(iii)APPARTUS REQUIRED
(a) Testing Machine
(b) Dial gauge
(c) Rock specimen along with concrete cast
(iv) PROCEDURE
A rock sample of suitable dimension was cut and the relevant dimensions of the specimen at the
shear zone cross section were measured using a measuring tape. Then, the apparent cross-
sectional area of the intact specimen was calculated. A concrete mix of M25 strength was
prepared and then it was cast into a desired shape of aforementioned dimensions along with the
rock specimens as per the instructions mentioned in the manual for the direct shear test by
ASTM. The concrete casts were allowed to gain its strength and it was cured during this period.
The casts were then placed into the shear box and the restraints were removed. After this four
dial gauges were installed to measure the normal displacement and a single dial gauge was used
for measuring shear displacement. As mentioned in manual, a small seating load of 500N was
applied to the specimen. The normal load was then continually increased till the stabilization.
This was done until the consecutive reading of normal displacement was found to be less than
0.05 mm. This normal load was found to be 5.5 kN and after this load shear load was applied
from one direction until peak strength was found. Then the application of the shear load was
further continued and the residual strength of the rock specimen was found. Finally the normal
and shear loading were removed and the experiment was concluded.
Average Table:
Then the graph is plotted from the data present in the table above.
0.4
0.35
0.3
Shear Strength (MPa)
0.25
0.2
Shear Stress(N/mm2)
0.15
0.1
0.05
0
0 2 4 6 8 10 12
Shear Displacement (mm)
(vii) CONCLUSION
Thus by using the Direct Shear Test Apparatus the shear strength of the discontinuities present
in rock specimen can be calculated along with its residual strength.
(viii) PRECAUTION
(i) The specimen must be cast into the concrete carefully and a minimum of 5 mm of depth of
rock must lie above the surface of concrete.
(ii) The readings in the dial gauge must be taken only after the few minutes after the samples
have settled after the application of load.
(iii ) Shear force should not be applied till stabilization of sample takes place by normal load.
(iv) Shear load should be removed and then the normal load after the completion of
experiment.