L + 1.0L_ + 1.6Lr
102  uLCB102 1.2D + 1.6Lr + 0.8WX

Revisión F 266
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-006

103  uLCB103 1.2D + 1.6Lr - 0.8WX


104  uLCB104 1.2D + 1.6Lr + 0.8WY
105  uLCB105 1.2D + 1.6Lr - 0.8WY
106  uLCB106 1.2D + 1.6WX + 0.5L + 1.0L_ + 0.5Lr
107  uLCB107 1.2D - 1.6WX + 0.5L + 1.0L_+ 0.5Lr
108  uLCB108 1.2D + 1.6WY + 0.5L + 1.0L_+ 0.5Lr
109  uLCB109 1.2D - 1.6WY + 0.5L + 1.0L_+ 0.5Lr
110  uLCB110 1.2D + 1.4(1.0EX + 0.3EY + 1.0EZ) + 0.5L + 1.0L_
111  uLCB111 1.2D + 1.4(1.0EX + 0.3EY - 1.0EZ) + 0.5L + 1.0L_
112  uLCB112 1.2D + 1.4(1.0EX - 0.3EY + 1.0EZ) + 0.5L + 1.0L_
113  uLCB113 1.2D + 1.4(1.0EX - 0.3EY - 1.0EZ) + 0.5L + 1.0L_
114  uLCB114 1.2D - 1.4(1.0EX + 0.3EY + 1.0EZ) + 0.5L + 1.0L_
115  uLCB115 1.2D - 1.4(1.0EX + 0.3EY - 1.0EZ) + 0.5L + 1.0L_
116  uLCB116 1.2D - 1.4(1.0EX - 0.3EY + 1.0EZ) + 0.5L + 1.0L_
117  uLCB117 1.2D - 1.4(1.0EX - 0.3EY - 1.0EZ) + 0.5L + 1.0L_
118  uLCB118 1.2D + 1.4(0.3EX + 1.0EY + 1.0EZ) + 0.5L + 1.0L_
119  uLCB119 1.2D + 1.4(0.3EX + 1.0EY - 1.0EZ) + 0.5L + 1.0L_
120  uLCB120 1.2D + 1.4(0.3EX – 1.0EY + 1.0EZ) + 0.5L + 1.0L_
121  uLCB121 1.2D + 1.4(0.3EX – 1.0EY - 1.0EZ) + 0.5L + 1.0L_
122  uLCB122 1.2D - 1.4(0.3EX + 1.0EY + 1.0EZ) + 0.5L + 1.0L_
123  uLCB123 1.2D - 1.4(0.3EX + 1.0EY - 1.0EZ) + 0.5L + 1.0L_
124  uLCB124 1.2D - 1.4(0.3EX – 1.0EY + 1.0EZ) + 0.5L + 1.0L_
125  uLCB125 1.2D - 1.4(0.3EX – 1.0EY - 1.0EZ) + 0.5L + 1.0L_
126  uLCB126 0.9D + 1.6WX
127  uLCB127 0.9D - 1.6WX
128  uLCB128 0.9D + 1.6WY
129  uLCB129 0.9D - 1.6WY
130  uLCB130 0.9D + 1.4(1.0EX + 0.3EY + 1.0EZ)
131  uLCB131 0.9D + 1.4(1.0EX + 0.3EY - 1.0EZ)
132  uLCB132 0.9D + 1.4(1.0EX - 0.3EY + 1.0EZ)

Revisión F 267
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-006

133  uLCB133 0.9D + 1.4(1.0EX - 0.3EY - 1.0EZ)


134  uLCB134 0.9D - 1.4(1.0EX + 0.3EY + 1.0EZ)
135  uLCB135 0.9D - 1.4(1.0EX + 0.3EY - 1.0EZ)
136  uLCB136 0.9D - 1.4(1.0EX - 0.3EY + 1.0EZ)
137  uLCB137 0.9D - 1.4(1.0EX - 0.3EY - 1.0EZ)
138  uLCB138 0.9D + 1.4(0.3EX + 1.0EY + 1.0EZ)
139  uLCB139 0.9D + 1.4(0.3EX + 1.0EY - 1.0EZ)
140  uLCB140 0.9D + 1.4(0.3EX – 1.0EY + 1.0EZ)
141  uLCB141 0.9D + 1.4(0.3EX – 1.0EY - 1.0EZ)
142  uLCB142 0.9D - 1.4(0.3EX + 1.0EY + 1.0EZ)
143  uLCB143 0.9D - 1.4(0.3EX + 1.0EY - 1.0EZ)
144  uLCB144 0.9D - 1.4(0.3EX – 1.0EY + 1.0EZ)
145  uLCB145 0.9D - 1.4(0.3EX – 1.0EY - 1.0EZ)
146  uLCB146 1.2D + 1.6L + 1.6(L_EM) + 0.5Lr
147  uLCB147 1.2D + 1.0(L_EM) + 1.6Lr + 0.5L

3.6.3 ASD Load Combination (for SILO Casing and Structure)


The ASD load combinations shall take into account the earthquake load in Technical Specification.
Technical Specification considered a nominal load, so it must be amplified by a factor 1.0.

No. Case Name Description


1 sLCB1 (D + T1)
2  sLCB2 (D + T1) + L + L_
3  sLCB3 (D + T1) + Lr
4  sLCB4 (D + T1) + 0.75L + 0.75L_ + 0.75Lr
5  sLCB5 (D + T1) + WX
6  sLCB6 (D + T1) - WX
7  sLCB7 (D + T1) + WY
8  sLCB8 (D + T1) - WY
9  sLCB9 (D + T1) + EX + 0.3EY + EZ
10  sLCB10 (D + T1) + EX + 0.3EY - EZ
11  sLCB11 (D + T1) + EX - 0.3EY + EZ

Revisión F 268
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-006

12  sLCB12 (D + T1) + EX - 0.3EY - EZ


13  sLCB13 (D + T1) - EX + 0.3EY + EZ
14  sLCB14 (D + T1) - EX + 0.3EY - EZ
15  sLCB15 (D + T1) - EX - 0.3EY + EZ
16  sLCB16 (D + T1) - EX - 0.3EY - EZ
17  sLCB17 (D + T1) + 0.3EX + EY + EZ
18  sLCB18 (D + T1) + 0.3EX + EY - EZ

19  sLCB19 (D + T1) + 0.3EX - EY + EZ


20  sLCB20 (D + T1) + 0.3EX - EY - EZ

21  sLCB21 (D + T1) - 0.3EX + EY + EZ


22  sLCB22 (D + T1) - 0.3EX + EY - EZ

23  sLCB23 (D + T1) - 0.3EX - EY + EZ


24  sLCB24 (D + T1) - 0.3EX - EY - EZ

25  sLCB25 (D + T1) + 0.75WX + 0.75L + 0.75L_ + 0.75Lr


26  sLCB26 (D + T1) - 0.75WX + 0.75L + 0.75L_ + 0.75Lr
27  sLCB27 (D + T1) + 0.75WY + 0.75L + 0.75L_ + 0.75Lr
28  sLCB28 (D + T1) - 0.75WY + 0.75L + 0.75L_ + 0.75Lr
29  sLCB29 (D + T1) + 0.75(EX + 0.3EY + EZ) + 0.75L + 0.75L_
30  sLCB30 (D + T1) + 0.75(EX + 0.3EY - EZ) + 0.75L + 0.75L_
31  sLCB31 (D + T1) + 0.75(EX - 0.3EY + EZ) + 0.75L + 0.75L_
32  sLCB32 (D + T1) + 0.75(EX - 0.3EY - EZ) + 0.75L + 0.75L_
33  sLCB33 (D + T1) + 0.75(-EX + 0.3EY + EZ) + 0.75L + 0.75L_
34  sLCB34 (D + T1) + 0.75(-EX + 0.3EY - EZ) + 0.75L + 0.75L_
35  sLCB35 (D + T1) + 0.75(-EX - 0.3EY + EZ) + 0.75L + 0.75L_
36  sLCB36 (D + T1) + 0.75(-EX - 0.3EY - EZ) + 0.75L + 0.75L_
37  sLCB37 (D + T1) + 0.75(0.3EX + EY + EZ) + 0.75L + 0.75L_
38  sLCB38 (D + T1) + 0.75(0.3EX + EY - EZ) + 0.75L + 0.75L_
39  sLCB39 (D + T1) + 0.75(0.3EX - EY + EZ) + 0.75L + 0.75L_
40  sLCB40 (D + T1) + 0.75(0.3EX - EY - EZ) + 0.75L + 0.75L_
41  sLCB41 (D + T1) + 0.75(-0.3EX + EY + EZ) + 0.75L + 0.75L_

Revisión F 269
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-006

42  sLCB42 (D + T1) + 0.75(-0.3EX + EY - EZ) + 0.75L + 0.75L_


43  sLCB43 (D + T1) + 0.75(-0.3EX - EY + EZ) + 0.75L + 0.75L_
44  sLCB44 (D + T1) + 0.75(-0.3EX - EY - EZ) + 0.75L + 0.75L_
45  sLCB45 0.6(D + T1) + WX
46  sLCB46 0.6(D + T1) - WX
47  sLCB47 0.6(D + T1) + WY
48  sLCB48 0.6(D + T1) - WY
49  sLCB49 0.6(D + T1) + EX + 0.3EY + EZ
50  sLCB50 0.6(D + T1) + EX + 0.3EY - EZ
51  sLCB51 0.6(D + T1) + EX - 0.3EY + EZ
52  sLCB52 0.6(D + T1) + EX - 0.3EY - EZ
53  sLCB53 0.6(D + T1) - EX + 0.3EY + EZ
54  sLCB54 0.6(D + T1) - EX + 0.3EY - EZ
55  sLCB55 0.6(D + T1) - EX - 0.3EY + EZ
56  sLCB56 0.6(D + T1) - EX - 0.3EY - EZ
57  sLCB57 0.6(D + T1) + 0.3EX + EY + EZ
58  sLCB58 0.6(D + T1) + 0.3EX + EY - EZ
59  sLCB59 0.6(D + T1) + 0.3EX - EY + EZ
60  sLCB60 0.6(D + T1) + 0.3EX - EY - EZ
61  sLCB61 0.6(D + T1) - 0.3EX + EY + EZ
62  sLCB62 0.6(D + T1) - 0.3EX + EY - EZ
63  sLCB63 0.6(D + T1) - 0.3EX - EY + EZ
64  sLCB64 0.6(D + T1) - 0.3EX - EY - EZ
65  sLCB65 (D + T1) + L + L_EM
66  sLCB66 (D + T1) + 0.75L + 0.75L_EM + 0.75Lr
67  sLCB67 (D + T2)
68  sLCB68 (D + T2) + L + L_
69  sLCB69 (D + T2) + Lr
70  sLCB70 (D + T2) + 0.75L + 0.75L_ + 0.75Lr
71  sLCB71 (D + T2) + WX

Revisión F 270
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-006

72  sLCB72 (D + T2) - WX


73  sLCB73 (D + T2) + WY
74  sLCB74 (D + T2) - WY
75  sLCB75 (D + T2) + EX + 0.3EY + EZ
76  sLCB76 (D + T2) + EX + 0.3EY - EZ
77  sLCB77 (D + T2) + EX - 0.3EY + EZ
78  sLCB78 (D + T2) + EX - 0.3EY - EZ
79  sLCB79 (D + T2) - EX + 0.3EY + EZ
80  sLCB80 (D + T2) - EX + 0.3EY - EZ
81  sLCB81 (D + T2) - EX - 0.3EY + EZ
82  sLCB82 (D + T2) - EX - 0.3EY - EZ
83  sLCB83 (D + T2) + 0.3EX + EY + EZ
84  sLCB84 (D + T2) + 0.3EX + EY - EZ

85  sLCB85 (D + T2) + 0.3EX - EY + EZ


86  sLCB86 (D + T2) + 0.3EX - EY - EZ

87  sLCB87 (D + T2) - 0.3EX + EY + EZ


88  sLCB88 (D + T2) - 0.3EX + EY - EZ

89  sLCB89 (D + T2) - 0.3EX - EY + EZ


90  sLCB90 (D + T2) - 0.3EX - EY - EZ

91  sLCB91 (D + T2) + 0.75WX + 0.75L + 0.75L_ + 0.75Lr


92  sLCB92 (D + T2) - 0.75WX + 0.75L + 0.75L_ + 0.75Lr
93  sLCB93 (D + T2) + 0.75WY + 0.75L + 0.75L_ + 0.75Lr
94  sLCB94 (D + T2) - 0.75WY + 0.75L + 0.75L_ + 0.75Lr
95  sLCB95 (D + T2) + 0.75(EX + 0.3EY + EZ) + 0.75L + 0.75L_
96  sLCB96 (D + T2) + 0.75(EX + 0.3EY - EZ) + 0.75L + 0.75L_
97  sLCB97 (D + T2) + 0.75(EX - 0.3EY + EZ) + 0.75L + 0.75L_
98  sLCB98 (D + T2) + 0.75(EX - 0.3EY - EZ) + 0.75L + 0.75L_
99  sLCB99 (D + T2) + 0.75(-EX + 0.3EY + EZ) + 0.75L + 0.75L_
100  sLCB100 (D + T2) + 0.75(-EX + 0.3EY - EZ) + 0.75L + 0.75L_
101  sLCB101 (D + T2) + 0.75(-EX - 0.3EY + EZ) + 0.75L + 0.75L_

Revisión F 271
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-006

102  sLCB102 (D + T2) + 0.75(-EX - 0.3EY - EZ) + 0.75L + 0.75L_


103  sLCB103 (D + T2) + 0.75(0.3EX + EY + EZ) + 0.75L + 0.75L_
104  sLCB104 (D + T2) + 0.75(0.3EX + EY - EZ) + 0.75L + 0.75L_
105  sLCB105 (D + T2) + 0.75(0.3EX - EY + EZ) + 0.75L + 0.75L_
106  sLCB106 (D + T2) + 0.75(0.3EX - EY - EZ) + 0.75L + 0.75L_
107  sLCB107 (D + T2) + 0.75(-0.3EX + EY + EZ) + 0.75L + 0.75L_
108  sLCB108 (D + T2) + 0.75(-0.3EX + EY - EZ) + 0.75L + 0.75L_
109  sLCB109 (D + T2) + 0.75(-0.3EX - EY + EZ) + 0.75L + 0.75L_
110  sLCB110 (D + T2) + 0.75(-0.3EX - EY - EZ) + 0.75L + 0.75L_
111  sLCB111 0.6(D + T2) + WX
112  sLCB112 0.6(D + T2) - WX
113  sLCB113 0.6(D + T2) + WY
114  sLCB114 0.6(D + T2) - WY
115  sLCB115 0.6(D + T2) + EX + 0.3EY + EZ
116  sLCB116 0.6(D + T2) + EX + 0.3EY - EZ
117  sLCB117 0.6(D + T2) + EX - 0.3EY + EZ
118  sLCB118 0.6(D + T2) + EX - 0.3EY - EZ
119  sLCB119 0.6(D + T2) - EX + 0.3EY + EZ
120  sLCB120 0.6(D + T2) - EX + 0.3EY - EZ
121  sLCB121 0.6(D + T2) - EX - 0.3EY + EZ
122  sLCB122 0.6(D + T2) - EX - 0.3EY - EZ
123  sLCB123 0.6(D + T2) + 0.3EX + EY + EZ
124  sLCB124 0.6(D + T2) + 0.3EX + EY - EZ
125  sLCB125 0.6(D + T2) + 0.3EX - EY + EZ
126  sLCB126 0.6(D + T2) + 0.3EX - EY - EZ
127  sLCB127 0.6(D + T2) - 0.3EX + EY + EZ
128  sLCB128 0.6(D + T2) - 0.3EX + EY - EZ
129  sLCB129 0.6(D + T2) - 0.3EX - EY + EZ
130  sLCB130 0.6(D + T2) - 0.3EX - EY - EZ
131  sLCB131 (D + T2) + L + L_EM

Revisión F 272
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-006

132  sLCB132 (D + T2) + 0.75L + 0.75L_EM + 0.75Lr


133  sLCB133 D
134  sLCB134 D + L + L_
135  sLCB135 D + Lr
136  sLCB136 D + 0.75L + 0.75L_ + 0.75Lr
137  sLCB137 D + WX
138  sLCB138 D - WX
139  sLCB139 D + WY
140  sLCB140 D - WY
141  sLCB141 D + EX + 0.3EY + EZ
142  sLCB142 D + EX + 0.3EY - EZ
143  sLCB143 D + EX - 0.3EY + EZ
144  sLCB144 D + EX - 0.3EY - EZ
145  sLCB145 D - EX + 0.3EY + EZ
146  sLCB146 D - EX + 0.3EY - EZ
147  sLCB147 D - EX - 0.3EY + EZ
148  sLCB148 D - EX - 0.3EY - EZ
149  sLCB149 D + 0.3EX + EY + EZ
150  sLCB150 D + 0.3EX + EY - EZ

151  sLCB151 D + 0.3EX - EY + EZ


152  sLCB152 D + 0.3EX - EY - EZ

153  sLCB153 D - 0.3EX + EY + EZ


154  sLCB154 D - 0.3EX + EY - EZ

155  sLCB155 D - 0.3EX - EY + EZ


156  sLCB156 D - 0.3EX - EY - EZ

157  sLCB157 D + 0.75WX + 0.75L + 0.75L_ + 0.75Lr


158  sLCB158 D - 0.75WX + 0.75L + 0.75L_ + 0.75Lr
159  sLCB159 D + 0.75WY + 0.75L + 0.75L_ + 0.75Lr
160  sLCB160 D - 0.75WY + 0.75L + 0.75L_ + 0.75Lr
161  sLCB161 D + 0.75(EX + 0.3EY + EZ) + 0.75L + 0.75L_

Revisión F 273
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-006

162  sLCB162 D + 0.75(EX + 0.3EY - EZ) + 0.75L + 0.75L_


163  sLCB163 D + 0.75(EX - 0.3EY + EZ) + 0.75L + 0.75L_
164  sLCB164 D + 0.75(EX - 0.3EY - EZ) + 0.75L + 0.75L_
165  sLCB165 D + 0.75(-EX + 0.3EY + EZ) + 0.75L + 0.75L_
166  sLCB166 D + 0.75(-EX + 0.3EY - EZ) + 0.75L + 0.75L_
167  sLCB167 D + 0.75(-EX - 0.3EY + EZ) + 0.75L + 0.75L_
168  sLCB168 D + 0.75(-EX - 0.3EY - EZ) + 0.75L + 0.75L_
169  sLCB169 D + 0.75(0.3EX + EY + EZ) + 0.75L + 0.75L_
170  sLCB170 D + 0.75(0.3EX + EY - EZ) + 0.75L + 0.75L_
171  sLCB171 D + 0.75(0.3EX - EY + EZ) + 0.75L + 0.75L_
172  sLCB172 D + 0.75(0.3EX - EY - EZ) + 0.75L + 0.75L_
173  sLCB173 D + 0.75(-0.3EX + EY + EZ) + 0.75L + 0.75L_
174  sLCB174 D + 0.75(-0.3EX + EY - EZ) + 0.75L + 0.75L_
175  sLCB175 D + 0.75(-0.3EX - EY + EZ) + 0.75L + 0.75L_
176  sLCB176 D + 0.75(-0.3EX - EY - EZ) + 0.75L + 0.75L_
177  sLCB177 0.6D + WX
178  sLCB178 0.6D - WX
179  sLCB179 0.6D + WY
180  sLCB180 0.6D - WY
181  sLCB181 0.6D + EX + 0.3EY + EZ
182  sLCB182 0.6D + EX + 0.3EY - EZ
183  sLCB183 0.6D + EX - 0.3EY + EZ
184  sLCB184 0.6D + EX - 0.3EY - EZ
185  sLCB185 0.6D - EX + 0.3EY + EZ
186  sLCB186 0.6D - EX + 0.3EY - EZ
187  sLCB187 0.6D - EX - 0.3EY + EZ
188  sLCB188 0.6D - EX - 0.3EY - EZ
189  sLCB189 0.6D + 0.3EX + EY + EZ
190  sLCB190 0.6D + 0.3EX + EY - EZ
191  sLCB191 0.6D + 0.3EX - EY + EZ

Revisión F 274
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-006

192  sLCB192 0.6D + 0.3EX - EY - EZ


193  sLCB193 0.6D - 0.3EX + EY + EZ
194  sLCB194 0.6D - 0.3EX + EY - EZ
195  sLCB195 0.6D - 0.3EX - EY + EZ
196  sLCB196 0.6D - 0.3EX - EY - EZ
197  sLCB197 D + L + L_EM
198  sLCB198 D + 0.75L + 0.75L_EM + 0.75Lr

Note: Due the Silo's double symmetry, it's not necessary to consider the seismic 30% combination
rule for the plate allowable stresses checking.

Note 2: It's allowed to not consider the seismic 30% combination for structure and foundations design,
if a more detailed seismic directionality analysis show that this effect is irrelevant.

Revisión F 275
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-006

4. STRUCTURAL SYSTEM
4.1 Structural System and Analysis Condition
The seismic force-resisting system is Concentrically Braced Frame (CBF). A braced frame is
subjected primarily to axial forces.
Structural analysis program use SAP 2000. It’s performed to analyze three dimension structural
systems for checking serviceability of this structure on lateral load, designing column, beam and
brace.
4.1.1 Boundary Conditions
The boundary condition of column at ground level will be defined as a pinned connection in all the
Concetrical Braced Frames Structures.

If Necessary to define a Moment Frame Structure to Comply the Process Requirements, the boundary
condition of column at ground level will be defines as a semi-rigid moment connection in both
horizontal translational degrees of freedoms.

The semi – rigid condition is defined as a rotational spring with an associated rotational stiffness
according to the base plate and anchor bolts configuration, in order to determine this value it will be
necessary to build a detailed model of the column base and the anchor configuration.

4.1.2 Connection Condition between Silo Casing and Structure


The connection between Silo and it Support Structure will be a sliding support with the gap length
defined according to the Thermal Loads displacements.

After that, the gap length will be checked for the earthquake loads displacements, if these
displacements are larger than the gap length the entire seismic load of the Casing will be transferred
to the support structure so the structure must be design as if the connection with de Silo were a fixed
(Non Sliding) connection.

4.1.3 Structural Element


- One dimensional element for steel structure modeling purposes as follows:
Korea Standard Section
Material = Steel KS D 3503 : SS400, Steel KS D 3515 : SM490

Revisión F 276
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-006

- Shell element for SILO casing modeling purposes as follows:


Material = Steel KS D 3503 : SS400 (See section 2.2)

Revisión F 277
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-006

Revisión F 278
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-006

4.2 Base Plate and Anchor System

Column reaction resulting from the structural analysis shall be used for the design of base plates and
anchor bolts. Column base plate and anchor bolts shall be designed as per ACI 318-08 and AISC
360-05.
Base plate is made to transfer the column loads and moments to the footings and foundations. Anchor
rods are designed to provide the required resistance to loads which result from load combination
stipulated in Section 3.7.
The requirement that anchor bolts of columns shall have a projection of at least eight diameters and
no less than 250 mm measured from the base plates (according to Section 8.6.2 of NCh 2369),
provides adequate anchor bolts length to eventually allow for yielding of the anchor bolt under severe
earthquake loading.

Typical Detail of Column Base in Figure A.1 of NCh 2369 of 2003

Revisión F 279
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-006

5. STRUCTURAL ANALYSIS
5.1 Base Shear and Equivalent Mass
These results are calculated by the analysis model for earthquake load.
If the base shear force is lower than the minimum base shear (0.12 X total weight), the scale-up factor
(12% of total weight / base shear) should be applied for earthquake load according to the Section
5.4.5 of NCh 2369 of 2003.

5.1.1 Mass Distribution


The self-weight is converted into masses automatically in SAP2000 program.
Seismic mass percentages are considered according to Technical Specification.
It shall be considered the following percentage of seismic mass for live load:

Section Seismic Mass Percentage (%)

Area of Normal Use, Floor Live Load 25

Roof without Transit 0

Silos 100

5.2 Natural Vibration Mode


These results are calculated by the analysis model. The analysis shall include a sufficient number of
vibration modes for the sum of equivalent masses in each analysis direction is equal to or higher than
90% of the total mass.

5.3 Support Reaction


These results are calculated by the analysis model in three directions.

Since the earthquake load was computed trough a Response Spectrum Analysis, its reactions are
absolute values. In order to design the foundations of this structure it is necessary to assign the sign
for each reaction according to the predominant modal shapes in the respective direction.

Revisión F 280
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-006

5.4 Displacement

5.4.1 Displacement due to the Earthquake Load

The displacement for earthquake load can verified according to the Section 6.1 and 6.3.
d = d0 + R1dd
Where,
d = Seismic Deformation
dd = Deformation due to non-seismic service loads
R1 = Factor resulting from multiplying the R factor derived from Table 5.6 of NCh 2369 of 2003 by the
quotient Q0/Qmin provided that Q0/Qmin ne lower or equal to 1.0. However, for the quotient
Q0/Qmin a value under 0.5 shall not be used. If this quotient is higher than 1.0, R1 =R shall be
used.

The maximum seismic deformation for other structures is below:


dmax = 0.015 h
Where,
h = Height between floors of between two points located on the same vertical.

5.4.2 Separation between Structures

The separation between structures is calculated based on section 6.2 of NCh 2369. The purpose of
preventing impacts between adjoining structures, their separation shall be bigger than the highest of
the following values:

1) S = ((R1i ddi)2 + (R1j ddj)2)1/2 + d0i + d0j


2) S = 0.002 (hi + hj)
3) 30mm

Where, ddi, ddj : Deformation calculated with R-factor reduced earthquake load of the structures i and j
d0i, d0j : Deformation due to non-seismic service loads
R1i ,R1j : Response modification factors R1 used for the design of the structures i and j
hi, hj : Height at the considered level of the structures I and j measured from their respective
base levels

Revisión F 281
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-006

6. MEMBER DESIGN
The design of steel structures shall comply with “Earthquake-Resistant Design of Industrial Structures
and Facilities NCh 2369” and “Specification for Structural Steel Buildings AISC 360-05”.
The maximum slenderness can be considered in the design:

Element kl / r

Columns 1.5π√(E/Fy)
Other Elements in Compression 1.5π√(E/Fy)
Element in Traction 240
Bracing Resisting Seismic Load 1.5π√(E/Fy)

Member design was checked about all members of column, beam and brace and so on. On this
report, attached calculation note is about what the worst case of the load combination cases each
member.

Revisión F 282
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-006

6.1 Column Design

6.1.1 Design Load


Load from LRFD Combination
- Pr : Maximum Axial Force
- Mr : Maximum Bending Moment
- Vr : Maximum Shear Force

6.1.2 Schematic Drawing

6.1.3 Verification (AISC360-05, NCh 2369)


1) Slenderness Ratio
- KL / r < 1.5π√(E/Fy)......(OK)
2) Seismic Width-Thickness
- λf = bf / 2tf < λps (for flange)......(OK)
- λw = h / tw < λps (for web)......(OK)
3) Axial Strength
- Pr / Pc < 1.0......(OK)
4) Bending Strength
- Mrx / Mcx < 1.0......(OK)
- Mry / Mcy < 1.0......(OK)
5) Combined Strength (Compression + Bending)
- For Pr / Pc ≥ 0.2 => Rmax = Pr / Pc + 8/9 X (Mrx / Mcx + Mry / Mcy) < 1.0......(OK)
- For Pr / Pc < 0.2 => Rmax = Pr / 2Pc + (Mrx / Mcx + Mry / Mcy) < 1.0......(OK)
6) Shear Strength
- Vrx / Vcx < 1.0......(OK)
- Vry / Vcy < 1.0......(OK)

Revisión F 283
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-006

Where,
λps : Limiting Width-Thickness Ratio
Pc : Design Compressive Strength
Mc : Design Flexural Strength
Vc : Design Shear Strength

Revisión F 284
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-006

6.2 Beam and Girder Design

6.2.1 Design Load


Load from LRFD Combination
- Pr : Maximum Axial Force
- Mr : Maximum Bending Moment
- Vr : Maximum Shear Force

6.2.2 Schematic Drawing

6.2.3 Verification (AISC360-05, NCh 2369)


1) Slenderness Ratio
- KL / r < 1.5π√(E/Fy)......(OK)
2) Seismic Width-Thickness
- λf = bf / 2tf < λps (for flange)......(OK)
- λw = h / tw < λps (for web)......(OK)
3) Axial Strength
- Pr / Pc < 1.0......(OK)
4) Bending Strength
- Mrx / Mcx < 1.0......(OK)
- Mry / Mcy < 1.0......(OK)
5) Combined Strength (Compression + Bending)
- For Pr / Pc ≥ 0.2 => Rmax = Pr / Pc + 8/9 X (Mrx / Mcx + Mry / Mcy) < 1.0......(OK)
- For Pr / Pc < 0.2 => Rmax = Pr / 2Pc + (Mrx / Mcx + Mry / Mcy) < 1.0......(OK)
6) Shear Strength
- Vrx / Vcx < 1.0......(OK)
- Vry / Vcy < 1.0......(OK)

Revisión F 285
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-006

Where,
λps : Limiting Width-Thickness Ratio
Pc : Design Compressive Strength
Mc : Design Flexural Strength
Vc : Design Shear Strength

Revisión F 286
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-006

6.3 Brace Design

6.3.1 Design Load


Load from LRFD Combination
- Pr : Maximum Axial Force
- Mr : Maximum Bending Moment
- Vr : Maximum Shear Force

6.3.2 Schematic Drawing

6.3.3 Verification (AISC360-05, NCh 2369)


1) Slenderness Ratio
- KL / r < 1.5π√(E/Fy)......(OK)
2) Seismic Width-Thickness
- λf = bf / 2tf < λps (for flange)......(OK)
- λw = h / tw < λps (for web)......(OK)
3) Axial Strength
- Pr / Pc < 0.8......(OK)
4) Bending Strength
- Mrx / Mcx < 0.8......(OK)
- Mry / Mcy < 0.8......(OK)
5) Combined Strength (Compression + Bending)
- For Pr / Pc ≥ 0.2 => Rmax = Pr / Pc + 8/9 X (Mrx / Mcx + Mry / Mcy) < 0.8......(OK)
- For Pr / Pc < 0.2 => Rmax = Pr / 2Pc + (Mrx / Mcx + Mry / Mcy) < 0.8......(OK)
6) Shear Strength
- Vrx / Vcx < 0.8......(OK)
- Vry / Vcy < 0.8......(OK)

Revisión F 287
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-006

Where,
λps : Limiting Width-Thickness Ratio
Pc : Design Compressive Strength
Mc : Design Flexural Strength
Vc : Design Shear Strength

Revisión F 288
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-006

6.4 Connection Design

6.4.1 Column Splice

6.4.1.1 Design Load


Full Capacity of Column
- Pu : Maximum Axial Force (= Φ Fy Ag)
- Mu : Maximum Bending Moment (= Φ Fy Zx)
- Vu : Maximum Shear Force (= 0.6 Φ Fy Aw)
- Tu : Maximum Tensile Force at Flange (=Mu / Arm of Column)

6.4.1.2 Schematic Drawing

6.4.1.3 Verification (AISC360-05)


1) Bolt Strength
- Shear Strength ΦRn1 = Φ Ns Fn Ab
- Bearing Strength at Bolt Holes ΦRn2 = Min (Φ 1.2 Lc t Fu, Φ 2.4 d t Fu)
- Slip-Critical Connections ΦRn3 = Φ μ Du hsc Tb Ns
- ΦRn = Min (ΦRn1, ΦRn2, ΦRn3)
- Pu / ΦRn < Number of Bolt......(OK)
- Vu / ΦRn < Number of Bolt......(OK)
- Tu / ΦRn < Number of Bolt......(OK)
2) Web Splice Plate Verification
- Shear Yielding Φ 0.6 Fy Ag ≥ Vu......(OK)

Revisión F 289
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-006

- Shear Rupture Φ 0.6 Fu Anv ≥ Vu......(OK)


3) Flange Splice Plate Verification
- Tensile Yielding Φ Fy Ag ≥ Tu......(OK)
- Tensile Rupture Φ Fu Ae ≥ Tu......(OK)

Revisión F 290
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-006

6.4.2 Beam Connection

6.4.2.1 Design Load


1) Special Earthquake Load Combination
- Ru1 is determined due to the 1.2D + 0.5L + ΩE
2) 0.5 X Full Capacity for Shear
- Ru2 = 0.5 Φ 0.6 Fy Aw Cv
3) Ru = Max (Ru1, Ru2)
4) If the load from brace are transferred to the girder and beam directly, the connection would be
designed by full capacity of brace.

6.4.2.2 Schematic Drawing

6.4.2.3 Verification (AISC360-05)


1) Bolt Strength
- Shear Strength ΦRn1 = Φ Ns Fn Ab
- Bearing Strength at Bolt Holes ΦRn2 = Min (Φ 1.2 Lc t Fu, Φ 2.4 d t Fu)
- Slip-Critical Connections ΦRn3 = Φ μ Du hsc Tb Ns
- ΦRn = Min (ΦRn1, ΦRn2, ΦRn3)
- Ru / ΦRn < Number of Bolt......(OK)
2) Web Splice Plate Verification
- Shear Yielding Φ 0.6 Fy Ag ≥ Ru......(OK)
- Shear Rupture Φ 0.6 Fu Anv ≥ Ru......(OK)
3) Block Shear Rupture Verification
- Φ (0.6 Fu Anv + Ubs Fu Ant) ≥ Ru......(OK)
- Φ (0.6 Fy Agv + Ubs Fu Ant) ≥ Ru......(OK)

Revisión F 291
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-006

6.4.3 Brace to Gusset Connection

6.4.3.1 Design Load


Full Capacity of Brace
- Tu : Maximum Tensile Force (= Ry Fy Ag)
- Pu : Maximum Compressive Force (= 1.1 Ry Pn)
- Ruw : Force in Web
- Ruf : Force in Flange

6.4.3.2 Schematic Drawing


In case of H-Shape Brace In case of Channel Brace

6.4.3.3 Verification in case of H-Shape Brace (AISC360-05)


1) Bolt Strength
- Shear Strength ΦRn1 = Φ Ns Fn Ab
- Bearing Strength at Bolt Holes ΦRn2 = Min(Φ 1.2 Lc t Fu, Φ 2.4 d t Fu)
- Slip-Critical Connections ΦRn3 = Φ μ Du hsc Tb Ns
- ΦRn = Min(ΦRn1, ΦRn2, ΦRn3)
- Ruf / ΦRn < Number of Bolt......(OK)
- Ruw / ΦRn < Number of Bolt......(OK)

Revisión F 292
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-006

2) Tension Capacity of the Angles


- Tension Yielding Φ Fy Ag ≥ Ruf / 2......(OK)
Φ Fy Ag ≥ Ruw......(OK)
- Tension Rupture Φ Fu Ae ≥ Ruf / 2......(OK)
Φ Fu Ae ≥ Ruw......(OK)
3) Block Shear Rupture Verification of the Angles
- Φ (0.6 Rt Fu Anv + Ubs Rt Fu Ant) ≥ Ruf / 2......(OK)
- Φ (0.6 Ry Fy Agv + Ubs Rt Fu Ant) ≥ Ruf / 2......(OK)
- Φ (0.6 Rt Fu Anv + Ubs Rt Fu Ant) ≥ Rw......(OK)
- Φ (0.6 Ry Fy Agv + Ubs Rt Fu Ant) ≥ Rw......(OK)

6.4.3.4 Verification in case of Channel Brace (AISC360-05)


1) Bolt Strength
- Shear Strength ΦRn1 = Φ Ns Fn Ab
- Bearing Strength at Bolt Holes ΦRn2 = Min(Φ 1.2 Lc t Fu, Φ 2.4 d t Fu)
- Slip-Critical Connections ΦRn3 = Φ μ Du hsc Tb Ns
- ΦRn = Min(ΦRn1, ΦRn2, ΦRn3)
- Tu / ΦRn < Number of Bolt......(OK)
2) Net Section Fracture
- Φt Rt Fu Ae ≥ Tu......(OK)
3) Block Shear Rupture Verification of the Angles
- Φ (0.6 Rt Fu Anv + Ubs Rt Fu Ant) ≥ Tu......(OK)
- Φ (0.6 Ry Fy Agv + Ubs Rt Fu Ant) ≥ Tu......(OK)

Revisión F 293
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-006

6.4.4 Gusset Plate Design

6.4.4.1 Design Load


Full Capacity of Brace
- Tu : Maximum Tensile Force (= Ry Fy Ag)
- Pu : Maximum Compressive Force (= 1.1 Ry Pn)

6.4.4.2 Schematic Drawing


Concept Drawing Design Force of Gusset Plate

Whitmore Section of Gusset Plate

6.4.4.3 Verification (AISC360-05)


1) Design the Weld at the Gusset-Column Interface

Revisión F 294
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-006

- fv = Huc / 2β
- fa = Vuc / 2β
- fb = 0
- fpeak = √[fv2 + (fa + fb)2]
- favg = (1/2) × {√[(fa - fb)2 + fv2] +√[(fa + fb)2+ fv2]}
- fr = 1.25 X favg (If fpeak / favg < 1.25)
- fr = fpeak (If fpeak / favg ≥ 1.25)
- s ≥ fr / (0.7 (0.9) (0.6) Fy (2))......(OK)
- tmin (=2 (0.9) (0.6) Fy 0.7s / (0.75 (0.6) Fu) < thickness of gusset plate......(OK)
2) Yielding of Gusset Plate
- ΦRn (=Φ Fy t) > MAX.(fv,fa)......(OK)
3) Column Web Yielding
- ΦRn (=Φ Fy tw) > fr......(OK)
4) Column Web Crippling
- ΦRn = Φ 0.8 tw2 [1 + 3(N / d) (tw / tf)1.5] √(E Fyw tf / tw) > Huc......(OK)
5) Design the Weld at the Gusset-Beam Interface (In Tension and Compression)
- fv = Hub / 2α
- fa = Vub / 2α
- fb = Mub / Sw (Sw = (2α)2 / 6)
- fpeak = √[fv2 + (fa + fb)2]
- favg = (1/2) × {√[(fa - fb)2 + fv2] +√[(fa + fb)2+ fv2]}
- fr = 1.25 X favg (If fpeak / favg < 1.25)
- fr = fpeak (If fpeak / favg ≥ 1.25)
- s ≥ fr / (0.7 (0.9) (0.6) Fy (2))......(OK)
- tmin (=2 (0.9) (0.6) Fy 0.7s / (0.75 (0.6) Fu) < thickness of gusset plate......(OK)
6) Yielding of Gusset Plate
- ΦRn (=Φ Fy t) > MAX.(fv,fa)......(OK)
7) Beam Web Yielding
- ΦRn (=Φ Fy tw) > fr......(OK)
8) Beam Web Local Yielding (if the brace connection is located in center of girder)
- ft = fa + fb
- fc = fa – fb
- Lt = [ft / (ft + tc)] / Lg
- Ru = (1/2) Lt ft
- ΦRn = (5k + N) Fyw tw

Revisión F 295
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-006

- Ru < ΦRn......(OK)
9) Beam Web Crippling
- Ru = [Mub / (N2 / 4)] (N / 2) + Vub = 2Mub / N + Vub
- ΦRn = Φ 0.4 tw2 [1 + 3(N / d) (tw / tf)1.5] √(E Fyw tf / tw) (N/d ≤ 0.2)
- ΦRn = Φ 0.4 tw2 [1 + (4N / d - 0.2) (tw / tf)1.5] √(E Fyw tf / tw) (N/d > 0.2)
- Ru < ΦRn......(OK)
10) Beam Web Crippling (if the brace connection is located in center of girder)
- Ru = (1/2) (Lg - Lt) fc
- ΦRn = Φ 0.8 tw2 [1 + 3(N / d) (tw / tf)1.5] √(E Fyw tf / tw)
- Ru < ΦRn......(OK)
11) Compression Buckling of Gusset Plate
- Φc Fcr Ag > Pu......(OK) (The Ag should be considered whitmore section)
12) Tensile Yielding of Gusset Plate
- Φt Fy Ag > Tu X Ratio of Resisting Bolt......(OK) (The Ag should be considered whitmore section)

Revisión F 296
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-006

6.5 Base Plate and Anchor Bolt Design

6.5.1 Design Load


Load from LRFD Combination
- Pu : Maximum Compressive Force
- Tu : Maximum Tensile Force
- Mu : Maximum Bending Moment
- Vu : Maximum Shear Force

6.5.2 Schematic Drawing

6.5.3 Verification (AISC360-05, ACI318-08)


1) Bearing Stress of Base Plate
- Fp = 0.85 Φ fc √(A2 / A1)
- fp = Pu (1+6e / (N or B)) / A (In case of e < (N or B) / 6)
- fp < Fp......(OK)
2) Thickness of Base Plate
- t1 = √ (ß x fp x u2 / 1.5 Fy) (ß : derived by Roak’s Table)
- t2 = √ (ß x fp x (B / 2)2 / 1.5 Fy) (ß : derived by Roak’s Table)
- t > Max.(t1,t2) ......(OK)
3) Embedded Depth and Width of the Shear Key
- Φ Vn = 0.85 Φ fc A > Vu......(OK)
4) Thickness of Shear Key
- treq = √ (ß x fp x Max(W/2-t/2, d+G)2 / 1.5 Fy) (ß : derived by Roak’s Table)
- treq > t ......(OK)

Revisión F 297
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-006

5) Bearing Strength of the Concrete


- Fp = 0.85 Φ fc √(A2 / A1)
- fp = Vu / (W X d)
- fp < Fp......(OK)
6) Anchor Bolt Verification
- Tension Strength : 0.75 Φ Nn = 0.75 Φ n Ase Fut > Tu......(OK)
- Tb = (Tu / 2 + (Mbuilt-in / (d-d’)) / Number of Bolt
- Ase,req = Tu / (0.75 Φ Tb) < Ase......(OK)
- Concrete Breakout Strength : Ncb = ANc / ANco x ψed,N x ψc,N x ψcp,N x Nb > Tu......(OK)
7) Design of Rib Plate
- Height of Rib Plate : 8d of 250mm
- Ru : Reaction due to the anchor bolt full capacity
- Φ Pn = Φ Ag Fcr > Ru......(OK)
- fa : Axial Stress due to the concrete pressure
- Fc > fa......(OK)
8) Design of Upper Plate
M : Bending Moment due to the anchor bolt full capacity
- Φ Fy Z = Φ Fy u t2 / 4 > M......(OK)
9) Design of Anchor Plate
M : Bending Moment due to the anchor bolt full capacity
- Φ Fy Z = Φ Fy u t2 / 4 > M......(OK)

Revisión F 298
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-006

6.6 Connection between SILO and Structure

6.6.1 Design Load


Load from LRFD Combination
- Pu : Maximum Compressive Force
- Tu : Maximum Tensile Force
- Vu : Maximum Shear Force

6.6.2 Schematic Drawing

6.6.3 Verification (AISC360-05, NCh 2369)


1) Bolt Strength
- Shear Strength ΦRn1 = Φ Ns Fnv Ab
- Bearing Strength at Bolt Holes ΦRn2 = Min (Φ 1.0 Lc t Fu, Φ 2.0 d t Fu)
- ΦRn = Min (ΦRn1, ΦRn2)
- Vu / ΦRn < (1/2) X Number of Bolt......(OK)
- Tension Capacity ΦTn1 = Φ Fnt Ab
- Combined Tension and Shear Capacity ΦTn2 = {1.3 Fnt – (Fnt / Φ Fnv) fv} Ab
- ΦTn = Min (ΦTn1, ΦTn2)
- Tu / ΦTn < (1/2) X Number of Bolt......(OK)
2) Gap Size of Bolt Hole
- by temperature : δ = α (∆T) DSILO < Gap Size......(OK)
- If the relative displacement at the sliding support due to earthquake loading is larger than the

Revisión F 299
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-006

available gap of bolt hole, the analysis model should be modified only for earthquake load case as
fixed support.
3) Bearing Strength of Sliding Pad
- 0.9 fc A > Pu......(OK)
4) Beam Web Crippling
- ΦRn = Φ 0.8 tw2 [1 + 3(N / d) (tw / tf)1.5] √(E Fyw tf / tw) > Pu......(OK)
5) Beam Web Local Yielding
- ΦRn = (5k + N) Fyw tw > Pu......(OK)

Revisión F 300
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-006

7. CASING CALCULATION NOTE

Revisión F 301
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-006

7.1 SILO Casing Design

7.1.1 Design Load


Load from ASD Combination

7.1.2 Schematic Drawing

7.1.3 Verification (NCh 2369, EN 1991-4, EN 1993-4-1)


1) Effective Stress
- σe < 0.6 x Fy......(OK) (σe derived by analysis modeling)
2) Combined Compressive Stress
- σcr = 135 Fy x t / D < 0.8 Fy
- σc < σcr......(OK) (σc derived by analysis modeling)
3) Design of Transition Junctions and Supporting Ring Girders
- σ < 0.6 x Fy......(OK) (σ derived by analysis modeling, effective stress)

Revisión F 302
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-001

ANEXO 6: CRITERIOS DE DISEÑO ESPECIFICOS PARA DISEÑO


DE DUCTOS

303 de 392

Revisión F
DESIGN CRITERIA FOR DUCT SUPPORT TOTAL 89 HOJAS
STRUCTURE AND CASING (Incluyendo Portada)

PROPOSITO

Para Revisión
 NOMBRE CONTRATO EPC POR EL SISTEMA DE
PROYECTO DESULFURIZACION DE GASES - FGD - PARA
LA CENTRAL TARAPACÁ Para Aprobación

 NOMBRE FGD CENTRAL TARAPACÁ Para Construcción


SISTEMA
Para Oferta
 N° DOCUMENTO DCTO413-C8-VVT-000-007
Para Información
 TITULO DESIGN CRITERIA FOR DUCT SUPPORT
STRUCTURE AND CASING

 CLIENTE ENDESA S.A.

F 29-12-2014 JCR VBS NCR Para Aprobación

E 22-12-2014 JCR VBS NCR Para Aprobación

D 25-11-2014 JCR VBS NCR Para Aprobación

C 27-10-2014 JCR VBS NCR Para Aprobación

B 30-09-2014 JCR VBS NCR Para Aprobación

A 24-09-2014 JCR VBS NCR Coordinación Interna - - -

PREP. REV. APR. REV. REV. APR.


Rev
FECHA DESCRIPCION
.
STX HI ENDESA S.A.

PROPIETARIO:

CONTRATISTA:
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-007

DESIGN CRITERIA FOR DUCT


SUPPORT STRUCTURE AND CASING

Rev. F

308
Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-007

Contents

1 INTRODUCTION
1.1 Location
1.2 Weather
1.3 Scope

2 STRUCTURAL DESIGN CRITERIA


2.1 Design Code and Reference
2.2 Materials
2.3 Structural Analysis and Design Program

3 DESIGN LOADS
3.1 Dead Load
3.2 Live Load
3.3 Thermal Load
3.4 Pressure Load
3.5 Wind Load
3.6 Earthquake Load
3.7 Load Combination

4 STRUCTURAL SYSTEM
4.1 Structural System and Analysis Condition
4.2 Base Plate and Anchor System

5 STRUCTURAL ANALYSIS
5.1 Base Shear and Equivalent Mass
5.2 Natural Vibration Mode
5.3 Support Reaction
5.4 Displacement
5.5 Displacement of Sliding Support
5.6 Expansion Joint
6 MEMBER DESIGN
6.1 Column Design

309
Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-007

6.2 Beam and Girder Design


6.3 Brace Design
6.4 Connection Design
6.5 Base Plate and Anchor Bolt Design
6.6 Connection between Duct and Structure

7 CASING CALCULATION NOTE


7.1 Duct Casing Design

310
Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-007

1. INTRODUCTION
1.1 Location
The Tarapacá Thermal Power Plant (158 MW), henceforth the Power Plant, owned by Compañía
Eléctrica Tarapacá S.A., hereinafter CELTA S.A or CELTA, is located on the I Region of Chile,
approximately 60km south of Iquique, by the coast, on the area known as Punta Patache.

1.2 Weather
Weather conditions in the sector are as follows:
Barometric Pressure(Average): 1,015 millibars
Ambient Temperature: Maximum 31.3℃, Minimum 8℃
Relative Humidity(Mean): 78%

1.3 Scope
This is design criteria for Duct support structure and casing.

311
Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-007

2. STRUCTURAL DESIGN CRITERIA


The structural design criteria in this report were calculated according to Technical Specification.

2.1 Design Code and Reference


Code Code & Reference Remarks
Earthquake-Resistant Design of Industrial Structures and
NCh 2369 Seismic Design
Facilities
ETG 1015 General Technical Specifications – Seismic Design Seismic Design
NCh 432 Structural Design – Wind Loads Wind Load
Structural Design – General Dispositions and
NCh 3171 Load Combination
Combinations of Load
ASCE 7-05 Minimum Design Loads for Building and Other Structures Load Combination
AISC 360-05 Specification for Structural Steel Buildings Steel Design
Anchoring to
ACI 318-08 Building Code Requirements for Structural Concrete
Concrete
2010 ASME Boiler $ Pressure Vessel Code Section Ⅱ
ASME 2010 Material Properties
Par D : Properties (Metric) Materials
"Standard Specification for Zinc (Hot Galvanized)
ASTM-A123 Coatings on Products Fabricated from Rolled, Pressed
and Forged Steel Shapes, Plates, Bars and Strip".
Fabrication
Pipe Institute "Standard ES-3"
(P.F.I).
ASME B31.2 "Fuel Gas Piping
ASME B31.3 Process Piping
ASTM D4618- Standard Specification for Design and Fabrication of Flue
92 (Reapproved Gas Desulfurization System Components for Protective
2010) Lining Aplication.
ASTM B31.8-
Gas Transmission and Distribution Piping Systems
2003.-
The Structural Design of Air and Gas Ducts of Power
ASCE
Stations and Industrial Boiler Applications

312
Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-007

2.2 Materials
Tensile Modulus of
Standard Symbol Yield Strength Remarks
Strength Elasticity
Structural Steel /
KS D 3503 235 MPa (t ≤ 40mm)
SS 400 400 MPa 200,000 MPa Anchor Bolt / Duct
JIS G 3101 215 MPa (t > 40mm)
Casing
KS D 3515 315 MPa (t ≤ 40mm)
SM490 490 MPa 200,000 MPa Structural Steel
JIS G 3106 295 MPa (t > 40mm)
ASTM A36 250 MPa 400 MPa 200,000 MPa Anchor Bolt

Standard Symbol Nominal Tensile Stress Nominal Shear Stress Remarks


KS B 1010 F10T 736 MPa 392 MPa
High Strength Bolt
ASTM A325 620 MPa 330 MPa
/ Torque Shear Bolt
ASTM A490 780 MPa 414 MPa

* Friction Coefficient 0.35 : Class A surface ( unpainted clean mill scale steel surfaces or surfaces with
Class A coatings on blast-cleaned steel and hot-dipped galvanized and roughened surfaces)
Material properties in operation temperature (180℃) (ASME 2010 U, Y-1, TM-1)

Modulus of
Symbol Yield Strength Tensile Strength Remarks
Elasticity
SS 400 204 MPa 400 MPa 193,200 MPa SA-36

The material properties for determine the required strength of element and connection are included
KBC 2009 (Korean Building Code 2009) section 0713.6.2.

In section 0713.6.2 of KBC 2009 (Original)

313
Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-007

In section 0713.6.2 of KBC 2009 (Translation)

0713.6.2 Material Properties for determine the required strength of member and connection
(1) When estimate the required strength of each member (member or connection) by the provision of
this section, the required strength should be calculated based on the expected yield strength Ry Fy
of connected member. In here, Fy is the minimum yield strength of connected member and Ry is

314
Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-007

the ratio of expected yield strength and minimum yield strength.

(2) The design strength ФRn should be at least the required strength. When estimate the nominal

Strength Rn for fracture and yield state, the expected tensile strength Rt Fu and expected yield
Strength Ry Fy can be used instead of Fu and Fy.
(3) The values of Ry and Rt are in the table 0713.6.1.

<Table 0713.6.1> The values of Ry and Rt for each type of steel

Application Ry Rt
KS SS400, SSC400, SWH400,
KS STK400, STK490, SPSR400, SPSR490, 1.3 1.2
STKN400, STKN490
Structural Rolled Shapes
Steel and Cold Formed KS SM400, SM490, SM520
Steel KS SPAR295, SPAP235, SPAP325, 1.2 1.2
SCW490-CF
KS SHN400, SHN490 1.1 1.1
KS SS400 1.3 1.2
KS SM490, SM490TMC, SM520,
SM520TMC, SM570, SM570TMC, 1.2 1.2
Plate KS SMA400, SMA490, SMA570
KS SN400, SN490 1.1 1.1
HSA800 1.1 1.1

2.3 Structural Analysis and Design Program


Software Program Code & Reference Remarks
3D Static & Dynamic Analysis -
SAP 2000
Member Design

SAFE Foundation Analysis

315
Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-007

3. DESIGN LOADS
3.1 Dead Load (D)
Dead load is the load due to the permanent weight of all structural and nonstructural components of a
construction, including thermal insulation, ladders and others.

Item Density or Load Remark


7,850 kg/m3
Steel SS 400, SM 490
(=76.98 kN/m3)
50 kg/m2
Grating ARRIGONI ARS-5 33 kg/m2.
(=0.49 kN/m2)
100 kg/m3
Insulation -
(=0.98 kN/m3)

3.2 Live Load (L , L_ and Lr)


It shall be included in this load category, the content of tanks, silos, hoppers, ducting, mobile and
transient loads and weight of people, equipment and tools, and other material agglomerations.
Live load is calculated according to Technical Specification.

Item Load Remark


400kg/m2
Offices, Hallways, Stairs (L) -
(= 3.92 kN/m2)
Roof not exposed to traffic 100 kg/m2
-
(Lr) (= 0.98 kN/m2)
Density : 1.0 after SDA and 1.25 before It should not be
SDA (tonf/m3 for structural design) considered the 0.5
Fly Ash (L_)
Fly Ash Load in Horizontal Duct or <45º: factor in load
30% of the Height combination.

3.3 Thermal Load (T)

3.3.1 External Temperature (Te)


Effect of temperature on the structure, due to climatic conditions of the area
Metal structures for temperature variation depends on local conditions, but it will not be less than
±25℃.

3.3.2 Gas Temperature (Tg)


It shall be considered the effect of high temperatures of gas flow, per process. The operation
temperature is 180℃

316
Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-007

3.3.3 Strain due to the Temperature

Where,
α = 1.2×10-5 /℃, coefficient of thermal expansion
∆T = ±25℃ (Steel exposed to ambient)
∆T = +180℃ (Casing which contacts with gas)

3.4 Pressure Load (F)


The pressure load is a negative pressure which generate inside the Duct. The following pressure load
is used.
- Duct Design Pressure: -400 mmH20 ( -0.040 kg/cm2)

317
Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-007

3.5 Wind Load (WX, WY)


Wind load is calculated based on NCh 432 Table 1.

Structures located in open country, facing the ocean, or locations under similar conditions, in the
judgment of the Reviewing Authority

Height above the NCh 432 Chapter 6.5


Basic pressure, q Basic pressure, q
ground ×1.2
[kg/m2] [kPa]
[m] [kPa]
0 70 0.69 0.82
4 70 0.69 0.82
7 95 0.93 1.12
10 106 1.04 1.25
15 118 1.16 1.39
20 126 1.24 1.48
30 137 1.34 1.61
40 145 1.42 1.71
50 151 1.48 1.78
75 163 1.60 1.92
100 170 1.67 2.00
150 182 1.78 2.14
200 191 1.87 2.25
300 209 2.05 2.46

318
Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-007

3.6 Earthquake Load (EX, EY, EZ)

3.6.1 Earthquake Load


The total base shear shall be computed from the expression.
V = C X W ≥ 0.12 W
Where,
V Base shear
C Seismic coefficient, obtained directly from the design spectrum.
W Total seismic weight of the structure or system, computed as the sum of dead load of
structure and equipment

3.6.1.1 Earthquake action for horizontal direction


The design spectrum is calculated based on ETG1015 figure 1.
Applied coefficients are as follows:
Ground Acceleration a/g = 0.4
Response Modification Factors: R = 3.0
Equivalent viscous damping: ζ = 0.02

3.6.1.2 Earthquake action for vertical direction


The vertical earthquake shall be considered according to Section 5.5 of NCh 2369 Standard, with
seismic coefficient equal to 2 A0 / 3g.

319
Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-007

Coordinates of the corner point for a/g = 0.4

ζ T1 T2 A/g
0.005 0.113 0.451 1.472
0.01 0.115 0.461 1.284
0.02 0.119 0.474 1.096
0.03 0.121 0.485 0.984
0.05 0.125 0.499 0.848
0.07 0.128 0.512 0.756
0.10 0.134 0.535 0.656
0.20 0.148 0.591 0.468
Equation of hyperbolic branch:

(T2<=T<=2.5 s)

320
Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-007

3.6.2 Methods of Analysis


In order to compute the forces and displacements in a given structural system when subjected to the
earthquake action, a response spectrum analysis shell be performed.

3.6.3 Number of Modes


The analysis shall include a sufficient number of vibration modes for the sum of equivalent masses in
each analysis direction is equal to or higher than 90% of the total mass.

3.6.4 Mode Superposition


In order to obtain an estimate of the maximum values of any response quantity considered in the
analysis, the maximum values of the corresponding responses computed for the individual mode of
vibration shall be combined with the CQC superposition criterion normally called “Complete Quadratic
Combination”, recommended in Chilean code Section 5.4.4 of NCh 2369.
The following expressions summarize the mode superposition procedure:

Where,
S Modal combination
Si , Sj Maximum values of mode contributions i and j
ζ Damping ratio
Ti, Tj Period of mode i and j

321
Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-007

3.6.5 Coupling of earthquake action for Support Structure


For the case of dynamic analysis, the requirements of Section 5.1.2 of Chilean code NCh 2369
regarding the effect of the combination of the seismic horizontal components effect are applicable.
This requires that the modal shape and frequencies have to be analyzed and if they are found to be
coupled without a clear or predominant directional acceleration input shall be performed instead of
two independent analyses. This can be implemented by carrying out two different three dimensional
analyses; in each of them the earthquake action input (acceleration spectrum ordinates) shall be
100% of the Project Specification design spectrum in on direction plus 30% of the Project
Specification design spectrum in the orthogonal direction.

Point 5.1.2 of NCh-2369 clearly indicates that it is not necessary to combine the horizontal
components of the seismic action, ie can be analyzed separately for earthquake acting in both
directions considered analysis and design with the unfavorable situation.

Exceptions to this rule structures that have significant torsional irregularities, for which it requires rigid
diaphragms own buildings. The situation is important to consider in the corner columns orthogonal
building rigid frames that share these corner columns. In cases like this should be at 100% overlap in
a direction analysis 30% of the analyzes in the other direction and the same for the other direction
relative to the first. This exception should be applied to irregular structured buildings preferably those
based on rigid frames.

3.6.6 Seismic Mass Percentage for Live Load


Seismic mass percentages are considered according to Technical Specification.
It shall be considered the following percentage of seismic mass for live load:

Section Seismic Mass Percentage (%)

Area of Normal Use, Floor Live Load 25

Roof without Transit 0

Ducting 100

322
Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-007

3.7 Load Combination

3.7.1 Basic Load Case


D Dead Load
F Pressure Load
T1 Thermal Load (∆T = +25℃ in case of steel exposed to ambient, ∆T = +180℃ in case of
casing which contacts with gas)
T2 Thermal Load (∆T = -25℃ in case of steel exposed to ambient, ∆T = +180℃ in case of
casing which contacts with gas)
T3 Thermal Load (∆T = +180℃ in case of casing which contacts with gas)
T4 Thermal Load (∆T = -25℃ in case of steel exposed to ambient)
T5 Thermal Load (∆T = -25℃ in case of steel exposed to ambient)
L Live Load
Lr Roof live load not exposed to traffic
L_1 Fly Ash Load
WX Wind Load X direction
WY Wind Load Y direction
EX Earthquake Load X direction
EY Earthquake Load Y direction
EZ Earthquake Load Vertical direction

3.7.2 LRFD Load Combination (for Anchor System and Foundations)


The LRFD load combinations shall take into account the earthquake load in Technical Specification.
Technical Specification considered a nominal load, so it must be amplified by a factor 1.4., as
indicated in the following table

No. Case Name Description


1 uLCB1 1.4(D + F + T1)
2 uLCB2 1.2(D + F + T1) + 1.6L + 1.6 L_ + 0.5Lr
3  uLCB3 1.2(D + F + T1) + 1.6 Lr + 0.5L + L_
4  uLCB4 1.2(D + F + T1) + 1.6 Lr + 0.8WX
5  uLCB5 1.2(D + F + T1) + 1.6 Lr - 0.8WX
6  uLCB6 1.2(D + F + T1) + 1.6 Lr + 0.8WY
7  uLCB7 1.2(D + F + T1) + 1.6 Lr - 0.8WY

323
Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-007

8  uLCB8 1.2(D + F + T1) + 1.6WX + 0.5L + 1.0L_ + 0.5Lr


9  uLCB9 1.2(D + F + T1) - 1.6WX + 0.5L + 1.0L_ + 0.5Lr
10  uLCB10 1.2(D + F + T1) + 1.6WY + 0.5L + 1.0L_ + 0.5Lr
11  uLCB11 1.2(D + F + T1) - 1.6WY + 0.5L + 1.0L_ + 0.5Lr
12  uLCB12 1.2(D + F + T1) + 1.4(1.0EX + 0.3EY + 1.0EZ) + 0.5L + 1.0L_
13  uLCB13 1.2(D + F + T1) + 1.4(1.0EX + 0.3EY - 1.0EZ) + 0.5L + 1.0L_
14  uLCB14 1.2(D + F + T1) + 1.4(1.0EX - 0.3EY + 1.0EZ) + 0.5L + 1.0L_
15  uLCB15 1.2(D + F + T1) + 1.4(1.0EX - 0.3EY - 1.0EZ) + 0.5L + 1.0L_
16  uLCB16 1.2(D + F + T1) - 1.4(1.0EX + 0.3EY + 1.0EZ) + 0.5L + 1.0L_
17  uLCB17 1.2(D + F + T1) - 1.4(1.0EX + 0.3EY - 1.0EZ) + 0.5L + 1.0L_
18  uLCB18 1.2(D + F + T1) - 1.4(1.0EX - 0.3EY + 1.0EZ) + 0.5L + 1.0L_
19  uLCB19 1.2(D + F + T1) - 1.4(1.0EX - 0.3EY - 1.0EZ) + 0.5L + 1.0L_
20  uLCB20 1.2(D + F + T1) + 1.4(0.3EX + 1.0EY + 1.0EZ) + 0.5L + 1.0L_
21  uLCB21 1.2(D + F + T1) + 1.4(0.3EX + 1.0EY - 1.0EZ) + 0.5L + 1.0L_
22  uLCB22 1.2(D + F + T1) + 1.4(0.3EX – 1.0EY + 1.0EZ) + 0.5L + 1.0L_
23  uLCB23 1.2(D + F + T1) + 1.4(0.3EX – 1.0EY - 1.0EZ) + 0.5L + 1.0L_
24  uLCB24 1.2(D + F + T1) - 1.4(0.3EX + 1.0EY + 1.0EZ) + 0.5L + 1.0L_
25  uLCB25 1.2(D + F + T1) - 1.4(0.3EX + 1.0EY - 1.0EZ) + 0.5L + 1.0L_
26  uLCB26 1.2(D + F + T1) - 1.4(0.3EX – 1.0EY + 1.0EZ) + 0.5L + 1.0L_
27  uLCB27 1.2(D + F + T1) - 1.4(0.3EX – 1.0EY - 1.0EZ) + 0.5L + 1.0L_
28  uLCB28 0.9(D + T1) + 1.6WX
29  uLCB29 0.9(D + T1) - 1.6WX
30  uLCB30 0.9(D + T1) + 1.6WY
31  uLCB31 0.9(D + T1) - 1.6WY
32  uLCB32 0.9(D + F + T1) + 1.4(1.0EX + 0.3EY + 1.0EZ)
33  uLCB33 0.9(D + F + T1) + 1.4(1.0EX + 0.3EY - 1.0EZ)
34  uLCB34 0.9(D + F + T1) + 1.4(1.0EX - 0.3EY + 1.0EZ)
35  uLCB35 0.9(D + F + T1) + 1.4(1.0EX - 0.3EY - 1.0EZ)
36  uLCB36 0.9(D + F + T1) - 1.4(1.0EX + 0.3EY + 1.0EZ)
37  uLCB37 0.9(D + F + T1) - 1.4(1.0EX + 0.3EY - 1.0EZ)
38  uLCB38 0.9(D + F + T1) - 1.4(1.0EX - 0.3EY + 1.0EZ)

324
Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-007

39  uLCB39 0.9(D + F + T1) - 1.4(1.0EX - 0.3EY - 1.0EZ)


40  uLCB40 0.9(D + F + T1) + 1.4(0.3EX + 1.0EY + 1.0EZ)
41  uLCB41 0.9(D + F + T1) + 1.4(0.3EX + 1.0EY - 1.0EZ)
42  uLCB42 0.9(D + F + T1) + 1.4(0.3EX – 1.0EY + 1.0EZ)
43  uLCB43 0.9(D + F + T1) + 1.4(0.3EX – 1.0EY - 1.0EZ)
44  uLCB44 0.9(D + F + T1) - 1.4(0.3EX + 1.0EY + 1.0EZ)
45  uLCB45 0.9(D + F + T1) - 1.4(0.3EX + 1.0EY - 1.0EZ)
46  uLCB46 0.9(D + F + T1) - 1.4(0.3EX – 1.0EY + 1.0EZ)
47  uLCB47 0.9(D + F + T1) - 1.4(0.3EX – 1.0EY - 1.0EZ)
48  uLCB48 1.4(D + F + T2)
49  uLCB49 1.2(D + F + T2) + 1.6L + 1.6 L_ + 0.5Lr
50  uLCB50 1.2(D + F + T2) + 1.6 Lr + 0.5L + L_
51  uLCB51 1.2(D + F + T2) + 1.6 Lr + 0.8WX
52  uLCB52 1.2(D + F + T2) + 1.6 Lr - 0.8WX
53  uLCB53 1.2(D + F + T2) + 1.6 Lr + 0.8WY
54  uLCB54 1.2(D + F + T2) + 1.6 Lr - 0.8WY
55  uLCB55 1.2(D + F + T2) + 1.6WX + 0.5L + 1.0L_ + 0.5Lr
56  uLCB56 1.2(D + F + T2) - 1.6WX + 0.5L + 1.0L_ + 0.5Lr
57  uLCB57 1.2(D + F + T2) + 1.6WY + 0.5L + 1.0L_ + 0.5Lr
58  uLCB58 1.2(D + F + T2) - 1.6WY + 0.5L + 1.0L_ + 0.5Lr
59  uLCB59 1.2(D + F + T2) + 1.4(1.0EX + 0.3EY + 1.0EZ) + 0.5L + 1.0L_
60  uLCB60 1.2(D + F + T2) + 1.4(1.0EX + 0.3EY - 1.0EZ) + 0.5L + 1.0L_
61  uLCB61 1.2(D + F + T2) + 1.4(1.0EX - 0.3EY + 1.0EZ) + 0.5L + 1.0L_
62  uLCB62 1.2(D + F + T2) + 1.4(1.0EX - 0.3EY - 1.0EZ) + 0.5L + 1.0L_
63  uLCB63 1.2(D + F + T2) - 1.4(1.0EX + 0.3EY + 1.0EZ) + 0.5L + 1.0L_
64  uLCB64 1.2(D + F + T2) - 1.4(1.0EX + 0.3EY - 1.0EZ) + 0.5L + 1.0L_
65  uLCB65 1.2(D + F + T2) - 1.4(1.0EX - 0.3EY + 1.0EZ) + 0.5L + 1.0L_
66  uLCB66 1.2(D + F + T2) - 1.4(1.0EX - 0.3EY - 1.0EZ) + 0.5L + 1.0L_
67  uLCB67 1.2(D + F + T2) + 1.4(0.3EX + 1.0EY + 1.0EZ) + 0.5L + 1.0L_
68  uLCB68 1.2(D + F + T2) + 1.4(0.3EX + 1.0EY - 1.0EZ) + 0.5L + 1.0L_
69  uLCB69 1.2(D + F + T2) + 1.4(0.3EX – 1.0EY + 1.0EZ) + 0.5L + 1.0L_

325
Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-007

70  uLCB70 1.2(D + F + T2) + 1.4(0.3EX – 1.0EY - 1.0EZ) + 0.5L + 1.0L_


71  uLCB71 1.2(D + F + T2) - 1.4(0.3EX + 1.0EY + 1.0EZ) + 0.5L + 1.0L_
72  uLCB72 1.2(D + F + T2) - 1.4(0.3EX + 1.0EY - 1.0EZ) + 0.5L + 1.0L_
73  uLCB73 1.2(D + F + T2) - 1.4(0.3EX – 1.0EY + 1.0EZ) + 0.5L + 1.0L_
74  uLCB74 1.2(D + F + T2) - 1.4(0.3EX – 1.0EY - 1.0EZ) + 0.5L + 1.0L_
75  uLCB75 0.9(D + T2) + 1.6WX
76  uLCB76 0.9(D + T2) - 1.6WX
77  uLCB77 0.9(D + T2) + 1.6WY
78  uLCB78 0.9(D + T2) - 1.6WY
79  uLCB79 0.9(D + F + T2) + 1.4(1.0EX + 0.3EY + 1.0EZ)
80  uLCB80 0.9(D + F + T2) + 1.4(1.0EX + 0.3EY - 1.0EZ)
81  uLCB81 0.9(D + F + T2) + 1.4(1.0EX - 0.3EY + 1.0EZ)
82  uLCB82 0.9(D + F + T2) + 1.4(1.0EX - 0.3EY - 1.0EZ)
83  uLCB83 0.9(D + F + T2) - 1.4(1.0EX + 0.3EY + 1.0EZ)
84  uLCB84 0.9(D + F + T2) - 1.4(1.0EX + 0.3EY - 1.0EZ)
85  uLCB85 0.9(D + F + T2) - 1.4(1.0EX - 0.3EY + 1.0EZ)
86  uLCB86 0.9(D + F + T2) - 1.4(1.0EX - 0.3EY - 1.0EZ)
87  uLCB87 0.9(D + F + T2) + 1.4(0.3EX + 1.0EY + 1.0EZ)
88  uLCB88 0.9(D + F + T2) + 1.4(0.3EX + 1.0EY - 1.0EZ)
89  uLCB89 0.9(D + F + T2) + 1.4(0.3EX – 1.0EY + 1.0EZ)
90  uLCB90 0.9(D + F + T2) + 1.4(0.3EX – 1.0EY - 1.0EZ)
91  uLCB91 0.9(D + F + T2) - 1.4(0.3EX + 1.0EY + 1.0EZ)
92  uLCB92 0.9(D + F + T2) - 1.4(0.3EX + 1.0EY - 1.0EZ)
93  uLCB93 0.9(D + F + T2) - 1.4(0.3EX – 1.0EY + 1.0EZ)
94  uLCB94 0.9(D + F + T2) - 1.4(0.3EX – 1.0EY - 1.0EZ)
95  uLCB95 1.4(D + F + T3)
96  uLCB96 1.2(D + F + T3) + 1.6L + 1.6 L_ + 0.5Lr
97  uLCB97 1.2(D + F + T3) + 1.6 Lr + 0.5L + L_
98  uLCB98 1.2(D + F + T3) + 1.6 Lr + 0.8WX
99  uLCB99 1.2(D + F + T3) + 1.6 Lr - 0.8WX
100  uLCB100 1.2(D + F + T3) + 1.6 Lr + 0.8WY

326
Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-007

101  uLCB101 1.2(D + F + T3) + 1.6 Lr - 0.8WY


102  uLCB102 1.2(D + F + T3) + 1.6WX + 0.5L + 1.0L_ + 0.5Lr
103  uLCB103 1.2(D + F + T3) - 1.6WX + 0.5L + 1.0L_ + 0.5Lr
104  uLCB104 1.2(D + F + T3) + 1.6WY + 0.5L + 1.0L_ + 0.5Lr
105  uLCB105 1.2(D + F + T3) - 1.6WY + 0.5L + 1.0L_ + 0.5Lr
106  uLCB106 1.2(D + F + T3) + 1.4(1.0EX + 0.3EY + 1.0EZ) + 0.5L + 1.0L_
107  uLCB107 1.2(D + F + T3) + 1.4(1.0EX + 0.3EY - 1.0EZ) + 0.5L + 1.0L_
108  uLCB108 1.2(D + F + T3) + 1.4(1.0EX - 0.3EY + 1.0EZ) + 0.5L + 1.0L_
109  uLCB109 1.2(D + F + T3) + 1.4(1.0EX - 0.3EY - 1.0EZ) + 0.5L + 1.0L_
110  uLCB110 1.2(D + F + T3) - 1.4(1.0EX + 0.3EY + 1.0EZ) + 0.5L + 1.0L_
111  uLCB111 1.2(D + F + T3) - 1.4(1.0EX + 0.3EY - 1.0EZ) + 0.5L + 1.0L_
112  uLCB112 1.2(D + F + T3) - 1.4(1.0EX - 0.3EY + 1.0EZ) + 0.5L + 1.0L_
113  uLCB113 1.2(D + F + T3) - 1.4(1.0EX - 0.3EY - 1.0EZ) + 0.5L + 1.0L_
114  uLCB114 1.2(D + F + T3) + 1.4(0.3EX + 1.0EY + 1.0EZ) + 0.5L + 1.0L_
115  uLCB115 1.2(D + F + T3) + 1.4(0.3EX + 1.0EY - 1.0EZ) + 0.5L + 1.0L_
116  uLCB116 1.2(D + F + T3) + 1.4(0.3EX – 1.0EY + 1.0EZ) + 0.5L + 1.0L_
117  uLCB117 1.2(D + F + T3) + 1.4(0.3EX – 1.0EY - 1.0EZ) + 0.5L + 1.0L_
118  uLCB118 1.2(D + F + T3) - 1.4(0.3EX + 1.0EY + 1.0EZ) + 0.5L + 1.0L_
119  uLCB119 1.2(D + F + T3) - 1.4(0.3EX + 1.0EY - 1.0EZ) + 0.5L + 1.0L_
120  uLCB120 1.2(D + F + T3) - 1.4(0.3EX – 1.0EY + 1.0EZ) + 0.5L + 1.0L_
121  uLCB121 1.2(D + F + T3) - 1.4(0.3EX – 1.0EY - 1.0EZ) + 0.5L + 1.0L_
122  uLCB122 0.9(D + T3) + 1.6WX
123  uLCB123 0.9(D + T3) - 1.6WX
124  uLCB124 0.9(D + T3) + 1.6WY
125  uLCB125 0.9(D + T3) - 1.6WY
126  uLCB126 0.9(D + F + T3) + 1.4(1.0EX + 0.3EY + 1.0EZ)
127  uLCB127 0.9(D + F + T3) + 1.4(1.0EX + 0.3EY - 1.0EZ)
128  uLCB128 0.9(D + F + T3) + 1.4(1.0EX - 0.3EY + 1.0EZ)
129  uLCB129 0.9(D + F + T3) + 1.4(1.0EX - 0.3EY - 1.0EZ)
130  uLCB130 0.9(D + F + T3) - 1.4(1.0EX + 0.3EY + 1.0EZ)
131  uLCB131 0.9(D + F + T3) - 1.4(1.0EX + 0.3EY - 1.0EZ)

327
Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-007

132  uLCB132 0.9(D + F + T3) - 1.4(1.0EX - 0.3EY + 1.0EZ)


133  uLCB133 0.9(D + F + T3) - 1.4(1.0EX - 0.3EY - 1.0EZ)
134  uLCB134 0.9(D + F + T3) + 1.4(0.3EX + 1.0EY + 1.0EZ)
135  uLCB135 0.9(D + F + T3) + 1.4(0.3EX + 1.0EY - 1.0EZ)
136  uLCB136 0.9(D + F + T3) + 1.4(0.3EX – 1.0EY + 1.0EZ)
137  uLCB137 0.9(D + F + T3) + 1.4(0.3EX – 1.0EY - 1.0EZ)
138  uLCB138 0.9(D + F + T3) - 1.4(0.3EX + 1.0EY + 1.0EZ)
139  uLCB139 0.9(D + F + T3) - 1.4(0.3EX + 1.0EY - 1.0EZ)
140  uLCB140 0.9(D + F + T3) - 1.4(0.3EX – 1.0EY + 1.0EZ)
141  uLCB141 0.9(D + F + T3) - 1.4(0.3EX – 1.0EY - 1.0EZ)
142  uLCB142 1.4(D + F + T4)
143  uLCB143 1.2(D + F + T4) + 1.6L + 1.6 L_ + 0.5Lr
144  uLCB144 1.2(D + F + T4) + 1.6 Lr + 0.5L + L_
145  uLCB145 1.2(D + F + T4) + 1.6 Lr + 0.8WX
146  uLCB146 1.2(D + F + T4) + 1.6 Lr - 0.8WX
147  uLCB147 1.2(D + F + T4) + 1.6 Lr + 0.8WY
148  uLCB148 1.2(D + F + T4) + 1.6 Lr - 0.8WY
149  uLCB149 1.2(D + F + T4) + 1.6WX + 0.5L + 1.0L_ + 0.5Lr
150  uLCB150 1.2(D + F + T4) - 1.6WX + 0.5L + 1.0L_ + 0.5Lr
151  uLCB151 1.2(D + F + T4) + 1.6WY + 0.5L + 1.0L_ + 0.5Lr
152  uLCB152 1.2(D + F + T4) - 1.6WY + 0.5L + 1.0L_ + 0.5Lr
153  uLCB153 1.2(D + F + T4) + 1.4(1.0EX + 0.3EY + 1.0EZ) + 0.5L + 1.0L_
154  uLCB154 1.2(D + F + T4) + 1.4(1.0EX + 0.3EY - 1.0EZ) + 0.5L + 1.0L_
155  uLCB155 1.2(D + F + T4) + 1.4(1.0EX - 0.3EY + 1.0EZ) + 0.5L + 1.0L_
156  uLCB156 1.2(D + F + T4) + 1.4(1.0EX - 0.3EY - 1.0EZ) + 0.5L + 1.0L_
157  uLCB157 1.2(D + F + T4) - 1.4(1.0EX + 0.3EY + 1.0EZ) + 0.5L + 1.0L_
158  uLCB158 1.2(D + F + T4) - 1.4(1.0EX + 0.3EY - 1.0EZ) + 0.5L + 1.0L_
159  uLCB159 1.2(D + F + T4) - 1.4(1.0EX - 0.3EY + 1.0EZ) + 0.5L + 1.0L_
160  uLCB160 1.2(D + F + T4) - 1.4(1.0EX - 0.3EY - 1.0EZ) + 0.5L + 1.0L_
161  uLCB161 1.2(D + F + T4) + 1.4(0.3EX + 1.0EY + 1.0EZ) + 0.5L + 1.0L_
162  uLCB162 1.2(D + F + T4) + 1.4(0.3EX + 1.0EY - 1.0EZ) + 0.5L + 1.0L_

328
Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-007

163  uLCB163 1.2(D + F + T4) + 1.4(0.3EX – 1.0EY + 1.0EZ) + 0.5L + 1.0L_


164  uLCB164 1.2(D + F + T4) + 1.4(0.3EX – 1.0EY - 1.0EZ) + 0.5L + 1.0L_
165  uLCB165 1.2(D + F + T4) - 1.4(0.3EX + 1.0EY + 1.0EZ) + 0.5L + 1.0L_
166  uLCB166 1.2(D + F + T4) - 1.4(0.3EX + 1.0EY - 1.0EZ) + 0.5L + 1.0L_
167  uLCB167 1.2(D + F + T4) - 1.4(0.3EX – 1.0EY + 1.0EZ) + 0.5L + 1.0L_
168  uLCB168 1.2(D + F + T4) - 1.4(0.3EX – 1.0EY - 1.0EZ) + 0.5L + 1.0L_
169  uLCB169 0.9(D + T4) + 1.6WX
170  uLCB170 0.9(D + T4) - 1.6WX
171  uLCB171 0.9(D + T4) + 1.6WY
172  uLCB172 0.9(D + T4) - 1.6WY
173  uLCB173 0.9(D + F + T4) + 1.4(1.0EX + 0.3EY + 1.0EZ)
174  uLCB174 0.9(D + F + T4) + 1.4(1.0EX + 0.3EY - 1.0EZ)
175  uLCB175 0.9(D + F + T4) + 1.4(1.0EX - 0.3EY + 1.0EZ)
176  uLCB176 0.9(D + F + T4) + 1.4(1.0EX - 0.3EY - 1.0EZ)
177  uLCB177 0.9(D + F + T4) - 1.4(1.0EX + 0.3EY + 1.0EZ)
178  uLCB178 0.9(D + F + T4) - 1.4(1.0EX + 0.3EY - 1.0EZ)
179  uLCB179 0.9(D + F + T4) - 1.4(1.0EX - 0.3EY + 1.0EZ)
180  uLCB180 0.9(D + F + T4) - 1.4(1.0EX - 0.3EY - 1.0EZ)
181  uLCB181 0.9(D + F + T4) + 1.4(0.3EX + 1.0EY + 1.0EZ)
182  uLCB182 0.9(D + F + T4) + 1.4(0.3EX + 1.0EY - 1.0EZ)
183  uLCB183 0.9(D + F + T4) + 1.4(0.3EX – 1.0EY + 1.0EZ)
184  uLCB184 0.9(D + F + T4) + 1.4(0.3EX – 1.0EY - 1.0EZ)
185  uLCB185 0.9(D + F + T4) - 1.4(0.3EX + 1.0EY + 1.0EZ)
186  uLCB186 0.9(D + F + T4) - 1.4(0.3EX + 1.0EY - 1.0EZ)
187  uLCB187 0.9(D + F + T4) - 1.4(0.3EX – 1.0EY + 1.0EZ)
188  uLCB188 0.9(D + F + T4) - 1.4(0.3EX – 1.0EY - 1.0EZ)
189  uLCB189 1.4(D + F + T5)
190  uLCB190 1.2(D + F + T5) + 1.6L + 1.6 L_ + 0.5Lr
191  uLCB191 1.2(D + F + T5) + 1.6 Lr + 0.5L + L_
192  uLCB192 1.2(D + F + T5) + 1.6 Lr + 0.8WX
193  uLCB193 1.2(D + F + T5) + 1.6 Lr - 0.8WX

329
Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-007

194  uLCB194 1.2(D + F + T5) + 1.6 Lr + 0.8WY


195  uLCB195 1.2(D + F + T5) + 1.6 Lr - 0.8WY
196  uLCB196 1.2(D + F + T5) + 1.6WX + 0.5L + 1.0L_ + 0.5Lr
197  uLCB197 1.2(D + F + T5) - 1.6WX + 0.5L + 1.0L_ + 0.5Lr
198  uLCB198 1.2(D + F + T5) + 1.6WY + 0.5L + 1.0L_ + 0.5Lr
199  uLCB199 1.2(D + F + T5) - 1.6WY + 0.5L + 1.0L_ + 0.5Lr
200  uLCB200 1.2(D + F + T5) + 1.4(1.0EX + 0.3EY + 1.0EZ) + 0.5L + 1.0L_
201  uLCB201 1.2(D + F + T5) + 1.4(1.0EX + 0.3EY - 1.0EZ) + 0.5L + 1.0L_
202  uLCB202 1.2(D + F + T5) + 1.4(1.0EX - 0.3EY + 1.0EZ) + 0.5L + 1.0L_
203  uLCB203 1.2(D + F + T5) + 1.4(1.0EX - 0.3EY - 1.0EZ) + 0.5L + 1.0L_
204  uLCB204 1.2(D + F + T5) - 1.4(1.0EX + 0.3EY + 1.0EZ) + 0.5L + 1.0L_
205  uLCB205 1.2(D + F + T5) - 1.4(1.0EX + 0.3EY - 1.0EZ) + 0.5L + 1.0L_
206  uLCB206 1.2(D + F + T5) - 1.4(1.0EX - 0.3EY + 1.0EZ) + 0.5L + 1.0L_
207  uLCB207 1.2(D + F + T5) - 1.4(1.0EX - 0.3EY - 1.0EZ) + 0.5L + 1.0L_
208  uLCB208 1.2(D + F + T5) + 1.4(0.3EX + 1.0EY + 1.0EZ) + 0.5L + 1.0L_
209  uLCB209 1.2(D + F + T5) + 1.4(0.3EX + 1.0EY - 1.0EZ) + 0.5L + 1.0L_
210  uLCB210 1.2(D + F + T5) + 1.4(0.3EX – 1.0EY + 1.0EZ) + 0.5L + 1.0L_
211  uLCB211 1.2(D + F + T5) + 1.4(0.3EX – 1.0EY - 1.0EZ) + 0.5L + 1.0L_
212  uLCB212 1.2(D + F + T5) - 1.4(0.3EX + 1.0EY + 1.0EZ) + 0.5L + 1.0L_
213  uLCB213 1.2(D + F + T5) - 1.4(0.3EX + 1.0EY - 1.0EZ) + 0.5L + 1.0L_
214  uLCB214 1.2(D + F + T5) - 1.4(0.3EX – 1.0EY + 1.0EZ) + 0.5L + 1.0L_
215  uLCB215 1.2(D + F + T5) - 1.4(0.3EX – 1.0EY - 1.0EZ) + 0.5L + 1.0L_
216  uLCB216 0.9(D + T5) + 1.6WX
217  uLCB217 0.9(D + T5) - 1.6WX
218  uLCB218 0.9(D + T5) + 1.6WY
219  uLCB219 0.9(D + T5) - 1.6WY
220  uLCB220 0.9(D + F + T5) + 1.4(1.0EX + 0.3EY + 1.0EZ)
221  uLCB221 0.9(D + F + T5) + 1.4(1.0EX + 0.3EY - 1.0EZ)
222  uLCB222 0.9(D + F + T5) + 1.4(1.0EX - 0.3EY + 1.0EZ)
223  uLCB223 0.9(D + F + T5) + 1.4(1.0EX - 0.3EY - 1.0EZ)
224  uLCB224 0.9(D + F + T5) - 1.4(1.0EX + 0.3EY + 1.0EZ)

330
Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-007

225  uLCB225 0.9(D + F + T5) - 1.4(1.0EX + 0.3EY - 1.0EZ)


226  uLCB226 0.9(D + F + T5) - 1.4(1.0EX - 0.3EY + 1.0EZ)
227  uLCB227 0.9(D + F + T5) - 1.4(1.0EX - 0.3EY - 1.0EZ)
228  uLCB228 0.9(D + F + T5) + 1.4(0.3EX + 1.0EY + 1.0EZ)
229  uLCB229 0.9(D + F + T5) + 1.4(0.3EX + 1.0EY - 1.0EZ)
230  uLCB230 0.9(D + F + T5) + 1.4(0.3EX – 1.0EY + 1.0EZ)
231  uLCB231 0.9(D + F + T5) + 1.4(0.3EX – 1.0EY - 1.0EZ)
232  uLCB232 0.9(D + F + T5) - 1.4(0.3EX + 1.0EY + 1.0EZ)
233  uLCB233 0.9(D + F + T5) - 1.4(0.3EX + 1.0EY - 1.0EZ)
234  uLCB234 0.9(D + F + T5) - 1.4(0.3EX – 1.0EY + 1.0EZ)
235  uLCB235 0.9(D + F + T5) - 1.4(0.3EX – 1.0EY - 1.0EZ)
236  uLCB236 1.4(D + F)
237  uLCB237 1.2(D + F) + 1.6L + 1.6 L_ + 0.5Lr
238  uLCB238 1.2(D + F) + 1.6 Lr + 0.5L + L_
239  uLCB239 1.2(D + F) + 1.6 Lr + 0.8WX
240  uLCB240 1.2(D + F) + 1.6 Lr - 0.8WX
241  uLCB241 1.2(D + F) + 1.6 Lr + 0.8WY
242  uLCB242 1.2(D + F) + 1.6 Lr - 0.8WY
243  uLCB243 1.2(D + F) + 1.6WX + 0.5L + 1.0L_ + 0.5Lr
244  uLCB244 1.2(D + F) - 1.6WX + 0.5L + 1.0L_ + 0.5Lr
245  uLCB245 1.2(D + F) + 1.6WY + 0.5L + 1.0L_ + 0.5Lr
246  uLCB246 1.2(D + F) - 1.6WY + 0.5L + 1.0L_ + 0.5Lr
247  uLCB247 1.2(D + F) + 1.4(1.0EX + 0.3EY + 1.0EZ) + 0.5L + 1.0L_
248  uLCB248 1.2(D + F) + 1.4(1.0EX + 0.3EY - 1.0EZ) + 0.5L + 1.0L_
249  uLCB249 1.2(D + F) + 1.4(1.0EX - 0.3EY + 1.0EZ) + 0.5L + 1.0L_
250  uLCB250 1.2(D + F) + 1.4(1.0EX - 0.3EY - 1.0EZ) + 0.5L + 1.0L_
251  uLCB251 1.2(D + F) - 1.4(1.0EX + 0.3EY + 1.0EZ) + 0.5L + 1.0L_
252  uLCB252 1.2(D + F) - 1.4(1.0EX + 0.3EY - 1.0EZ) + 0.5L + 1.0L_
253  uLCB253 1.2(D + F) - 1.4(1.0EX - 0.3EY + 1.0EZ) + 0.5L + 1.0L_
254  uLCB254 1.2(D + F) - 1.4(1.0EX - 0.3EY - 1.0EZ) + 0.5L + 1.0L_
255  uLCB255 1.2(D + F) + 1.4(0.3EX + 1.0EY + 1.0EZ) + 0.5L + 1.0L_

331
Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-007

256  uLCB256 1.2(D + F) + 1.4(0.3EX + 1.0EY - 1.0EZ) + 0.5L + 1.0L_


257  uLCB257 1.2(D + F) + 1.4(0.3EX – 1.0EY + 1.0EZ) + 0.5L + 1.0L_
258  uLCB258 1.2(D + F) + 1.4(0.3EX – 1.0EY - 1.0EZ) + 0.5L + 1.0L_
259  uLCB259 1.2(D + F) - 1.4(0.3EX + 1.0EY + 1.0EZ) + 0.5L + 1.0L_
260  uLCB260 1.2(D + F) - 1.4(0.3EX + 1.0EY - 1.0EZ) + 0.5L + 1.0L_
261  uLCB261 1.2(D + F) - 1.4(0.3EX – 1.0EY + 1.0EZ) + 0.5L + 1.0L_
262  uLCB262 1.2(D + F) - 1.4(0.3EX – 1.0EY - 1.0EZ) + 0.5L + 1.0L_
263  uLCB263 0.9(D) + 1.6WX
264  uLCB264 0.9(D) - 1.6WX
265  uLCB265 0.9(D) + 1.6WY
266  uLCB266 0.9(D) - 1.6WY
267  uLCB267 0.9(D + F) + 1.4(1.0EX + 0.3EY + 1.0EZ)
268  uLCB268 0.9(D + F) + 1.4(1.0EX + 0.3EY - 1.0EZ)
269  uLCB269 0.9(D + F) + 1.4(1.0EX - 0.3EY + 1.0EZ)
270  uLCB270 0.9(D + F) + 1.4(1.0EX - 0.3EY - 1.0EZ)
271  uLCB271 0.9(D + F) - 1.4(1.0EX + 0.3EY + 1.0EZ)
272  uLCB272 0.9(D + F) - 1.4(1.0EX + 0.3EY - 1.0EZ)
273  uLCB273 0.9(D + F) - 1.4(1.0EX - 0.3EY + 1.0EZ)
274  uLCB274 0.9(D + F) - 1.4(1.0EX - 0.3EY - 1.0EZ)
275  uLCB275 0.9(D + F) + 1.4(0.3EX + 1.0EY + 1.0EZ)
276  uLCB276 0.9(D + F) + 1.4(0.3EX + 1.0EY - 1.0EZ)
277  uLCB277 0.9(D + F) + 1.4(0.3EX – 1.0EY + 1.0EZ)
278  uLCB278 0.9(D + F) + 1.4(0.3EX – 1.0EY - 1.0EZ)
279  uLCB279 0.9(D + F) - 1.4(0.3EX + 1.0EY + 1.0EZ)
280  uLCB280 0.9(D + F) - 1.4(0.3EX + 1.0EY - 1.0EZ)
281  uLCB281 0.9(D + F) - 1.4(0.3EX – 1.0EY + 1.0EZ)
282  uLCB282 0.9(D + F) - 1.4(0.3EX – 1.0EY - 1.0EZ)
283  uLCB283 1.4(D + T1)
284  uLCB284 1.2(D + T1) + 1.6L + 1.6 L_ + 0.5Lr
285  uLCB285 1.2(D + T1) + 1.6 Lr + 0.5L + L_
286  uLCB286 1.2(D + T1) + 1.6 Lr + 0.8WX

332
Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-007

287  uLCB287 1.2(D + T1) + 1.6 Lr - 0.8WX


288  uLCB288 1.2(D + T1) + 1.6 Lr + 0.8WY
289  uLCB289 1.2(D + T1) + 1.6 Lr - 0.8WY
290  uLCB290 1.2(D + T1) + 1.6WX + 0.5L + 1.0L_ + 0.5Lr
291  uLCB291 1.2(D + T1) - 1.6WX + 0.5L + 1.0L_ + 0.5Lr
292  uLCB292 1.2(D + T1) + 1.6WY + 0.5L + 1.0L_ + 0.5Lr
293  uLCB293 1.2(D + T1) - 1.6WY + 0.5L + 1.0L_ + 0.5Lr
294  uLCB294 1.2(D + T1) + 1.4(1.0EX + 0.3EY + 1.0EZ) + 0.5L + 1.0L_
295  uLCB295 1.2(D + T1) + 1.4(1.0EX + 0.3EY - 1.0EZ) + 0.5L + 1.0L_
296  uLCB296 1.2(D + T1) + 1.4(1.0EX - 0.3EY + 1.0EZ) + 0.5L + 1.0L_
297  uLCB297 1.2(D + T1) + 1.4(1.0EX - 0.3EY - 1.0EZ) + 0.5L + 1.0L_
298  uLCB298 1.2(D + T1) - 1.4(1.0EX + 0.3EY + 1.0EZ) + 0.5L + 1.0L_
299  uLCB299 1.2(D + T1) - 1.4(1.0EX + 0.3EY - 1.0EZ) + 0.5L + 1.0L_
300  uLCB300 1.2(D + T1) - 1.4(1.0EX - 0.3EY + 1.0EZ) + 0.5L + 1.0L_
301  uLCB301 1.2(D + T1) - 1.4(1.0EX - 0.3EY - 1.0EZ) + 0.5L + 1.0L_
302  uLCB302 1.2(D + T1) + 1.4(0.3EX + 1.0EY + 1.0EZ) + 0.5L + 1.0L_
303  uLCB303 1.2(D + T1) + 1.4(0.3EX + 1.0EY - 1.0EZ) + 0.5L + 1.0L_
304  uLCB304 1.2(D + T1) + 1.4(0.3EX – 1.0EY + 1.0EZ) + 0.5L + 1.0L_
305  uLCB305 1.2(D + T1) + 1.4(0.3EX – 1.0EY - 1.0EZ) + 0.5L + 1.0L_
306  uLCB306 1.2(D + T1) - 1.4(0.3EX + 1.0EY + 1.0EZ) + 0.5L + 1.0L_
307  uLCB307 1.2(D + T1) - 1.4(0.3EX + 1.0EY - 1.0EZ) + 0.5L + 1.0L_
308  uLCB308 1.2(D + T1) - 1.4(0.3EX – 1.0EY + 1.0EZ) + 0.5L + 1.0L_
309  uLCB309 1.2(D + T1) - 1.4(0.3EX – 1.0EY - 1.0EZ) + 0.5L + 1.0L_
310  uLCB310 0.9(D + T1) + 1.4(1.0EX + 0.3EY + 1.0EZ)
311  uLCB311 0.9(D + T1) + 1.4(1.0EX + 0.3EY - 1.0EZ)
312  uLCB312 0.9(D + T1) + 1.4(1.0EX - 0.3EY + 1.0EZ)
313  uLCB313 0.9(D + T1) + 1.4(1.0EX - 0.3EY - 1.0EZ)
314  uLCB314 0.9(D + T1) - 1.4(1.0EX + 0.3EY + 1.0EZ)
315  uLCB315 0.9(D + T1) - 1.4(1.0EX + 0.3EY - 1.0EZ)
316  uLCB316 0.9(D + T1) - 1.4(1.0EX - 0.3EY + 1.0EZ)
317  uLCB317 0.9(D + T1) - 1.4(1.0EX - 0.3EY - 1.0EZ)

333
Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-007

318  uLCB318 0.9(D + T1) + 1.4(0.3EX + 1.0EY + 1.0EZ)


319  uLCB319 0.9(D + T1) + 1.4(0.3EX + 1.0EY - 1.0EZ)
320  uLCB320 0.9(D + T1) + 1.4(0.3EX – 1.0EY + 1.0EZ)
321  uLCB321 0.9(D + T1) + 1.4(0.3EX – 1.0EY - 1.0EZ)
322  uLCB322 0.9(D + T1) - 1.4(0.3EX + 1.0EY + 1.0EZ)
323  uLCB323 0.9(D + T1) - 1.4(0.3EX + 1.0EY - 1.0EZ)
324  uLCB324 0.9(D + T1) - 1.4(0.3EX – 1.0EY + 1.0EZ)
325  uLCB325 0.9(D + T1) - 1.4(0.3EX – 1.0EY - 1.0EZ)
326  uLCB326 1.4(D + T2)
327  uLCB327 1.2(D + T2) + 1.6L + 1.6 L_ + 0.5Lr
328  uLCB328 1.2(D + T2) + 1.6 Lr + 0.5L + L_
329  uLCB329 1.2(D + T2) + 1.6 Lr + 0.8WX
330 uLCB330 1.2(D + T2) + 1.6 Lr - 0.8WX
331 uLCB331 1.2(D + T2) + 1.6 Lr + 0.8WY
332 uLCB332 1.2(D + T2) + 1.6 Lr - 0.8WY
333 uLCB333 1.2(D + T2) + 1.6WX + 0.5L + 1.0L_ + 0.5Lr
334 uLCB334 1.2(D + T2) - 1.6WX + 0.5L + 1.0L_ + 0.5Lr
335 uLCB335 1.2(D + T2) + 1.6WY + 0.5L + 1.0L_ + 0.5Lr
336 uLCB336 1.2(D + T2) - 1.6WY + 0.5L + 1.0L_ + 0.5Lr
337 uLCB337 1.2(D + T2) + 1.4(1.0EX + 0.3EY + 1.0EZ) + 0.5L + 1.0L_
338 uLCB338 1.2(D + T2) + 1.4(1.0EX + 0.3EY - 1.0EZ) + 0.5L + 1.0L_
339 uLCB339 1.2(D + T2) + 1.4(1.0EX - 0.3EY + 1.0EZ) + 0.5L + 1.0L_
340 uLCB340 1.2(D + T2) + 1.4(1.0EX - 0.3EY - 1.0EZ) + 0.5L + 1.0L_
341 uLCB341 1.2(D + T2) - 1.4(1.0EX + 0.3EY + 1.0EZ) + 0.5L + 1.0L_
342 uLCB342 1.2(D + T2) - 1.4(1.0EX + 0.3EY - 1.0EZ) + 0.5L + 1.0L_
343 uLCB343 1.2(D + T2) - 1.4(1.0EX - 0.3EY + 1.0EZ) + 0.5L + 1.0L_
344 uLCB344 1.2(D + T2) - 1.4(1.0EX - 0.3EY - 1.0EZ) + 0.5L + 1.0L_
345 uLCB345 1.2(D + T2) + 1.4(0.3EX + 1.0EY + 1.0EZ) + 0.5L + 1.0L_
346 uLCB346 1.2(D + T2) + 1.4(0.3EX + 1.0EY - 1.0EZ) + 0.5L + 1.0L_
347 uLCB347 1.2(D + T2) + 1.4(0.3EX – 1.0EY + 1.0EZ) + 0.5L + 1.0L_
348 uLCB348 1.2(D + T2) + 1.4(0.3EX – 1.0EY - 1.0EZ) + 0.5L + 1.0L_

334
Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-007

349 uLCB349 1.2(D + T2) - 1.4(0.3EX + 1.0EY + 1.0EZ) + 0.5L + 1.0L_


350 uLCB350 1.2(D + T2) - 1.4(0.3EX + 1.0EY - 1.0EZ) + 0.5L + 1.0L_
351 uLCB351 1.2(D + T2) - 1.4(0.3EX – 1.0EY + 1.0EZ) + 0.5L + 1.0L_
352 uLCB352 1.2(D + T2) - 1.4(0.3EX – 1.0EY - 1.0EZ) + 0.5L + 1.0L_
353 uLCB353 0.9(D + T2) + 1.4(1.0EX + 0.3EY + 1.0EZ)
354 uLCB354 0.9(D + T2) + 1.4(1.0EX + 0.3EY - 1.0EZ)
355 uLCB355 0.9(D + T2) + 1.4(1.0EX - 0.3EY + 1.0EZ)
356 uLCB356 0.9(D + T2) + 1.4(1.0EX - 0.3EY - 1.0EZ)
357 uLCB357 0.9(D + T2) - 1.4(1.0EX + 0.3EY + 1.0EZ)
358 uLCB358 0.9(D + T2) - 1.4(1.0EX + 0.3EY - 1.0EZ)
359 uLCB359 0.9(D + T2) - 1.4(1.0EX - 0.3EY + 1.0EZ)
360 uLCB360 0.9(D + T2) - 1.4(1.0EX - 0.3EY - 1.0EZ)
361 uLCB361 0.9(D + T2) + 1.4(0.3EX + 1.0EY + 1.0EZ)
362 uLCB362 0.9(D + T2) + 1.4(0.3EX + 1.0EY - 1.0EZ)
363 uLCB363 0.9(D + T2) + 1.4(0.3EX – 1.0EY + 1.0EZ)
364 uLCB364 0.9(D + T2) + 1.4(0.3EX – 1.0EY - 1.0EZ)
365 uLCB365 0.9(D + T2) - 1.4(0.3EX + 1.0EY + 1.0EZ)
366 uLCB366 0.9(D + T2) - 1.4(0.3EX + 1.0EY - 1.0EZ)
367 uLCB367 0.9(D + T2) - 1.4(0.3EX – 1.0EY + 1.0EZ)
368 uLCB368 0.9(D + T2) - 1.4(0.3EX – 1.0EY - 1.0EZ)
369 uLCB369 1.4(D + T3)
370 uLCB370 1.2(D + T3) + 1.6L + 1.6 L_ + 0.5Lr
371 uLCB371 1.2(D + T3) + 1.6 Lr + 0.5L + L_
372 uLCB372 1.2(D + T3) + 1.6 Lr + 0.8WX
373 uLCB373 1.2(D + T3) + 1.6 Lr - 0.8WX
374 uLCB374 1.2(D + T3) + 1.6 Lr + 0.8WY
375 uLCB375 1.2(D + T3) + 1.6 Lr - 0.8WY
376 uLCB376 1.2(D + T3) + 1.6WX + 0.5L + 1.0L_ + 0.5Lr
377 uLCB377 1.2(D + T3) - 1.6WX + 0.5L + 1.0L_ + 0.5Lr
378 uLCB378 1.2(D + T3) + 1.6WY + 0.5L + 1.0L_ + 0.5Lr
379 uLCB379 1.2(D + T3) - 1.6WY + 0.5L + 1.0L_ + 0.5Lr
380 uLCB380 1.2(D + T3) + 1.4(1.0EX + 0.3EY + 1.0EZ) + 0.5L + 1.0L_

335
Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-007

381 uLCB381 1.2(D + T3) + 1.4(1.0EX + 0.3EY - 1.0EZ) + 0.5L + 1.0L_


382 uLCB382 1.2(D + T3) + 1.4(1.0EX - 0.3EY + 1.0EZ) + 0.5L + 1.0L_
383 uLCB383 1.2(D + T3) + 1.4(1.0EX - 0.3EY - 1.0EZ) + 0.5L + 1.0L_
384 uLCB384 1.2(D + T3) - 1.4(1.0EX + 0.3EY + 1.0EZ) + 0.5L + 1.0L_
385 uLCB385 1.2(D + T3) - 1.4(1.0EX + 0.3EY - 1.0EZ) + 0.5L + 1.0L_
386 uLCB386 1.2(D + T3) - 1.4(1.0EX - 0.3EY + 1.0EZ) + 0.5L + 1.0L_
387 uLCB387 1.2(D + T3) - 1.4(1.0EX - 0.3EY - 1.0EZ) + 0.5L + 1.0L_
388 uLCB388 1.2(D + T3) + 1.4(0.3EX + 1.0EY + 1.0EZ) + 0.5L + 1.0L_
389 uLCB389 1.2(D + T3) + 1.4(0.3EX + 1.0EY - 1.0EZ) + 0.5L + 1.0L_
390 uLCB390 1.2(D + T3) + 1.4(0.3EX – 1.0EY + 1.0EZ) + 0.5L + 1.0L_
391 uLCB391 1.2(D + T3) + 1.4(0.3EX – 1.0EY - 1.0EZ) + 0.5L + 1.0L_
392 uLCB392 1.2(D + T3) - 1.4(0.3EX + 1.0EY + 1.0EZ) + 0.5L + 1.0L_
393 uLCB393 1.2(D + T3) - 1.4(0.3EX + 1.0EY - 1.0EZ) + 0.5L + 1.0L_
394 uLCB394 1.2(D + T3) - 1.4(0.3EX – 1.0EY + 1.0EZ) + 0.5L + 1.0L_
395 uLCB395 1.2(D + T3) - 1.4(0.3EX – 1.0EY - 1.0EZ) + 0.5L + 1.0L_
396 uLCB396 0.9(D + T3) + 1.4(1.0EX + 0.3EY + 1.0EZ)
397 uLCB397 0.9(D + T3) + 1.4(1.0EX + 0.3EY - 1.0EZ)
398 uLCB398 0.9(D + T3) + 1.4(1.0EX - 0.3EY + 1.0EZ)
399 uLCB399 0.9(D + T3) + 1.4(1.0EX - 0.3EY - 1.0EZ)
400 uLCB400 0.9(D + T3) - 1.4(1.0EX + 0.3EY + 1.0EZ)
401 uLCB401 0.9(D + T3) - 1.4(1.0EX + 0.3EY - 1.0EZ)
402 uLCB402 0.9(D + T3) - 1.4(1.0EX - 0.3EY + 1.0EZ)
403 uLCB403 0.9(D + T3) - 1.4(1.0EX - 0.3EY - 1.0EZ)
404 uLCB404 0.9(D + T3) + 1.4(0.3EX + 1.0EY + 1.0EZ)
405 uLCB405 0.9(D + T3) + 1.4(0.3EX + 1.0EY - 1.0EZ)
406 uLCB406 0.9(D + T3) + 1.4(0.3EX – 1.0EY + 1.0EZ)
407 uLCB407 0.9(D + T3) + 1.4(0.3EX – 1.0EY - 1.0EZ)
408 uLCB408 0.9(D + T3) - 1.4(0.3EX + 1.0EY + 1.0EZ)
409 uLCB409 0.9(D + T3) - 1.4(0.3EX + 1.0EY - 1.0EZ)
410 uLCB410 0.9(D + T3) - 1.4(0.3EX – 1.0EY + 1.0EZ)
411 uLCB411 0.9(D + T3) - 1.4(0.3EX – 1.0EY - 1.0EZ)
412 uLCB412 1.4(D + T4)

336
Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-007

413 uLCB413 1.2(D + T4) + 1.6L + 1.6 L_ + 0.5Lr


414 uLCB414 1.2(D + T4) + 1.6 Lr + 0.5L + L_
415 uLCB415 1.2(D + T4) + 1.6 Lr + 0.8WX
416 uLCB416 1.2(D + T4) + 1.6 Lr - 0.8WX
417 uLCB417 1.2(D + T4) + 1.6 Lr + 0.8WY
418 uLCB418 1.2(D + T4) + 1.6 Lr - 0.8WY
419 uLCB419 1.2(D + T4) + 1.6WX + 0.5L + 1.0L_ + 0.5Lr
420 uLCB420 1.2(D + T4) - 1.6WX + 0.5L + 1.0L_ + 0.5Lr
421 uLCB421 1.2(D + T4) + 1.6WY + 0.5L + 1.0L_ + 0.5Lr
422 uLCB422 1.2(D + T4) - 1.6WY + 0.5L + 1.0L_ + 0.5Lr
423 uLCB423 1.2(D + T4) + 1.4(1.0EX + 0.3EY + 1.0EZ) + 0.5L + 1.0L_
424 uLCB424 1.2(D + T4) + 1.4(1.0EX + 0.3EY - 1.0EZ) + 0.5L + 1.0L_
425 uLCB425 1.2(D + T4) + 1.4(1.0EX - 0.3EY + 1.0EZ) + 0.5L + 1.0L_
426 uLCB426 1.2(D + T4) + 1.4(1.0EX - 0.3EY - 1.0EZ) + 0.5L + 1.0L_
427 uLCB427 1.2(D + T4) - 1.4(1.0EX + 0.3EY + 1.0EZ) + 0.5L + 1.0L_
428 uLCB428 1.2(D + T4) - 1.4(1.0EX + 0.3EY - 1.0EZ) + 0.5L + 1.0L_
429 uLCB429 1.2(D + T4) - 1.4(1.0EX - 0.3EY + 1.0EZ) + 0.5L + 1.0L_
430 uLCB430 1.2(D + T4) - 1.4(1.0EX - 0.3EY - 1.0EZ) + 0.5L + 1.0L_
431 uLCB431 1.2(D + T4) + 1.4(0.3EX + 1.0EY + 1.0EZ) + 0.5L + 1.0L_
432 uLCB432 1.2(D + T4) + 1.4(0.3EX + 1.0EY - 1.0EZ) + 0.5L + 1.0L_
433 uLCB433 1.2(D + T4) + 1.4(0.3EX – 1.0EY + 1.0EZ) + 0.5L + 1.0L_
434 uLCB434 1.2(D + T4) + 1.4(0.3EX – 1.0EY - 1.0EZ) + 0.5L + 1.0L_
435 uLCB435 1.2(D + T4) - 1.4(0.3EX + 1.0EY + 1.0EZ) + 0.5L + 1.0L_
436 uLCB436 1.2(D + T4) - 1.4(0.3EX + 1.0EY - 1.0EZ) + 0.5L + 1.0L_
437 uLCB437 1.2(D + T4) - 1.4(0.3EX – 1.0EY + 1.0EZ) + 0.5L + 1.0L_
438 uLCB438 1.2(D + T4) - 1.4(0.3EX – 1.0EY - 1.0EZ) + 0.5L + 1.0L_
439 uLCB439 0.9(D + T4) + 1.4(1.0EX + 0.3EY + 1.0EZ)
440 uLCB440 0.9(D + T4) + 1.4(1.0EX + 0.3EY - 1.0EZ)
441 uLCB441 0.9(D + T4) + 1.4(1.0EX - 0.3EY + 1.0EZ)
442 uLCB442 0.9(D + T4) + 1.4(1.0EX - 0.3EY - 1.0EZ)
443 uLCB443 0.9(D + T4) - 1.4(1.0EX + 0.3EY + 1.0EZ)
444 uLCB444 0.9(D + T4) - 1.4(1.0EX + 0.3EY - 1.0EZ)

337
Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-007

445 uLCB445 0.9(D + T4) - 1.4(1.0EX - 0.3EY + 1.0EZ)


446 uLCB446 0.9(D + T4) - 1.4(1.0EX - 0.3EY - 1.0EZ)
447 uLCB447 0.9(D + T4) + 1.4(0.3EX + 1.0EY + 1.0EZ)
448 uLCB448 0.9(D + T4) + 1.4(0.3EX + 1.0EY - 1.0EZ)
449 uLCB449 0.9(D + T4) + 1.4(0.3EX – 1.0EY + 1.0EZ)
450 uLCB450 0.9(D + T4) + 1.4(0.3EX – 1.0EY - 1.0EZ)
451 uLCB451 0.9(D + T4) - 1.4(0.3EX + 1.0EY + 1.0EZ)
452 uLCB452 0.9(D + T4) - 1.4(0.3EX + 1.0EY - 1.0EZ)
453 uLCB453 0.9(D + T4) - 1.4(0.3EX – 1.0EY + 1.0EZ)
454 uLCB454 0.9(D + T4) - 1.4(0.3EX – 1.0EY - 1.0EZ)
455 uLCB455 1.4(D + T5)
456 uLCB456 1.2(D + T5) + 1.6L + 1.6 L_ + 0.5Lr
457 uLCB457 1.2(D + T5) + 1.6 Lr + 0.5L + L_
458 uLCB458 1.2(D + T5) + 1.6 Lr + 0.8WX
459 uLCB459 1.2(D + T5) + 1.6 Lr - 0.8WX
460 uLCB460 1.2(D + T5) + 1.6 Lr + 0.8WY
461 uLCB461 1.2(D + T5) + 1.6 Lr - 0.8WY
462 uLCB462 1.2(D + T5) + 1.6WX + 0.5L + 1.0L_ + 0.5Lr
463 uLCB463 1.2(D + T5) - 1.6WX + 0.5L + 1.0L_ + 0.5Lr
464 uLCB464 1.2(D + T5) + 1.6WY + 0.5L + 1.0L_ + 0.5Lr
465 uLCB465 1.2(D + T5) - 1.6WY + 0.5L + 1.0L_ + 0.5Lr
466 uLCB466 1.2(D + T5) + 1.4(1.0EX + 0.3EY + 1.0EZ) + 0.5L + 1.0L_
467 uLCB467 1.2(D + T5) + 1.4(1.0EX + 0.3EY - 1.0EZ) + 0.5L + 1.0L_
468 uLCB468 1.2(D + T5) + 1.4(1.0EX - 0.3EY + 1.0EZ) + 0.5L + 1.0L_
469 uLCB469 1.2(D + T5) + 1.4(1.0EX - 0.3EY - 1.0EZ) + 0.5L + 1.0L_
470 uLCB470 1.2(D + T5) - 1.4(1.0EX + 0.3EY + 1.0EZ) + 0.5L + 1.0L_
471 uLCB471 1.2(D + T5) - 1.4(1.0EX + 0.3EY - 1.0EZ) + 0.5L + 1.0L_
472 uLCB472 1.2(D + T5) - 1.4(1.0EX - 0.3EY + 1.0EZ) + 0.5L + 1.0L_
473 uLCB473 1.2(D + T5) - 1.4(1.0EX - 0.3EY - 1.0EZ) + 0.5L + 1.0L_
474 uLCB474 1.2(D + T5) + 1.4(0.3EX + 1.0EY + 1.0EZ) + 0.5L + 1.0L_
475 uLCB475 1.2(D + T5) + 1.4(0.3EX + 1.0EY - 1.0EZ) + 0.5L + 1.0L_
476 uLCB476 1.2(D + T5) + 1.4(0.3EX – 1.0EY + 1.0EZ) + 0.5L + 1.0L_

338
Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-007

477 uLCB477 1.2(D + T5) + 1.4(0.3EX – 1.0EY - 1.0EZ) + 0.5L + 1.0L_


478 uLCB478 1.2(D + T5) - 1.4(0.3EX + 1.0EY + 1.0EZ) + 0.5L + 1.0L_
479 uLCB479 1.2(D + T5) - 1.4(0.3EX + 1.0EY - 1.0EZ) + 0.5L + 1.0L_
480 uLCB480 1.2(D + T5) - 1.4(0.3EX – 1.0EY + 1.0EZ) + 0.5L + 1.0L_
481 uLCB481 1.2(D + T5) - 1.4(0.3EX – 1.0EY - 1.0EZ) + 0.5L + 1.0L_
482 uLCB482 0.9(D + T5) + 1.4(1.0EX + 0.3EY + 1.0EZ)
483 uLCB483 0.9(D + T5) + 1.4(1.0EX + 0.3EY - 1.0EZ)
484 uLCB484 0.9(D + T5) + 1.4(1.0EX - 0.3EY + 1.0EZ)
485 uLCB485 0.9(D + T5) + 1.4(1.0EX - 0.3EY - 1.0EZ)
486 uLCB486 0.9(D + T5) - 1.4(1.0EX + 0.3EY + 1.0EZ)
487 uLCB487 0.9(D + T5) - 1.4(1.0EX + 0.3EY - 1.0EZ)
488 uLCB488 0.9(D + T5) - 1.4(1.0EX - 0.3EY + 1.0EZ)
489 uLCB489 0.9(D + T5) - 1.4(1.0EX - 0.3EY - 1.0EZ)
490 uLCB490 0.9(D + T5) + 1.4(0.3EX + 1.0EY + 1.0EZ)
491 uLCB491 0.9(D + T5) + 1.4(0.3EX + 1.0EY - 1.0EZ)
492 uLCB492 0.9(D + T5) + 1.4(0.3EX – 1.0EY + 1.0EZ)
493 uLCB493 0.9(D + T5) + 1.4(0.3EX – 1.0EY - 1.0EZ)
494 uLCB494 0.9(D + T5) - 1.4(0.3EX + 1.0EY + 1.0EZ)
495 uLCB495 0.9(D + T5) - 1.4(0.3EX + 1.0EY - 1.0EZ)
496 uLCB496 0.9(D + T5) - 1.4(0.3EX – 1.0EY + 1.0EZ)
497 uLCB497 0.9(D + T5) - 1.4(0.3EX – 1.0EY - 1.0EZ)
498 uLCB498 1.4(D)
499 uLCB499 1.2(D) + 1.6L + 1.6 L_ + 0.5Lr
500 uLCB500 1.2(D) + 1.6 Lr + 0.5L + L_
501 uLCB501 1.2(D) + 1.6 Lr + 0.8WX
502 uLCB502 1.2(D) + 1.6 Lr - 0.8WX
503 uLCB503 1.2(D) + 1.6 Lr + 0.8WY
504 uLCB504 1.2(D) + 1.6 Lr - 0.8WY
505 uLCB505 1.2(D) + 1.6WX + 0.5L + 1.0L_ + 0.5Lr
506 uLCB506 1.2(D) - 1.6WX + 0.5L + 1.0L_ + 0.5Lr
507 uLCB507 1.2(D) + 1.6WY + 0.5L + 1.0L_ + 0.5Lr
508 uLCB508 1.2(D) - 1.6WY + 0.5L + 1.0L_ + 0.5Lr

339
Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-007

509 uLCB509 1.2(D) + 1.4(1.0EX + 0.3EY + 1.0EZ) + 0.5L + 1.0L_


510 uLCB510 1.2(D) + 1.4(1.0EX + 0.3EY - 1.0EZ) + 0.5L + 1.0L_
511 uLCB511 1.2(D) + 1.4(1.0EX - 0.3EY + 1.0EZ) + 0.5L + 1.0L_
512 uLCB512 1.2(D) + 1.4(1.0EX - 0.3EY - 1.0EZ) + 0.5L + 1.0L_
513 uLCB513 1.2(D) - 1.4(1.0EX + 0.3EY + 1.0EZ) + 0.5L + 1.0L_
514 uLCB514 1.2(D) - 1.4(1.0EX + 0.3EY - 1.0EZ) + 0.5L + 1.0L_
515 uLCB515 1.2(D) - 1.4(1.0EX - 0.3EY + 1.0EZ) + 0.5L + 1.0L_
516 uLCB516 1.2(D) - 1.4(1.0EX - 0.3EY - 1.0EZ) + 0.5L + 1.0L_
517 uLCB517 1.2(D) + 1.4(0.3EX + 1.0EY + 1.0EZ) + 0.5L + 1.0L_
518 uLCB518 1.2(D) + 1.4(0.3EX + 1.0EY - 1.0EZ) + 0.5L + 1.0L_
519 uLCB519 1.2(D) + 1.4(0.3EX – 1.0EY + 1.0EZ) + 0.5L + 1.0L_
520 uLCB520 1.2(D) + 1.4(0.3EX – 1.0EY - 1.0EZ) + 0.5L + 1.0L_
521 uLCB521 1.2(D) - 1.4(0.3EX + 1.0EY + 1.0EZ) + 0.5L + 1.0L_
522 uLCB522 1.2(D) - 1.4(0.3EX + 1.0EY - 1.0EZ) + 0.5L + 1.0L_
523 uLCB523 1.2(D) - 1.4(0.3EX – 1.0EY + 1.0EZ) + 0.5L + 1.0L_
524 uLCB524 1.2(D) - 1.4(0.3EX – 1.0EY - 1.0EZ) + 0.5L + 1.0L_
525 uLCB525 0.9(D) + 1.4(1.0EX + 0.3EY + 1.0EZ)
526 uLCB526 0.9(D) + 1.4(1.0EX + 0.3EY - 1.0EZ)
527 uLCB527 0.9(D) + 1.4(1.0EX - 0.3EY + 1.0EZ)
528 uLCB528 0.9(D) + 1.4(1.0EX - 0.3EY - 1.0EZ)
529 uLCB529 0.9(D) - 1.4(1.0EX + 0.3EY + 1.0EZ)
530 uLCB530 0.9(D) - 1.4(1.0EX + 0.3EY - 1.0EZ)
531 uLCB531 0.9(D) - 1.4(1.0EX - 0.3EY + 1.0EZ)
532 uLCB532 0.9(D) - 1.4(1.0EX - 0.3EY - 1.0EZ)
533 uLCB533 0.9(D) + 1.4(0.3EX + 1.0EY + 1.0EZ)
534 uLCB534 0.9(D) + 1.4(0.3EX + 1.0EY - 1.0EZ)
535 uLCB535 0.9(D) + 1.4(0.3EX – 1.0EY + 1.0EZ)
536 uLCB536 0.9(D) + 1.4(0.3EX – 1.0EY - 1.0EZ)
537 uLCB537 0.9(D) - 1.4(0.3EX + 1.0EY + 1.0EZ)
538 uLCB538 0.9(D) - 1.4(0.3EX + 1.0EY - 1.0EZ)
539 uLCB539 0.9(D) - 1.4(0.3EX – 1.0EY + 1.0EZ)
540 uLCB540 0.9(D) - 1.4(0.3EX – 1.0EY - 1.0EZ)

340
Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-007

3.7.3 ASD Load Combination (for Duct Casing and Structure)


The ASD load combinations shall take into account the earthquake load in Technical Specification.
Technical Specification considered a nominal load, so it must be amplified by a factor 1.0.

No. Case Name Description


1 sLCB1 (D + F + T1)
2  sLCB2 (D + F + T1) + L + L_
3  sLCB3 (D + F + T1) + Lr
4  sLCB4 (D + F + T1) + 0.75L + 0.75L_ + 0.75Lr
5  sLCB5 (D + F + T1) + WX
6  sLCB6 (D + F + T1) - WX
7  sLCB7 (D + F + T1) + WY
8  sLCB8 (D + F + T1) - WY
9  sLCB9 (D + F + T1) + EX + 0.3EY + EZ
10  sLCB10 (D + F + T1) + EX + 0.3EY - EZ
11  sLCB11 (D + F + T1) + EX - 0.3EY + EZ
12  sLCB12 (D + F + T1) + EX - 0.3EY - EZ
13  sLCB13 (D + F + T1) - EX + 0.3EY + EZ
14  sLCB14 (D + F + T1) - EX + 0.3EY - EZ
15  sLCB15 (D + F + T1) - EX - 0.3EY + EZ
16  sLCB16 (D + F + T1) - EX - 0.3EY - EZ
17  sLCB17 (D + F + T1) + 0.3EX - EY + EZ
18  sLCB18 (D + F + T1) + 0.3EX + EY - EZ
19  sLCB19 (D + F + T1) + 0.3EX - EY + EZ
20  sLCB20 (D + F + T1) + 0.3EX - EY - EZ
21  sLCB21 (D + F + T1) – 0.3EX + EY + EZ
22  sLCB22 (D + F + T1) – 0.3EX + EY - EZ
23  sLCB23 (D + F + T1) – 0.3EX - EY + EZ
24  sLCB24 (D + F + T1) – 0.3EX - EY - EZ
25  sLCB25 (D + F + T1) + 0.75WX + 0.75L+ 0.75L_ + 0.75Lr
26  sLCB26 (D + F + T1) - 0.75WX + 0.75L+ 0.75L_ + 0.75Lr

341
Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-007

27  sLCB27 (D + F + T1) + 0.75WY + 0.75L+ 0.75L_ + 0.75Lr


28  sLCB28 (D + F + T1) - 0.75WY + 0.75L+ 0.75L_ + 0.75Lr
29  sLCB29 (D + F + T1) + 0.75(EX + 0.3EY + EZ) + 0.75L+ 0.75L_
30  sLCB30 (D + F + T1) + 0.75(EX + 0.3EY - EZ) + 0.75L+ 0.75L_
31  sLCB31 (D + F + T1) + 0.75(EX - 0.3EY + EZ) + 0.75L+ 0.75L_
32  sLCB32 (D + F + T1) + 0.75(EX - 0.3EY - EZ) + 0.75L+ 0.75L_
33  sLCB33 (D + F + T1) + 0.75(-EX + 0.3EY + EZ) + 0.75L+ 0.75L_
34  sLCB34 (D + F + T1) + 0.75(-EX + 0.3EY - EZ) + 0.75L+ 0.75L_
35  sLCB35 (D + F + T1) + 0.75(-EX - 0.3EY + EZ) + 0.75L+ 0.75L_
36  sLCB36 (D + F + T1) + 0.75(-EX - 0.3EY - EZ) + 0.75L+ 0.75L_
37  sLCB37 (D + F + T1) + 0.75(0.3EX + EY + EZ) + 0.75L+ 0.75L_
38  sLCB38 (D + F + T1) + 0.75(0.3EX + EY - EZ) + 0.75L+ 0.75L_
39  sLCB39 (D + F + T1) + 0.75(0.3EX - EY + EZ) + 0.75L+ 0.75L_
40  sLCB40 (D + F + T1) + 0.75(0.3EX - EY - EZ) + 0.75L+ 0.75L_
41  sLCB41 (D + F + T1) + 0.75(-0.3EX + EY + EZ) + 0.75L+ 0.75L_
42  sLCB42 (D + F + T1) + 0.75(-0.3EX + EY - EZ) + 0.75L+ 0.75L_
43  sLCB43 (D + F + T1) + 0.75(-0.3EX - EY + EZ) + 0.75L+ 0.75L_
44  sLCB44 (D + F + T1) + 0.75(-0.3EX - EY - EZ) + 0.75L+ 0.75L_
45  sLCB45 0.6(D+ T1) + WX
46  sLCB46 0.6(D+ T1) - WY
47  sLCB47 0.6(D+ T1) + WY
48  sLCB48 0.6(D+ T1) - WY
49  sLCB49 0.6(D + F + T1) + EX + 0.3EY + EZ
50  sLCB50 0.6(D + F + T1) + EX + 0.3EY - EZ
51  sLCB51 0.6(D + F + T1) + EX - 0.3EY + EZ
52  sLCB52 0.6(D + F + T1) + EX - 0.3EY - EZ
53  sLCB53 0.6(D + F + T1) - EX + 0.3EY + EZ
54  sLCB54 0.6(D + F + T1) - EX + 0.3EY - EZ
55  sLCB55 0.6(D + F + T1) - EX - 0.3EY + EZ
56  sLCB56 0.6(D + F + T1) - EX - 0.3EY - EZ
57  sLCB57 0.6(D + F + T1) + 0.3EX + EY + EZ

342
Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-007

58  sLCB58 0.6(D + F + T1) + 0.3EX + EY - EZ

59  sLCB59 0.6(D + F + T1) + 0.3EX - EY + EZ

60  sLCB60 0.6(D + F + T1) + 0.3EX - EY - EZ

61  sLCB61 0.6(D + F + T1) - 0.3EX + EY + EZ

62  sLCB62 0.6(D + F + T1) - 0.3EX + EY - EZ

63  sLCB63 0.6(D + F + T1) - 0.3EX - EY + EZ

64  sLCB64 0.6(D + F + T1) - 0.3EX - EY - EZ

65  sLCB65 (D + F + T2)


66  sLCB66 (D + F + T2) + L + L_
67  sLCB67 (D + F + T2) + Lr
68  sLCB68 (D + F + T2) + 0.75L + 0.75L_ + 0.75Lr
69  sLCB69 (D + F + T2) + WX
70  sLCB70 (D + F + T2) - WX
71  sLCB71 (D + F + T2) + WY
72  sLCB72 (D + F + T2) - WY
73  sLCB73 (D + F + T2) + EX + 0.3EY + EZ
74  sLCB74 (D + F + T2) + EX + 0.3EY - EZ
75  sLCB75 (D + F + T2) + EX - 0.3EY + EZ
76  sLCB76 (D + F + T2) + EX - 0.3EY - EZ
77  sLCB77 (D + F + T2) - EX + 0.3EY + EZ
78  sLCB78 (D + F + T2) - EX + 0.3EY - EZ
79  sLCB79 (D + F + T2) - EX - 0.3EY + EZ
80  sLCB80 (D + F + T2) - EX - 0.3EY - EZ
81  sLCB81 (D + F + T2) + 0.3EX + EY + EZ
82  sLCB82 (D + F + T2) + 0.3EX + EY - EZ
83  sLCB83 (D + F + T2) + 0.3EX - EY + EZ
84  sLCB84 (D + F + T2) + 0.3EX - EY – EZ
85  sLCB85 (D + F + T2) - 0.3EX + EY + EZ
86  sLCB86 (D + F + T2) - 0.3EX + EY - EZ
87  sLCB87 (D + F + T2) - 0.3EX - EY + EZ
88  sLCB88 (D + F + T2) - 0.3EX - EY – EZ

343
Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-007

89  sLCB89 (D + F + T2) + 0.75WX + 0.75L+ 0.75L_ + 0.75Lr


90  sLCB90 (D + F + T2) - 0.75WX + 0.75L+ 0.75L_ + 0.75Lr
91  sLCB91 (D + F + T2) + 0.75WY + 0.75L+ 0.75L_ + 0.75Lr
92  sLCB92 (D + F + T2) - 0.75WY + 0.75L+ 0.75L_ + 0.75Lr
93  sLCB93 (D + F + T2) + 0.75(EX + 0.3EY + EZ) + 0.75L+ 0.75L_
94  sLCB94 (D + F + T2) + 0.75(EX + 0.3EY - EZ) + 0.75L+ 0.75L_
95  sLCB95 (D + F + T2) + 0.75(EX - 0.3EY + EZ) + 0.75L+ 0.75L_
96  sLCB96 (D + F + T2) + 0.75(EX - 0.3EY - EZ) + 0.75L+ 0.75L_
97  sLCB97 (D + F + T2) + 0.75(-EX + 0.3EY + EZ) + 0.75L+ 0.75L_
98  sLCB98 (D + F + T2) + 0.75(-EX + 0.3EY - EZ) + 0.75L+ 0.75L_
99  sLCB99 (D + F + T2) + 0.75(-EX - 0.3EY + EZ) + 0.75L+ 0.75L_
100  sLCB100 (D + F + T2) + 0.75(-EX - 0.3EY - EZ) + 0.75L+ 0.75L_
101  sLCB101 (D + F + T2) + 0.75(0.3EX + EY + EZ) + 0.75L+ 0.75L_
102  sLCB102 (D + F + T2) + 0.75(0.3EX + EY - EZ) + 0.75L+ 0.75L_
103  sLCB103 (D + F + T2) + 0.75(0.3EX - EY + EZ) + 0.75L+ 0.75L_
104  sLCB104 (D + F + T2) + 0.75(0.3EX - EY - EZ) + 0.75L+ 0.75L_
105  sLCB105 (D + F + T2) + 0.75(-0.3EX + EY + EZ) + 0.75L+ 0.75L_
106  sLCB106 (D + F + T2) + 0.75(-0.3EX + EY - EZ) + 0.75L+ 0.75L_
107  sLCB107 (D + F + T2) + 0.75(-0.3EX - EY + EZ) + 0.75L+ 0.75L_
108  sLCB108 (D + F + T2) + 0.75(-0.3EX - EY - EZ) + 0.75L+ 0.75L_
109  sLCB109 0.6(D+ T2) + WX
110  sLCB110 0.6(D+ T2) - WY
111  sLCB111 0.6(D+ T2) + WY
112  sLCB112 0.6(D+ T2) - WY
113  sLCB113 0.6(D + F + T2) + EX + 0.3EY + EZ
114  sLCB114 0.6(D + F + T2) + EX + 0.3EY - EZ
115  sLCB115 0.6(D + F + T2) + EX - 0.3EY + EZ
116  sLCB116 0.6(D + F + T2) + EX - 0.3EY – EZ
117  sLCB117 0.6(D + F + T2) - EX + 0.3EY + EZ
118  sLCB118 0.6(D + F + T2) - EX + 0.3EY - EZ
119  sLCB119 0.6(D + F + T2) - EX - 0.3EY + EZ

344
Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-007

120  sLCB120 0.6(D + F + T2) - EX - 0.3EY – EZ


121  sLCB121 0.6(D + F + T2) + 0.3EX + EY + EZ
122  sLCB122 0.6(D + F + T2) + 0.3EX + EY - EZ
123  sLCB123 0.6(D + F + T2) + 0.3EX - EY + EZ
124  sLCB124 0.6(D + F + T2) + 0.3EX - EY – EZ
125  sLCB125 0.6(D + F + T2) - 0.3EX + EY + EZ
126  sLCB126 0.6(D + F + T2) - 0.3EX + EY - EZ
127  sLCB127 0.6(D + F + T2) - 0.3EX - EY + EZ
128  sLCB128 0.6(D + F + T2) - 0.3EX - EY – EZ
129  sLCB129 (D + F + T3)
130  sLCB130 (D + F + T3) + L + L_
131  sLCB131 (D + F + T3) + Lr
132  sLCB132 (D + F + T3) + 0.75L + 0.75L_ + 0.75Lr
133  sLCB133 (D + F + T3) + WX
134  sLCB134 (D + F + T3) - WX
135  sLCB135 (D + F + T3) + WY
136  sLCB136 (D + F + T3) - WY
137  sLCB137 (D + F + T3) + EX + 0.3EY + EZ
138  sLCB138 (D + F + T3) + EX + 0.3EY - EZ
139  sLCB139 (D + F + T3) + EX - 0.3EY + EZ
140  sLCB140 (D + F + T3) + EX - 0.3EY – EZ
141  sLCB141 (D + F + T3) - EX + 0.3EY + EZ
142  sLCB142 (D + F + T3) - EX + 0.3EY - EZ
143  sLCB143 (D + F + T3) - EX - 0.3EY + EZ
144  sLCB144 (D + F + T3) - EX - 0.3EY – EZ
145  sLCB145 (D + F + T3) + 0.3EX + EY + EZ
146  sLCB146 (D + F + T3) + 0.3EX + EY - EZ
147  sLCB147 (D + F + T3) + 0.3EX - EY + EZ
148  sLCB148 (D + F + T3) + 0.3EX - EY – EZ
149  sLCB149 (D + F + T3) - 0.3EX + EY + EZ
150  sLCB150 (D + F + T3) - 0.3EX + EY - EZ

345
Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-007

151  sLCB151 (D + F + T3) - 0.3EX - EY + EZ


152  sLCB152 (D + F + T3) - 0.3EX - EY - EZ
153  sLCB153 (D + F + T3) + 0.75WX + 0.75L+ 0.75L_ + 0.75Lr
154  sLCB154 (D + F + T3) - 0.75WX + 0.75L+ 0.75L_ + 0.75Lr
155  sLCB155 (D + F + T3) + 0.75WY + 0.75L+ 0.75L_ + 0.75Lr
156  sLCB156 (D + F + T3) - 0.75WY + 0.75L+ 0.75L_ + 0.75Lr
157  sLCB157 (D + F + T3) + 0.75(EX + 0.3EY + EZ) + 0.75L+ 0.75L_
158  sLCB158 (D + F + T3) + 0.75(EX + 0.3EY - EZ) + 0.75L+ 0.75L_
159  sLCB159 (D + F + T3) + 0.75(EX - 0.3EY + EZ) + 0.75L+ 0.75L_
160  sLCB160 (D + F + T3) + 0.75(EX - 0.3EY - EZ) + 0.75L+ 0.75L_
161  sLCB161 (D + F + T3) + 0.75(-EX + 0.3EY + EZ) + 0.75L+ 0.75L_
162  sLCB162 (D + F + T3) + 0.75(-EX + 0.3EY - EZ) + 0.75L+ 0.75L_
163  sLCB163 (D + F + T3) + 0.75(-EX - 0.3EY + EZ) + 0.75L+ 0.75L_
164  sLCB164 (D + F + T3) + 0.75(-EX - 0.3EY - EZ) + 0.75L+ 0.75L_
165  sLCB165 (D + F + T3) + 0.75(0.3EX + EY + EZ) + 0.75L+ 0.75L_
166  sLCB166 (D + F + T3) + 0.75(0.3EX + EY - EZ) + 0.75L+ 0.75L_
167  sLCB167 (D + F + T3) + 0.75(0.3EX - EY + EZ) + 0.75L+ 0.75L_
168  sLCB168 (D + F + T3) + 0.75(0.3EX - EY - EZ) + 0.75L+ 0.75L_
169  sLCB169 (D + F + T3) + 0.75(-0.3EX + EY + EZ) + 0.75L+ 0.75L_
170  sLCB170 (D + F + T3) + 0.75(-0.3EX + EY - EZ) + 0.75L+ 0.75L_
171  sLCB171 (D + F + T3) + 0.75(-0.3EX - EY + EZ) + 0.75L+ 0.75L_
172  sLCB172 (D + F + T3) + 0.75(-0.3EX - EY - EZ) + 0.75L+ 0.75L_
173  sLCB173 0.6(D+ T3) + WX
174  sLCB174 0.6(D+ T3) - WY
175  sLCB175 0.6(D+ T3) + WY
176  sLCB176 0.6(D+ T3) - WY
177  sLCB177 0.6(D + F + T3) + EX + 0.3EY + EZ
178  sLCB178 0.6(D + F + T3) + EX + 0.3EY - EZ
179  sLCB179 0.6(D + F + T3) + EX - 0.3EY + EZ
180  sLCB180 0.6(D + F + T3) + EX - 0.3EY - EZ
181  sLCB181 0.6(D + F + T3) + EX + 0.3EY + EZ

346
Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-007

182  sLCB182 0.6(D + F + T3) - EX + 0.3EY - EZ


183  sLCB183 0.6(D + F + T3) - EX - 0.3EY + EZ
184  sLCB184 0.6(D + F + T3) - EX - 0.3EY - EZ
185  sLCB185 0.6(D + F + T3) + 0.3EX + EY + EZ
186  sLCB186 0.6(D + F + T3) + 0.3EX + EY - EZ

187  sLCB187 0.6(D + F + T3) + 0.3EX - EY + EZ


188  sLCB188 0.6(D + F + T3) + 0.3EX - EY - EZ

189  sLCB189 0.6(D + F + T3) - 0.3EX + EY + EZ


190  sLCB190 0.6(D + F + T3) - 0.3EX + EY - EZ

191  sLCB191 0.6(D + F + T3) - 0.3EX - EY + EZ


192  sLCB192 0.6(D + F + T3) - 0.3EX - EY - EZ

193  sLCB193 (D + F + T4)


194  sLCB194 (D + F + T4) + L + L_
195  sLCB195 (D + F + T4) + Lr
196  sLCB196 (D + F + T4) + 0.75L + 0.75L_ + 0.75Lr
197  sLCB197 (D + F + T4) + WX
198  sLCB198 (D + F + T4) - WX
199  sLCB199 (D + F + T4) + WY
200  sLCB200 (D + F + T4) - WY
201  sLCB201 (D + F + T4) + EX + 0.3EY + EZ
202  sLCB202 (D + F + T4) + EX + 0.3EY - EZ
203  sLCB203 (D + F + T4) + EX - 0.3EY + EZ
204  sLCB204 (D + F + T4) + EX - 0.3EY - EZ
205  sLCB205 (D + F + T4) - EX + 0.3EY + EZ
206  sLCB206 (D + F + T4) - EX + 0.3EY - EZ
207  sLCB207 (D + F + T4) - EX - 0.3EY + EZ
208  sLCB208 (D + F + T4) - EX - 0.3EY - EZ
209  sLCB209 (D + F + T4) + 0.3EX + EY + EZ
210  sLCB210 (D + F + T4) + 0.3EX + EY - EZ
211  sLCB211 (D + F + T4) + 0.3EX - EY + EZ
212  sLCB212 (D + F + T4) + 0.3EX - EY – EZ

347
Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-007

213  sLCB213 (D + F + T4) - 0.3EX + EY + EZ


214  sLCB214 (D + F + T4) - 0.3EX + EY - EZ
215  sLCB215 (D + F + T4) - 0.3EX - EY + EZ
216  sLCB216 (D + F + T4) - 0.3EX - EY – EZ
217  sLCB217 (D + F + T4) + 0.75WX + 0.75L+ 0.75L_ + 0.75Lr
218  sLCB218 (D + F + T4) - 0.75WX + 0.75L+ 0.75L_ + 0.75Lr
219  sLCB219 (D + F + T4) + 0.75WY + 0.75L+ 0.75L_ + 0.75Lr
220  sLCB220 (D + F + T4) - 0.75WY + 0.75L+ 0.75L_ + 0.75Lr
221  sLCB221 (D + F + T4) + 0.75(EX + 0.3EY + EZ) + 0.75L+ 0.75L_
222  sLCB222 (D + F + T4) + 0.75(EX + 0.3EY - EZ) + 0.75L+ 0.75L_
223  sLCB223 (D + F + T4) + 0.75(EX - 0.3EY + EZ) + 0.75L+ 0.75L_
224  sLCB224 (D + F + T4) + 0.75(EX - 0.3EY - EZ) + 0.75L+ 0.75L_
225  sLCB225 (D + F + T4) + 0.75(-EX + 0.3EY + EZ) + 0.75L+ 0.75L_
226  sLCB226 (D + F + T4) + 0.75(-EX + 0.3EY - EZ) + 0.75L+ 0.75L_
227  sLCB227 (D + F + T4) + 0.75(-EX - 0.3EY + EZ) + 0.75L+ 0.75L_
228  sLCB228 (D + F + T4) + 0.75(-EX - 0.3EY - EZ) + 0.75L+ 0.75L_
229  sLCB229 (D + F + T4) + 0.75(0.3EX + EY + EZ) + 0.75L+ 0.75L_
230  sLCB230 (D + F + T4) + 0.75(0.3EX + EY - EZ) + 0.75L+ 0.75L_
231  sLCB231 (D + F + T4) + 0.75(0.3EX - EY + EZ) + 0.75L+ 0.75L_
232  sLCB232 (D + F + T4) + 0.75(0.3EX - EY - EZ) + 0.75L+ 0.75L_
233  sLCB233 (D + F + T4) + 0.75(-0.3EX + EY + EZ) + 0.75L+ 0.75L_
234  sLCB234 (D + F + T4) + 0.75(-0.3EX + EY - EZ) + 0.75L+ 0.75L_
235  sLCB235 (D + F + T4) + 0.75(-0.3EX - EY + EZ) + 0.75L+ 0.75L_
236  sLCB236 (D + F + T4) + 0.75(-0.3EX - EY - EZ) + 0.75L+ 0.75L_
237  sLCB237 0.6(D+ T4) + WX
238  sLCB238 0.6(D+ T4) - WY
239  sLCB239 0.6(D+ T4) + WY
240  sLCB240 0.6(D+ T4) - WY
241  sLCB241 0.6(D + F + T4) + EX + 0.3EY + EZ
242  sLCB242 0.6(D + F + T4) + EX + 0.3EY - EZ
243  sLCB243 0.6(D + F + T4) + EX - 0.3EY + EZ

348
Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-007

244  sLCB244 0.6(D + F + T4) + EX - 0.3EY - EZ


245  sLCB245 0.6(D + F + T4) - EX + 0.3EY + EZ
246  sLCB246 0.6(D + F + T4) - EX + 0.3EY - EZ
247  sLCB247 0.6(D + F + T4) - EX - 0.3EY + EZ
248  sLCB248 0.6(D + F + T4) - EX - 0.3EY - EZ
249  sLCB249 0.6(D + F + T4) + 0.3EX + EY + EZ
250  sLCB250 0.6(D + F + T4) + 0.3EX + EY - EZ

251  sLCB251 0.6(D + F + T4) + 0.3EX - EY + EZ


252  sLCB252 0.6(D + F + T4) + 0.3EX - EY - EZ

253  sLCB253 0.6(D + F + T4) - 0.3EX + EY + EZ


254  sLCB254 0.6(D + F + T4) - 0.3EX + EY - EZ

255  sLCB255 0.6(D + F + T4) - 0.3EX - EY + EZ


256  sLCB256 0.6(D + F + T4) - 0.3EX - EY - EZ

257  sLCB257 (D + F + T5)


258  sLCB258 (D + F + T5) + L + L_
259  sLCB259 (D + F + T5) + Lr
260  sLCB260 (D + F + T5) + 0.75L + 0.75L_ + 0.75Lr
261  sLCB261 (D + F + T5) + WX
262  sLCB262 (D + F + T5) - WX
263  sLCB263 (D + F + T5) + WY
264  sLCB264 (D + F + T5) - WY
265  sLCB265 (D + F + T5) + EX + 0.3EY + EZ
266  sLCB266 (D + F + T5) + EX + 0.3EY - EZ
267  sLCB267 (D + F + T5) + EX - 0.3EY + EZ
268  sLCB268 (D + F + T5) + EX - 0.3EY - EZ
269  sLCB269 (D + F + T5) - EX + 0.3EY + EZ
270  sLCB270 (D + F + T5) - EX + 0.3EY - EZ
271  sLCB271 (D + F + T5) - EX - 0.3EY + EZ
272  sLCB272 (D + F + T5) - EX - 0.3EY - EZ
273  sLCB273 (D + F + T5) + 0.3EX + EY + EZ
274  sLCB274 (D + F + T5) + 0.3EX + EY - EZ

349
Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-007

275  sLCB275 (D + F + T5) + 0.3EX - EY + EZ


276  sLCB276 (D + F + T5) + 0.3EX - EY - EZ
277  sLCB277 (D + F + T5) - 0.3EX + EY + EZ
278  sLCB278 (D + F + T5) - 0.3EX + EY - EZ
279  sLCB279 (D + F + T5) - 0.3EX - EY + EZ
280  sLCB280 (D + F + T5) - 0.3EX - EY - EZ
281  sLCB281 (D + F + T5) + 0.75WX + 0.75L+ 0.75L_ + 0.75Lr
282  sLCB282 (D + F + T5) - 0.75WX + 0.75L+ 0.75L_ + 0.75Lr
283  sLCB283 (D + F + T5) + 0.75WY + 0.75L+ 0.75L_ + 0.75Lr
284  sLCB284 (D + F + T5) - 0.75WY + 0.75L+ 0.75L_ + 0.75Lr
285  sLCB285 (D + F + T5) + 0.75(EX + 0.3EY + EZ) + 0.75L+ 0.75L_
286  sLCB286 (D + F + T5) + 0.75(EX + 0.3EY - EZ) + 0.75L+ 0.75L_
287  sLCB287 (D + F + T5) + 0.75(EX - 0.3EY + EZ) + 0.75L+ 0.75L_
288  sLCB288 (D + F + T5) + 0.75(EX - 0.3EY - EZ) + 0.75L+ 0.75L_
289  sLCB289 (D + F + T5) + 0.75(-EX + 0.3EY + EZ) + 0.75L+ 0.75L_
290  sLCB290 (D + F + T5) + 0.75(-EX + 0.3EY - EZ) + 0.75L+ 0.75L_
291  sLCB291 (D + F + T5) + 0.75(-EX - 0.3EY + EZ) + 0.75L+ 0.75L_
292  sLCB292 (D + F + T5) + 0.75(-EX - 0.3EY - EZ) + 0.75L+ 0.75L_
293  sLCB293 (D + F + T5) + 0.75(0.3EX + EY + EZ) + 0.75L+ 0.75L_
294  sLCB294 (D + F + T5) + 0.75(0.3EX + EY - EZ) + 0.75L+ 0.75L_
295  sLCB295 (D + F + T5) + 0.75(0.3EX - EY + EZ) + 0.75L+ 0.75L_
296  sLCB296 (D + F + T5) + 0.75(0.3EX - EY - EZ) + 0.75L+ 0.75L_
297  sLCB297 (D + F + T5) + 0.75(-0.3EX + EY + EZ) + 0.75L+ 0.75L_
298  sLCB298 (D + F + T5) + 0.75(-0.3EX + EY - EZ) + 0.75L+ 0.75L_
299  sLCB299 (D + F + T5) + 0.75(-0.3EX - EY + EZ) + 0.75L+ 0.75L_
300  sLCB300 (D + F + T5) + 0.75(-0.3EX - EY - EZ) + 0.75L+ 0.75L_
301  sLCB301 0.6(D+ T5) + WX
302  sLCB302 0.6(D+ T5) - WY
303  sLCB303 0.6(D+ T5) + WY
304  sLCB304 0.6(D+ T5) - WY
305  sLCB305 0.6(D + F + T5) + EX + 0.3EY + EZ

350
Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-007

306  sLCB306 0.6(D + F + T5) + EX + 0.3EY - EZ


307  sLCB307 0.6(D + F + T5) + EX - 0.3EY + EZ
308  sLCB308 0.6(D + F + T5) + EX - 0.3EY - EZ
309  sLCB309 0.6(D + F + T5) - EX + 0.3EY + EZ
310  sLCB310 0.6(D + F + T5) - EX + 0.3EY - EZ
311  sLCB311 0.6(D + F + T5) - EX - 0.3EY + EZ
312  sLCB312 0.6(D + F + T5) - EX - 0.3EY - EZ
313  sLCB313 0.6(D + F + T5) + 0.3EX + EY + EZ
314  sLCB314 0.6(D + F + T5) + 0.3EX + EY - EZ

315  sLCB315 0.6(D + F + T5) + 0.3EX - EY + EZ


316  sLCB316 0.6(D + F + T5) + 0.3EX - EY – EZ

317  sLCB317 0.6(D + F + T5) - 0.3EX + EY + EZ


318  sLCB318 0.6(D + F + T5) - 0.3EX + EY - EZ

319  sLCB319 0.6(D + F + T5) - 0.3EX - EY + EZ


320  sLCB320 0.6(D + F + T5) - 0.3EX - EY – EZ

321  sLCB321 (D + F)
322  sLCB322 (D + F) + L + L_
323  sLCB323 (D + F) + Lr
324  sLCB324 (D + F) + 0.75L + 0.75L_ + 0.75Lr
325  sLCB325 (D + F) + WX
326  sLCB326 (D + F) - WX
327  sLCB327 (D + F) + WY
328  sLCB328 (D + F) - WY
329  sLCB329 (D + F) + EX + 0.3EY + EZ
330  sLCB330 (D + F) + EX + 0.3EY – EZ
331  sLCB331 (D + F) + EX - 0.3EY + EZ
332  sLCB332 (D + F) + EX - 0.3EY – EZ
333  sLCB333 (D + F) - EX + 0.3EY + EZ
334  sLCB334 (D + F) - EX + 0.3EY – EZ
335  sLCB335 (D + F) - EX - 0.3EY + EZ
336  sLCB336 (D + F) - EX - 0.3EY – EZ

351
Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-007

337  sLCB337 (D + F) + 0.3EX + EY + EZ


338  sLCB338 (D + F) + 0.3EX + EY – EZ
339  sLCB339 (D + F) + 0.3EX - EY + EZ
340  sLCB340 (D + F) + 0.3EX - EY – EZ
341  sLCB341 (D + F) - 0.3EX + EY + EZ
342  sLCB342 (D + F) - 0.3EX + EY – EZ
343  sLCB343 (D + F) - 0.3EX - EY + EZ
344  sLCB344 (D + F) - 0.3EX - EY – EZ
345  sLCB345 (D + F) + 0.75WX + 0.75L+ 0.75L_ + 0.75Lr
346  sLCB346 (D + F) - 0.75WX + 0.75L+ 0.75L_ + 0.75Lr
347  sLCB347 (D + F) + 0.75WY + 0.75L+ 0.75L_ + 0.75Lr
348  sLCB348 (D + F) - 0.75WY + 0.75L+ 0.75L_ + 0.75Lr
349  sLCB349 (D + F) + 0.75(EX + 0.3EY + EZ) + 0.75L+ 0.75L_
350  sLCB350 (D + F) + 0.75(EX + 0.3EY - EZ) + 0.75L+ 0.75L_
351  sLCB351 (D + F) + 0.75(EX - 0.3EY + EZ) + 0.75L+ 0.75L_
352  sLCB352 (D + F) + 0.75(EX - 0.3EY - EZ) + 0.75L+ 0.75L_
353  sLCB353 (D + F) + 0.75(-EX + 0.3EY + EZ) + 0.75L+ 0.75L_
354  sLCB354 (D + F) + 0.75(-EX + 0.3EY - EZ) + 0.75L+ 0.75L_
355  sLCB355 (D + F) + 0.75(-EX - 0.3EY + EZ) + 0.75L+ 0.75L_
356  sLCB356 (D + F) + 0.75(-EX - 0.3EY - EZ) + 0.75L+ 0.75L_
357  sLCB357 (D + F) + 0.75(0.3EX + EY + EZ) + 0.75L+ 0.75L_
358  sLCB358 (D + F) + 0.75(0.3EX + EY - EZ) + 0.75L+ 0.75L_
359  sLCB359 (D + F) + 0.75(0.3EX - EY + EZ) + 0.75L+ 0.75L_
360  sLCB360 (D + F) + 0.75(0.3EX - EY - EZ) + 0.75L+ 0.75L_
361  sLCB361 (D + F) + 0.75(-0.3EX + EY + EZ) + 0.75L+ 0.75L_
362  sLCB362 (D + F) + 0.75(-0.3EX + EY - EZ) + 0.75L+ 0.75L_
363  sLCB363 (D + F) + 0.75(-0.3EX - EY + EZ) + 0.75L+ 0.75L_
364  sLCB364 (D + F) + 0.75(-0.3EX - EY - EZ) + 0.75L+ 0.75L_
365  sLCB365 0.6(D) + WX
366  sLCB366 0.6(D) - WY
367  sLCB367 0.6(D) + WY

352
Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-007

368  sLCB368 0.6(D) - WY


369  sLCB369 0.6(D + F) + EX + 0.3EY + EZ
370  sLCB370 0.6(D + F) + EX + 0.3EY - EZ
371  sLCB371 0.6(D + F) + EX - 0.3EY + EZ
372  sLCB372 0.6(D + F) + EX - 0.3EY - EZ
373  sLCB373 0.6(D + F) - EX + 0.3EY + EZ
374  sLCB374 0.6(D + F) - EX + 0.3EY - EZ
375  sLCB375 0.6(D + F) - EX - 0.3EY + EZ
376  sLCB376 0.6(D + F) - EX - 0.3EY - EZ
377  sLCB377 0.6(D + F) + 0.3EX + EY + EZ
378  sLCB378 0.6(D + F) + 0.3EX + EY - EZ
379  sLCB379 0.6(D + F) + 0.3EX - EY + EZ
380  sLCB380 0.6(D + F) + 0.3EX - EY - EZ
381  sLCB381 0.6(D + F) - 0.3EX + EY + EZ
382  sLCB382 0.6(D + F) - 0.3EX + EY - EZ
383  sLCB383 0.6(D + F) - 0.3EX - EY + EZ
384  sLCB384 0.6(D + F) - 0.3EX - EY - EZ
385  sLCB385 (D + T1)
386  sLCB386 (D + T1) + L + L_
387  sLCB387 (D + T1) + Lr
388  sLCB388 (D + T1) + 0.75L + 0.75L_ + 0.75Lr
389  sLCB389 (D + T1) + WX
390  sLCB390 (D + T1) - WX
391  sLCB391 (D + T1) + WY
392  sLCB392 (D + T1) - WY
393  sLCB393 (D + T1) + EX + 0.3EY + EZ
394  sLCB394 (D + T1) + EX + 0.3EY - EZ
395  sLCB395 (D + T1) + EX - 0.3EY + EZ
396  sLCB396 (D + T1) + EX - 0.3EY - EZ
397  sLCB397 (D + T1) - EX + 0.3EY + EZ
398  sLCB398 (D + T1) - EX + 0.3EY - EZ

353
Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-007

399  sLCB399 (D + T1) - EX - 0.3EY + EZ


400  sLCB400 (D + T1) - EX - 0.3EY - EZ
401  sLCB401 (D + T1) + 0.3EX + EY + EZ
402  sLCB402 (D + T1) + 0.3EX + EY - EZ
403  sLCB403 (D + T1) + 0.3EX - EY + EZ
404  sLCB404 (D + T1) + 0.3EX - EY - EZ
405  sLCB405 (D + T1) - 0.3EX + EY + EZ
406  sLCB406 (D + T1) - 0.3EX + EY - EZ
407  sLCB407 (D + T1) - 0.3EX - EY + EZ
408  sLCB408 (D + T1) - 0.3EX - EY - EZ
409  sLCB409 (D + T1) + 0.75WX + 0.75L+ 0.75L_ + 0.75Lr
410  sLCB410 (D + T1) - 0.75WX + 0.75L+ 0.75L_ + 0.75Lr
411  sLCB411 (D + T1) + 0.75WY + 0.75L+ 0.75L_ + 0.75Lr
412  sLCB412 (D + T1) - 0.75WY + 0.75L+ 0.75L_ + 0.75Lr
413  sLCB413 (D + T1) + 0.75(EX + 0.3EY + EZ) + 0.75L+ 0.75L_
414  sLCB414 (D + T1) + 0.75(EX + 0.3EY - EZ) + 0.75L+ 0.75L_
415  sLCB415 (D + T1) + 0.75(EX - 0.3EY + EZ) + 0.75L+ 0.75L_
416  sLCB416 (D + T1) + 0.75(EX - 0.3EY - EZ) + 0.75L+ 0.75L_
417  sLCB417 (D + T1) + 0.75(-EX + 0.3EY + EZ) + 0.75L+ 0.75L_
418  sLCB418 (D + T1) + 0.75(-EX + 0.3EY - EZ) + 0.75L+ 0.75L_
419  sLCB419 (D + T1) + 0.75(-EX - 0.3EY + EZ) + 0.75L+ 0.75L_
420  sLCB420 (D + T1) + 0.75(-EX - 0.3EY - EZ) + 0.75L+ 0.75L_
421  sLCB421 (D + T1) + 0.75(0.3EX + EY + EZ) + 0.75L+ 0.75L_
422  sLCB422 (D + T1) + 0.75(0.3EX + EY - EZ) + 0.75L+ 0.75L_
423  sLCB423 (D + T1) + 0.75(0.3EX - EY + EZ) + 0.75L+ 0.75L_
424  sLCB424 (D + T1) + 0.75(0.3EX - EY - EZ) + 0.75L+ 0.75L_
425  sLCB425 (D + T1) + 0.75(-0.3EX + EY + EZ) + 0.75L+ 0.75L_
426  sLCB426 (D + T1) + 0.75(-0.3EX + EY - EZ) + 0.75L+ 0.75L_
427  sLCB427 (D + T1) + 0.75(-0.3EX - EY + EZ) + 0.75L+ 0.75L_
428  sLCB428 (D + T1) + 0.75(-0.3EX - EY - EZ) + 0.75L+ 0.75L_
429  sLCB429 0.6(D + T1) + EX + 0.3EY + EZ

354
Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-007

430  sLCB430 0.6(D + T1) + EX + 0.3EY – EZ


431  sLCB431 0.6(D + T1) + EX - 0.3EY + EZ
432  sLCB432 0.6(D + T1) + EX - 0.3EY - EZ
433  sLCB433 0.6(D + T1) - EX + 0.3EY + EZ
434  sLCB434 0.6(D + T1) - EX + 0.3EY – EZ
435  sLCB435 0.6(D + T1) - EX - 0.3EY + EZ
436  sLCB436 0.6(D + T1) - EX - 0.3EY - EZ
437  sLCB437 0.6(D + T1) + 0.3EX + EY + EZ
438  sLCB438 0.6(D + T1) + 0.3EX + EY - EZ

439  sLCB439 0.6(D + T1) + 0.3EX - EY + EZ


440  sLCB440 0.6(D + T1) + 0.3EX - EY - EZ

441  sLCB441 0.6(D + T1) - 0.3EX + EY + EZ


442  sLCB442 0.6(D + T1) - 0.3EX + EY - EZ

443  sLCB443 0.6(D + T1) - 0.3EX - EY + EZ


444  sLCB444 0.6(D + T1) - 0.3EX - EY - EZ

445  sLCB445 (D + T2)


446  sLCB446 (D + T2) + L + L_
447  sLCB447 (D + T2) + Lr
448  sLCB448 (D + T2) + 0.75L + 0.75L_ + 0.75Lr
449  sLCB449 (D + T2) + WX
450  sLCB450 (D + T2) - WX
451  sLCB451 (D + T2) + WY
452  sLCB452 (D + T2) - WY
453  sLCB453 (D + T2) + EX + 0.3EY + EZ
454  sLCB454 (D + T2) + EX + 0.3EY - EZ
455  sLCB455 (D + T2) + EX - 0.3EY + EZ
456  sLCB456 (D + T2) + EX - 0.3EY - EZ
457  sLCB457 (D + T2) - EX + 0.3EY + EZ
458  sLCB458 (D + T2) - EX + 0.3EY - EZ
459  sLCB459 (D + T2) - EX - 0.3EY + EZ
460  sLCB460 (D + T2) - EX - 0.3EY - EZ

355
Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-007

461  sLCB461 (D + T2) + 0.3EX + EY + EZ


462  sLCB462 (D + T2) + 0.3EX + EY - EZ
463  sLCB463 (D + T2) + 0.3EX - EY + EZ
464  sLCB464 (D + T2) + 0.3EX - EY - EZ
465  sLCB465 (D + T2) - 0.3EX + EY + EZ
466  sLCB466 (D + T2) - 0.3EX + EY - EZ
467  sLCB467 (D + T2) - 0.3EX - EY + EZ
468  sLCB468 (D + T2) - 0.3EX - EY - EZ
469  sLCB469 (D + T2) + 0.75WX + 0.75L+ 0.75L_ + 0.75Lr
470  sLCB470 (D + T2) - 0.75WX + 0.75L+ 0.75L_ + 0.75Lr
471  sLCB471 (D + T2) + 0.75WY + 0.75L+ 0.75L_ + 0.75Lr
472  sLCB472 (D + T2) - 0.75WY + 0.75L+ 0.75L_ + 0.75Lr
473  sLCB473 (D + T2) + 0.75(EX + 0.3EY + EZ) + 0.75L+ 0.75L_
474  sLCB474 (D + T2) + 0.75(EX + 0.3EY - EZ) + 0.75L+ 0.75L_
475  sLCB475 (D + T2) + 0.75(EX – 0.3EY + EZ) + 0.75L+ 0.75L_
476  sLCB476 (D + T2) + 0.75(EX – 0.3EY - EZ) + 0.75L+ 0.75L_
477  sLCB477 (D + T2) + 0.75(-EX + 0.3EY + EZ) + 0.75L+ 0.75L_
478  sLCB478 (D + T2) + 0.75(-EX + 0.3EY - EZ) + 0.75L+ 0.75L_
479  sLCB479 (D + T2) + 0.75(-EX – 0.3EY + EZ) + 0.75L+ 0.75L_
480  sLCB480 (D + T2) + 0.75(-EX – 0.3EY - EZ) + 0.75L+ 0.75L_
481  sLCB481 (D + T2) + 0.75(0.3EX + EY + EZ) + 0.75L+ 0.75L_
482  sLCB482 (D + T2) + 0.75(0.3EX + EY - EZ) + 0.75L+ 0.75L_
483  sLCB483 (D + T2) + 0.75(0.3EX - EY + EZ) + 0.75L+ 0.75L_
484  sLCB484 (D + T2) + 0.75(0.3EX - EY - EZ) + 0.75L+ 0.75L_
485  sLCB485 (D + T2) + 0.75(-0.3EX + EY + EZ) + 0.75L+ 0.75L_
486  sLCB486 (D + T2) + 0.75(-0.3EX + EY - EZ) + 0.75L+ 0.75L_
487  sLCB487 (D + T2) + 0.75(-0.3EX - EY + EZ) + 0.75L+ 0.75L_
488  sLCB488 (D + T2) + 0.75(-0.3EX - EY - EZ) + 0.75L+ 0.75L_
489  sLCB489 0.6(D + T2) + EX + 0.3EY + EZ
490  sLCB490 0.6(D + T2) + EX + 0.3EY - EZ
491  sLCB491 0.6(D + T2) + EX - 0.3EY + EZ

356
Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-007

492  sLCB492 0.6(D + T2) + EX - 0.3EY - EZ


493  sLCB493 0.6(D + T2) - EX + 0.3EY + EZ
494  sLCB494 0.6(D + T2) - EX + 0.3EY - EZ
495  sLCB495 0.6(D + T2) - EX - 0.3EY + EZ
496  sLCB496 0.6(D + T2) - EX - 0.3EY - EZ
497  sLCB497 0.6(D + T2) + 0.3EX + EY + EZ
498  sLCB498 0.6(D + T2) + 0.3EX + EY - EZ

499  sLCB499 0.6(D + T2) + 0.3EX - EY + EZ


500  sLCB500 0.6(D + T2) + 0.3EX - EY - EZ

501  sLCB501 0.6(D + T2) - 0.3EX + EY + EZ


502  sLCB502 0.6(D + T2) - 0.3EX + EY - EZ

503  sLCB503 0.6(D + T2) - 0.3EX - EY + EZ


504  sLCB504 0.6(D + T2) - 0.3EX - EY - EZ

505  sLCB505 (D + T3)


506  sLCB506 (D + T3) + L + L_
507  sLCB507 (D + T3) + Lr
508  sLCB508 (D + T3) + 0.75L + 0.75L_ + 0.75Lr
509  sLCB509 (D + T3) + WX
510  sLCB510 (D + T3) - WX
511  sLCB511 (D + T3) + WY
512  sLCB512 (D + T3) - WY
513  sLCB513 (D + T3) + EX + 0.3EY + EZ
514  sLCB514 (D + T3) + EX + 0.3EY - EZ
515  sLCB515 (D + T3) + EX - 0.3EY + EZ
516  sLCB516 (D + T3) + EX - 0.3EY - EZ
517  sLCB517 (D + T3) - EX + 0.3EY + EZ
518  sLCB518 (D + T3) - EX + 0.3EY - EZ
519  sLCB519 (D + T3) - EX - 0.3EY + EZ
520  sLCB520 (D + T3) - EX - 0.3EY - EZ
521  sLCB521 (D + T3) + 0.3EX + EY + EZ
522  sLCB522 (D + T3) + 0.3EX + EY - EZ

357
Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-007

523  sLCB523 (D + T3) + 0.3EX - EY + EZ


524  sLCB524 (D + T3) + 0.3EX - EY - EZ
525  sLCB525 (D + T3) - 0.3EX + EY + EZ
526  sLCB526 (D + T3) - 0.3EX + EY - EZ
527  sLCB527 (D + T3) - 0.3EX - EY + EZ
528  sLCB528 (D + T3) - 0.3EX - EY - EZ
529  sLCB529 (D + T3) + 0.75WX + 0.75L+ 0.75L_ + 0.75Lr
530  sLCB530 (D + T3) - 0.75WX + 0.75L+ 0.75L_ + 0.75Lr
531  sLCB531 (D + T3) + 0.75WY + 0.75L+ 0.75L_ + 0.75Lr
532  sLCB532 (D + T3) - 0.75WY + 0.75L+ 0.75L_ + 0.75Lr
533  sLCB533 (D + T3) + 0.75(EX + 0.3EY + EZ) + 0.75L+ 0.75L_
534  sLCB534 (D + T3) + 0.75(EX + 0.3EY - EZ) + 0.75L+ 0.75L_
535  sLCB535 (D + T3) + 0.75(EX - 0.3EY + EZ) + 0.75L+ 0.75L_
536  sLCB536 (D + T3) + 0.75(EX - 0.3EY - EZ) + 0.75L+ 0.75L_
537  sLCB537 (D + T3) + 0.75(-EX + 0.3EY + EZ) + 0.75L+ 0.75L_
538  sLCB538 (D + T3) + 0.75(-EX + 0.3EY - EZ) + 0.75L+ 0.75L_
539  sLCB539 (D + T3) + 0.75(-EX - 0.3EY + EZ) + 0.75L+ 0.75L_
540  sLCB540 (D + T3) + 0.75(-EX - 0.3EY - EZ) + 0.75L+ 0.75L_
541  sLCB541 (D + T3) + 0.75(0.3EX + EY + EZ) + 0.75L+ 0.75L_
542  sLCB542 (D + T3) + 0.75(0.3EX + EY - EZ) + 0.75L+ 0.75L_
543  sLCB543 (D + T3) + 0.75(0.3EX - EY + EZ) + 0.75L+ 0.75L_
544  sLCB544 (D + T3) + 0.75(0.3EX - EY - EZ) + 0.75L+ 0.75L_
545  sLCB545 (D + T3) + 0.75(-0.3EX + EY + EZ) + 0.75L+ 0.75L_
546  sLCB546 (D + T3) + 0.75(-0.3EX + EY - EZ) + 0.75L+ 0.75L_
547  sLCB547 (D + T3) + 0.75(-0.3EX - EY + EZ) + 0.75L+ 0.75L_
548  sLCB548 (D + T3) + 0.75(-0.3EX - EY - EZ) + 0.75L+ 0.75L_
549  sLCB549 0.6(D + T3) + EX + 0.3EY + EZ
550  sLCB550 0.6(D + T3) + EX + 0.3EY - EZ
551  sLCB551 0.6(D + T3) + EX - 0.3EY + EZ
552  sLCB552 0.6(D + T3) + EX - 0.3EY - EZ
553  sLCB553 0.6(D + T3) - EX + 0.3EY + EZ

358
Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-007

554  sLCB554 0.6(D + T3) - EX + 0.3EY - EZ


555  sLCB555 0.6(D + T3) - EX - 0.3EY + EZ
556  sLCB556 0.6(D + T3) - EX - 0.3EY - EZ
557  sLCB557 0.6(D + T3) + 0.3EX + EY + EZ
558  sLCB558 0.6(D + T3) + 0.3EX + EY - EZ

559  sLCB559 0.6(D + T3) + 0.3EX - EY + EZ


560  sLCB560 0.6(D + T3) + 0.3EX - EY - EZ

561  sLCB561 0.6(D + T3) - 0.3EX + EY + EZ


562  sLCB562 0.6(D + T3) - 0.3EX + EY - EZ

563  sLCB563 0.6(D + T3) - 0.3EX - EY + EZ


564  sLCB564 0.6(D + T3) - 0.3EX - EY - EZ

565  sLCB565 (D + T4)


566  sLCB566 (D + T4) + L + L_
567  sLCB567 (D + T4) + Lr
568  sLCB568 (D + T4) + 0.75L + 0.75L_ + 0.75Lr
569  sLCB569 (D + T4) + WX
570  sLCB570 (D + T4) - WX
571  sLCB571 (D + T4) + WY
572  sLCB572 (D + T4) - WY
573  sLCB573 (D + T4) + EX + 0.3EY + EZ
574  sLCB574 (D + T4) + EX + 0.3EY - EZ
575  sLCB575 (D + T4) + EX - 0.3EY + EZ
576  sLCB576 (D + T4) + EX - 0.3EY - EZ
577  sLCB577 (D + T4) - EX + 0.3EY + EZ
578  sLCB578 (D + T4) - EX + 0.3EY - EZ
579  sLCB579 (D + T4) - EX - 0.3EY + EZ
580  sLCB580 (D + T4) - EX - 0.3EY - EZ
581  sLCB581 (D + T4) + 0.3EX + EY + EZ
582  sLCB582 (D + T4) + 0.3EX + EY - EZ
583  sLCB583 (D + T4) + 0.3EX - EY + EZ
584  sLCB584 (D + T4) + 0.3EX - EY - EZ

359
Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-007

585  sLCB585 (D + T4) - 0.3EX + EY + EZ


586  sLCB586 (D + T4) - 0.3EX + EY - EZ
587  sLCB587 (D + T4) - 0.3EX - EY + EZ
588  sLCB588 (D + T4) - 0.3EX - EY - EZ
589  sLCB589 (D + T4) + 0.75WX + 0.75L+ 0.75L_ + 0.75Lr
590  sLCB590 (D + T4) - 0.75WX + 0.75L+ 0.75L_ + 0.75Lr
591  sLCB591 (D + T4) + 0.75WY + 0.75L+ 0.75L_ + 0.75Lr
592  sLCB592 (D + T4) - 0.75WY + 0.75L+ 0.75L_ + 0.75Lr
593  sLCB593 (D + T4) + 0.75(EX + 0.3EY + EZ) + 0.75L+ 0.75L_
594  sLCB594 (D + T4) + 0.75(EX + 0.3EY - EZ) + 0.75L+ 0.75L_
595  sLCB595 (D + T4) + 0.75(EX - 0.3EY + EZ) + 0.75L+ 0.75L_
596  sLCB596 (D + T4) + 0.75(EX - 0.3EY - EZ) + 0.75L+ 0.75L_
597  sLCB597 (D + T4) + 0.75(-EX + 0.3EY + EZ) + 0.75L+ 0.75L_
598  sLCB598 (D + T4) + 0.75(-EX + 0.3EY - EZ) + 0.75L+ 0.75L_
599  sLCB599 (D + T4) + 0.75(-EX - 0.3EY + EZ) + 0.75L+ 0.75L_
600  sLCB600 (D + T4) + 0.75(-EX - 0.3EY - EZ) + 0.75L+ 0.75L_
601  sLCB601 (D + T4) + 0.75(0.3EX + EY + EZ) + 0.75L+ 0.75L_
602  sLCB602 (D + T4) + 0.75(0.3EX + EY - EZ) + 0.75L+ 0.75L_
603  sLCB603 (D + T4) + 0.75(0.3EX - EY + EZ) + 0.75L+ 0.75L_
604  sLCB604 (D + T4) + 0.75(0.3EX - EY - EZ) + 0.75L+ 0.75L_
605  sLCB605 (D + T4) + 0.75(-0.3EX + EY + EZ) + 0.75L+ 0.75L_
606  sLCB606 (D + T4) + 0.75(-0.3EX + EY - EZ) + 0.75L+ 0.75L_
607  sLCB607 (D + T4) + 0.75(-0.3EX - EY + EZ) + 0.75L+ 0.75L_
608  sLCB608 (D + T4) + 0.75(-0.3EX - EY - EZ) + 0.75L+ 0.75L_
609  sLCB609 0.6(D + T4) + EX + 0.3EY + EZ
610  sLCB610 0.6(D + T4) + EX + 0.3EY - EZ
611  sLCB611 0.6(D + T4) + EX - 0.3EY + EZ
612  sLCB612 0.6(D + T4) + EX - 0.3EY - EZ
613  sLCB613 0.6(D + T4) - EX + 0.3EY + EZ
614  sLCB614 0.6(D + T4) - EX + 0.3EY - EZ
615  sLCB615 0.6(D + T4) - EX - 0.3EY + EZ

360
Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-007

616  sLCB616 0.6(D + T4) - EX - 0.3EY - EZ


617  sLCB617 0.6(D + T4) + 0.3EX + EY + EZ
618  sLCB618 0.6(D + T4) + 0.3EX + EY - EZ

619  sLCB619 0.6(D + T4) + 0.3EX - EY + EZ


620  sLCB620 0.6(D + T4) + 0.3EX - EY - EZ

621  sLCB621 0.6(D + T4) - 0.3EX + EY + EZ


622  sLCB622 0.6(D + T4) - 0.3EX + EY - EZ

623  sLCB623 0.6(D + T4) - 0.3EX - EY + EZ


624  sLCB624 0.6(D + T4) - 0.3EX - EY - EZ

625  sLCB625 (D + T5)


626  sLCB626 (D + T5) + L + L_
627  sLCB627 (D + T5) + Lr
628  sLCB628 (D + T5) + 0.75L + 0.75L_ + 0.75Lr
629  sLCB629 (D + T5) + WX
630  sLCB630 (D + T5) - WX
631  sLCB631 (D + T5) + WY
632  sLCB632 (D + T5) - WY
633  sLCB633 (D + T5) + EX + 0.3EY + EZ
634  sLCB634 (D + T5) + EX + 0.3EY - EZ
635  sLCB635 (D + T5) + EX - 0.3EY + EZ
636  sLCB636 (D + T5) + EX - 0.3EY - EZ
637  sLCB637 (D + T5) - EX + 0.3EY + EZ
638  sLCB638 (D + T5) - EX + 0.3EY - EZ
639  sLCB639 (D + T5) - EX - 0.3EY + EZ
640  sLCB640 (D + T5) - EX - 0.3EY - EZ
641  sLCB641 (D + T5) + 0.3EX + EY + EZ
642  sLCB642 (D + T5) + 0.3EX + EY - EZ
643  sLCB643 (D + T5) + 0.3EX - EY + EZ
644  sLCB644 (D + T5) + 0.3EX - EY - EZ
645  sLCB645 (D + T5) - 0.3EX + EY + EZ
646  sLCB646 (D + T5) - 0.3EX + EY - EZ

361
Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-007

647  sLCB647 (D + T5) - 0.3EX - EY + EZ


648  sLCB648 (D + T5) - 0.3EX - EY - EZ
649  sLCB649 (D + T5) + 0.75WX + 0.75L+ 0.75L_ + 0.75Lr
650  sLCB650 (D + T5) - 0.75WX + 0.75L+ 0.75L_ + 0.75Lr
651  sLCB651 (D + T5) + 0.75WY + 0.75L+ 0.75L_ + 0.75Lr
652  sLCB652 (D + T5) - 0.75WY + 0.75L+ 0.75L_ + 0.75Lr
653  sLCB653 (D + T5) + 0.75(EX + 0.3EY + EZ) + 0.75L+ 0.75L_
654  sLCB654 (D + T5) + 0.75(EX + 0.3EY - EZ) + 0.75L+ 0.75L_
655  sLCB655 (D + T5) + 0.75(EX - 0.3EY + EZ) + 0.75L+ 0.75L_
656  sLCB656 (D + T5) + 0.75(EX - 0.3EY - EZ) + 0.75L+ 0.75L_
657  sLCB657 (D + T5) + 0.75(-EX + 0.3EY + EZ) + 0.75L+ 0.75L_
658  sLCB658 (D + T5) + 0.75(-EX + 0.3EY - EZ) + 0.75L+ 0.75L_
659  sLCB659 (D + T5) + 0.75(-EX - 0.3EY + EZ) + 0.75L+ 0.75L_
660  sLCB660 (D + T5) + 0.75(-EX - 0.3EY - EZ) + 0.75L+ 0.75L_
661  sLCB661 (D + T5) + 0.75(0.3EX + EY + EZ) + 0.75L+ 0.75L_
662  sLCB662 (D + T5) + 0.75(0.3EX + EY - EZ) + 0.75L+ 0.75L_
663  sLCB663 (D + T5) + 0.75(0.3EX - EY + EZ) + 0.75L+ 0.75L_
664  sLCB664 (D + T5) + 0.75(0.3EX - EY - EZ) + 0.75L+ 0.75L_
665  sLCB665 (D + T5) + 0.75(-0.3EX + EY + EZ) + 0.75L+ 0.75L_
666  sLCB666 (D + T5) + 0.75(-0.3EX + EY - EZ) + 0.75L+ 0.75L_
667  sLCB667 (D + T5) + 0.75(-0.3EX - EY + EZ) + 0.75L+ 0.75L_
668  sLCB668 (D + T5) + 0.75(-0.3EX - EY - EZ) + 0.75L+ 0.75L_
669  sLCB669 0.6(D + T5) + EX + 0.3EY + EZ
670  sLCB670 0.6(D + T5) + EX + 0.3EY - EZ
671  sLCB671 0.6(D + T5) + EX - 0.3EY + EZ
672  sLCB672 0.6(D + T5) + EX - 0.3EY - EZ
673  sLCB673 0.6(D + T5) - EX + 0.3EY + EZ
674  sLCB674 0.6(D + T5) - EX + 0.3EY - EZ
675  sLCB675 0.6(D + T5) - EX - 0.3EY + EZ
676  sLCB676 0.6(D + T5) - EX - 0.3EY - EZ
677  sLCB677 0.6(D + T5) + 0.3EX + EY + EZ

362
Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-007

678  sLCB678 0.6(D + T5) + 0.3EX + EY - EZ

679  sLCB679 0.6(D + T5) + 0.3EX - EY + EZ


680  sLCB680 0.6(D + T5) + 0.3EX - EY - EZ

681  sLCB681 0.6(D + T5) - 0.3EX + EY + EZ


682  sLCB682 0.6(D + T5) - 0.3EX + EY - EZ

683  sLCB683 0.6(D + T5) - 0.3EX - EY + EZ


684  sLCB684 0.6(D + T5) - 0.3EX - EY - EZ

685  sLCB685 (D)


686  sLCB686 (D) + L + L_
687  sLCB687 (D) + Lr
688  sLCB688 (D) + 0.75L + 0.75L_ + 0.75Lr
689  sLCB689 (D) + WX
690  sLCB690 (D) - WX
691  sLCB691 (D) + WY
692  sLCB692 (D) - WY
693  sLCB693 (D) + EX + 0.3EY + EZ
694  sLCB694 (D) + EX + 0.3EY - EZ
695  sLCB695 (D) + EX - 0.3EY + EZ
696  sLCB696 (D) + EX - 0.3EY - EZ
697  sLCB697 (D) - EX + 0.3EY + EZ
698  sLCB698 (D) - EX + 0.3EY - EZ
699  sLCB699 (D) - EX - 0.3EY + EZ
700  sLCB700 (D) - EX - 0.3EY - EZ
701  sLCB701 (D) + 0.3EX + EY + EZ
702  sLCB702 (D) + 0.3EX + EY - EZ
703  sLCB703 (D) + 0.3EX - EY + EZ
704  sLCB704 (D) + 0.3EX - EY - EZ
705  sLCB705 (D) - 0.3EX + EY + EZ
706  sLCB706 (D) - 0.3EX + EY - EZ
707  sLCB707 (D) - 0.3EX - EY + EZ
708  sLCB708 (D) - 0.3EX - EY - EZ

363
Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-007

709  sLCB709 (D) + 0.75WX + 0.75L+ 0.75L_ + 0.75Lr


710  sLCB710 (D) - 0.75WX + 0.75L+ 0.75L_ + 0.75Lr
711  sLCB711 (D) + 0.75WY + 0.75L+ 0.75L_ + 0.75Lr
712  sLCB712 (D) - 0.75WY + 0.75L+ 0.75L_ + 0.75Lr
713  sLCB713 (D) + 0.75(EX + 0.3EY + EZ) + 0.75L+ 0.75L_
714  sLCB714 (D) + 0.75(EX + 0.3EY - EZ) + 0.75L+ 0.75L_
715  sLCB715 (D) + 0.75(EX - 0.3EY + EZ) + 0.75L+ 0.75L_
716  sLCB716 (D) + 0.75(EX - 0.3EY - EZ) + 0.75L+ 0.75L_
717  sLCB717 (D) + 0.75(-EX + 0.3EY + EZ) + 0.75L+ 0.75L_
718  sLCB718 (D) + 0.75(-EX + 0.3EY - EZ) + 0.75L+ 0.75L_
719  sLCB719 (D) + 0.75(-EX - 0.3EY + EZ) + 0.75L+ 0.75L_
720  sLCB720 (D) + 0.75(-EX - 0.3EY - EZ) + 0.75L+ 0.75L_
721  sLCB721 (D) + 0.75(0.3EX + EY + EZ) + 0.75L+ 0.75L_
722  sLCB722 (D) + 0.75(0.3EX + EY - EZ) + 0.75L+ 0.75L_
723  sLCB723 (D) + 0.75(0.3EX - EY + EZ) + 0.75L+ 0.75L_
724  sLCB724 (D) + 0.75(0.3EX - EY - EZ) + 0.75L+ 0.75L_
725  sLCB725 (D) + 0.75(-0.3EX + EY + EZ) + 0.75L+ 0.75L_
726  sLCB726 (D) + 0.75(-0.3EX + EY - EZ) + 0.75L+ 0.75L_
727  sLCB727 (D) + 0.75(-0.3EX - EY + EZ) + 0.75L+ 0.75L_
728  sLCB728 (D) + 0.75(-0.3EX - EY - EZ) + 0.75L+ 0.75L_
729  sLCB729 0.6(D) + EX + 0.3EY + EZ
730  sLCB730 0.6(D) + EX + 0.3EY - EZ
731  sLCB731 0.6(D) + EX - 0.3EY + EZ
732  sLCB732 0.6(D) + EX - 0.3EY - EZ
733  sLCB733 0.6(D) - EX + 0.3EY + EZ
734  sLCB734 0.6(D) - EX + 0.3EY - EZ
735  sLCB735 0.6(D) - EX - 0.3EY + EZ
736  sLCB736 0.6(D) - EX - 0.3EY - EZ
737  sLCB737 0.6(D) + 0.3EX + EY + EZ
738  sLCB738 0.6(D) + 0.3EX + EY - EZ

739  sLCB739 0.6(D) + 0.3EX - EY + EZ

364
Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-007

740  sLCB740 0.6(D) + 0.3EX - EY - EZ

741  sLCB741 0.6(D) - 0.3EX + EY + EZ


742  sLCB742 0.6(D) - 0.3EX + EY - EZ

743  sLCB743 0.6(D) - 0.3EX - EY + EZ


744  sLCB744 0.6(D) - 0.3EX - EY - EZ

365
Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-007

4. STRUCTURAL SYSTEM
4.1 Structural System and Analysis Condition
The seismic force-resisting system is Concentrically Braced Frame (CBF). A braced frame is
subjected primarily to axial forces.
Structural analysis program use SAP 2000. It’s performed to analyze three dimension structural
systems for checking serviceability of this structure on lateral load, designing column, beam and
brace.

4.1.1 Boundary Conditions


The boundary condition of column at ground level will be defined as a pinned connection in all the
Concetrical Braced Frames Structures.

If Necessary to define a Moment Frame Structure to Comply the Process Requirements, the boundary
condition of column at ground level will be defines as a semi-rigid moment connection in both
horizontal translational degrees of freedoms.

The semi – rigid condition is defined as a rotational spring with an associated rotational stiffness
according to the base plate and anchor bolts configuration, in order to determine this value it will be
necessary to build a detailed model of the column base and the anchor configuration.

4.1.2 Connection Condition between Duct Casing and Structure


The connection condition between duct casing and structure is sliding condition according to the duct
configuration. The gap size for sliding is determined by displacement due to the temperature load
(180℃).

For confined supports, which reduces the transfer of heat loads to the structure particularly in ducts
with revised L-shaped

4.1.3 Structural Element


- One dimensional element for steel structure modeling purposes as follows:
Korea Standard Section
Material = Steel KS D 3503 : SS400, Steel KS D 3515 : SM490

366
Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-007

- Shell element for Duct casing modeling purposes as follows:


Material = Steel KS D 3503 : SS400 (See section 2.2)

367
Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-007

368
Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-007

4.2 Base Plate and Anchor System


Column reaction resulting from the structural analysis shall be used for the design of base plates and
anchor bolts. Column base plate and anchor bolts shall be designed as per ACI 318-08 and AISC
360-05.
Base plate is made to transfer the column loads and moments to the footings and foundations. Anchor
rods are designed to provide the required resistance to loads which result from load combination
stipulated in Section 3.7.
The requirement that anchor bolts of columns shall have a projection of at least eight diameters and
no less than 250 mm measured from the base plates (according to Section 8.6.2 of NCh 2369),
provides adequate anchor bolts length to eventually allow for yielding of the anchor bolt under severe
earthquake loading.

Typical Detail of Column Base in Figure A.1 of NCh 2369 of 2003

369
Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-007

5. STRUCTURAL ANALYSIS
5.1 Base Shear and Equivalent Mass
These results are calculated by the analysis model for earthquake load.
If the base shear force is lower than the minimum base shear (0.12 X total weight), the scale-up factor
(12% of total weight / base shear) should be applied for earthquake load according to the Section
5.4.5 of NCh 2369 of 2003.

5.1.1 Mass Distribution


The self-weight is converted into masses automatically in SAP 2000 program.
Seismic mass percentages are considered according to Technical Specification.
It shall be considered the following percentage of seismic mass for live load:

Section Seismic Mass Percentage (%)

Area of Normal Use, Floor Live Load 25

Roof without Transit 0

Ducting 100

5.2 Natural Vibration Mode


These results are calculated by the analysis model. The analysis shall include a sufficient number of
vibration modes for the sum of equivalent masses in each analysis direction is equal to or higher than
90% of the total mass.

5.3 Support Reaction


These results are calculated by the analysis model in three directions.

Since the earthquake load was computed trough a Response Spectrum Analysis, its reactions are
absolute values. In order to design the foundations of this structure it is necessary to assign the sign
for each reaction according to the predominant modal shapes in the respective direction.

370
Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-007

5.4 Displacement

5.4.1 Displacement due to the Earthquake Load

The displacement for earthquake load can verified according to the Section 6.1 and 6.3.
d = d0 + R1dd
Where,
d = Seismic Deformation
dd = Deformation due to non-seismic service loads
R1 = Factor resulting from multiplying the R factor derived from Table 5.6 of NCh 2369 of 2003 by the
quotient Q0/Qmin provided that Q0/Qmin ne lower or equal to 1.0. However, for the quotient
Q0/Qmin a value under 0.5 shall not be used. If this quotient is higher than 1.0, R1 =R shall be
used.

The maximum seismic deformation for other structures is below:


dmax = 0.015 h
Where,
h = Height between floors of between two points located on the same vertical.

5.4.2 Separation between Structures

The separation between structures is calculated based on section 6.2 of NCh 2369. The purpose of
preventing impacts between adjoining structures, their separation shall be bigger than the highest of
the following values:

1) S = ((R1i ddi)2 + (R1j ddj)2)1/2 + d0i + d0j


2) S = 0.002 (hi + hj)
3) 30mm

Where, ddi, ddj : Deformation calculated with R-factor reduced earthquake load of the structures i and j
d0i, d0j : Deformation due to non-seismic service loads
R1i ,R1j : Response modification factors R1 used for the design of the structures i and j
hi, hj : Height at the considered level of the structures I and j measured from their respective
base levels

371
Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-007

5.5 Displacement of Sliding Support

Gap of the Sliding Support should be define according to the maximum displacement for all load
combinations.

5.6 Expansion Joint


Displacement of Expansion Joint due to the ASD load combination < E.J Capacity (Axial Compression,
Axial Extension, Lateral)........(OK)

372
Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-007

6. MEMBER DESIGN
The design of steel structures shall comply with “Earthquake-Resistant Design of Industrial Structures
and Facilities NCh 2369” and “Specification for Structural Steel Buildings AISC 360-05”.
The maximum slenderness can be considered in the design:

Element kl / r

Columns 1.5π√(E/Fy)
Other Elements in Compression 1.5π√(E/Fy)
Element in Traction 240
Bracing Resisting Seismic Load 1.5π√(E/Fy)

Member design was checked about all members of column, beam and brace and so on. On this
report, attached calculation note is about what the worst case of the load combination cases each
member.

373
Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-007

6.1 Column Design

6.1.1 Design Load


Load from LRFD Combination
- Pr : Maximum Axial Force
- Mr : Maximum Bending Moment
- Vr : Maximum Shear Force

6.1.2 Schematic Drawing

6.1.3 Verification (AISC360-05, NCh 2369)


1) Slenderness Ratio
- KL / r < 1.5π√(E/Fy)......(OK)
2) Seismic Width-Thickness
- λf = bf / 2tf < λps (for flange)......(OK)
- λw = h / tw < λps (for web)......(OK)
3) Axial Strength
- Pr / Pc < 1.0......(OK)
4) Bending Strength
- Mrx / Mcx < 1.0......(OK)
- Mry / Mcy < 1.0......(OK)
5) Combined Strength (Compression + Bending)
- For Pr / Pc ≥ 0.2 => Rmax = Pr / Pc + 8/9 X (Mrx / Mcx + Mry / Mcy) < 1.0......(OK)
- For Pr / Pc < 0.2 => Rmax = Pr / 2Pc + (Mrx / Mcx + Mry / Mcy) < 1.0......(OK)
6) Shear Strength
- Vrx / Vcx < 1.0......(OK)
- Vry / Vcy < 1.0......(OK)

374
Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-007

Where,
λps : Limiting Width-Thickness Ratio
Pc : Design Compressive Strength
Mc : Design Flexural Strength
Vc : Design Shear Strength

375
Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-007

6.2 Beam and Girder Design

6.2.1 Design Load


Load from LRFD Combination
- Pr : Maximum Axial Force
- Mr : Maximum Bending Moment
- Vr : Maximum Shear Force

6.2.2 Schematic Drawing

6.2.3 Verification (AISC360-05, NCh 2369)


1) Slenderness Ratio
- KL / r < 1.5π√(E/Fy)......(OK)
2) Seismic Width-Thickness
- λf = bf / 2tf < λps (for flange)......(OK)
- λw = h / tw < λps (for web)......(OK)
3) Axial Strength
- Pr / Pc < 1.0......(OK)
4) Bending Strength
- Mrx / Mcx < 1.0......(OK)
- Mry / Mcy < 1.0......(OK)
5) Combined Strength (Compression + Bending)
- For Pr / Pc ≥ 0.2 => Rmax = Pr / Pc + 8/9 X (Mrx / Mcx + Mry / Mcy) < 1.0......(OK)
- For Pr / Pc < 0.2 => Rmax = Pr / 2Pc + (Mrx / Mcx + Mry / Mcy) < 1.0......(OK)
6) Shear Strength
- Vrx / Vcx < 1.0......(OK)
- Vry / Vcy < 1.0......(OK)

376
Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-007

Where,
λps : Limiting Width-Thickness Ratio
Pc : Design Compressive Strength
Mc : Design Flexural Strength
Vc : Design Shear Strength

377
Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-007

6.3 Brace Design

6.3.1 Design Load


Load from LRFD Combination
- Pr : Maximum Axial Force
- Mr : Maximum Bending Moment
- Vr : Maximum Shear Force

6.3.2 Schematic Drawing

6.3.3 Verification (AISC360-05, NCh 2369)


1) Slenderness Ratio
- KL / r < 1.5π√(E/Fy)......(OK)
2) Seismic Width-Thickness
- λf = bf / 2tf < λps (for flange)......(OK)
- λw = h / tw < λps (for web)......(OK)
3) Axial Strength
- Pr / Pc < 0.8......(OK)
4) Bending Strength
- Mrx / Mcx < 0.8......(OK)
- Mry / Mcy < 0.8......(OK)
5) Combined Strength (Compression + Bending)
- For Pr / Pc ≥ 0.2 => Rmax = Pr / Pc + 8/9 X (Mrx / Mcx + Mry / Mcy) < 0.8......(OK)
- For Pr / Pc < 0.2 => Rmax = Pr / 2Pc + (Mrx / Mcx + Mry / Mcy) < 0.8......(OK)
6) Shear Strength
- Vrx / Vcx < 0.8......(OK)
- Vry / Vcy < 0.8......(OK)

378
Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-007

Where,
λps : Limiting Width-Thickness Ratio
Pc : Design Compressive Strength
Mc : Design Flexural Strength
Vc : Design Shear Strength

379
Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-007

6.4 Connection Design

6.4.1 Column Splice

6.4.1.1 Design Load


Full Capacity of Column
- Pu : Maximum Axial Force (= Φ Fy Ag)
- Mu : Maximum Bending Moment (= Φ Fy Zx)
- Vu : Maximum Shear Force (= 0.6 Φ Fy Aw)
- Tu : Maximum Tensile Force at Flange (=Mu / Arm of Column)

6.4.1.2 Schematic Drawing

6.4.1.3 Verification (AISC360-05)


1) Bolt Strength
- Shear Strength ΦRn1 = Φ Ns Fn Ab
- Bearing Strength at Bolt Holes ΦRn2 = Min (Φ 1.2 Lc t Fu, Φ 2.4 d t Fu)
- Slip-Critical Connections ΦRn3 = Φ μ Du hsc Tb Ns
- ΦRn = Min (ΦRn1, ΦRn2, ΦRn3)
- Pu / ΦRn < Number of Bolt......(OK)
- Vu / ΦRn < Number of Bolt......(OK)
- Tu / ΦRn < Number of Bolt......(OK)
2) Web Splice Plate Verification
- Shear Yielding Φ 0.6 Fy Ag ≥ Vu......(OK)

380
Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-007

- Shear Rupture Φ 0.6 Fu Anv ≥ Vu......(OK)


3) Flange Splice Plate Verification
- Tensile Yielding Φ Fy Ag ≥ Tu......(OK)
- Tensile Rupture Φ Fu Ae ≥ Tu......(OK)

381
Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-007

6.4.2 Beam Connection

6.4.2.1 Design Load


1) Special Earthquake Load Combination
- Ru1 is determined due to the 1.2D + 0.5L + ΩE
2) 0.5 X Full Capacity for Shear
- Ru2 = 0.5 Φ 0.6 Fy Aw Cv
3) Ru = Max (Ru1, Ru2)
4) If the load from brace are transferred to the girder and beam directly, the connection would be
designed by full capacity of brace.

6.4.2.2 Schematic Drawing

6.4.2.3 Verification (AISC360-05)


1) Bolt Strength
- Shear Strength ΦRn1 = Φ Ns Fn Ab
- Bearing Strength at Bolt Holes ΦRn2 = Min (Φ 1.2 Lc t Fu, Φ 2.4 d t Fu)
- Slip-Critical Connections ΦRn3 = Φ μ Du hsc Tb Ns
- ΦRn = Min (ΦRn1, ΦRn2, ΦRn3)
- Ru / ΦRn < Number of Bolt......(OK)
2) Web Splice Plate Verification
- Shear Yielding Φ 0.6 Fy Ag ≥ Ru......(OK)
- Shear Rupture Φ 0.6 Fu Anv ≥ Ru......(OK)
3) Block Shear Rupture Verification
- Φ (0.6 Fu Anv + Ubs Fu Ant) ≥ Ru......(OK)
- Φ (0.6 Fy Agv + Ubs Fu Ant) ≥ Ru......(OK)

382
Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-007

6.4.3 Brace to Gusset Connection

6.4.3.1 Design Load


Full Capacity of Brace
- Tu : Maximum Tensile Force (= Ry Fy Ag)
- Pu : Maximum Compressive Force (= 1.1 Ry Pn)
- Ruw : Force in Web
- Ruf : Force in Flange

6.4.3.2 Schematic Drawing


In case of H-Shape Brace In case of Channel Brace

6.4.3.3 Verification in case of H-Shape Brace (AISC360-05)


1) Bolt Strength
- Shear Strength ΦRn1 = Φ Ns Fn Ab
- Bearing Strength at Bolt Holes ΦRn2 = Min(Φ 1.2 Lc t Fu, Φ 2.4 d t Fu)
- Slip-Critical Connections ΦRn3 = Φ μ Du hsc Tb Ns
- ΦRn = Min(ΦRn1, ΦRn2, ΦRn3)
- Ruf / ΦRn < Number of Bolt......(OK)
- Ruw / ΦRn < Number of Bolt......(OK)

383
Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-007

2) Tension Capacity of the Angles


- Tension Yielding Φ Fy Ag ≥ Ruf / 2......(OK)
Φ Fy Ag ≥ Ruw......(OK)
- Tension Rupture Φ Fu Ae ≥ Ruf / 2......(OK)
Φ Fu Ae ≥ Ruw......(OK)
3) Block Shear Rupture Verification of the Angles
- Φ (0.6 Rt Fu Anv + Ubs Rt Fu Ant) ≥ Ruf / 2......(OK)
- Φ (0.6 Ry Fy Agv + Ubs Rt Fu Ant) ≥ Ruf / 2......(OK)
- Φ (0.6 Rt Fu Anv + Ubs Rt Fu Ant) ≥ Rw......(OK)
- Φ (0.6 Ry Fy Agv + Ubs Rt Fu Ant) ≥ Rw......(OK)

6.4.3.4 Verification in case of Channel Brace (AISC360-05)


1) Bolt Strength
- Shear Strength ΦRn1 = Φ Ns Fn Ab
- Bearing Strength at Bolt Holes ΦRn2 = Min(Φ 1.2 Lc t Fu, Φ 2.4 d t Fu)
- Slip-Critical Connections ΦRn3 = Φ μ Du hsc Tb Ns
- ΦRn = Min(ΦRn1, ΦRn2, ΦRn3)
- Tu / ΦRn < Number of Bolt......(OK)
2) Net Section Fracture
- Φt Rt Fu Ae ≥ Tu......(OK)
3) Block Shear Rupture Verification of the Angles
- Φ (0.6 Rt Fu Anv + Ubs Rt Fu Ant) ≥ Tu......(OK)
- Φ (0.6 Ry Fy Agv + Ubs Rt Fu Ant) ≥ Tu......(OK)

384
Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-007

6.4.4 Gusset Plate Design

6.4.4.1 Design Load


Full Capacity of Brace
- Tu : Maximum Tensile Force (= Ry Fy Ag)
- Pu : Maximum Compressive Force (= 1.1 Ry Pn)

6.4.4.2 Schematic Drawing


Concept Drawing Design Force of Gusset Plate

Whitmore Section of Gusset Plate

6.4.4.3 Verification (AISC360-05)


1) Design the Weld at the Gusset-Column Interface

385
Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-007

- fv = Huc / 2β
- fa = Vuc / 2β
- fb = 0
- fpeak = √[fv2 + (fa + fb)2]
- favg = (1/2) × {√[(fa - fb)2 + fv2] +√[(fa + fb)2+ fv2]}
- fr = 1.25 X favg (If fpeak / favg < 1.25)
- fr = fpeak (If fpeak / favg ≥ 1.25)
- s ≥ fr / (0.7 (0.9) (0.6) Fy (2))......(OK)
- tmin (=2 (0.9) (0.6) Fy 0.7s / (0.75 (0.6) Fu) < thickness of gusset plate......(OK)
2) Yielding of Gusset Plate
- ΦRn (=Φ Fy t) > MAX.(fv,fa)......(OK)
3) Column Web Yielding
- ΦRn (=Φ Fy tw) > fr......(OK)
4) Column Web Crippling
- ΦRn = Φ 0.8 tw2 [1 + 3(N / d) (tw / tf)1.5] √(E Fyw tf / tw) > Huc......(OK)
5) Design the Weld at the Gusset-Beam Interface (In Tension and Compression)
- fv = Hub / 2α
- fa = Vub / 2α
- fb = Mub / Sw (Sw = (2α)2 / 6)
- fpeak = √[fv2 + (fa + fb)2]
- favg = (1/2) × {√[(fa - fb)2 + fv2] +√[(fa + fb)2+ fv2]}
- fr = 1.25 X favg (If fpeak / favg < 1.25)
- fr = fpeak (If fpeak / favg ≥ 1.25)
- s ≥ fr / (0.7 (0.9) (0.6) Fy (2))......(OK)
- tmin (=2 (0.9) (0.6) Fy 0.7s / (0.75 (0.6) Fu) < thickness of gusset plate......(OK)
6) Yielding of Gusset Plate
- ΦRn (=Φ Fy t) > MAX.(fv,fa)......(OK)
7) Beam Web Yielding
- ΦRn (=Φ Fy tw) > fr......(OK)
8) Beam Web Local Yielding (if the brace connection is located in center of girder)
- ft = fa + fb
- fc = fa – fb
- Lt = [ft / (ft + tc)] / Lg
- Ru = (1/2) Lt ft
- ΦRn = (5k + N) Fyw tw

386
Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-007

- Ru < ΦRn......(OK)
9) Beam Web Crippling
- Ru = [Mub / (N2 / 4)] (N / 2) + Vub = 2Mub / N + Vub
- ΦRn = Φ 0.4 tw2 [1 + 3(N / d) (tw / tf)1.5] √(E Fyw tf / tw) (N/d ≤ 0.2)
- ΦRn = Φ 0.4 tw2 [1 + (4N / d - 0.2) (tw / tf)1.5] √(E Fyw tf / tw) (N/d > 0.2)
- Ru < ΦRn......(OK)
10) Beam Web Crippling (if the brace connection is located in center of girder)
- Ru = (1/2) (Lg - Lt) fc
- ΦRn = Φ 0.8 tw2 [1 + 3(N / d) (tw / tf)1.5] √(E Fyw tf / tw)
- Ru < ΦRn......(OK)
11) Compression Buckling of Gusset Plate
- Φc Fcr Ag > Pu......(OK) (The Ag should be considered whitmore section)
12) Tensile Yielding of Gusset Plate
- Φt Fy Ag > Tu X Ratio of Resisting Bolt......(OK) (The Ag should be considered whitmore section)

387
Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-007

6.5 Base Plate and Anchor Bolt Design

6.5.1 Design Load


Load from LRFD Combination
- Pu : Maximum Compressive Force
- Tu : Maximum Tensile Force
- Mu : Maximum Bending Moment
- Vu : Maximum Shear Force

It should be considered biaxial bending on the base plate check.


It should be considered biaxial bending to define the anchor bolts design forces.

6.5.2 Schematic Drawing

6.5.3 Verification (AISC360-05, ACI318-08)


1) Bearing Stress of Base Plate
- Fp = 0.85 Φ fc √(A2 / A1)
- fp = Pu (1+6e / (N or B)) / A (In case of e < (N or B) / 6)
- fp < Fp......(OK)
2) Thickness of Base Plate
- t1 = √ (ß x fp x u2 / 1.5 Fy) (ß : derived by Roak’s Table)
- T3 = √ (ß x fp x (B / 2)2 / 1.5 Fy) (ß : derived by Roak’s Table)
- t > Max.(t1,T3) ......(OK)
3) Embedded Depth and Width of the Shear Key
- Φ Vn = 0.85 Φ fc A > Vu......(OK)

388
Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-007

4) Thickness of Shear Key


- treq = √ (ß x fp x Max(W/2-t/2, d+G)2 / 1.5 Fy) (ß : derived by Roak’s Table)
- treq > t ......(OK)
5) Bearing Strength of the Concrete
- Fp = 0.85 Φ fc √(A2 / A1)
- fp = Vu / (W X d)
- fp < Fp......(OK)
6) Anchor Bolt Verification
- Tension Strength : 0.75 Φ Nn = 0.75 Φ n Ase Fut > Tu......(OK)
- Tb = (Tu / 2 + (Mbuilt-in / (d-d’)) / Number of Bolt
- Ase,req = Tu / (0.75 Φ Tb) < Ase......(OK)
- Concrete Breakout Strength : Ncb = ANc / ANco x ψed,N x ψc,N x ψcp,N x Nb > Tu......(OK)
7) Design of Rib Plate
- Height of Rib Plate : 8d of 250mm
- Ru : Reaction due to the anchor bolt full capacity
- Φ Pn = Φ Ag Fcr > Ru......(OK)
- fa : Axial Stress due to the concrete pressure
- Fc > fa......(OK)
8) Design of Upper Plate
M : Bending Moment due to the anchor bolt full capacity
- Φ Fy Z = Φ Fy u T3 / 4 > M......(OK)
9) Design of Anchor Plate
M : Bending Moment due to the anchor bolt full capacity
- Φ Fy Z = Φ Fy u T3 / 4 > M......(OK)

389
Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-007

6.6 Connection between Duct and Structure

6.6.1 Design Load


Load from ASD Combination
- Pc : Maximum Compressive Force
- Pt : Maximum Tensile Force
- Vu : Maximum Shear Force

6.6.2 Schematic Drawing

6.6.3 Verification (AISC360-05)


1) Guide Bar for Tension
- Mu = P t / 6 x e
- Mn / Ω = Fy Sx / Ω > Mu......(OK)
2) Welding at the Support
- f v = Vu / H
- fa = Pc / l
- fb = 0
- fpeak = √[fv2 + (fa + fb)2]
- favg = (1/2) × {√[(fa - fb)2 + fv2] +√[(fa + fb)2+ fv2]}
- fr = 1.25 X favg (If fpeak / favg < 1.25)
- fr = fpeak (If fpeak / favg ≥ 1.25)

390
Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-007

- s ≥ fr / (0.7 (0.9) (0.6) Fy (2))......(OK)


3) Welding at the Stopper
- Aw = (0.7s) l
- Sw = (0.7s) l2 / 6
- σu = Mu / Sw
- τu = Vu / Aw
- √(σu + τu) < 0.6 Fy / Ω......(OK)
4) Beam Web Crippling
- ΦRn = Φ 0.8 tw2 [1 + 3(N / d) (tw / tf)1.5] √(E Fyw tf / tw) > Pc......(OK)
5) Beam Web Local Yielding
- ΦRn = (5k + N) Fyw tw > Pc......(OK)

391
Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-007

7. CASING CALCULATION NOTE

392
Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-007

7.1 Duct Casing Design

7.1.1 Design Load


Load from ASD Combination

7.1.2 Schematic Drawing

7.1.3 Verification

The Duct designs is governed by the Nch. 2369 Of. 2003, American Petroleum Institute and ASME
codes. Although these codes set design requirements for the service loads, the structural design for
flue gas ducts for power plants is not governed by any design code.

The structural behavior of the ducts is defined according the flexure of the duct plate between its
supports, wich has no difference with the standard beam design according to the AISC or AISI design
codes.

Although the duct design must satisfy the Steel Structure Design Codes and the Design Basis of CTT
Project, the following criterias must be considered.

A.- GENERAL DESIGN CRITERIA

1. Every duct connected to structures must be supported separately, in order to avoid eventual
impacts with the connected structures. According to the above, the separation between
structure and duct and the expansion joint will be defined to avoid the contact between theirs
for the seismic loads displacements. The separation length between the structure and the duct
will be defined according to the Nch. 2369 Of. 2003, section 6.

2. If it’s neccesary, sliding support, separation or gaps will be provided in order to avoid the
hammer effect between structure.

3. The duct supports will be distributed in order to allow thermal expansion of the ducts and
simultaneously provide structural links necessary to withstand seismic forces. To comply these

393
Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-007

requirements is allowed to use Mechanical or Elastomeric sliding supports or another accepted


by RSI. Also is allowed to use support plates with slotted holes or oversized holes.

4. When a large duct is supported in different elevations of a structure, all the necessary
provisions in order to avoid the interaction with the structure must be considered, otherwise the
seismic analysis must consider the mass and the inertial forces due the additional degrees of
freedom of the duct.

5. The heavy hanger elements which need free vertical or horizontal displacement for thermal
expansion or another operational reasons, must be fixed to the support structure so as to avoid
the oscillations due collisions of one another during an earthquake. The joint elements, whether
hangers or sliding support must be capable to transfer the seismic forces without restrain the
thermal displacement.

6. Duct horizontal forces should be transferred to the structures trough supports designed for this
function. These supports must not restrain the differential displacements between the duct and
the structure.

7. The Ducts must be consult corrosion protection as necessary. The external protection to the
duct will comply with the manufacturer requirements and the ASTM corresponding code. In
case that galvanized outer protection was specified, it will be executed according with the AST
A123 code.

8. The seismic action will be considered acting simultaneously in the most unfavorable operation
status (Open or Closed Valves, Hot or Cold Temperature). The duct weight must consider the
Duct weight, its content, insulation and lining.

B.- SPECIAL DESGIN CRITERIA

For desing purpose, it is neccesary to differentiate between rectangular and rounded ducts, special
design criteria for each kind of duct are detailed below.

B1. Rectangular Duct

1. In this case, the plates that make up the duct must act jointly with structural elements that stiffen
the plate, in which case the plate is supported between said members. The boundary elements
that make up the duct must be designed to withstand the load from duct plates.

2. It’s allowed to consider in the design the collaborative action of the plate – stiffener, in which
case the collaborative plate width must be considered in an 12t extension from each side of the
stiffener. By the way, the collaborative width mustn't be overlapped with the collaborative width of
another stiffener. Finally to consider this collaborativa action the plate - stiffener connection must
be trough a continous welding.

394
Revisión F
FUEL GAS DESULFURIZACION
FOR TARAPACA POWER PLANT (158MW)
DCTO413-C8-VVT-000-007

3. The analysis of the rectangular section duct plates can be made trough a finite elements model
or the classic theory of plates.

4. It’s necessary to check the local buckling for the plate section.

B2. Rounded Ducts

1. In this case, to build the analysis model the gross area of the duct must be considered as the
effective area.

2. In case of duct subject high axial loads, the allowable tension for elastic buckling is defined by
the following expression:

E t
 adm  0,174  where:  adm ≤ 0,375·Fy
D
where:
t : Plate Thickness
D : Diameter of Duct
 adm : Elastic Buckling Allowable Stress
E : Elasticity Modulus
Fy : Yield Strength o

3. In the inelastic buckling zone (  adm ≥ 3/8·Fy = 0,375·Fy) is allowed to considera a linear variation
of the allowable tension stress between 0,6·Fy y 3/8·Fy, while D/t varies from 0 to 0.464 E/Fy.

4. The duct only will change of direction in right angles, so that during an earthquake the axial
displacements of the duct will not be restrained for rigid points. It is possible to do some
exceptions in case of operational requirements; in these cases, the system flexibility should be
analyzed in detail. Unusually is allowed to place flexible joint on the direction changes.

395
Revisión F

Anda mungkin juga menyukai