Date: 7/20/2018
Partner name:
World Assembly of Muslim Youth (WAMY) – Philippines Office
Project Title
TUBE WELL 2018
Project Purpose
This project will contribute clean water for the residents especially for the Muslim minority
population.
Tube Well Project Report
For Serantau Muslim Relief Projects
Project Location
Tube Location GPS Coordinate
Well No Town District Country
1 Purok 5, Tapol Drive, Barangay Mampang, Philippines
Darussalam Village Zamboanga City 6°54'42"N, 122°8'53"E
2 Purok 6, MMPC Barangay Mampang, Philippines
Drive, Fishpond Zamboanga City
3 Purok 8, MMPC Barangay Mampang, Philippines
Drive, Fishpond Zamboanga City
4 Purok 8, Baregon Barangay Tugbungan, Philippines 6°55'10.4''N, 122°6'16.6''E
Drive Zamboanga City
5 Purok 6, Luciano Barangay Mampang, Philippines 6°54'42"N, 122°8'53"E
Drive Zamboanga City
6 Purok 2, Shanty Barangay Pasonanca, Philippines 6.9214° N, 122.0790° E
Town Drive Zamboanga City
Total Beneficiaries:
27 Families
All Tube Well projects (6) were completed timely with close supervision on the ground.
The six tube well surely helps the less fortunate residents in Zamboanga City especially
in the areas where water is highly needed.
One of the water well was built outside the Masjeed, allowing it to be beneficial to the
Jamaah and the community. Another water well was along the cemetery of a Muslims
grave which allows it to be useful for cleansing the body of the dead which sometimes
people brought to the area not yet cleansed as well for other purposes like ablution,
etc.
Tube Well Project Report
For Serantau Muslim Relief Projects
2. Difficulties faces during handling the program and action to overcome it:
The nameplate per water system is an issue in Zamboanga, since it is done manually
according to the contractor of the water well. And it is also a bit expensive and takes 3-
5 days per name plate. The option taken was to print it in Manila in an Acrylic Form and
shipped it to Zamboanga all at once, which resolved both challenges.
3. Any changes required during this project and what affect did have on the delivery
The implementer cannot provide accurate GPS Coordinate as it doesn’t shows in the
google map. However, satellite images of the location especially the village are hereby
provided.
Note***
Let it known that all six (6) tube well were implemented through our contractor in
Zamboanga City which agreed for a specific budget per water well.
4.0 CHECKLIST
We at Pertubuhan Kebajikan Serantau Muslim require evidence which demonstrates that the work
was carried out satisfactorily and can show our involvement in this project.
5.0 DECLARATION
Name
Adzhar J. Madjid
Position
Admin. & Accounting In-charge
Signature: Stamp:
Tube Well Project Report
For Serantau Muslim Relief Projects
ATTACHMENT A
Project No.1
Purok 5, Tapol Drive, Darussalam Village, Barangay Mampang Zamboanga City
Before:
Tube Well Project Report
For Serantau Muslim Relief Projects
During
Tube Well Project Report
For Serantau Muslim Relief Projects
Turn-Over
Tube Well Project Report
For Serantau Muslim Relief Projects
Project No.2:
Purok 6, MMPC Drive, Fishpond, Barangay Mampang, Zamboanga City
Before
Tube Well Project Report
For Serantau Muslim Relief Projects
During
Tube Well Project Report
For Serantau Muslim Relief Projects
Turn-Over
Tube Well Project Report
For Serantau Muslim Relief Projects
Project No.3
Purok 8, Drive MMPC, Fishpond, Barangay Mampang, Zamboanga City
Before
Tube Well Project Report
For Serantau Muslim Relief Projects
During
Tube Well Project Report
For Serantau Muslim Relief Projects
Turn-Over
Tube Well Project Report
For Serantau Muslim Relief Projects
Project No.4
Purok 8, Drive, Baregon, Barangay Tugbungan, Zamboanga City
Before
Tube Well Project Report
For Serantau Muslim Relief Projects
During
Tube Well Project Report
For Serantau Muslim Relief Projects
Turn-Over
Tube Well Project Report
For Serantau Muslim Relief Projects
Project No.5
Purok 6 Drive, Barangay Mampang Luciano, Zamboanga City
Before
Tube Well Project Report
For Serantau Muslim Relief Projects
During
Tube Well Project Report
For Serantau Muslim Relief Projects
Turn-over
Tube Well Project Report
For Serantau Muslim Relief Projects
Project No.6
Purok 2, Shanty Town Drive, Barangay Pasonanca, Zamboanga City
Before
Tube Well Project Report
For Serantau Muslim Relief Projects
During
Tube Well Project Report
For Serantau Muslim Relief Projects
Turn-Over
Tube Well Project Report
For Serantau Muslim Relief Projects
ATTACHMENT B
Financial Statement and Voucher for Implementing Six (6) Water Wel
@500/waterpump and
Tranpostation and Food allowance
TOTAL: in Philippine Peso 87,754.00
Received Budget in US Dollar (during received exchange rate) = USD1,800.00 x Php52.00 93,600.00
Difference: in Philippine Peso 5,846.00
In USD 112.40
Prepared by:
Lailanie Sali
Executive Staff, WAMY Philippines
Noted by:
Adzhar J. Madjid
Admin. & Accounting In-charge, WAMY Philippines
Tube Well Project Report
For Serantau Muslim Relief Projects
Tube Well Project Report
For Serantau Muslim Relief Projects
Tube Well Project Report
For Serantau Muslim Relief Projects
Tube Well Project Report
For Serantau Muslim Relief Projects
Tube Well Project Report
For Serantau Muslim Relief Projects
Tube Well Project Report
For Serantau Muslim Relief Projects
Tube Well Project Report
For Serantau Muslim Relief Projects
Tube Well Project Report
For Serantau Muslim Relief Projects
Tube Well Project Report
For Serantau Muslim Relief Projects
Tube Well Project Report
For Serantau Muslim Relief Projects
Tube Well Project Report
For Serantau Muslim Relief Projects
Tube Well Project Report
For Serantau Muslim Relief Projects
Tube Well Project Report
For Serantau Muslim Relief Projects
Tube Well Project Report
For Serantau Muslim Relief Projects
Tube Well Project Report
For Serantau Muslim Relief Projects
Tube Well Project Report
For Serantau Muslim Relief Projects
Tube Well Project Report
For Serantau Muslim Relief Projects
Tube Well Project Report
For Serantau Muslim Relief Projects
Tube Well Project Report
For Serantau Muslim Relief Projects
Tube Well Project Report
For Serantau Muslim Relief Projects
Tube Well Project Report
For Serantau Muslim Relief Projects