PMC:DJ4:EN:000 ver.3.0
PMP® Exam Power Prep
PMC:DJ4:EN:000 ver.3.0
© Copyright CMF Solutions and TwentyEighty Strategy Execution
October 2015
All rights reserved.
No part of this publication may be reproduced, stored in a retrieval system, or transmitted, in any
form or by any means, electronic, mechanical, photocopying, recording, or otherwise, without the
prior written permission of CMF Solutions and ESI International.
All material from A Guide to the Project Management Body of Knowledge (PMBOK® Guide) is
reprinted with permission of the Project Management Institute, Four Campus Boulevard, Newtown
Square, Pennsylvania 19073-3299, USA, a worldwide organization for advancing the state-of-the-art
in project management. Phone: (610) 356-4600; Fax: (610) 356-4647.
PMI did not participate in the development of this publication and has not reviewed the content for
accuracy. PMI does not endorse or otherwise sponsor this publication and makes no warranty,
guarantee, or representation, expressed or implied, as to its accuracy or content. PMI does not have
any financial interest in this publication and has not contributed any financial resources.
PMI, PMP, and PMBOK are registered marks of the Project Management Institute, Inc.
Unit 1: Introduction
Course Guidelines
The Exam
Test-taking Strategies
Formula List
Unit 1: Introduction
The Power Prep approach is designed to reduce your total study time, eliminate wasted
effort on “nice to know” information that is not actually tested, and maximize your
chance of passing the PMP® exam on the first try. Many students have taken the exam
within two weeks of completing the class (some within several days).
The course covers the management topics tested by PMI (integration, scope, time, cost,
quality, human resource, communication, risk, procurement, and stakeholder). The
daily agenda involves a comprehensive review of two or three of these topics followed
by practice exams and personal study. The instructor is available to answer questions.
Key materials and a typical five-day agenda are provided below. Note that the agenda
may be modified as appropriate.
Key Materials:
PMBOK® Guide, 5th edition, 2013
Reference Manual (for Self-Study):
1. Unit on each testable topic
2. Drill Practice (at the end of each unit)
3. Summary of Processes (Unit 14)
4. Exercises (Unit 15)
Course Slides
Practice Exams
Formula and Process Guide
PMI, PMP, and PMBOK are registered marks of the Project Management Institute, Inc.
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 1-1
Introduction
1. Review the chapters covered during that day. Also read any referenced
pages or paragraphs from the PMBOK® Guide.
2. Engage in group study and exercises, as appropriate.
3. Review the Drill Practice topics at the end of each chapter.
4. Take the practice exams for that day’s topics.
5. Participate in question and answer sessions.
Course Guidelines
Warnings:
Beware of your personal experience and the “real world.”
Your individual self-study is vital.
Watch out for information overload. Well-meaning friends may overload
you with outdated material or simply too many references!
This is not entertaining or fun (but it’s worth it).
Slow Me Down:
At some point you may get lost or need more time to make notes.
Take notes and use a highlighter, even if you normally do not.
Cell phones: set on silent or vibrate during class as well as during self-study in
the afternoon.
Take or make calls in the hallway or a conference room.
Laptops: if you must work on something urgent, take it outside the room. No
tap, tap, tapping behind your classmate’s ear.
Conversations: unless you can whisper and keep your conversation brief, take it
outside the room. These courtesies should also be practiced during afternoon
study.
1-2 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Introduction
The Exam
Computerized at Prometric (formerly Sylvan Learning Center)
Multiple choice (200 questions with 4 choices per question)
Four hours to complete the exam
Passing score:
25 “control” or “pre-test” questions; not counted in your score
Need 106 out of remaining 175 to pass (a 61% score)
Beware 65% score: all 25 control questions correct but only 105 of the
others correct (your score is 65% but you failed by one question because
the control questions do not count toward your score)
Questions randomly generated from a test bank
Questions jump from topic to topic (no defined sections)
No penalty for guessing (so don’t leave any questions unanswered)
First time pass rates:
Approximately 60% overall
Approximately 75% to 90% with good exam prep course
Approximately 95% with Power Prep
Test-taking Strategies
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 1-3
Introduction
Read all the choices as there may be a better or more inclusive answer:
Example: Austin can best be described as __________________
a. the capital of Texas
b. the capital and gateway to the hill country of Texas
c. the home of the University of Texas Aggies
d. the home of the University of Texas Armadillos
[“a” is correct but “b” is more inclusive and therefore the best
answer]
Eliminate incorrect or highly implausible choices:
Example: The capital of Alabama is ____________
a. Birmingham
b. Montgomery
c. Edmonton
d. Calgary
[You may know nothing about Alabama but you know that
Edmonton and Calgary are Canadian cities and can eliminate them.
Your chance of guessing correctly is now much better, 50% instead
of only 25%.]
Be alert: answers to a question can sometimes be found in the stem of
another question!
Carefully note “red flag” words such as all, always, never, and
completely. Any choice using these words is less likely to be correct.
Look for the “odd one out” (a choice that doesn’t fit the pattern of the
other choices):
To transfer most of the cost risk to the contractor, the client may
use a ___________ contract.
a. cost plus incentive fee
b. cost plus fixed fee
c. cost plus award fee
d. fixed price
[Choice “d” stands out as a likely correct answer even if you are
clueless about contracts!]
1-4 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Introduction
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 1-5
Introduction
1-6 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Introduction
NOTE 2: Practice “Brain Dumping” the formula list on page 1-7 until you can
reproduce it from memory.
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 1-7
Introduction
Formula List
Variance Plan – Actual
Time: PERT e(t) (O + 4M + P) / 6
PERT σ (P - O) / 6
Three-Point e(t) (O + M + P) / 3
Cost: PV (Present Value) Cash Flow / (1 + i)t
BCR (Benefit Cost Ratio) Revenues / Costs (1.0 breakeven, >1 profitable, <1 loss)
TC (Total Cost) Fixed Cost + Variable Cost
Earned Value (EV):
CV = Cost Variance EV - AC (negative variance is cost overrun)
SV = Schedule Variance EV - PV (negative variance is behind schedule)
CPI = Cost Performance Index EV / AC (less than one is cost overrun)
SPI = Schedule Performance Index EV / PV (less than one is behind schedule)
EAC = Estimate at Completion BAC / CPI (Variances typical of future)
EAC = Estimate at Completion AC + (BAC - EV) (Variances not typical of future)
EAC = Estimate at Completion AC + [(BAC-EV) / (CPI x SPI)] (Considers cost & schedule)
ETC = Estimate to Complete EAC - AC (variance typical) or BAC - EV (variance atypical)
VAC = Variance at Completion BAC - EAC
TCPI = To Complete Performance Index (BAC - EV) / (BAC - AC) or (BAC-EV) / (EAC-AC)
Percent Complete EV / BAC (how much project work is completed)
Percent Spent AC / BAC (what percent of budget has been spent)
EV Rules: Percent Complete Rule EV = % complete x PV
50-50 Rule EV = 50% x Budget (take remaining 50% at completion)
Percent Complete (Total Project) EV = % complete of entire budget x BAC
EV Acronym Changes: PV BCWS (Budgeted Cost of Work Scheduled)
EV BCWP (Budgeted Cost of Work Performed)
AC ACWP (Actual Cost of Work Performed)
Quality/Sigma: Plus / Minus One Sigma 68.3%
Plus / Minus Two Sigma 95.5%
Plus / Minus Three Sigma 99.7% (Defect rate of 3 per thousand)
Plus / Minus Six Sigma 99.9997% (“The Five 9’s”: Defect rate of 3.4 per million)
Communication channels [N x (N -1)] / 2 where N = number of team members
Risk: EMV (Expected Monetary Value) Amount at stake x Probability
Decision tree (probability of a path) Multiply probabilities along the path
Probability Event (A) Not Happening 1 - Probability (A)
Probability (A & B) Probability (A) x Probability (B)
Probability of Heads Twice in a Row 50% x 50% = 25%
Procurement: (Ceiling Price - Target Price) + Target Cost
Point of Total Assumption (PTA) Buyer Share
Contract Fee Adjustment (Target Cost – Actual Cost) x seller’s share
Contract Fee (or profit) Target Fee + Fee Adjustment
Contract Price Cost + Fee (or Profit)
1-8 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 2: PMI Concepts
Self-Study
This unit covers testable material from the first two chapters of the PMBOK® Guide.
Even though the first two chapters are not considered official knowledge areas, they
contain basic concepts that are often tested.
Temporary means the project has a definite beginning and ending (finite
duration). Temporary does not necessarily indicate a project of short
duration.
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 2-1
Unit 2: PMI Concepts
Program: Programs are larger in scope than projects and it is also not as clear
when a program should end. PMI says “a program is a group of projects managed in a
coordinated way to obtain benefits not available from managing them individually”
(PMBOK® Guide, p. 9). Programs often have elements of ongoing, cyclical operations.
2-2 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 2: PMI Concepts
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 2-3
Unit 2: PMI Concepts
Role of the Project Manager (PMBOK® Guide, pp. 16-18): The project
manager is the critical link between the project team and other parts of the organization
so that project objectives are met and organizational strategies are achieved. PMI
identifies 3 competencies (knowledge, performance, and personal skills) and also
provides a list of interpersonal skills needed to work effectively with the team and other
stakeholders. The skills are listed at least 3 places in the PMBOK® Guide, and we will
address them in detail in the unit on human resource management.
2-4 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 2: PMI Concepts
a. The project manager may be chosen from the lowest working level in a
functional organization. In this case, the project manager tends to have
extremely limited authority (PMI says “little or none”).
2. Matrix: The matrix form of organization maintains the vertical functional lines
of authority, but adds a horizontal structure for the project managers. In this
approach, projects take on a more visible and official posture across corporate
divisions. Functional divisions are expected to support new projects when they
are established. In a matrix organization, project managers interact with
functional managers to acquire the resources they need to support their projects.
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 2-5
Unit 2: PMI Concepts
Advantages Disadvantages
Functional
Easier management of specialists More emphasis on functional
Clear accountability and reporting specialty than project needs
No career path
Projects not a priority
Matrix
Project objectives more visible More than one boss for teams
Improved PM control over resources Complex information flows
(compared to functional)
Different priorities (functional vs.
More support from functional PM)
disciplines
Team members are “borrowed” so
Better utilization of resources (time- getting commitment may be difficult
sharing)
Extensive effort needed to establish
People maintain a “functional home” policies and procedures
Better information flow than Difficult resource allocation and
functional (horizontal and vertical) project priority issues
Projectized
Ultimate authority for PM No home when project completed
Efficient project organization May not maintain professionalism in
Loyalty to the project functional disciplines
More effective communication Duplication of facilities, job functions,
(physical collocation of the team) and individual resources
2-6 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 2: PMI Concepts
See Table 2-1 in the PMBOK® Guide, p. 22 for a summary of these organizational
forms.
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 2-7
Unit 2: PMI Concepts
2-8 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 2: PMI Concepts
Project Team (PMBOK® Guide, pp. 35-38): The project team consists of
people with the right knowledge and skills to carry out the work. They come from
various groups and how they interact is affected significantly by the
organizational structure chosen for the project. PMI defines the following roles
for project teams:
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 2-9
Unit 2: PMI Concepts
Project staff: Members of the team who carry out the work outlined in the
deliverables.
Supporting experts: Functional experts often referred to as SMEs
(subject matter experts) who perform functions such as procurement,
finance, engineering, quality control, and so on.
User or customer representatives: Those who act as liaisons to accept
deliverables, advise on requirements, and ensure proper coordination.
Sellers: Vendors, suppliers, and contractors. They are external sources
providing various portions of the work and there is generally some form of
contract or legal agreement in place.
Business partners and members: External companies with a special
relationship (alliance, certified provider of certain specialized work).
Members of these business partners are sometimes assigned to work on
the project team to ensure proper coordination and communication.
2-10 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 2: PMI Concepts
Self-Study
Drill Practice: PMI Concepts
Question Answer
5. Which organizational structure would tend 5. The matrix requires both vertical and
to have the most complex information and horizontal information flows (p. 2-6).
communication flows?
6. What is the relevance of project 6. The project team must identify the needs
stakeholders in achieving project success? and expectations of stakeholders and then
continue to manage them carefully.
Stakeholders can have a positive or negative
effect (p. 2-9).
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 2-11
Unit 2: PMI Concepts
8. What is the difference between a program 8. Programs are larger in scope, often involve
and a project? several interrelated projects, and have a less
definite end date (pp. 2-1/2).
10. What is project management? 10. The application of knowledge, skills, tools,
and techniques to project activities to meet
project requirements (p. 2-2).
11. What are the four basic obligations 11. Responsibility, respect, fairness, and
established by the PMI® Code of Ethics and honesty (p. 2-1). More detail is contained in
Professional Conduct? Appendix I, p. 2-13.
12. What activities do portfolio managers 12. Portfolio managers are involved in
engage in? selecting and initiating projects and programs
that support the strategic objectives of the
overall organization (p. 2-3).
13. When does an important stakeholder have 13. As part of the initiating process; the earlier
the greatest chance to influence project the better (p. 2-10).
outcomes?
14. When is the amount at stake the greatest 14. The farther you are into the project
on a project? timeline, the more investment there is that
could be lost if the project failed or were
cancelled. For example, there is more at
stake (investment to potentially lose) late in
executing compared to early in executing (p. 2-
10 and slide 2-31).
15. Where would you look for lessons learned 15. OPA (Organizational Process Assets) in
or historical files? the knowledge base (p. 2-8).
16. In which organizational structure does the 16. Projectized (p.2-6).
project manager have the most authority?
2-12 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 2: PMI Concepts
Appendix I
PMI® Code of Ethics and Professional Conduct
Note: PMI no longer tracks exam questions on professional and social responsibility in
a separate category. Instead, any such questions are simply part of the structure for the
five process groups. There do not appear to be a significant number of questions on
this topic.
The PMI® Code of Ethics and Professional Conduct may be found on the PMI web site.
It is also contained in the PMP® Handbook. It is approximately 6 pages long and is
paraphrased here for your convenience.
The Code Applies to:
All PMI members
Anyone holding a PMI certification
Anyone who is a candidate for a PMI certification
Anyone serving PMI in a volunteer capacity
Structure of the Code
The code is organized into standards of conduct for 4 key values:
1. Responsibility
2. Respect
3. Fairness
4. Honesty
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 2-13
Unit 2: PMI Concepts
2-14 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 2: PMI Concepts
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 2-15
Unit 2: PMI Concepts
2-16 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 2: PMI Concepts
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 2-17
Unit 2: PMI Concepts
Appendix II
International Project Management
PMI has endorsed the following reference in their guidelines for managing international
projects.
The questions in this area focus primarily on the ethical dilemmas that face project
managers who must manage across borders, cultures, and differing management
philosophies. Above all, Terence Brake indicates that project managers in cross-
cultural situations must be adaptable. The ability to embrace diversity and accept the
norms of other cultures is also important. You should remember that “ethnocentrism”
is bad (if you are a project manager facing international challenges). Ethnocentrism is
the inherent belief that your own culture is superior, leading to difficulty in accepting the
customs practiced by your counterparts in other countries. Ethnocentrism may easily
lead to condescending behavior toward international partners and, therefore, may cause
damage to such projects.
The following is a summary of key points from the Terence Brake and Danielle
Walker book, Doing Business Internationally:
2-18 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 2: PMI Concepts
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 2-19
Unit 2: PMI Concepts
2-20 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 2: PMI Concepts
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 2-21
Unit 2: PMI Concepts
Collectivist WE over I
(Focus on loyalty to cohesive groups. Harmony is more
important than speaking one’s mind. Morale may be harmed
by placing workers in competition for a promotion or reward.
Group decisions take precedence over individual decisions.
Planning is done according to shared values of the group.
Promotion based on things like seniority rather than merit.)
2-22 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 2: PMI Concepts
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 2-23
Unit 2: PMI Concepts
Watch Your Manners Be more polite and formal than usual. Use formal names
and titles until you are invited to do otherwise.
Communicate Respect Take time to learn names and titles; learn their correct
pronunciations; learn some of the host county’s
language; handle business cards with care; place them in
a special folder.
Prepare Well and Seek Learn as much as you can about the foreign culture
Confirmation before making your visit. But don’t assume too much or
make hasty attributions. Whenever you can, check that
your understanding is correct.
Global Negotiation Guidelines: PMI believes that global negotiations should take
place in an atmosphere of trust and openness.
Negotiate in good faith. Be genuine and honest.
Learn as much about the other side as you can (cultural orientation, social,
economic, political, religious concerns.) This is the pathway to understanding.
Prepare well; expect many questions; know your range of negotiable outcomes.
Spend time building rapport. Be modest but confident.
Expect ambiguity; don’t rush to attempt straightening it out. You will be perceived as
pushy.
Respect status and power differences.
Persuade rather than debate.
Don’t make early concessions; be firm and make concessions only if the negotiation
is locked.
Expect negotiations to take time. Be patient.
Soften your directness; don’t cause the other side to lose face.
2-24 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 2: PMI Concepts
Additional Terminology
Abusive Manner:
Treating someone in a manner which results in physical harm or creates feelings of fear,
humiliation, or exploitation.
Conflict of Interest:
A conflict of interest occurs when you are in a position to influence outcomes on behalf
of one party when such outcomes could affect other parties with whom you have
competing loyalties.
Culture Shock:
The feeling of disorientation experienced by a person suddenly subjected to an
unfamiliar culture or way of life.
Custom:
A traditional and widely accepted way of behaving or doing something that is specific to
a particular society, place, or time.
Empathy:
The power of identifying mentally with another person so that you might comprehend
their circumstances or feelings.
Ethical:
Conformity with a code of behavior for a business or particular profession. See moral.
Ethnocentrism:
A belief in the superiority of your own culture. When collaborating with international
partners, ethnocentrism may lead to condescending behavior that alienates others.
Legal:
Concerned with or based on the law.
Moral:
Concerned with principles of right or wrong behavior and the goodness or badness of
human character. Generally accepted standards of goodness and righteousness in
behavior, character, and conduct. See ethical.
Paralingual:
Factors that are ancillary to language proper. They include the pitch, tone, inflection,
rate, and amplitude of someone’s voice.
Proxemics:
The study of socially conditioned spatial factors in ordinary human relations. In English:
the study and awareness of comfortable personal distance (or space) when interacting
with other people. Are you comfortable standing very close to others or do you prefer
more distance, perhaps arm’s length?
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 2-25
Unit 3: Processes
Project Information
Self-Study
Unit 3: Processes
(PMBOK® Guide, Chapter 3)
This unit covers testable material from Chapter 3 of the PMBOK® Guide. Even though
the chapter is not considered an official knowledge area, it contains basic concepts that
are often tested.
Important characteristics of these process groups follow (PMBOK® Guide, pp. 39-41):
They are linked by the results they produce; that is, the result of one becomes
an input to another.
They are overlapping & iterating rather than discrete, one-time events (for
example, executing the plan may uncover problems requiring an update to
the plan).
The process groups occur in all phases of a project; that is, each phase
needs to be initiated, planned, executed, and so on. The processes also
cross phases. Closing a phase becomes the input needed to initiate the next
phase.
The process groups are not phases; rather, the process groups are used
during each phase to get things done. For example, the design phase must
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 3-1
Unit 3: Processes
Your exam results will be provided in relation to these 5 process groups. You will
be told whether your test results were proficient (above average), moderately
proficient (average), or below proficient (below average) for each process group.
You will not be provided with a numerical score or percentage of questions
answered correctly.
Typical Activities Associated with Each Process Group. The following lists match
typical activities to the process groups in which they most likely occur.
Initiating (The exam has occasionally used the term “concept phase” for these activities)
3-2 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 3: Processes
Planning:
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 3-3
Unit 3: Processes
Closing:
3-4 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 3: Processes
Project Information (PMBOK® Guide, pp. 58-59): PMI has refined the terminology
associated with project information as follows:
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 3-5
Unit 3: Processes
Building Blocks of the PMBOK® Guide (Knowledge Areas, Process Groups, and
Processes), pp. 60-61:
PMI has organized their body of knowledge using three fundamental building blocks:
knowledge areas, process groups, and processes. The table on page 3-7 of this
reference manual illustrates the relationships among these building blocks.
Knowledge Areas: Each knowledge area (shown as the column on the left) has a
corresponding chapter in the PMBOK® Guide. They represent management areas that
must be handled by any project manager. In other words, project managers must
manage scope, time, cost, quality, human resources, and so on.
Process Groups: In the real world, management of projects also tends to unfold in a
somewhat chronological fashion. A potential project is investigated and authorized
(initiated), then planned, executed, and closed. Throughout the project, progress is
continually monitored and controlled. PMI refers to these five chronological steps as
process groups and indicates that they typically occur on most projects. They are
shown as the other five columns on the table. Definitions for each process group were
shown previously.
Processes: The body of the table identifies 47 processes. Each row shows the
processes that belong to that knowledge area. Each column shows the processes that
belong to that process group.
The following mnemonic devices may help you memorize the knowledge areas and
process groups. For the ten knowledge areas, the saying is, “I Should Take Control
and Quit Helping Customers Ruin Project Success;” (the first letter of each word
represents a knowledge area). For the five process groups, the mnemonic is IPECC.
3-6 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 3: Processes
Note: There are 26, 48, 62, 50, and 14 exam questions from each of the process groups,
respectively. These numbers include any questions on professional responsibility.
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 3-7
Unit 3: Processes
The following 3 pages address: 1. PMI’s distinction between the contents of the project
management plan and other project documents and 2. The acronyms used in this
manual.
3-8 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 3: Processes
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 3-9
Unit 3: Processes
3-10 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 3: Processes
Self-Study
Drill Practice: Processes
Question Answer
5. In which process group are the scope and 5. The initiation process (sometimes referred
objectives usually determined? to as the concept phase). There is a high-
level scope associated with the project charter
(p. 3-2).
6. In which project process group would 6. Initiation (or historically called the concept
feasibility studies normally be performed? phase) (p. 3-2).
7. Process groups and project phases are 7. False: The process groups occur in all
interchangeable terms. True or False? phases of a project; that is, each phase needs
to be initiated, planned, executed, controlled,
and closed. For example, a design phase
would be initiated, planned, executed,
controlled, and closed (p. 3-1).
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 3-11
Unit 3: Processes
3-12 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 3: Processes
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 3-13
Unit 3: Processes
12. Which process group deals with 12. Monitoring and controlling: measures
measuring performance and calculating performance, identifies variances, and
variances? determines whether corrective action is
needed (pp. 3-1, 3-4).
13. What is the difference between work 13. Work performance data measures the raw
performance data and work performance performance outcomes of project work. For
information? example, data might determine that Task A
actually cost $500 and took 4 days. Work
performance information is the interpretation of
that data. Is Task A over budget, under
budget, or on budget? Similarly, is it ahead,
behind, or exactly on schedule? (p. 3-4)
3-14 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 4: Integration
Management
Other Topics
Self-Study
Unit 4: Integration Management
(PMBOK® Guide, Chapter 4)
Major Processes
4.1 Develop Project Charter (a charter formally authorizes a project or phase and
documents initial requirements)
4.2 Develop Project Management Plan (integrating subsidiary plans into a master
project management plan)
4.3 Direct and Manage Project Work (performing the work defined in the project
management plan to achieve the project’s objectives)
4.4 Monitor and Control Project Work (tracking, reviewing, and regulating progress
toward meeting performance objectives)
4.5 Perform Integrated Change Control (reviewing all change requests and
managing all changes to the project)
4.6 Close Project or Phase (finalizing all activities for a project or phase)
You will notice that each process has inputs, tools, and outputs. Unit 14 provides a
summary of these inputs, tools, and outputs for all 47 processes. Unit 15 provides
exercises to further assist in memorizing this vast amount of information.
A project charter is a written document that formally recognizes and authorizes the
existence of a new project. It also documents initial requirements that satisfy
stakeholders’ needs and objectives. On this basis, a project manager is identified and
assigned as early as is feasible. PMI now recommends that the PM be assigned during
development of the charter but never later than the start of planning. The charter:
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 4-1
Unit 4: Integration Management
Five Key Inputs for Develop Project Charter (PMBOK® Guide, p. 68):
Business need
Product scope description
Strategic plan (how the project supports the organization’s goals)
4-2 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 4: Integration Management
Two Key Tools for Develop Project Charter (PMBOK® Guide, p. 71):
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 4-3
Unit 4: Integration Management
One Key Output for Develop Project Charter (PMBOK® Guide, p. 71):
The project management plan defines how the project will be executed, monitored,
controlled, and closed. It is a key integrative document that is usually developed by
the entire team (even though it is the PM’s responsibility to see that the plan gets
done). Development of the plan uses the outputs of the other planning processes
(scope, schedule, cost, quality, HR, communication, risk, procurement and stakeholder)
to create a consistent, coherent document that can be used to guide both execution and
control of a project. Key points include:
The completed plan must be presented to appropriate stakeholders for
approval to proceed.
Changes to the plan are approved using the integrated change control
process.
The project management plan provides the guide for performing all project
work and also forms the baseline against which any changes are made.
4-4 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 4: Integration Management
Four Key Inputs for Develop Project Management Plan (PMBOK® Guide, p.
74):
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 4-5
Unit 4: Integration Management
Two Key Tools for Develop Project Management Plan (PMBOK® Guide, p. 76):
One Key Output for Develop Project Management Plan (PMBOK® Guide, p.
76):
4-6 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 4: Integration Management
The following three baselines are also established by the project management
plan:
Cost, Schedule, and Scope
This process involves performing the work identified in the project management plan.
Some of the activities are the responsibility of the project manager and other activities
belong to various team members. Also, work performance information describing the
actual status of required deliverables is collected and fed into the performance reporting
process (PMBOK® Guide, p. 81). The many actions performed during execution of the
project management plan include the following:
Set up a project organization
Acquire, develop, and manage the project team
Obtain and manage other resources (materials, equipment, facilities)
Lead, manage, and/or perform activities to meet project objectives
Perform quality assurance
Manage the flow of information in accordance with the communication
management plan
Generate project data for status reports and forecasts
Conduct change control and implement approved changes:
Corrective action (bringing work results back in line with the plan)
Preventive action (ensuring future work remains in line with the plan)
Defect repair (modifying a nonconforming product or work result)
Establish and manage project communication channels
Manage risks
Obtain quotes, bids, and proposals as needed (for outsourced work)
Manage sellers (contractors)
Manage stakeholders and maintain stakeholder relationships
Collect and document lessons learned
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 4-7
Unit 4: Integration Management
Four Key Inputs for Direct and Manage Project Work (PMBOK® Guide, p. 82):
4-8 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 4: Integration Management
Three Key Tools for Direct and Manage Project Work (PMBOK® Guide, p. 83):
1. Expert Judgment: Expertise provided by the project manager and the team
while executing the project management plan.
3. Meetings: Used to address pertinent topics during the direct and manage
work process. PMI identifies three types of meetings:
Information exchange
Brainstorming and/or evaluating options
Decision making
Meetings should have a clearly defined purpose, agenda, time frame, and be
documented with minutes. While not always possible, PMI believes that face-to-
face meetings are the most effective.
Five Key Outputs for Direct and Manage Project Work (PMBOK® Guide, p. 84):
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 4-9
Unit 4: Integration Management
3. Change Requests: When issues arise during a project, change requests are
used to modify procedures, scope, cost, schedule, or quality. These changes
may lead to the use of corrective actions, preventive actions, defect repairs, or
various updates. Change requests may be optional or come from a mandatory
legal requirement. They may originate from an internal or an external source.
For the exam, be aware of possible “situational” questions that could involve
various parties (functional manager, senior manager, or customer) wanting to
make a change to the project. In all cases, the appropriate first response is to
evaluate the impact of the change and then meet with the team to discuss
alternatives. Common incorrect choices often involve meeting first with
management or the customer.
Requirements documents
Project logs (issue, defects, assumptions, etc.)
Risk register
Stakeholder register
4-10 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 4: Integration Management
Seven Key Inputs for Monitor and Control Project Work (PMBOK® Guide, p.
88):
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 4-11
Unit 4: Integration Management
4. Validated Changes: Any changes that have been through the Perform
Integrated Change Control process and have been approved. These changes
must now be implemented.
Status of deliverables
Implementation status for change requests
Forecasts
4-12 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 4: Integration Management
Four Key Tools for Monitor and Control Project Work (PMBOK® Guide, p. 91):
4. Meetings: PMI states that the project team and other stakeholders typically
hold two types of meetings: user groups and review meetings. They further
indicate that meetings may be face-to-face (preferred), virtual, formal, or informal.
Four Key Outputs for Monitor and Control Project Work (PMBOK® Guide, p.
92):
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 4-13
Unit 4: Integration Management
Projects almost never run exactly according to the plan and, accordingly, changes are a
normal part of project management. Integrated change control is performed constantly
throughout the entire project life cycle to effectively manage the change process. The
integrated change control process includes reviewing all change requests as well as
approving and managing changes to any of the following: deliverables, organizational
processes, project documents, and the project management plan. The following
activities are part of integrated change control:
4-14 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 4: Integration Management
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 4-15
Unit 4: Integration Management
Five Key Inputs for Perform Integrated Change Control (PMBOK® Guide, p.
97):
3. Change Requests: Change requests are outputs with this single exception.
Integrated change control is not needed or used unless a change has, in fact,
been requested.
4-16 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 4: Integration Management
Three Key Tools for Perform Integrated Change Control (PMBOK® Guide, p.
98):
1. Expert Judgment: In this case, it is important to get the right subject matter
experts on the CCB.
Four Key Outputs for Perform Integrated Change Control (PMBOK® Guide, p.
99):
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 4-17
Unit 4: Integration Management
2. Change Log: The change log documents all change requests and the
resulting decisions and associated rationale. The expected impact on project
baselines is also documented.
4. Project Documents Updates: The change request log and any documents
that are subject to the formal change control process are updated, as needed.
This process finalizes all activities across all process groups to formally close a phase
or the entire project, as appropriate. The following activities are involved:
When closing the entire project, the project manager should review all
information from closure of the previous phases. The purpose of this step is
to ensure that all project work is complete and that objectives have been met.
Since project scope is measured against the project management plan, the
project manager should review the project management plan to ensure
completion of all work identified in the plan.
The close project or phase process should also establish procedures to
document the reasons if a project is terminated before completion.
This process also establishes the actions needed for administrative closure,
which include:
The activities needed to satisfy the exit criteria for the phase or project.
The activities needed to transfer the product, service, or result to the
next phase, to production, or to operations.
Activities to collect records, audit successes and failures, document
lessons learned, and archive information for future use.
4-18 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 4: Integration Management
Three Key Inputs for Close Project or Phase (PMBOK® Guide, p. 102):
Three Key Tools for Close Project or Phase (PMBOK® Guide, p. 102
3. Meetings: The types of meetings identified for this process include lessons
learned, closeout, user group, and review meetings.
Two Key Outputs for Close Project or Phase (PMBOK® Guide, p. 103):
1. Final Product, Service, or Result Transition: The name says it all. The
product, service, or result created by the phase or project must be transitioned or
delivered to the next step.
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 4-19
Unit 4: Integration Management
Other Topics:
Management by Objectives (MBO): MBO is a topic that has been tested but not
covered explicitly in the PMBOK® Guide. This process for setting objectives was
developed by Peter Drucker. The most famous feature of MBO is joint
development of the objectives, which means that management and the employees
collaborate to jointly establish the objectives.
For the exam, you need to know the three steps involved in using MBO: 1)
establish realistic, clearly stated objectives, 2) evaluate (measure) whether the
objectives are being met, and 3) take action if the evaluation so warrants.
You should know that an objective is “clear” if different parties can agree on a
single meaning.
You should also know that MBO will be most successful if supported by top
management.
4-20 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 4: Integration Management
Because of the threat of a bad report card or termination of the project, the
process is often fraught with the following potential problems:
Roles and responsibilities: You must know the appropriate roles for the following
key players in the project environment.
Senior management:
Assign a project manager
Empower the project manager
Protect the project from outside influences
Approve the overall project management plan
Sponsor:
The person or group that provides financial resources for the project
(PMBOK® Guide page 32). The sponsor champions the project during
initiation and may also continue exert influence for the benefit of the
project as it proceeds. Finally, the sponsor usually leads the project
selection process through formal authorization and plays a significant
role in the development of the initial scope and charter.
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 4-21
Unit 4: Integration Management
Project manager:
In charge of the project, but not necessarily the resources
Held accountable for failure
Plans the project (WBS, Project Management Plan, and so on)
Develops estimates and schedules
Assigns tasks to team members
Team members:
Help develop WBS
Provide estimates on their tasks
Help create a realistic schedule
Accomplish their tasks
Attempt to resolve conflicts among themselves before escalating
4-22 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 4: Integration Management
Self-Study
Drill Practice: Integration Management
Question Answer
1. Name three main objectives of integrated 1. a) Identify a method for requesting changes
change control. to established baselines, b) Improve the
project by considering the impact of a change,
Note: All page numbers in this drill practice refer to & c) Communicate all changes to stakeholders
this reference manual unless otherwise indicated. (p. 4-15)
Change control:
A collection of formal, documented
procedures that defines how project
deliverables and documentation are
controlled, changed, and approved.
(pp. 4-14 to 4-16)
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 4-23
Unit 4: Integration Management
8. Name three important things that must be 8. a) Verify that exit criteria have been met
accomplished as part of closing a project. (e.g. deliverables completed), b) Products or
services have been transferred to owners or
next step, and c) Document the reasons if a
project is terminated before it is completed (p.
4-18).
4-24 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 4: Integration Management
12. Project management plans are usually 12. the project team (the PM is responsible
developed by ______. but must rely on various functional experts for
development of the plan) (p. 4-4).
14. When is the project charter created? Who 14. The charter is normally developed as part
is responsible for it? of the initiating process group (or, historically,
PMI has also referred to the concept phase.)
Ideally, the project manager would help write
the charter but it should be signed by a senior
manager, external to the project (pp. 3-2 and 4-
1/2).
15. Input #2 for Close Project or Phase is 15. Output #1 for Validate Scope is accepted
accepted deliverables. Which of the other 46 deliverables (pp. 4-19 and 14-2).
processes creates that data?
16. Which integration management process 16. Monitor and Control Project Work (p. 4-11).
provides the primary focus on tracking,
reviewing, and regulating project progress?
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 4-25
Unit 5: Scope Management
Major Processes
Self-Study
Unit 5: Scope Management
(PMBOK® Guide, Chapter 5)
Scope management ensures that a project includes all the work required but only the
work required to complete the project successfully. In other words, proper scope
management carefully identifies what is and what is not included in the project. The
following six processes comprise scope management.
Major Processes
5.1 Plan Scope Management (creating a scope management plan that documents
how project scope will be defined, validated, and controlled)
5.2 Collect Requirements (defining and documenting stakeholders’ needs and
requirements to meet project objectives)
5.3 Define Scope (developing a detailed description of the project and product)
5.4 Create WBS (subdividing project deliverables into smaller, more manageable
components)
5.5 Validate Scope (formalizing acceptance of completed project deliverables)
5.6 Control Scope (monitoring status of the project and product scope, and managing
changes to the scope baseline)
Product scope: The features and functions embodied in the product, service,
or result. Product scope is measured against the product requirements
(Sections 5.2 and 5.3: Collect Requirements and Define Scope).
Project scope: The management activities required to deliver the product,
service, or result. Project scope is measured against the project
management plan (Section 4.2).
The scope baseline consists of the approved versions of the project scope statement,
the WBS (work breakdown structure), and the WBS dictionary. The approved scope
baseline should only be changed using formal change control procedures. The
approved baseline is the basis for deciding whether scope requirements are being met
(especially relevant during the processes for validating and controlling scope).
The scope management plan documents how project scope will be defined, validated,
and controlled. In essence, it provides guidance on how the other five scope
management processes are to be accomplished.
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 5-1
Unit 5: Scope Management
Four Key Inputs for Plan Scope Management (PMBOK® Guide, p. 108):
2. Project Charter: Described in the PMBOK® Guide, p. 66, Section 4.1, the
charter provides high-level project and product requirements. As such, it forms a
starting point for the development of detailed requirements.
Organizational culture
Infrastructure (resource availability)
Personnel administration
Marketplace conditions
5-2 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 5: Scope Management
Two Key Tools for Plan Scope Management (PMBOK® Guide, p. 109):
2. Meetings: The project manager, sponsor, selected team members, and other
selected stakeholders may attend meetings to develop the scope management
plan.
Two Key Outputs for Plan Scope Management (PMBOK® Guide, p. 109):
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 5-3
Unit 5: Scope Management
Requirements become the foundation for other vital project management activities:
5-4 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 5: Scope Management
Collect Requirements
4. Project Charter: Described in PMBOK® Guide, p. 66, Section 4.1, the charter
provides high-level project and product requirements. As such, it forms a starting
point for the development of detailed requirements.
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 5-5
Unit 5: Scope Management
4. Group Creativity Techniques: The following examples are all ways for
groups to generate ideas about any desired topic. In this case, the groups are
identifying and documenting requirements.
Brainstorming: A group-oriented technique for quickly generating
ideas about both project and product requirements.
Nominal Group Technique: An enhanced version of brainstorming
which includes voting and prioritizing the group’s ideas.
Idea/Mind Mapping: The non-linear diagramming of different ideas in a
group into a single map for the purpose of highlighting agreements and
differences and also generating new ideas.
Affinity Diagram: A technique for sorting a large number of detailed,
specific ideas into logical groups.
5-6 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 5: Scope Management
6. Questionnaires and Surveys: Written sets of questions that help reach large
audiences quickly and also enable statistical analysis of data.
10. Context Diagrams: Context diagrams are visual depictions of product scope
such as processes, equipment or computer systems. The diagram shows how
various entities (people and other systems) interact to produce inputs and
outputs.
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 5-7
Unit 5: Scope Management
Business
Stakeholder
Solution (product, service, or result)
Transition
Quality
Project
5-8 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 5: Scope Management
Scope definition produces a written, detailed scope statement that is crucial to project
success. This statement represents an agreement between the project team and the
customer and defines which requirements collected earlier will actually be included in
the scope and which will be excluded. The project team and appropriate stakeholders
conduct a needs assessment and use it as the basis to develop written project
requirements. Assumptions, constraints, and risks are identified and validated as
necessary. The level of uncertainty (difficulty) in defining scope will naturally be greater
with more complex projects.
Define Scope
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 5-9
Unit 5: Scope Management
2. Product Analysis: This tool is helpful when the project is producing a product
rather than a service or other result. These techniques help translate project
objectives into measurable deliverables and requirements. Examples of these
techniques include product breakdown, requirements analysis, systems
engineering, value engineering, and value analysis. Project engineers use these
techniques to better understand and develop product requirements.
5-10 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 5: Scope Management
Stakeholder register
Requirements documentation
Requirements traceability matrix
Key points:
The WBS subdivides the work into smaller components (this process is
called decomposition). Each descending level of the WBS represents an
increasingly detailed description of the work.
Tasks (items) at the lowest level of the WBS are called work packages.
The work package is the level at which the work can be adequately
scheduled, cost estimated, monitored, and controlled. Accurate work
packages are a major factor in accurate project planning.
A detailed description of each work package is contained in a WBS
dictionary.
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 5-11
Unit 5: Scope Management
Create WBS
1. Scope Management Plan: Specifies how to create the WBS from the
detailed scope statement (previous process) and how to maintain the WBS
throughout the project.
5-12 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 5: Scope Management
The PMBOK® Guide indicates that the first level of decomposition can be
displayed in the following ways:
Major deliverables
Major subprojects done by organizations outside the project team
Phases of the project life cycle
Hybrid mixtures of all the above (e.g., phases at the first level of
decomposition and then deliverables within each phase)
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 5-13
Unit 5: Scope Management
5-14 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 5: Scope Management
Scope validation is the process of obtaining formal acceptance of the project scope by
stakeholders. It involves reviewing work results to see whether tasks were completed
correctly. If a project is terminated early, scope validation should document the extent
of the work completed. Scope validation differs from quality control in that validation is
primarily concerned with acceptance of the work whereas quality control is primarily
concerned with correctness of the work. Quality control is usually performed slightly
ahead of validation, but the two processes may overlap somewhat.
Validate Scope
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 5-15
Unit 5: Scope Management
5-16 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 5: Scope Management
This process monitors the status of project and product scope and also manages any
changes to the scope baseline. Successful control of scope changes prevents the
uncontrolled expansion of project scope known as “scope creep”. This process uses
integrated change control to deal with all requested changes and recommended
corrective or preventive actions. As described in the integrated change control process,
scope change control is concerned with:
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 5-17
Unit 5: Scope Management
Control Scope
1. Project Management Plan: The scope baseline is the object being controlled
and it consists of the scope statement, WBS, and WBS dictionary. Other
relevant portions of the project management plan include the scope, change,
configuration, and requirements management plans.
4. Work Performance Data: Relevant work performance data at this point may
include the number of change requests received, number of requests accepted,
and the number of deliverables completed.
5-18 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 5: Scope Management
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 5-19
Unit 5: Scope Management
5-20 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 5: Scope Management
Self-Study
Drill Practice: Scope Management
Question Answer
3. As project complexity increases, what will 3. It will probably increase (p. 5-9).
happen to the level of uncertainty in defining
the project scope?
4. What is the difference between product 4. Product scope is the features and functions
scope and project scope? designed into the product or service
(measured against product requirements).
Project scope is management activities
performed by the team (measured against the
project management plan) (p. 5-1).
8. As used in a WBS, what does the term 8. A cost category that represents the work
“cost account” mean? assigned to a single responsible organizational
unit, i.e., the lowest level in the WBS at which
organizational responsibility is assigned. Also
called a control account (p. 5-14).
9. What is the WBS numbering system called 9. Code of Accounts or Chart of Accounts
and what does it provide?
Provides:
1. Allocation of budget to specific tasks
2. Tracking of performance/spending against
specific work packages (tasks)
3. Identifying the level of detail for specific
tasks (pp. 5-12 & 5-14)
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 5-21
Unit 5: Scope Management
Question Answer
10. What role do stakeholders play in 10. Defining stakeholders’ needs is the
collecting requirements? primary purpose of the process called Collect
Requirements. Knowing who the stakeholders
are and interviewing them in various ways is
how requirements are documented (pp. 5-3 and
5-5,Inputs #3 & #5).
12. How does an OBS differ from a WBS? 12. OBS = Organizational breakdown
structure and is used to show which work
elements (tasks) have been assigned to which
organizational units (p. 5-12)
13. Activities at the lowest level of the WBS 13. work packages (pp. 5-11 & 5-13)
are referred to as ______.
15. What is the difference between scope 15. Scope validation is primarily concerned
validation and quality control? with acceptance of the work; quality control is
concerned with the correctness of the work (p.
5-15).
16. What is scope control (the formal name of 16. Monitoring the status of the project and
the process is control scope)? product scope and managing changes to the
scope baseline (p. 3-17)
18. What is the tool for control scope? 18. Variance analysis (p. 5-19)
19. What is the scope management plan? 19. Documents how project scope will be
5-22 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 5: Scope Management
Question Answer
20. What two important issues does variance 20. As part of control scope:
analysis deal with?
a ) Identifying the magnitude of variances
(plan versus actual)
21. Change requests are outputs for which 21. Validate scope and control scope.
two scope management processes? Change requests may be issued as a result of
either of these activities and should be
handled using integrated change procedures
(pp. 5-17 & 5-19).
23. The subdivision of project deliverables 23. decomposition (pp. 5-11 to 5-13)
into smaller components is called ______.
24. What are the inputs for collect 24. The scope management plan,
requirements? requirements management plan, stakeholder
management plan, project charter and
stakeholder register (p. 5-5).
25. What is the Code of Accounts and what is 25. A numbering system used to identify each
another name for it? element of the WBS. Also known as a Chart
of Accounts (pp. 5-12 & 5-14).
26. What is a requirements traceability 26. A table that links each requirement to its
matrix? origin such as business needs or
opportunities, project goals, etc. (p. 5-8)
27. What is the scope baseline composed of? 27. The scope statement, the WBS, and the
WBS dictionary (pp. 5-1 & 5-14 to 5-15).
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 5-23
Unit 5: Scope Management
Question Answer
28. What is alternatives generation and what 28. Alternatives generation is a tool of define
is it used for? scope and is used to ensure that all
approaches to doing the work have been
considered. The PMBOK® Guide, p. 123,
identifies brainstorming, lateral thinking, and
analysis of alternatives as examples of how to
perform alternatives generation. (p. 5-10).
29. Changes in the scope may affect the other 29. scope, schedule, and cost. (p. 5-19, Output
components of the triple constraint. The triple #3, Control Scope)
constraint of project management includes
__________.
5-24 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 6: Time Management
Major Processes
Other Topics
Self-Study
Unit 6: Time Management
(PMBOK® Guide, Chapter 6)
The questions on this topic focus heavily on scheduling techniques, network diagrams,
Gantt charts, the critical path, compressing the schedule, PERT, and float. You may or
may not have to actually work a network diagram, but you will be expected to answer
fundamental questions about the critical path, float, crashing a project schedule, and
dealing with various dependencies such as finish-to-finish or start-to-start.
Major Processes
6.1 Plan Schedule Management (establishing procedures for planning, developing,
managing, executing, and controlling the schedule)
6.2 Define Activities (identifying specific activities to be accomplished)
6.3 Sequence Activities (identifying and documenting relationships among activities)
6.4 Estimate Activity Resources (estimating type and quantity of resources needed)
6.5 Estimate Activity Durations (approximating the number of work periods to
complete individual activities with estimated resources)
6.6 Develop Schedule (analyzing sequences, durations, resource requirements, and
schedule constraints to create the schedule)
6.7 Control Schedule (monitoring the status of the project to update progress and
managing changes to the schedule baseline)
PMI indicates that defining and sequencing activities, estimating resources and
durations, and development of the schedule are discrete but tightly linked steps in
building a project schedule. On some projects, especially smaller ones, these discrete
steps are viewed and performed as a single process.
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 6-1
Unit 6: Time Management
Four Key Inputs for Plan Schedule Management (PMBOK® Guide, p. 146):
Three Key Tools for Plan Schedule Management (PMBOK® Guide, p. 147):
6-2 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 6: Time Management
One Key Output for Plan Schedule Management (PMBOK® Guide, p. 148):
Activity definition involves identifying and documenting the specific activities that must
be performed to produce the deliverables identified by the WBS. Activities are planned
down to the work package level, which is the lowest level displayed in the WBS. PMI
also says that work packages may be decomposed another level, which is designated
as activities or schedule activities.
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 6-3
Unit 6: Time Management
Define Activities
2. Scope Baseline: The information explicitly used at this step includes the
WBS, project deliverables, constraints, and assumptions.
Organizational structure
Published information from commercial databases
Project management information systems
6-4 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 6: Time Management
list includes all the activities necessary to complete each work package.
Involving team members in the decomposition may lead to more accurate results.
2. Activity Attributes: Much like the WBS dictionary, activity attributes include
detailed information for each activity. The amount of information increases as
the project progresses (progressive elaboration). Activity attributes include the
following information:
3. Milestone List: Milestones are important points in time and they have zero
duration. Milestones may be requested or demanded by the customer,
management, the team, or may be required by the contract. Typical milestones
often include the date on which important activities should begin or end.
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 6-5
Unit 6: Time Management
Sequence Activities
6-6 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 6: Time Management
7. Organizational Process Assets (OPA): The specific OPA that may affect
the sequencing of project activities include (PMBOK® Guide, p. 156):
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 6-7
Unit 6: Time Management
PDMs offer several advantages over other methods (such as arrow diagrams):
The technique does not require the use of “dummy” activities whenever
multiple dependencies are needed in a schedule.
Finally, the technique adds the concept of lag and lead times between
activities.
3. Leads and Lags: Adjustment of lead and lag times may help define the
timing of the work more accurately. A lead time allows the successor (follow-on)
task to be accelerated. Conversely, a lag time delays the successor activity.
6-8 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 6: Time Management
The course slides show visual examples of network diagrams and key
issues associated with them.
Determining what resources (people, equipment, material, and facilities) will be needed,
along with the associated quantities and time frames. Resource issues also apply to
the cost estimating process.
Eight Key Inputs for Estimate Activity Resources (PMBOK® Guide, p. 162):
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 6-9
Unit 6: Time Management
Staffing policies
Procedures for renting or purchasing supplies and equipment
Historical information about resource usage on similar projects
Five Key Tools for Estimate Activity Resources (PMBOK® Guide, p. 164):
1. Expert Judgment: Appropriate subject matter experts will help judge the
accuracy of resource estimates.
2. Alternative Analysis: This analysis considers the various options for doing
the work and assures that appropriate resource estimates are available. For
example, a project might pursue either of two technological possibilities; there
may be a choice between manual or automated tools/processes; or various
levels of resource capabilities may be considered.
3. Published Estimating Data: Some industries and trade groups collect and
publish cost, schedule, and resource data for specific types of work.
6-10 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 6: Time Management
Resource availability
Resource rates
Resource calendars
Resource breakdown structures (RBS)
Three Key Outputs for Estimate Activity Resources (PMBOK® Guide, p. 165):
Activity list
Activity attributes
Resource calendars
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 6-11
Unit 6: Time Management
Duration estimating coordinates information about activity scope, resource types and
quantities, and resource calendars so that a realistic schedule can be developed.
Duration estimating has been defined as assessing the number of work periods needed
to complete an activity. Estimates should be:
Produced by the people most familiar with the work (or at least approved by
them). This observation refers to the importance of expert judgment.
Progressively elaborated. In other words, estimates will usually become more
accurate as the quality of the input data improves.
Adjusted for the effects of “elapsed time” (whether or not weekends are
treated as work periods). Note: Project management software makes it
much easier to assess the effect of these elapsed times on a project
schedule.
Duration estimating should also consider the difference between effort and duration. If
four people work 10 hours each on a task, the total effort that must be paid for is 40
person-hours. If those four people are working simultaneously, i.e., in parallel, the
duration to complete the work will be 10 hours. In summary, durations are used for
scheduling and effort is used to estimate costs.
6-12 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 6: Time Management
Ten Key Inputs for Estimate Activity Durations (PMBOK® Guide, p. 167):
7. Risk Register: Provides the list of potential risk events, the results of risk
analysis, and the appropriate response plans.
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 6-13
Unit 6: Time Management
Six Key Tools for Estimate Activity Durations (PMBOK® Guide, p. 169):
6-14 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 6: Time Management
Most Likely: The most likely scenario as seen by someone familiar with
the work.
In similar fashion, a well-known technique for doing the same thing is PERT
(Program Evaluation and Review Technique). The differences among PERT,
three-point estimate, and CPM (Critical Path Method) will be discussed in the
next process on schedule development.
PMI has identified the following methods for handling reserve. These methods
also apply to cost estimating.
Two Key Outputs for Estimate Activity Durations (PMBOK® Guide, p. 172):
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 6-15
Unit 6: Time Management
Activity attributes
Assumptions inherent in the duration estimates
Develop Schedule
2. Activity List: Described in Section 6.2.3.1 (identifies the activities that must
be scheduled).
6-16 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 6: Time Management
9. Risk Register: Described in Section 11.2.3.1 (identifies risk events that may
affect the schedule).
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 6-17
Unit 6: Time Management
2. Critical Path Method: Calculates theoretical start and finish dates for all
schedule activities without regard to resource limitations. The technique:
Uses a forward and backward pass to determine early and late times.
Calculates available float or slack (float or slack indicates where any
flexibility in the schedule exists to delay activities without delaying the
project).
Determines the critical path (the longest path, the path with zero float
or the least float available, the shortest possible duration for the
project). It is possible to have more than one critical path, which would
make the schedule more risky.
The critical path may have positive total float if the project is ahead of
schedule or negative total float if the project is behind schedule.
A near-critical path exists when the duration of a path is almost as long
as that of the critical path. If the activities on such a path are subject to
considerable risk or variation, those activities must be monitored as
carefully as those on the critical path.
Historically, the exam has asked numerous questions about PERT (Program
Evaluation and Review Technique) as well as any differences between PERT
and CPM (Critical Path Method). The course slides will examine these issues.
3. Critical Chain Method: This technique modifies the schedule to account for
limited resources. The critical path is first determined using a normal process
without resource limitations. Next, resource limitations are applied and a
resource-constrained schedule is produced. The resource-constrained critical
path is known as the critical chain.
6-18 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 6: Time Management
Non-work activities called duration buffers are added to the end of activity
sequences. One of these buffers is known as the project buffer and is placed at
the end of the critical chain. Other buffers, called feeding buffers, are placed at
any point where non-critical tasks feed into the critical chain. The size of each
buffer should reflect the uncertainty associated with that sequence of tasks.
Compared to traditional approaches, the schedule is managed by monitoring the
duration buffers (comparing remaining buffer amounts to remaining activity
durations) instead of managing float and the critical path.
In time periods with too much work for the available resources, some
of the work may be moved into other time periods. This is often
done by moving tasks with available positive float. This guideline or
rule of thumb is referred to as a “heuristic” by some people.
Note: Be aware that resource leveling tends to result in a project
duration that is longer than originally planned.
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 6-19
Unit 6: Time Management
as: a component is not delivered on time, defective parts arrive, a labor strike
occurs, or an extreme weather problem (hurricane, blizzard, lightning strike)
occurs. This technique is related to the use of simulation programs.
6. Leads and Lags: Leads and lags may be adjusted to develop viable, realistic
schedules. They make it easier to delay or accelerate work.
1. Schedule Baseline: The approved schedule, which then becomes the plan
against which to measure performance. The schedule baseline is a component
of the project management plan and is also part of the triple constraint.
6-20 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 6: Time Management
Bar charts (also called Gantt charts) which are easy to read and used
frequently in presentations. Gantt charts show activity start and finish dates,
activity durations, and dependencies. They are especially good for showing
progress or variance. They may also be used to display summary tasks,
which are sometimes referred to as hammock activities (a group of related
schedule activities aggregated at a summary level).
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 6-21
Unit 6: Time Management
Controlling the schedule involves monitoring schedule status and managing schedule
changes. Schedule change control is concerned with the usual factors:
Control Schedule
6-22 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 6: Time Management
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 6-23
Unit 6: Time Management
5. Leads and Lags: Used to bring the schedule back in line with the plan by
delaying or accelerating work (Section 6.6.2.6).
7. Scheduling Tool: The schedule data are updated to reflect actual progress.
Manual or automated scheduling methods are used to produce an updated
schedule.
6-24 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 6: Time Management
Other Topics:
Monte Carlo analysis: You should know that CPM and PERT tend to understate
schedule durations in comparison to Monte Carlo. This is because Monte Carlo
simulation can account for path convergence whereas CPM and PERT cannot.
This topic is addressed in more detail in the chapter on risk management. A
course slide visually displays this relationship.
Note: Additional practice network diagrams are included in the course slides
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 6-25
Unit 6: Time Management
6-26 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 6: Time Management
Self-Study
Drill Practice: Time Management
Question Answer
2. Name two methods of compressing project 2. Crashing and Fast Tracking (p. 6-20).
duration.
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 6-27
Unit 6: Time Management
8. How is schedule variance calculated? 8. Plan - Actual (pp. 1-7 and 6-23 & 24)
12. What is the critical path? 12. The longest path through the project
network. Also the path with the least slack
(float).
6-28 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 6: Time Management
15. What are the advantages of a bar (Gantt) 15. Easy to construct and easy to read; bar
chart? charts are an easy way to show progress or
status (i.e., schedule variances) (p. 6-21).
16. Define activity duration estimating. 16. Assessing the number of work periods it
will take to complete an activity (p. 6-12).
17. What are the two outputs of estimate 17. Activity duration estimates and project
activity durations? documents updates (pp. 6-15 & 6-16).
18. What is a hammock activity? 18. A summary level task that shows the start
of the first activity and the end of the last
activity in a series of related activities. May be
displayed as part of a Gantt chart (p. 6-21).
19. What are the inputs to define activities? 19. The schedule management plan, scope
baseline, enterprise environmental factors,
and organizational process assets (p. 6-4).
20. What is the schedule baseline? 20. It is the approved project schedule; i.e.,
the original plan plus or minus approved
changes.
21. What information does a simulation 21. A range of potential project durations with
provide? associated probabilities (p. 6-20).
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 6-29
Unit 6: Time Management
22. What is an indicator of flexibility in the 22. Activities that have positive slack (float)
schedule? provide flexibility as to start times and
resource usage (p. 6-18, tool #2).
23. What is a dummy activity? 23. A task with zero duration; used in arrow
diagram networks to correctly show multiple
dependencies (logical relationships). Not
needed in precedence diagrams (p. 6-8, tool #1
and course slides 6-28 & 32).
24. Who should develop the project 24. The project team (it is the PM’s
schedule? responsibility, but like development of most
plans, the expertise of various team members
is needed to complete the schedule) (Same
logic as for project management plan, p. 4-4).
6-30 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 6: Time Management
29. The arrow diagram method is limited to 29. Finish-to-start (p. 6-8)
what single kind of logical dependency?
o = optimistic time
m = most likely time
p = pessimistic time
36. What is the schedule management plan? 36. A component of the project management
plan that specifies how the schedule will be
developed, managed, executed, and
controlled.
(pp. 6-1 and 6-3)
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 6-31
Unit 7: Cost
Management
Major Processes
Other Topics
Self-Study
Unit 7: Cost Management
(PMBOK® Guide, Chapter 7)
The questions on this topic have historically been more difficult than average for some
exam takers because of unfamiliarity with some of the math. You will be responsible for
a broad range of cost concepts and the subject of earned value. The good news is that
you don’t have to be a certified public accountant to answer the questions; they are
approached from a project manager’s perspective.
NOTE: You may use a basic six-function calculator, which is built into the
computer at the test center. If you prefer, you may also ask for a handheld
calculator. The calculator will not be programmable or be capable of automated
statistical functions.
Major Processes
You should be aware that PMI endorses the concept of life cycle cost (also called the
“total cost of ownership”). Specifically, project teams should consider not only the
project costs, but also the entire life cycle cost of the major project deliverables. For
instance, the PM might lower project costs by reducing the number and extent of design
reviews. However, those project savings are likely to cause a substantially greater
increase in operating costs for the customer. Life cycle costs include the following
components:
Project costs (some industries call this the acquisition cost)
Operating and maintenance costs incurred by the user
Disposal costs incurred at the end of an item’s useful life (must be done in a safe
and environmentally responsible manner)
NOTE: PMI observes that the ability to influence costs is greatest in the early stages of
a project and numerous government and industry studies have drawn the same
conclusion. Therefore, early scope definition is critical to successful cost performance.
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 7-1
Unit 7: Cost Management
Plan cost management establishes procedures for planning, managing, expending, and
controlling project costs. This plan is a component of the project management plan.
Four Key Inputs for Plan Cost Management (PMBOK® Guide, p. 196):
7-2 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 7: Cost Management
Three Key Tools for Plan Cost Management (PMBOK® Guide, p. 198):
One Key Output for Plan Cost Management (PMBOK® Guide, p. 198):
Units of measure: For example, the unit of measure for tracking key
resources and time might be days, weeks, or months of effort. The unit of
measure for materials might be liters, tons, or cubic yards and so on.
Level of precision: Will a cost estimate of $995.60 be rounded to $1000
or will a different rule be applied?
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 7-3
Unit 7: Cost Management
Level of accuracy: The acceptable range for cost estimates (which may
be affected by various factors including the stage of the project life cycle
and the quality of the available data). See specific ranges of accuracy
provided in the next process (Estimate Costs).
Organizational procedures links: The extent to which the WBS and
control accounts (cost accounts) will be used to plan and track cost
information. Using a code of accounts numerical identifier, each control
account is linked to the organization’s accounting system.
Control thresholds: Establishes an allowable amount of variation before
corrective action is triggered.
Rules of performance measurement: Earned Value rules for calculating
how much credit to take for partially completed activities (e.g., 0-100, 50-
50, and so on). Will be covered later in the chapter.
Reporting formats and process descriptions: The processes of
estimating, budgeting, and control are described and desired formats for
reporting are established.
Cost estimating involves developing an estimate of the costs of all resources needed to
complete the project. The resources that need to be estimated include labor,
equipment, materials, facilities, services, and any special categories such as
contingency or an allowance for anticipated inflation.
The accuracy of estimates tends to improve as a project moves through its life cycle.
Ranges of accuracy that are used in some industries and have been tested in the past
include:
7-4 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 7: Cost Management
Estimate Costs
1. Cost Management Plan: Defines how costs will be managed and controlled,
including methods and levels of accuracy.
3. Scope Baseline: The following three items form the scope baseline and
contain information that is necessary for accurate cost estimating.
Scope statement: Contains the product description, key deliverables,
constraints, and assumptions. For cost estimating, a decision must be
made as to whether the estimates will include only direct costs or will
also include indirect costs.
WBS: Provides a structure to organize the cost estimates into useful
categories (cost accounts or control accounts).
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 7-5
Unit 7: Cost Management
4. Project Schedule: Cost estimates are closely related to what resources will
be used and for how long (activity durations). Data from Estimate Activity
Resources (Section 6.4) and Estimate Activity Durations (Section 6.5) must be
coordinated carefully with cost estimating.
5. Risk Register: The risk register should be reviewed so that projected risk
mitigation costs may be included in the cost estimates.
Uses the actual costs from a similar project and adjusts the estimate
according to whether the current project is expected to be harder or
easier than the previous one.
Also called top-down estimating.
Done early in the project life cycle in most cases.
Is a form of expert judgment.
Less costly than other techniques but also less accurate.
7-6 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 7: Cost Management
4. Bottom-up Estimating: Estimating the cost of individual work items and then
“rolling up” or summarizing the estimates to get a project total. The most widely
accepted technique uses the work packages as the “individual items”. As the
items estimated get smaller, the estimates usually become more accurate but
also more costly to develop.
5. Three-Point Estimating: Used exactly in the same way that it was for
duration estimates. Three-point or PERT estimates are useful when there is
underlying uncertainty in the work. As before, optimistic, most likely, and
pessimistic estimates are used to calculate an average cost that considers the
range of uncertainty in the estimates. The formulas are the same except that the
estimates are for costs rather than durations. PMI states that the following two
distributions are used to distinguish three-point from PERT:
Triangular distribution: Used to model the three-point method
where the average cost would be calculated as a simple average of
the three estimates. E(c) = (O + M + P) / 3
Beta distribution: Used to model the PERT method where the
average cost is calculated with a weighted average approach
(same as for schedule). E(c) = (O + 4M + P) / 6
Place the money into the budget for an individual work package that is
considered risky. This approach is for handling “known unknowns,” is
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 7-7
Unit 7: Cost Management
The use of either type of reserve is intended to reduce the chance of a cost
overrun and the topic is discussed further in the chapter on risk management.
7. Cost of Quality (COQ): The cost of quality includes activities such as training
and audits that are done as part of quality management (which will be covered in
more detail in the chapter on quality).
7-8 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 7: Cost Management
Cost budgeting involves aggregating estimated cost estimates for all individual activities
or work packages so that a cost baseline can be established for measuring
performance. The baseline includes authorized budgets and contingency reserves, but
excludes management reserves (the extra amount for “unknown unknowns”).
Determine Budget
1. Cost Management Plan: Describes how project costs will be managed and
controlled.
2. Scope Baseline: The following three items form the scope baseline and
contain information that is relevant to establishing the cost baseline.
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 7-9
Unit 7: Cost Management
3. Activity Cost Estimates: Cost estimates for each activity within a work
package are aggregated so that the cost of each individual work package is
known. Work package estimates can then be aggregated at the control account
level and so on.
7-10 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 7: Cost Management
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 7-11
Unit 7: Cost Management
Risk register
Cost estimates
Project schedule
Cost control is part of integrated change control. Effective cost control requires
management of the approved cost baseline (sometimes referred to as time-phased
budget) and any changes to that baseline. The two primary factors are managing cost
variances and cost changes. Cost control includes the following:
Control Costs
7-12 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 7: Cost Management
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 7-13
Unit 7: Cost Management
7-14 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 7: Cost Management
Cost estimates
Basis of estimates
Causes of variances
Corrective actions chosen and the reasons
Other lessons learned as a result of cost control
Other Topics:
Opportunity cost: The cost of choosing one alternative and giving up the
potential benefits of another alternative. The concept has special relevance
to project selection; failure to accurately assess opportunity costs may cause
a company to miss projects that would yield the best financial returns.
Sunk cost: Expended costs which you no longer control; “water over the
dam” so to speak. Sunk costs represent money already spent that cannot be
recovered. Financial management principles have long held that sunk costs
should be ignored when deciding whether to spend additional funds to
complete a project.
NOTE: The course slides cover numerous financial methods that have been
tested.
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 7-15
Unit 7: Cost Management
Payback period: The amount of time until net cumulative cash flows are
greater than zero, that is, the point at which the project first makes a net
cumulative profit. When comparing projects, the shortest payback period
indicates the project that will become profitable most quickly. However,
payback period may ignore the potential magnitude of the profit.
A BCR of 1.0 means that expected benefits (revenues) and costs are
equal, in other words, you have a “break-even” project.
A BCR less than 1.0 means that costs are expected to exceed
revenues, in other words, the project is expected to lose money.
A BCR greater than 1.0 is a profitable project; the higher the ratio the
better the project. For example, a BCR of 3.0 means that every dollar
invested in the project will generate a gross payback of $3.00.
PV = Vt / (1 + i)t
t = time period
7-16 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 7: Cost Management
Real-world projects do not consist of a single cash flow and, therefore, the
concept of evaluating multiple cash flows becomes necessary to properly
evaluate real projects. Discounted cash flows (DCF) and net present value
(NPV) are used to evaluate the estimated cash flows of real projects. DCF
calculations convert future cash flows into their present-day value. NPV uses
the calculations from discounted cash flows to determine whether a project will
recover any initial investment and make a profit.
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 7-17
Unit 7: Cost Management
7-18 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 7: Cost Management
Self-Study
Drill Practice: Cost Management
Question Answer
3. What is the EAC and how is it calculated? 3. The estimate at completion is a revised
estimate of total project cost and can be
calculated several ways (Course slides 7-50 to
7-52).
EAC = BAC / CPI (primary formula which
assumes that current performance will
continue into the future)
EAC = AC + (BAC-EV) (which assumes that
remaining work will be accomplished at the
original budgeted rate)
EAC = AC + [(BAC-EV) / (CPI x SPI)] (which
is used if you need to also consider the effect
of the schedule if you have an imposed
deadline)
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 7-19
Unit 7: Cost Management
Revenues / Costs
9. What is value analysis and how does the 9. A cost reduction tool comprised of four
process work? major steps:
a. Analyze a proposed design (determine
inherent functions)
b. Determine relative cost of each function
c. Assess whether each function is really
needed
d. Assess how to provide the necessary
functions at the lowest cost without
compromising quality or performance
(p. 7-18).
10. What is the cost management plan? 10. A component of the project management
plan that documents how estimating,
budgeting, and controlling are to be handled
(pp. 7-3 & 4).
12. What is a bottom-up cost estimate? 12. A bottom-up estimate uses three primary
steps:
a. Create a project WBS
b. Do detailed cost estimates for each work
package
c. Add the cost estimates to provide
estimates for higher levels in the WBS
(pp. 7-4 and 7-7).
13. What is an approximate range of accuracy 13. -5 to +10 percent (p. 7-4).
for a bottom-up estimate?
7-20 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 7: Cost Management
14. What is payback period? 14. The first time period in which net
cumulative revenues exceed net cumulative
costs.
15. Regression analysis relies on what kind of 15. Parametric (p. 7-17).
cost estimating?
16. What is an opportunity cost? 16. The benefit that is lost by investing in a
given project instead of an alternative.
(p. 7-15)
17. What is the cost baseline? 17. A time-phased budget used to measure
and monitor cost performance on a project (p.
7-11).
19. What is a sunk cost? 19. Costs already expended and no longer
under your control.
20. A BCR (benefit cost ratio) greater than 20. False. A BCR greater than one indicates
zero indicates a profitable project. True or a profitable project. Example: Assume
false? revenues are estimated at $50,000 and the
cost estimate is $100,000. The BCR would be
0.5 (greater than zero) but the project would
lose $50,000 (p. 7-16).
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 7-21
Unit 7: Cost Management
21. What is the learning curve theory? 21. The learning curve theory holds that costs
will decrease as you get better at doing a
repetitive task. Formally stated, the learning
curve approach says:
22. Present value is ______. 22. the value today of future cash flows
(p. 7-16).
26. Is ROI related to BCR in any way? 26. Yes. They both use revenues and costs
in the calculations. The difference is that ROI
subtracts costs from revenues in the
numerator. The result is that ROI = BCR-1.
To get ROI as a percentage, simply multiply
the ROI by 100. (p. 7-17).
7-22 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 7: Cost Management
27. Using more and more resources and 27. Law of diminishing returns (p. 7-18).
getting less and less resulting output describes
what law?
28. What document provides the basis to 28. WBS (a component of the scope baseline)
identify all the work that will incur costs on a (p. 7-5, Input #3).
project?
30. What is a Life Cycle Cost (LCC) estimate? 30. A cost estimate covering the entire cost of
ownership for the customer, i.e., the cost of
the project (acquiring the product or service),
the costs of operating and maintaining the
item, and disposition costs if appropriate (p. 7-
1).
31. What are the two conditions under which 31. Analogous estimates, while less costly
analogous estimating works best? than other techniques, are also less accurate.
They are most reliable when:
a. The previous projects used for comparison
are similar in fact and not just in appearance,
and
b. The estimators have the needed expertise
(p. 7-7).
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 7-23
Unit 7: Cost Management
33. In earned value, what is the 50-50 rule? 33. It is one way to determine how much work
has been completed on a project, i.e., the
BCWP.
36. What is the cost baseline? 36. A time-phased budget used to measure
and monitor cost performance. Often
displayed in the form of an S-curve (p. 7-11).
37. Is it possible to have multiple cost 37. Yes, especially on larger projects where
baselines? one might want to measure different aspects
of cost performance (p. 7-11).
7-24 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 7: Cost Management
39. What is an order of magnitude estimate? 39. A guesstimate or ballpark estimate usually
done early when detailed information is not
available.
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 7-25
Unit 8: Quality
Management
Major Processes
Other Topics
Self-Study
Unit 8: Quality Management
(PMBOK® Guide, Chapter 8)
Historically, quality management questions have been difficult for some exam takers for
two major reasons: 1) over-reliance on their previous training and personal experience
(rather than carefully reviewing PMI® terminology) and 2) mathematical concepts such
as process control and standard deviation have caused difficulty for some people.
Major Processes
8.1 Plan Quality Management (identifying quality requirements and standards and
how to demonstrate compliance)
8.2 Perform Quality Assurance (auditing quality requirements and quality control
measurements to ensure appropriate quality standards are used)
8.3 Control Quality (monitoring results to assess performance and recommend
necessary changes)
The PMBOK® Guide defines quality management as the processes required to ensure
that the project will satisfy the needs for which it was undertaken. PMI indicates that
their approach to quality management is intended to be compatible with the
International Organization for Standardization (ISO) as well as other well-known
approaches associated with Deming, Crosby, TQM, Six Sigma, Lean Six Sigma, and
Continuous Improvement.
PMI defines quality as the degree to which a set of inherent characteristics fulfills
requirements (PMBOK® Guide, p. 228). A critical part of the process is to identify
stakeholder needs and turn them into requirements. Needs may be explicitly stated or
implied.
Quality and grade are not the same thing. Grade is measured by features and functions
and a project team can choose a lower grade because it saves money and still meets
requirements (for example, a BMW would be nice but a Ford Focus may meet your
needs at a lower cost). However, low quality is always a problem because it means that
needs and requirements are not being met.
Although not specifically mentioned in the PMBOK® Guide, a related concept that often
appears on the exam is that of gold-plating. Gold-plating is providing a solution that
exceeds the original requirement and is bad to the extent that it may cause the project
to cost more and take longer. If the requirements are accurate, there is no reason to
exceed them (especially if doing so results in lost profits for the contractor).
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 8-1
Unit 8: Quality Management
Finally, PMI contends that achieving ISO compatibility means that quality management
must recognize the importance of:
8-2 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 8: Quality Management
Six Key Inputs for Plan Quality Management (PMBOK® Guide, p. 233):
c) Cost baseline: Documents planned costs and the time intervals for
measuring and reporting actual cost performance.
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 8-3
Unit 8: Quality Management
3. Risk Register: May contain information on threats and opportunities that may
affect quality (Section 11.2.3.1).
Eight Key Tools for Plan Quality Management (PMBOK® Guide, p. 235):
Less rework
Higher productivity
8-4 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 8: Quality Management
2. Cost of Quality (COQ): The total cost of efforts to achieve quality, which
includes the costs of conformance (preventing defects and assessing quality)
and non-conformance (fixing defects). Three specific categories of costs are
prevention, appraisal, and failure. Preventing defects is believed to reduce
overall costs and is preferred over costs of non-conformance.
3. Seven Basic Quality Tools: Also known as 7QC, the seven basic quality
tools include:
a) Cause and effect diagrams: You must know that cause and effect
diagrams are also called Ishikawa or Fishbone diagrams. They are used to
illustrate the possible factors that may be causing or influencing certain
problems. The problem statement is displayed at the “head of the fishbone” and
selected stakeholders ask “why” until an actionable root cause has been
identified. One possible use of fishbone diagrams is to investigate the special
variations known as “special causes” in control charts (covered below in item 3f).
PMI also emphasizes that they may be used to stimulate thinking and discussion.
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 8-5
Unit 8: Quality Management
The tool was named after an Italian economist who discovered that 80% of the
wealth in a particular region in Europe was held by only 20% of the population.
This discovery eventually was dubbed the 80/20 rule, indicating the importance
of focusing efforts toward improvement on the “significant few.”
Key points about control charts (read the following details as part of
your self-study):
Upper and lower control limits (UCL/LCL) must not be confused with
specification limits (USL/LSL). Control limits describe the natural
variation of a process; observations (process results) that fall within the
limits usually indicate normal, expected variations. Points outside the
limits mean that something has occurred that needs investigation and
8-6 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 8: Quality Management
The PMBOK® Guide states that control limits are generally set at plus or
minus three sigma from the mean.
Effect of standard deviation: Recall the concept of six sigma that was
mentioned in the time management section.
Six Sigma: You should know that PMI has observed that numerous
“modern” companies have adopted Six Sigma as the standard for
measuring quality. The more traditional approach was three sigma. The
difference is that six sigma captures about 99.9997% of outcomes
whereas three sigma only captures about 99.7%. That means that
defects would occur only about 3.4 times in a million under six sigma but
they would occur three times in a thousand under three sigma. In other
words, six sigma is a much more stringent quality control requirement.
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 8-7
Unit 8: Quality Management
standard deviations, which in turn mean more narrow control limits. The
converse is also true, i.e., smaller sample sizes tend toward larger
standard deviations and wider control limits.
PMI suggests that DOE is especially useful for determining how much testing is
needed and for optimizing the performance of processes and/or products.
7. Additional Quality Planning Tools: There are other techniques that can
assist in defining quality requirements, including:
Brainstorming
Force field analysis
Nominal group technique
Quality management and control tools (defined in Section 8.2.2.1)
8-8 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 8: Quality Management
Five Key Outputs for Plan Quality Management (PMBOK® Guide, p. 241):
1. Quality Management Plan: Describes how the project team will implement
its quality policy. The quality plan is an input to the overall project management
plan and describes the approaches for quality assurance, continuous process
improvement, and quality control. The plan should focus on efforts early in the
project that will reduce cost and schedule problems caused by rework.
2. Process Improvement Plan: A plan that details the steps for improving
existing processes. May include activities such as:
4. Quality Checklists: A structured tool to verify that all steps in a process have
been performed. Checklists are often used in the quality management process,
especially for complex tasks or for tasks performed frequently.
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 8-9
Unit 8: Quality Management
Quality assurance involves auditing quality requirements and results from quality control
measurements to ensure the project will use appropriate quality standards and
processes.
Five Key Inputs for Perform Quality Assurance (PMBOK® Guide, p. 244):
4. Quality Control Measurements: The results of quality control that are in turn
fed back to Quality Assurance to consider any potential changes in the
organization’s quality standards and processes. These measurements provide
8-10 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 8: Quality Management
Three Key Tools for Perform Quality Assurance (PMBOK® Guide, p. 245):
1. Quality Management and Control Tools: The tools for quality planning
(Section 8.1.2) and quality control (Section 8.3.2) may also be used for quality
assurance. Other relevant tools include (see PMBOK® Guide, Figure 8-10, p.
246):
Affinity diagrams (a kind of brainstorming tool used by a team to organize
large amounts of detailed data into logical categories)
Activity network diagrams (used to plan the appropriate sequence for a set
of activities or tasks; examples include arrow and precedence diagrams covered
previously in the time management chapter)
Matrix diagrams (a chart with rows, columns, and cells [problems, factors,
objectives respectively; the diagram attempts to show the strength of
relationships among these factors)
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 8-11
Unit 8: Quality Management
Four Key Outputs for Perform Quality Assurance (PMBOK® Guide, p. 247):
Auditing
Feedback
Correction
8-12 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 8: Quality Management
Quality evaluation: There are two kinds of evaluation you should know for the
exam. They are similar to the mid-project and post-project evaluations in the
integration management chapter, and they come from the literature on education:
Formative (also called a quality audit): Done during the project for the
purpose of making corrections.
Quality responsibility: Responsibility for quality can be viewed two ways (be
careful of the exact wording on this topic):
Quality control involves monitoring and recording specific project results to assess
performance and recommend necessary changes. Project results include both product
deliverables and project performance measures such as cost and schedule.
The primary differences between quality assurance and quality control are as follows:
Quality assurance is used during planning and executing to provide
confidence that stakeholders’ requirements will be met.
Quality control is used during executing and closing to provide formal
documentation that acceptance criteria have been met.
Prevention (keeping errors out of the process) and inspection (keeping errors
away from the customer).
Attribute sampling (the result conforms or it does not; an item is dented or not
dented) and variables sampling (results are measured to determine the degree
of conformity).
Tolerances (the result is acceptable if it’s within the range specified by the
tolerance) and control limits (the process is under control if the result falls within
the control limits).
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 8-13
Unit 8: Quality Management
Control Quality
1. Project management plan 1. Seven basic quality tools 1. Quality control measurements
2. Quality metrics 2. Statistical sampling 2. Validated changes
3. Quality checklists 3. Inspection 3. Verified deliverables
4. Work performance data 4. Approved change requests 4. Work performance information
5. Approved change requests review 5. Change requests
6. Deliverables 6. Project management plan
7. Project documents updates
8. Organizational process assets 7. Project documents updates
8. OPA updates
8-14 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 8: Quality Management
1. Seven Basic Quality Tools: Described in Section 8.1.2.3, the 7QC also
apply to quality control.
For the exam, you should know the conditions under which sampling is most
appropriate:
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 8-15
Unit 8: Quality Management
8-16 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 8: Quality Management
Other Topics:
Histograms, also called bar charts (grouping data and rank ordering, e.g.,
Pareto diagram)
Priority of Quality, Cost, and Schedule: Historically, quality received “lip service”
in many companies but was actually subservient to cost and schedule goals.
Modern thinking emphasizes that quality should share equal priority with cost and
schedule goals.
The primary responsibility for developing design specifications rests with the
project engineers.
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 8-17
Unit 8: Quality Management
back on. Zero work-in-process inventory forces a company to find and fix quality
problems or they will constantly miss their schedule commitments.
Motivation and quality: PMI advocates the belief that increased quality is the
likely result when team members display pride, commitment, and an interest in
workmanship. One way to harm such a culture is by allowing frequent turnover of
the people assigned to the project.
Marginal analysis: Optimal quality is reached at the point where the incremental
revenue from improvement equals the incremental cost to secure it.
8-18 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 8: Quality Management
Sample: Because populations can be quite large, we often examine only some
of the items hoping to get an accurate picture of the entire group at a lower
cost.
By comparison, +/- 6 sigma is the more modern, and also more stringent,
approach to setting quality standards. If processes are designed to a
standard of six sigma, you will only experience defects of approximately
three per million.
TQM (Total Quality Management): Know the following statement about TQM
(p. 229, PMBOK® Guide): TQM is an approach for implementing a quality
improvement program and for achieving continuous improvement
ISO 9000: This entry is provided to clarify the references on pp. 6-1 and 6-2 at
the beginning of the chapter. ISO 9000 is one aspect of the overall International
Organization for Standardization (ISO) program. Specifically, ISO 9000
describes a set of documented standards to ensure that organizations
consistently meet certain minimum levels of performance.
Run Chart: Trend analysis is performed using a run chart, which is a line graph
that plots data points in the order in which they occur (i.e., on a time scale). The
data may show:
Variation
Trends (is performance improving, deteriorating, or remaining
constant?)
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 8-19
Unit 8: Quality Management
8-20 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 8: Quality Management
Self-Study
Drill Practice: Quality Management
Question Answer
1. Who is responsible for project quality? 1. The PM (the word project is the key)
Note: All page numbers in this drill practice refer to (p. 8-13).
the reference manual unless otherwise indicated.
2. An assignable cause or variance indicates 2. there is a problem that is probably not just
that ______. the result of random events and therefore
needs to be corrected
(pp. 8-6/7).
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 8-21
Unit 8: Quality Management
9. What is the best way to improve the 9. Good design practices (designing in
reliability and maintainability of a product? reliability and maintainability), i.e., quality
should be designed in, not inspected in (p. 8-
17).
12. What quality control tool provides a bar 12. Pareto chart (or diagram) (p. 8-6)
chart that shows the greatest source of defects
or variances on the left and the fewest defects
on the right?
13. What is kaizen? 13. A Japanese concept meaning
incremental, continuous improvement
(p. 8-17).
8-22 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 8: Quality Management
17. When compared to cost and schedule, 17. Quality should be of equal importance
what priority should quality have? (p. 8-17).
18. What is the Rule of Seven? 18. When using control charts, if 7
consecutive observations fall above the
midpoint, below the midpoint, or trend in the
same direction they should be investigated as
if they had a special or assignable cause.
It is extremely unlikely that 7 outcomes in a
row would be on the same side of the mean if
the process is operating normally
(p. 8-7).
19. JIT (Just in Time) attempts to reduce 19. zero stock (pp. 8-17 & 18).
work-in-process inventory to ______.
20. What does the process Perform Quality 20. Auditing quality requirements and results
Assurance involve? from QC measurements to ensure appropriate
quality standards are used
(p. 8-10).
21. What is the difference between prevention 21. Prevention is keeping errors out of the
and inspection? process. Inspection is keeping errors out of
the hands of the customer
(pp. 8-2 & 13).
22. What is the difference between attribute 22. Attribute sampling checks whether a
and variable sampling? result conforms or not. Attributes can be
objective or subjective. Variable sampling
measures the result on a continuous scale
(measures the degree of conformity)
(pp. 8-13 & 18).
23. What is the difference between special 23. Special causes are unusual events that
causes and random causes? may signal a problem that needs correction.
Random causes are simply normal process
variations, i.e., nothing is wrong (pp. 8-6 & 7).
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 8-23
Unit 8: Quality Management
24. Which quality control tool would help you 24. Checksheets (p. 8-6)
count the number of defects and determine
their location?
26. What is the difference between control 26. Specification limits are the contractual
limits and specification limits? tolerances agreed to by the project
participants. Control limits describe the
capability of a particular process (pp. 8-6 & 7).
27. What does the term inspection mean and 27. Examination of a work product to
what are other names for the same thing? determine whether it conforms to
requirements. Inspection often involves
measurements. Also called audits, walk-
throughs, and reviews (pp. 8-15 & 16).
30. What are the three major types of costs 30. Prevention, appraisal, and failure (p. 8-5,
associated with conformance and Cost of Quality).
nonconformance?
8-24 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 8: Quality Management
32. Three standard deviations either side of 32. 99.7% (p. 8-19)
the mean of a normal distribution contains
what percent of the population?
33. What are control charts? 33. A graphic display of process results taken
over a period of time. They help determine if a
process is under control
(pp. 8-6 & 7).
35. What is the difference between grade and 35. Grade is a category or rank given to
quality? entities having the same functional use but
different features and functions (a high-end
luxury item or a simpler, cheaper version).
Quality is conformance to requirements.
Low quality is always a problem but low grade
may not be (i.e., customer chose a cheaper
solution) (p. 8-1).
36. What tool would help stimulate thinking 36. Cause and effect diagram. Note: you
and generate discussion about potential MUST know the alternate names (Ishikawa
causes of a problem? Diagram and Fishbone Diagram)
(p. 8-5)
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 8-25
Unit 9: Human
Resource Management
Major Processes
Other Topics
Self-Study
Unit 9: Human Resource Management
(PMBOK® Guide, Chapter 9)
The questions on this topic focus predominantly on people and behavioral issues; there
are some questions on traditional human resource administrative functions.
Major Processes
Human resource management involves organizing, managing, and leading the project
team. The processes are aimed at making the most effective use of the people
associated with the project, including all stakeholders (sponsors, customers, team
members, upper management, and others). The project sponsor should work directly
with the team to assist with funding, scope questions, and influencing other key
stakeholders for the benefit of the project. PMI encourages early involvement of key
team members in the planning process to improve the plan and to increase
commitment.
The project management team, a subset of the project team, is responsible for project
management and leadership. This group is also called the core, executive, or
leadership team.
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 9-1
Unit 9: Human Resource Management
The process must also identify required skill sets and consider that the project team is
competing for limited human resources.
Four Key Inputs for Plan Human Resource Management (PMBOK® Guide, p.
259):
9-2 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 9: Human Resource Management
Five Key Tools for Plan Human Resource Management (PMBOK® Guide, p.
261):
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 9-3
Unit 9: Human Resource Management
Key points:
The objective of this step is to make sure every work package has an
unambiguous owner. So, to avoid confusion, a RACI chart should
never show more than one person accountable for the same task.
In addition to the various charts, project assignments are also listed in
subsidiary management plans. For example, the risk management
plan assigns risk-related activities to team members.
A WBS displays deliverables and work packages.
An OBS (organizational breakdown structure) displays departments,
units, or teams and can show what work they are responsible for.
An RBS (resource breakdown structure) displays individual resources
(human, equipment, facilities) and can show what activities they are
involved in.
The RAM is the primary tool used to display information about roles
and responsibilities (who does what). The RAM does not show the
timing of the work (see Figure 9-5, PMBOK® Guide p. 262).
5. Meetings: Used so that team members can reach consensus about the
human resource management plan.
9-4 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 9: Human Resource Management
One Key Output for Plan Human Resource Management (PMBOK® Guide, p.
264):
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 9-5
Unit 9: Human Resource Management
Staff acquisition is getting the right people assigned to the project. Failure to do so in a
timely manner may affect schedules, costs, risks, quality, and ultimately customer
satisfaction.
Three Key Inputs for Acquire Project Team (PMBOK® Guide, p. 269):
9-6 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 9: Human Resource Management
Five Key Tools for Acquire Project Team (PMBOK® Guide, p. 270):
3. Acquisition: When an organization does not have the requisite staff or they
are committed to other projects, the needed skills can be procured from outside
the organization. Such an action is taken in lieu of hiring and training a
permanent employee.
4. Virtual Teams: Virtual teams spend little or no time working face to face.
Given modern technology, virtual teaming makes the following approaches
possible:
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 9-7
Unit 9: Human Resource Management
Three Key Outputs for Acquire Project Team (PMBOK® Guide, p. 272):
9-8 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 9: Human Resource Management
Three Key Inputs for Develop Project Team (PMBOK® Guide, p. 274):
3. Resource Calendars: Identifies when team members are available for team
development activities.
Seven Key Tools for Develop Project Team (PMBOK® Guide, p. 275):
1. Interpersonal Skills: Also called “soft skills”, PMI has historically identified
the following interpersonal skills that are useful for team development. They
include:
Problem solving: defining the problem, identifying alternatives, and
making a timely decision.
Leadership: developing a vision and strategy and motivating others to
achieve that vision
Influencing: getting things done even though you may have limited
formal power
Negotiation and conflict management: conferring with others to reach
an agreement or to overcome a problem
Communication: the exchange of information
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 9-9
Unit 9: Human Resource Management
PMI has also identified emotional intelligence, team building, and group
facilitation skills as highly appropriate for developing the team.
Be familiar with the following model that identifies five stages of team
development (known either as the Tuckman model or the Tuckman ladder):
Forming: Team members meet and learn about the project and their
roles. Members often experience confusion and uncertainty at this
point. Members tend to act in an independent manner and not be
open to other team members.
Storming: As work begins, team members may clash and compete
for desired assignments and outcomes. Opposing sub-groups may
form and differing ideas may produce conflict.
Norming: Team members begin to adjust behavior and support the
team. Team begins to trust each other and share ideas and
information.
Performing: Team functions as a well-organized, cohesive unit.
Issues are handled smoothly.
Adjourning: The work is completed and the team is released from the
project. Team may feel separation anxiety if they had matured
effectively into the performing stage.
9-10 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 9: Human Resource Management
5. Colocation: Placing team members in the same physical vicinity (also known
as a “tight matrix”) enhances communication and other team development
issues. When colocation is not possible, a “war room” may be used to help
create a better sense of identity with the project.
Key points:
Only desirable behavior should be rewarded.
Team members should not be punished for unrealistic expectations
imposed by senior management.
Rewarding only some team members may harm cooperation and
cohesiveness in the group.
Public recognition is effective with many people (not all).
Recognize performance during the project instead of waiting until
afterward.
Two Key Outputs for Develop Project Team (PMBOK® Guide, p. 278):
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 9-11
Unit 9: Human Resource Management
continuing goals for the future. The PMBOK® Guide mentions the following
indicators of good performance:
Project goals are met (technical, schedule, cost)
Improvements in personal, individual skills
Improvements in team cohesion (better communication, reduced
instances of conflict, and generally positive feelings)
Reduced turnover rates
Managing the team involves tracking team performance, providing feedback, resolving
issues, and coordinating changes. Important management skills for managing the team
include communication, negotiation, conflict management, and leadership.
Management of the team is complicated when members report to more than one
boss (a common challenge in matrix organizations wherein employees report to a
functional manager as well as a project manager).
Management of these dual reporting relationships is a critical success factor in
project management.
Six Key Inputs for Manage Project Team (PMBOK® Guide, p. 281):
1. Human Resource Management Plan: Portions of the plan that are relevant
at this point include roles and responsibilities, organizational structure, and the
staffing management plan.
9-12 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 9: Human Resource Management
Four Key Tools for Manage Project Team (PMBOK® Guide, p. 282):
Feedback for appraisals can come from supervisors directly observing the project
work or it can come from external sources. A common practice involves the use
of 360-degree feedback from multiple sources (peers, superiors, subordinates,
customers).
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 9-13
Unit 9: Human Resource Management
NOTE: Personality conflicts are the least likely kind of conflict on this list;
however, our intuition might lead most of us to consider personality to be a
major cause of conflict. Therefore, beware of personality conflict as a
“distractor” (incorrect) choice on these questions about conflict!
9-14 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 9: Human Resource Management
PMI recognizes five methods for responding to conflict. The methods were
adapted from the original work of Kenneth Thomas and Ralph Kilmann.
Technique Description
Problem Solve/Collaborate Approaching conflict as a problem to be solved
Using open exchange of information; searching for
alternatives that satisfy the needs of both parties,
i.e. “win-win”
Used when the issues are too important for
compromise
Historically, PMI called this the best method for
conflict resolution
PMBOK® Guide now says each approach has its
place (which is what TK originally said)
TK (Thomas and Kilmann) originally called this
collaborating
PMI has also called this “confronting”
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 9-15
Unit 9: Human Resource Management
Technique Description
Smooth/Accommodate Emphasizing areas of agreement rather than
areas of disagreement
Conceding one’s position to maintain harmony
and create goodwill
Used when contentious issues threaten ability to
reach an agreement
Concern: the agreement may be temporary
because the difficult issue was not resolved and
will re-emerge
TK: Called this accommodating
9-16 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 9: Human Resource Management
Five Key Outputs for Manage Project Team (PMBOK® Guide, p. 284):
3. Project Documents Updates: The issue log, roles description, and staff
assignments may be updated.
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 9-17
Unit 9: Human Resource Management
Other Topics:
Power and authority: PMI recognizes the following types of power and authority.
The concepts of power and authority in this context are almost interchangeable.
Reward power (authority): To the extent that project managers can provide
things that are valued by team members, they can elicit more dedication and
cooperation from the team. Examples of rewards include monetary bonuses,
time off, furniture or computer equipment, certificate of appreciation,
assistance with access to education or a desired job, and so on.
Coercive or penalty power: The basis of this power derives from the threat
of retaliation or withholding something of value. In general, PMI believes this
approach ought to be used as a last resort.
9-18 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 9: Human Resource Management
NOTE: PMI recommends maximum use of reward and expert power and
minimal use of coercive power.
Motivation theories: The following seven motivation and leadership theories are
of particular importance for the exam:
Theory X: The traditional view of the work force holds that workers are
inherently lazy, self-centered, and lacking ambition. Therefore, an
appropriate management style is strong, top-down control.
Theory Y: This view postulates that workers are inherently motivated
and eager to accept responsibility. An appropriate management style is
to focus on creating a productive work environment coupled with positive
rewards and reinforcement.
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 9-19
Unit 9: Human Resource Management
6. Blake and Mouton’s Managerial Grid: Blake and Mouton provided a model
that measures two aspects of how people lead:
9-20 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 9: Human Resource Management
Extravert vs. Introvert: Indicates how we interact with the world and
where we direct our energy. Extraverts are energized by being with
other people whereas introverts are energized by spending time alone.
Extraverts think out loud whereas introverts think things through inside
their head.
Sensing vs. Intuitive: Indicates the kind of information we naturally
notice. Sensing people trust what is certain, value common sense, and
are oriented to the present. Intuitive people like new ideas, value
innovation, and are oriented to the future.
Thinking vs. Feeling: Indicates our preferences when we make
decisions. Thinking people are logical, detached, and analytical. They
proceed in an objective way and prefer that justice is achieved as a
result of their decisions. Feeling people are fair-hearted, involved, and
subjective. They worry about how a decision will affect others
emotionally. They identify with the emotional pain of others and prefer
tact and harmony.
Judging vs. Perceiving: Indicates whether we prefer to live in a
structured way or a more spontaneous way. Judging people are planned
and orderly, are happiest when a decision has been made, derive
satisfaction from finishing projects, and take deadlines very seriously.
Perceiving people are spontaneous and flexible, are happiest when
options are still available, derive satisfaction from starting projects, and
consider deadlines to be “elastic.”
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 9-21
Unit 9: Human Resource Management
Advantages of delegating:
How to delegate:
What not to delegate: You should avoid delegating certain sensitive aspects
of leadership, such as:
Hiring
Firing
Pay
Organizational policy
Management of key stakeholders
9-22 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 9: Human Resource Management
The following resource planning tool is not covered in the PMBOK® Guide but
has appeared on the exam:
Kick-off meetings: You should know that 1) kick-off meetings are the
responsibility of the project manager (not upper management), and 2) you should
know the objectives of a kick-off meeting. The following list was published in a PMI
monograph:
Concurrent engineering:
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 9-23
Unit 9: Human Resource Management
Additional terminology:
Arbitration: Disputes heard by a neutral third party. The parties usually agree
in advance that they will abide by the resulting decision.
“H.R. functions”: Aside from the traditional roles of recruitment and hiring,
human resource departments may provide the following functions that are
relevant to project teams:
Training
Career planning
Team building
9-24 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 9: Human Resource Management
Self-Study
Drill Practice: Human Resource Management
Question Answer
5. In which direction is the balance of power 5. Power is shifted in favor of the functional
shifted in a weak matrix? managers in a weak matrix (p. 2-5).
8. What is one way to create a greater sense 8. Get and use a project war room so that the
of identity among team members? team can work in the same physical location
(p. 9-11, colocation)
9. Name five ways of dealing with conflict. 9. Problem solve/ Collaborate (Confront)
Compromise/Reconcile
Smooth/Accommodate
Withdraw/Avoid
Force/Direct (Compete) (pp. 9-15 & 16)
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 9-25
Unit 9: Human Resource Management
Question Answer
10. If both parties in a conflict employ forcing, 10. Stalemate or creating an enemy (p. 9-16)
what is a possible outcome?
11. What is concurrent engineering? 11. An attempt to lower costs and accelerate
schedules through the use of multi-functional
teams and overlapping of project phases
(p. 9-23).
12. What is the difference between a 12. A resource Gantt chart shows the timing
responsibility matrix and a resource Gantt of the tasks and a responsibility matrix does
chart? not (pp. 9-3, 9-4, and 9-23).
13. List five examples of fringe benefits. 13. Profit sharing, training, medical benefits,
education, and employer matching of social
security payments (p. 9-24).
14. Parking spaces and access to an 14. Perks, also referred to by the more formal
executive dining room are examples of name “perquisites”
______. (p. 9-24)
16. During a vitally important negotiation, one 16. Withdraw/avoid (p. 9-16)
of the parties has become angry and is now
acting in a confrontational, belligerent manner.
Which conflict method would be appropriate?
17. What does McGregor’s Theory X 17. Workers are inherently lazy and must be
postulate about the work force? managed with a strong, top-down approach
(p. 9-19).
18. What is the major difference between the 18. The authority of an expeditor is generally
authority of a project expeditor and that of a limited to the department or division headed by
project coordinator? his/her vice president. The authority of a
coordinator is more likely to work across
departments or divisions (p. 2-5).
19. How is productivity measured? 19. Output divided by input (p. 9-24)
9-26 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 9: Human Resource Management
Question Answer
21. David McClelland identified three needs 21. a) the need for achievement (people who
that motivate humans. They are ______. prefer tasks that provide for personal
responsibility and results based on their own
efforts), b) the need for power (people who
desire situations in which they wield power
and influence over others), and c) the need for
affiliation (people who are motivated by being
liked and accepted by others) (p. 9-20).
25. Which conflict resolution method is least 25. Smoothing (p. 9-16)
likely to produce a lasting solution?
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 9-27
Unit 9: Human Resource Management
Question Answer
26. Which conflict resolution approach is most 26. Problem solving (p. 9-15)
likely to produce a lasting solution?
28. When is matrix management particularly 28. On complex projects involving cross-
appropriate? functional effort (p. 2-5).
31. a) Name six interpersonal skills (also 31. Problem solving, leading, influencing,
referred to as general management skills) that negotiating, communicating, and motivating;
apply to project management. use the acronym “PLINCM”
(pp. 9-9/10).
32. Which theory measures a leader’s 32. Blake and Mouton’s Managerial Grid
concern for production versus concern for
(p. 9-20).
people?
9-28 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 10:
Communications
Management
Major Processes
Other Topics
Self-Study
Unit 10: Communications Management
(PMBOK® Guide, Chapter 10)
The questions on this topic are very straightforward and you can rely on “common
sense” for many of the questions. The PMI Director of Certification was once quoted as
saying, “If you know which end of the phone to talk into, you can pass this section.”
Major Processes
The PMBOK® Guide defines communication management as “the processes that are
required to ensure timely and appropriate planning, collection, creation, distribution,
storage, retrieval, management, control, monitoring, and ultimate disposition of project
information.” PMI notes that project managers spend most of their time communicating
with stakeholders who often have different perspectives, interests, and expertise.
Effective communication can bridge potential gaps among these stakeholders and
increase the chances of successful project outcomes.
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 10-1
Unit 10: Communication Management
PMI also suggests that the following general communication skills are important for
project managers:
Effective:
Information to the right audience
At the right time
In the right format
Efficient:
Providing only the information needed
Avoiding information overload
10-2 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 10: Communication Management
The concept of communication channels within a team is important for the exam.
You must know that as the project team grows larger, the number of
communication channels also increases. The number of channels provides a
measure of the complexity of communication on a given project. You must
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 10-3
Unit 10: Communication Management
10-4 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 10: Communication Management
Special note for the exam: PMI says that project managers spend as much as
90% of their time acquiring and communicating information! Senders and
receivers each have important and specific responsibilities during the
communication process:
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 10-5
Unit 10: Communication Management
5. Meetings: Provide a logical forum for the team to discuss the best way to
communicate project information and respond to stakeholders. Key points:
Most meetings involve resolving problems and/or making decisions.
While there are casual, informal meetings; most meetings should be
planned as to the time, place, and agenda. Minutes should be
documented and shared with appropriate stakeholders.
10-6 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 10: Communication Management
Manage Communications
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 10-7
Unit 10: Communication Management
10-8 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 10: Communication Management
While some reports are simple, more elaborate reports may address factors such as:
Past performance and forecasts of schedule and cost
Current status of risks and other issues
Work actually completed vs. work that should have been completed
Summary of changes approved
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 10-9
Unit 10: Communication Management
Control Communications
10-10 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 10: Communication Management
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 10-11
Unit 10: Communication Management
Other Topics:
10-12 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 10: Communication Management
5. Get a project war room: A location owned by the project team for meetings,
storage of information, and so on. Especially important if a tight matrix is not
possible. “Improves identity with the team.”
6. Make meetings effective: PMI surveys have revealed that meetings are a
major time sink for project managers. Effective use of everyone’s time is
crucial. Therefore, call meetings only when they are really needed. Follow
good meeting policies such as:
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 10-13
Unit 10: Communication Management
Note: PMI says there are four important roles for a meeting
chairperson. They are:
1. Encourage participation
2. Handle differences of opinion
3. Prevent drift and disruption
4. Periodically summarize key issues
Role of the project manager: PMI says the key to successful communication is a
project manager who is a good communicator. This statement may seem simplistic
and obvious, however, it is indeed very true!
10-14 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 10: Communication Management
Self-Study
Drill Practice: Communication Management
Question Answer
4. What type of communication should be 4. Formal, written (falls under the heading of
used to document customer acceptance of contractual issues) (p. 10-14)
major project deliverables?
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 10-15
Unit 10: Communication Management
Question Answer
12. Who is the key to all project 12. The project manager (p. 10-14)
communications?
14. The use of both formal and informal 14. project integration (p. 10-13).
communication is likely to enhance____.
16. Change requests is an output to which 16. Control Communication; all monitor and
communication process? control processes have change requests as an
output (p. 10-12)
17. Effective communicators have ______. 17. high regard for the opinions and feelings
of other people (p. 10-13).
18. What effect does disseminating the 18. Uncertainty is reduced and project
project management plan have on stakeholders are appropriately informed
performance? (p. 10-14).
10-16 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 10: Communication Management
Question Answer
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 10-17
Unit 10: Communication Management
Question Answer
26. The ______ process is part of planning 26. Plan Communications Management.
and produces what two outputs?
Communications management plan and
project documents updates (pp. 10-6 & 7).
10-18 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 11: Risk
Management
Major Processes
Other Topics
Self-Study
Unit 11: Risk Management
(PMBOK® Guide, Chapter 11)
Some exam takers may be unfamiliar with the basic concepts of probability, expected
monetary value, and decision trees. This unit will review all these concepts so that you
should not experience any particular difficulty.
Major Processes
11.1 Plan Risk Management (defining how to conduct risk management activities)
11.2 Identify Risks (determining which risks might affect the project)
11.3 Perform Qualitative Risk Analysis (qualitative analysis and prioritizing of risks)
11.4 Perform Quantitative Risk Analysis (numerically analyzing identified risks)
11.5 Plan Risk Responses (how to enhance opportunities and reduce threats)
11.6 Control Risks (identifying new risks, tracking identified risks, implementing risk
response plans, and evaluating risk management effectiveness)
Risk is defined as an uncertain event or condition that, if it occurs, can have either a
positive or a negative effect on the project objectives. A risk may have one or more
causes and one or more impacts if it occurs.
Known risks have been identified, analyzed, and can be managed using the processes
in this knowledge area. Known risks may be assigned a contingency reserve as part of
managing them. Unknown risks cannot be ascertained or managed adequately in
advance. A common method for dealing with unknown risks is to allocate management
reserve in the form of extra money, time, or resources.
Individuals and organizations have attitudes toward risk known as risk orientation, risk
tolerance, and risk preference. Some of us are risk takers and some are cautious risk
avoiders. In any event, risk management involves balancing a potential risk against a
potential reward. Another term that describes this concept of risk vs. reward is utility
theory or utility function. In the 5th edition of the PMBOK® Guide, PMI has drawn the
following distinctions among three risk-related terms:
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 11-1
Unit 11: Risk Management
Note: PMI distinguishes uncertainty from risk. They (and others) contend that
uncertainty occurs when there is a “lack of information that makes it difficult to estimate
the likelihood of an event.”
You should know that whenever PMI refers to risk factors, the following three items
comprise those factors:
1. Risk event: The precise description of what might happen to the project.
Also, you should know the difference between the two following types of risk:
The normal risk of doing business. Represents only an opportunity for loss.
11-2 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 11: Risk Management
Five Key Inputs for Plan Risk Management (PMBOK® Guide, p. 314):
1. Project Management Plan: The risk management plan being created at this
step should be consistent with other approved subsidiary management plans
(such as the scope, schedule, cost, quality, human resource, communication,
procurement, and stakeholder plans). The scope, schedule, and cost baselines
are of special importance.
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 11-3
Unit 11: Risk Management
Three Key Tools for Plan Risk Management (PMBOK® Guide, p. 315):
2. Expert Judgment: Improving the risk management plan by drawing upon the
expertise of groups or individuals such as:
Senior management and project stakeholders
Project managers who have worked similar projects
Subject matter experts, industry groups, and consultants
Professional and technical associations
11-4 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 11: Risk Management
One Key Output for Plan Risk Management (PMBOK® Guide, p. 316):
1. Risk Management Plan: The single output of risk planning is the risk
management plan. This plan addresses how risk identification, qualitative and
quantitative analysis, response planning, and control will be handled. The plan
may include the following:
Methodology
Roles and responsibilities
Budgeting and timing
Risk categories: May employ information from the RBS (Risk Breakdown
Structure)
Definitions of probability and impact: How to describe or measure the
likelihood that an event will occur and the effect on project objectives if it does
occur
Probability and impact matrix (more detail under qualitative analysis)
Revised stakeholder tolerances: Risk planning may cause shifts in how
much risk is considered acceptable for a specific project
Reporting formats and tracking (recording risk activities and audits)
Risk identification involves determining which risk events are likely to affect the project
and documenting their characteristics. Risk identification is not a one-time event; it
is an iterative process and normally leads to qualitative analysis. New risks may
emerge at any time and continued risk identification should be performed on a
regular basis throughout the project. During the identification of a risk, it may also
become apparent what the appropriate response should be. This information should be
recorded for subsequent use in the response planning process.
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 11-5
Unit 11: Risk Management
Identify Risks
11-6 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 11: Risk Management
6. Scope Baseline: The scope statement should include any assumptions that
have been made. Assumptions are inherently risky because of the uncertainty
embedded in them. The PMBOK® Guide treats assumptions as especially
important in the chapter on risk management. Assumptions must be identified,
documented, and periodically validated as to their accuracy.
Also, recall that one of the uses of the WBS is risk identification. It is usually
easier to assess the potential risk of a specific work package than to identify risks
for the entire project. The WBS also provides a method for tracking risks at
various levels (summary, control account, and work package levels).
10. Project Documents: The following risk-related project documents are aimed
at improving cross-team and stakeholder communication and may include:
Project charter
Project schedule and network diagrams
Issue log
Quality checklist
Other information (any additional information proven to be valuable in
risk identification)
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 11-7
Unit 11: Risk Management
11-8 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 11: Risk Management
External
Procurement
Legal
Poor planning
Changes in requirements
1. Risk Register: The risk register is built in stages as each risk management
process is performed. A plan is provided, risks are identified, risks are then
analyzed, response plans are developed, and on-going monitoring and control
follows next. New information is developed at each step.
For the exam, also know that a risk trigger is a symptom or warning sign that a
risk is about to occur. An example might be that the cost performance index is
moving out of acceptable thresholds.
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 11-9
Unit 11: Risk Management
Qualitative risk analysis is the process of assessing the likelihood and impact of
identified risks and prioritizing them according to their potential effect on project
objectives. This process is accomplished using established qualitative methods and
tools. The purpose is to help the project team focus on high priority risks and also to lay
the foundation for quantitative analysis should it be needed. Qualitative analysis takes
relatively less time and is less expensive to perform when compared to quantitative
analysis.
Five Key Inputs for Perform Qualitative Risk Analysis (PMBOK® Guide, p.
329):
1. Risk Management Plan: The risk plan provides assignment of roles and
responsibilities (for qualitative analysis activities), stakeholder risk tolerances,
definitions of probability and impact, risk categories that should be considered,
and the monetary and time resources to accomplish the risk activities.
2. Scope Baseline: The scope statement helps the team to understand the
basic nature of the project. Recurring, common projects are inherently less risky
because they have become known and are more predictable. Projects involving
state-of-the-art technology or a high degree of complexity tend to be more risky.
3. Risk Register: At this step, the list of identified risks would be available.
11-10 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 11: Risk Management
Six Key Tools for Perform Qualitative Risk Analysis (PMBOK® Guide, p. 330):
One Key Output for Perform Qualitative Risk Analysis (PMBOK® Guide, p.
333):
1. Project Documents Updates: The risk register and the assumptions log are
the two key documents that may be updated at this point. Updates to the risk
register may include the following:
Relative ranking or priority list for the project: The overall risk ranking
produces risk scores that can be compared among projects. The
information can be useful in several ways: support recommendations to
initiate, continue, or cancel a project; assign the right people to various
projects; and help support a benefit-cost analysis on a project.
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 11-11
Unit 11: Risk Management
List of risks for additional analysis and management: Risks with high
or moderate impacts may be further analyzed using additional techniques.
Quantitative analysis numerically analyzes the probability of each risk and its
consequence on project objectives. Sophisticated techniques such as Monte Carlo
simulation and decision tree analysis are used to do the following:
Determine the probability that specific project objectives can be met.
Quantify risk exposure so that cost and schedule reserves can be determined.
Identify which risks require the most attention.
Identify realistic cost, schedule, and performance targets.
There may be instances in which quantitative analysis is not needed or is not worth the
cost.
11-12 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 11: Risk Management
Six Key Inputs for Perform Quantitative Risk Analysis (PMBOK® Guide, p.
335):
1. Risk Management Plan: Again, the risk plan establishes roles and
responsibilities, the budget and time to do the analysis, risk categories, and
stakeholder risk tolerances.
2. Cost Management Plan: Provides the format and structure for handling cost-
related information and for handling reserves.
3. Schedule Management Plan: Provides the format and structure for handling
schedule-related information and for handling reserves.
4. Risk Register: At this step, the risk register provides a list of risks, risk
priorities, and risk categories (information from all the previous processes).
Three Key Tools for Perform Quantitative Risk Analysis (PMBOK® Guide, p.
336):
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 11-13
Unit 11: Risk Management
11-14 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 11: Risk Management
3. Expert Judgment: Subject matter experts are needed to provide data and
validate the results.
One Key Output for Perform Quantitative Risk Analysis (PMBOK® Guide, p.
341):
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 11-15
Unit 11: Risk Management
Two Key Inputs for Plan Risk Responses (PMBOK® Guide, p. 343):
1. Risk Management Plan: As before, the risk plan assigns people who own
specific risks, defines the thresholds for whether a risk is low, moderate, or high,
and provides the time and budget to conduct response activities.
Four Key Tools for Plan Risk Responses (PMBOK® Guide, p. 343):
11-16 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 11: Risk Management
Note: PMI states that avoidance and mitigation are appropriate for critical
risks with high impact, whereas transference and acceptance are more
appropriate for less critical risks with relatively low impact.
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 11-17
Unit 11: Risk Management
4. Expert Judgment: As always, people with the right experience, training, and
knowledge should be used for the task at hand (in this case, for response
planning).
Two Key Outputs for Plan Risk Responses (PMBOK® Guide, p. 346):
11-18 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 11: Risk Management
Schedule baseline
Cost baseline
Control Risks is the process of keeping track of identified risks, ensuring that risk
response plans are implemented, evaluating the effectiveness of risk responses,
monitoring residual risks, and identifying new risks. The purpose of control is to
determine whether:
Risk responses have been implemented.
Risk responses were effective (or new responses are needed).
Project assumptions are still valid.
Any risk triggers have occurred.
Risk exposure has changed.
Policies and procedures are being followed.
Any new risks have emerged.
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 11-19
Unit 11: Risk Management
Control Risks
2. Risk Register: Provides the list of identified risks, risk owners, agreed
responses, risk triggers (symptoms and warning signs), residual and secondary
risks, watch list of low priority risks, and planned reserves.
3. Work Performance Data: The status of the work is a major input to risk
control. Performance reports give insights into whether risks are occurring and
whether response plans need to be implemented. Specific status of interest
includes:
Deliverable status
Schedule progress
Costs incurred
11-20 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 11: Risk Management
1. Risk Reassessment: The project team should regularly check for new risks
as well as “reassessing” previously identified risks. At least three possible
scenarios should be considered: a) new risks may have emerged and a new
response plan must be devised, b) if a previously identified risk actually occurs,
the effectiveness of the response plan should be evaluated for lessons learned,
and c) if a risk does not occur, it should be officially closed out in the risk
register.
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 11-21
Unit 11: Risk Management
Corrective actions may include contingency plans (devised at the time a risk
event is identified and used later if the risk actually occurs) and workarounds
(passive acceptance of a risk where no action is taken until or unless the risk
event actually occurs). The major distinction is that workaround responses are
not planned in advance.
Other Topics:
Probability Theory:
Probability of heads on the fifth coin toss (50%, the probability on each
coin toss is independent of the others)
If the probability of an event occurring during any given month is .20, the
probability that the event will not occur during the third month is .80.
What is the probability that the event would not occur two months in a
row? (.80 x .80 = .64)
If the P(A) is .50 and the P(B) is .60, the probability that both A & B
would occur is .30 (multiply the probabilities).
11-22 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 11: Risk Management
Risk versus estimating range: When estimating, the wider the range is, the
more uncertain the project is.
Note: You are looking for the estimate with the widest range.
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 11-23
Unit 11: Risk Management
11-24 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 11: Risk Management
Self-Study
Drill Practice: Risk Management
Question Answer
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 11-25
Unit 11: Risk Management
Question Answer
9. How would one determine the probability 9. Multiply the probability of the two events.
that two independent events would both
occur? If the probability of one event is 60% and the
other is 80%, then the probability of both
events occurring is 48% (.60 x .80).
(p. 11-22)
10. What is the primary concern of risk 10. Tracking changes in the risk factors
control? throughout the project (p. 11-19).
11. What is the purpose of including a cost 11. Reduce the chance of a cost overrun.
reserve in the project budget? (p. 11-21, tool #5)
12. What is an advantage of decision trees? 12. The ability to consider risk event
interdependencies (p. 11-14 and slide 11-45).
15. 15.
a. What is the formula for calculating expected a. Multiply the probability of the event by the
monetary value (EMV?) estimated gain or loss (in dollars).
11-26 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 11: Risk Management
Question Answer
18. How would schedule estimates from 18. PERT estimates would tend to be more
PERT generally compare to those from Monte optimistic (possibly overly optimistic)
Carlo simulation? (pp. 11-13 & 14 and slide 11-38).
19. What is a major factor that affects the 19. The choice of probability distribution
results of Monte Carlo simulations? employed by the program (p. 11-14).
20. Is risk management concerned only with 20. No, risk management also considers the
negative or adverse factors? positive opportunities for gain (p. 9-1).
22. The process of determining what risk 22. identification (p. 11-5)
events may affect a project is called risk ____.
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 11-27
Unit 11: Risk Management
Question Answer
23. Which estimate has more risk: an 23. Estimates with a wider range of outcomes
estimate with a narrow range of outcomes or pose a greater risk as the outcomes are less
one with a wide range of outcomes? predictable.
Therefore, 30 days plus or minus 5 days is
more risky than 25 to 30 days
(p. 11-7, input #8, duration estimates).
26. What method would help you assess the 26. Tornado diagram (p. 11-14).
impact of highly uncertain variables on the rest
of the project?
28. What is the purpose of quantitative risk 28. Numerically analyze the probability and
analysis? impact of each identified risk (p. 11-12).
29. What is a decision tree? 29. A diagram that depicts key interactions
among decisions and chance events. The
branches of the tree represent either decisions
(shown as boxes, e.g., conduct a test or don’t
conduct a test) or chance events (shown as
circles, e.g., passed test or failed test).
(p. 11-14 and slides 11-38 and 11-42 to 11-46)
11-28 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 11: Risk Management
Question Answer
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 11-29
Unit 12: Procurement
Management
Major Processes
Other Topics
Self-Study
Unit 12: Procurement Management
(PMBOK® Guide, Chapter 12)
This knowledge area addresses the processes for purchasing or acquiring products and
services from outside the project team or organization.
Major Processes
12.1 Plan Procurement Management (documenting what to purchase, specifying the
approach, and identifying potential sellers)
12.2 Conduct Procurements (obtaining seller responses, selecting sellers, and
awarding contracts)
12.3 Control Procurements (managing procurement relationships, monitoring contract
performance, and making changes as needed)
12.4 Close Procurements (completing project procurements)
In the United States, contracts are legal, mutually binding documents and are subject to
remedy in the courts. Unless stated otherwise, you should assume that the buyer is
internal to the project team (or the team’s organization) and the seller is external to the
team.
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 12-1
Unit 12: Procurement Management
Nine Key Inputs for Plan Procurement Management (PMBOK® Guide, p. 360):
12-2 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 12: Procurement Management
5. Project Schedule: Contains required timelines that may also become the
rationale for entering into a contract (cannot meet the deadline with in-house
sources) or may be needed to evaluate the ability of a prospective contractor to
meet the schedule.
6. Activity Cost Estimates: If in-house costs are high, this may be a reason to
outsource or, conversely, the information may be needed to evaluate proposals
from prospective contractors.
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 12-3
Unit 12: Procurement Management
PMI recognizes three broad categories of contracts. The fixed price and cost
reimbursement categories have been of greatest interest on the certification
exam.
Fixed price (also called lump sum): Appropriate when the product is
well-defined and the risks are generally felt to be low. Risk is borne by the
seller because they are legally obligated to deliver the specified product
even if they incur a financial loss in doing so.
You must be familiar with seven specific types of contracts that fall under
the umbrella of the first two categories above (fixed price and cost
reimbursement). The course slides show examples.
12-4 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 12: Procurement Management
Cost Plus Award Fee (CPAF): As always, legitimate and allowable costs
are reimbursed and an additional fee is paid. In this case, qualitative
performance criteria are defined in the contract and the fee is paid based
on the buyer’s subjective judgment of the seller’s performance. The
buyer’s decision is not usually subject to appeal. Buyers like this
arrangement because it gives them enormous leverage with their sellers.
Award fee pools may be combined with virtually any type of contract.
Fixed Price Incentive Fee (FPIF): Provides the seller with a fixed price
plus a calculated fee based on performance. This contract type is similar
in concept to CPIF in that there is a sharing arrangement that provides an
incentive to control costs. However, in a CPIF arrangement, the seller is
guaranteed a minimum profit. In an FPIF arrangement, it is possible for
the seller to lose money. Therefore, risk is shifting onto the seller in this
type of contract. FPIF contracts also have a ceiling price and a point of
total assumption (PTA). The PTA is the level of cost at which the sharing
arrangement ceases and any further costs come 100 percent from the
seller’s profit. The course slides show an example of how to calculate the
PTA.
Firm Fixed Price (Lump sum): Contracted goods and services are
furnished at an agreed fixed price. The seller bears all the risk but is
potentially rewarded with a maximum profit potential. Best suited for
situations in which risk is low and the product can be well defined.
You should also be familiar with the concept of contract incentives. Incentives
provide a “carrot” aimed at bringing the objectives of the contractor in line with
those of the buyer. Incentives can be used in conjunction with any contract type;
real world experience has shown that incentives are extremely effective.
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 12-5
Unit 12: Procurement Management
Four Key Tools for Plan Procurement Management (PMBOK® Guide, p. 365):
The PMBOK® Guide also states that the analysis should consider not just the
project needs and costs but the overall organization’s needs and costs, as well.
For example, it may not be cost effective to purchase certain equipment or build
a new facility for an individual project. However, the equipment or facility may
also support other work in the rest of the organization.
12-6 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 12: Procurement Management
When the procurement is price driven, the terms bid and quotation are
used.
When the procurement is influenced by technical considerations and
other non-financial concerns, the term proposal is used.
A procurement can be initiated as a unilateral contract, which usually
means a purchase order for routine items at standard (catalog) prices.
Purchase orders become enforceable at the time the supplier ships the
requested items.
Alternatively, a procurement can be initiated as a bilateral contract using
one of four approaches:
a. Request for Information (RFI): This approach is not actually an
official request for a bid. Instead, it asks for “expressions of interest,”
solicits feedback regarding capacity and capability to perform the
work, and so on. The RFI responses may be useful in developing the
qualified sellers list.
b. Invitation for Bid (Sealed Bid): Used for routine, well-defined items.
Buyer wants bids to get the best price. Does not usually involve
negotiations and no discussion is allowed.
c. Request for Quotation: Used for relatively low dollar purchases of
commodity items. Discussion between buyer and seller is permitted.
This approach may be considered a “best value” search, which
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 12-7
Unit 12: Procurement Management
4. Source Selection Criteria: Used to rate or score proposals. The criteria may
be objective (the PM must have a PMP®) or subjective (the PM must have
appropriate experience). Sample criteria include:
Price and overall life cycle cost
Understanding of need
Technical capability
Past performance of seller
Financial and production capacity
Intellectual property and proprietary rights
Warranty
Risk
Management approach
This process obtains information such as bids and proposals from prospective sellers,
selects the winning response, and awards a legally binding contract. For the exam, one
notable activity is the use of qualified seller lists. Procurement (contracting)
specialists develop such lists from a variety of sources and use them to determine who
might have the ability to perform the needed work. These lists can also speed up the
process. Another notable fact is that bidder conferences, if used, are performed as
part of this step. Independent estimates may be important if the procurement is
noncompetitive and you need to ensure that prices are fair and reasonable.
12-8 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 12: Procurement Management
For large, complex procurements, this process may be performed numerous times for
multiple contracts. Also, a common practice is to screen the initial responses and
create a list of competitors “in the competitive range” (known to many people as the
“short list”). More detailed evaluations and negotiations are then conducted with sellers
on the short list. Another practice is the use of the “BAFO” technique (best and final
offer). The technique is used when procurement personnel want lower prices in the
proposals. Other key points:
Weighted evaluation scores are sometimes used to establish a preferred
negotiating sequence for proposals on the short list.
Proposals are often organized into different sections or volumes that are
evaluated separately by different experts. For example, common sections
evaluated separately are technical approach, price, schedule, management
approach, and past performance.
In some instances, organizations prefer (as a risk mitigation strategy or as a cost
competition factor) to have multiple suppliers for certain products.
Conduct Procurements
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 12-9
Unit 12: Procurement Management
12-10 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 12: Procurement Management
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 12-11
Unit 12: Procurement Management
The project manager may not be the lead negotiator but is usually present to
offer assistance.
Objectives of negotiation:
Deadline: “We have to catch a flight at 5:00 p.m. and must complete
the deal before we leave.”
Good cop/bad cop: One person is helpful and understanding while the
other is difficult and demanding.
Fait accompli: Pretending that some condition is essentially a “done
deal” or not negotiable at all.
Missing man: “I’m sorry, only my boss can agree to that request and he
or she isn’t here. Let’s agree to do ____________ instead. I can agree
to that.”
Limited authority: “I can’t agree to reduce the price by $100,000. I’m
only authorized to offer $50,000.”
Delay: “Let’s handle that issue at the next meeting.” May be a ploy
leading to a deadline tactic. “Oops, we’re running out of time, so let’s
sign this deal and work out any issues later.”
Personal Insults: Designed to intimidate you and/or undermine your
confidence.
Fair and reasonable: A personal appeal that may be posed with a great
deal of charm and “folksiness.” “You and I know what’s going on here.
Let’s be reasonable and work this out.”
1. Selected Sellers: Sellers who have been chosen as being in the competitive
range and who have submitted a proposal that has been accepted. The proposal
becomes the basis for the contract (subject to any last-minute negotiating of
terms and conditions).
12-12 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 12: Procurement Management
While there may be differences, the major components in most contracts include
the following:
Statement of work or deliverables
Period of performance and schedule baseline
Required performance reporting
Place of performance and delivery
Pricing and payment terms
Warranty and product support
Penalties and incentives
Subcontractor approvals
Handling of change requests
Dispute resolution procedures
Termination procedures and alternative dispute resolution procedures
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 12-13
Unit 12: Procurement Management
The buyer and the seller both perform control (also called contract administration) to
ensure that the other party meets its contractual obligations. The process involves
monitoring performance, managing interfaces if there are multiple providers, making
changes and corrections, and processing interim payments (often called progress
payments which are based on the seller’s progress in completing the work). In some
cases, control procurements may involve managing the early termination of a contract
(by mutual agreement, for default, or for convenience of the buyer). Several key project
management processes are used to help accomplish these aims:
Direct and manage project work (PMBOK® Guide, Section 4.3)
Control quality (PMBOK® Guide, Section 8.3)
Perform integrated change control (PMBOK® Guide, Section 4.5)
Control risks (PMBOK® Guide, Section 11.6)
Control Procurements
12-14 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 12: Procurement Management
2. Procurement Documents: The contract and the SOW are two of the most
important documents that would guide contract administration.
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 12-15
Unit 12: Procurement Management
If the parties cannot resolve a claim themselves, the matter is then handled
through whatever dispute resolution procedures were established in the contract.
Dispute resolution can occur during project performance or after a project has
been closed.
12-16 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 12: Procurement Management
Contract closure supports the close project or phase process (integration management,
Section 4.6) by completing each procurement. It involves product verification (was
the work completed correctly?) and administrative closeout (updating and archiving of
records). Early termination is a special case of contract closure and can result from a
mutual decision, from default by one of the parties, or for convenience of the buyer.
The rights of the parties should be defined in a terminations clause in the contract.
Close Procurements
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 12-17
Unit 12: Procurement Management
1. Closed Procurements: The buyer provides formal, written notice that the
contract has been completed.
12-18 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 12: Procurement Management
Other Topics:
Centralized:
More economical
Supports specialization of the contracting function
Less responsive to the specific needs of individual projects
Works well in functionally organized companies
Decentralized:
Project manager has more control
Contracting more responsive to individual project needs
Higher costs; duplication of effort
Works best in a projectized organization
Privity of contract: A legal term that recognizes that whereas a formal contractual
relationship exists between the buyer and the prime contractor, no such relationship
exists between the buyer and the subcontractors. It is legally improper for the buyer
to bypass the contractor and deal directly with a subcontractor.
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 12-19
Unit 12: Procurement Management
12-20 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 12: Procurement Management
Waiver: A party can intentionally or voluntarily relinquish rights they had under a
contract. For example, if a project manager accepts incomplete or defective work
and fails to demand correction, the contractor may be excused from meeting any
strict standards of performance.
Numerous students have cited concern about questions on closing the project and
closing a contract. The following review summarizes and compares these
concepts.
Involves performing the project closure portion of the project management plan
In a multi-phase project, may apply only to the activities for the given phase
Establishes procedures to:
1. Verify and document project deliverables
2. Formalize acceptance of deliverables by the customer
3. Investigate and document the reasons for any instance of early project
termination (before completion of the work)
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 12-21
Unit 12: Procurement Management
12-22 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 12: Procurement Management
Self-Study
Drill Practice: Procurement Management
Question Answer
5. What kind of costs should a make-or- 5. direct and indirect (p. 12-6)
buy analysis consider?
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 12-23
Unit 12: Procurement Management
Question Answer
12-24 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 12: Procurement Management
Question Answer
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 12-25
Unit 12: Procurement Management
Question Answer
20. Under which contract type would it be 20. Fixed price (“scope creep” in fixed price
most important for the contractor to arrangements could eat up profit or even result in
control contract changes? a monetary loss) (pp. 12-4 & 5).
22. What are source selection criteria? 22. As an output from plan procurement
management, these criteria are used to rate or
score proposals. The criteria may be objective or
subjective and can include:
Understanding of need
Life cycle cost
Technical capability
Management approach
Financial and production capability
Past performance
Intellectual property and warranty
(p. 12-8)
12-26 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 12: Procurement Management
Question Answer
26. Why are standard contract clauses 26. Because they are less costly to develop and
encouraged? they are legally sufficient for many contractual
situations (already tested and proven) (p. 12-20).
27. What is undefined work? 27. Arises when time is of the essence. Need to
start work but the price and related conditions
have not been negotiated yet.
Often uses a letter contract with the details to be
negotiated later.
Can also occur because of changes to an existing
contract; work proceeds on the basis of an
undefinitized change order (p. 12-20).
28. What are the tools used during close 28.
procurements? Procurement audits
Procurement negotiations
Records management system
(p. 12-18)
29. Why is a post-contract evaluation 29. To establish a historical database to assist in
important? future contractor selections; is considered part of
final lessons learned documentation (p. 12-18).
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 12-27
Unit 12: Procurement Management
Question Answer
32. What is another term that is very 32. SOR (Statement of Requirements) or SOO
similar in meaning to SOW? (Statement of Objectives). In some industries, the
term SOR refers to procurement items presented
as a problem to be solved (p. 12-7).
33. What is an RFP and what is it used 33. RFP = Request for Proposal
for?
It is used to solicit bids from prospective
contractors (pp. 12-7 & 8).
34. Define liquidated damages. 34. A contract provision that specifies monetary
liability if a party is in breach or fails to perform.
Often associated with failure to perform on time
(p. 12-20).
12-28 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 12: Procurement Management
Question Answer
a. You are purchasing 150 laptop a. RFQ (best value search for existing commodity
computers for the engineering school at items in the marketplace)
Imperial College, London, UK. You are
attempting to compare various factors
such as delivery schedule, price, and
technical specs.
b. You are redesigning university b. RFP (customized development of a solution and
classrooms to incorporate new for somewhat high monetary amounts)
technologies so that MBA students can
work interactively in teams and with the
professors.
c. You are making an annual purchase of c. IFB (also called a sealed bid, you are looking for
pencils, paper, and notebooks for the best price for routine items readily available in
employees at your company. the marketplace)
(pp. 12-7 & 8)
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 12-29
Unit 13: Stakeholder
Management
Major Processes
Self-Study
Unit 13: Stakeholder Management
(PMBOK® Guide, Chapter 13)
Stakeholder management identifies people, groups, and organizations that could impact
or be impacted by the project. The topic has increased in importance with each new
edition of the PMBOK® Guide.
Major Processes
13.1 Identify Stakeholders (identifying the interests, involvement, and impact of
people, groups, or organizations that could affect or be affected by the project)
13.2 Plan Stakeholder Management (developing appropriate management strategies
for engaging stakeholders throughout the project)
13.3 Manage Stakeholder Engagement (communicating and working with
stakeholders to meet needs and addressing issues as they occur)
13.4 Control Stakeholder Engagement (monitoring stakeholder relationships and
adjusting strategies as needed)
The PMBOK® Guide states that some stakeholders are likely to impact the project in a
positive way while others are more likely to impact the project in a negative way. It is
also true that some stakeholders have significantly more influence and power than
others. The ability of project managers to effectively manage stakeholders may literally
make the difference between success and failure. The following activities are part of
stakeholder management:
Identify all potential stakeholders
Assess the potential interest, influence, and power of each stakeholder
Understand stakeholder needs and expectations
Develop appropriate management strategies for various stakeholders
Effectively manage issues and conflicts as they arise
Continuously communicate with stakeholders
This process identifies people and organizations that may be impacted by the project
and determines their level of interest, involvement, and potential impact on project
success. It is vital to identify stakeholders early and devise strategies for maximizing
positive influences and minimizing negative impacts. Considering the limitations on a
project manager’s time and the potentially large number of stakeholders, it is also
necessary to prioritize the relative importance of each stakeholder.
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 13-1
Unit 13: Stakeholder Management
Identify Stakeholders
13-2 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 13: Stakeholder Management
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 13-3
Unit 13: Stakeholder Management
Four Key Inputs for Plan Stakeholder Management (PMBOK® Guide, p. 400):
Three Key Tools for Plan Stakeholder Management (PMBOK® Guide, p. 401):
2. Meetings: Provide a forum for the project team and other experts to discuss
the required level of stakeholder engagement needed for success.
13-4 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 13: Stakeholder Management
Two Key Outputs for Plan Stakeholder Management (PMBOK® Guide, p. 403):
Managing stakeholders involves identifying and satisfying their needs, handling issues
as they occur, and maintaining stakeholder engagement throughout the project life
cycle. The intent is to increase support and reduce resistance by effectively managing
both positive and negative stakeholders. Project managers must be aware that
stakeholder influence is at its greatest potential early in the project life cycle and
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 13-5
Unit 13: Stakeholder Management
3. Change Log: A change log documents all changes that occur during a project
and records the expected impact on the triple constraint. This information must
be shared with stakeholders so that there are no surprises.
13-6 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 13: Stakeholder Management
1. Issue Log: Used to record new issues and resolution of previously existing
issues.
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 13-7
Unit 13: Stakeholder Management
13-8 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 13: Stakeholder Management
2. Issue Log: As before, the issue log is updated if there are new issues and
also whenever previous issues are resolved.
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 13-9
Unit 13: Stakeholder Management
13-10 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 13: Stakeholder Management
Stakeholder notifications
Project records, reports, and presentations
Feedback from stakeholders
Lessons learned from managing stakeholders
Other Topics: There are no other topics for this knowledge area.
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 13-11
Unit 13: Stakeholder Management
13-12 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 13: Stakeholder Management
Self-Study
Drill Practice: Stakeholder Management
Question Answer
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 13-13
Unit 13: Stakeholder Management
Question Answer
13-14 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 13: Stakeholder Management
Question Answer
18. When is the potential for stakeholders to 18. Early in the project life cycle.
influence project outcomes at its greatest? (p. 13-5).
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 13-15
Unit 13: Stakeholder Management
Question Answer
13-16 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 14: Summary of 47 Project
Management Processes
Integration Management
Scope Management
Time Management
Cost Management
Quality Management
Communication Management
Risk Management
Procurement Management
Stakeholder Management
Summary of 47 project management processes (PMBOK® Guide, 5th edition, 2013)
Integration Management: processes & activities needed to properly coordinate all aspects of the project to meet stakeholder expectations.
Process Inputs Tools Outputs Process
Group
4.1 Develop Project Charter: 1. Project statement of work (SOW) 1. Expert judgment 1. Project charter Initiating
authorizes a project or phase 2. Business case 2. Facilitation techniques
3. Agreements
4. Enterprise environmental factors
5. Organizational process assets
4.2 Develop Project Management 1. Project charter 1. Expert judgment 1. Project management plan Planning
Plan: collection of all subsidiary 2. Outputs from other processes 2. Facilitation techniques
plans 3. Enterprise environmental factors
4. Organizational process assets
4.3 Direct & Manage Project Work: 1. Project management plan 1. Expert judgment 1. Deliverables Executing
leading and performing the work in 2. Approved change requests 2. Project management 2. Work performance data
the plan 3. Enterprise environmental factors information system 3. Change requests
4. Organizational process assets 3. Meetings 4. Project management plan
updates
5. Project documents updates
4.4 Monitor & Control Project Work: 1. Project management plan 1. Expert judgment 1. Change requests Monitoring &
constantly measure and report 2. Schedule forecasts 2. Analytical techniques 2. Work performance reports Controlling
performance; determine appropriate 3. Cost forecasts 3. Project management 3. Project management plan
preventive & corrective action 4. Validated changes information system updates
5. Work performance information 4. Meetings 4. Project documents updates
6. Enterprise environmental factors
7. Organizational process assets
4.5 Perform Integrated Change 1. Project management plan 1. Expert judgment 1. Approved change requests Monitoring &
Control: continuously manage 2. Work performance reports 2. Meetings 2. Change log Controlling
changes & maintain a baseline 3. Change requests 3. Change control tools 3. Project management plan
4. Enterprise environmental factors updates
5. Organizational process assets 4. Project documents updates
4.6 Close Project or Phase: 1. Project management plan 1. Expert judgment 1. Final product, service, or result Closing
procedures to close a project or a 2. Accepted deliverables 2. Analytical techniques transition
phase 3. Organizational process assets 3. Meetings 2. OPA updates
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 14-1
Scope Management: processes needed to ensure the project includes all the work required and only the work required to complete the project successfully;
carefully identifies what is and is not included in the project (i.e. project boundaries).
Process Inputs Tools Outputs Process
Group
5.1 Plan Scope Management: how 1. Project management plan 1. Expert judgment 1. Scope management plan Planning
scope will be defined, validated, 2. Project charter 2. Meetings 2. Requirements management
and controlled 3. Enterprise environmental factors plan
4. Organizational process assets
5.2 Collect Requirements: define 1. Scope management plan 1. Interviews 1. Requirements documentation Planning
and document stakeholder needs to 2. Requirements management plan 2. Focus groups 2. Requirements traceability
meet project objectives 3. Stakeholder management plan 3. Facilitated workshops matrix
4. Project charter 4. Group creativity techniques
5. Stakeholder register 5. Group decision-making
techniques
6. Questionnaires and
surveys
7. Observations
8. Prototypes
9. Benchmarking
10. Context diagrams
11. Document analysis
5.3 Define Scope: develops a 1. Scope management plan 1. Expert judgment 1. Project scope statement Planning
detailed, written scope statement 2. Project charter 2. Product analysis 2. Project documents updates
3. Requirements documentation 3. Alternatives generation
4. Organizational process assets 4. Facilitated workshops
5.4 Create WBS: subdivides the 1. Scope management plan 1. Decomposition 1. Scope baseline Planning
work into smaller, more 2. Project scope statement 2. Expert judgment 2. Project documents updates
manageable components 3. Requirements documentation
4. Enterprise environmental factors
5. Organizational process assets
5.5 Validate Scope: formalizing 1. Project management plan 1. Inspection 1. Accepted deliverables Monitoring &
acceptance of completed project 2. Requirements documentation 2. Group decision-making 2. Change requests Controlling
deliverables. 3. Requirements traceability matrix techniques 3. Work performance
4. Verified deliverables information
5. Work performance data 4. Project documents updates
5.6 Control Scope: monitoring 1. Project management plan 1. Variance analysis 1. Work performance Monitoring &
status and controlling changes to 2. Requirements documentation information Controlling
the project scope. 3. Requirements traceability matrix 2. Change requests
4. Work performance data 3. Project management plan
5. Organizational process assets updates
4. Project documents updates
5. OPA updates
14-2 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Time Management: processes needed to ensure timely completion of the project.
Process Inputs Tools Outputs Process
Group
6.1 Plan Schedule Management: 1. Project management plan 1. Expert judgment 1. Schedule management plan Planning
planning, developing, managing, 2. Project charter 2. Analytical techniques
executing, and controlling the 3. Enterprise environmental factors 3. Meetings
schedule. 4. Organizational process assets
6.2 Define Activities: identifying the 1. Schedule management plan 1. Decomposition 1. Activity list Planning
activities that must be performed. 2. Scope baseline 2. Rolling wave planning 2. Activity attributes
3. Enterprise environmental factors 3. Expert judgment 3. Milestone list
4. Organizational process assets
6.3 Sequence Activities: identifying 1. Schedule management plan 1. Precedence diagramming 1. Project schedule network Planning
activity dependencies. 2. Activity list method (PDM) diagrams
3. Activity attributes 2. Dependency determination 2. Project documents updates
4. Milestone list 3. Leads and lags
5. Project scope statement
6. Enterprise environmental factors
7. Organizational process assets
6.4 Estimate Activity Resources: 1. Schedule management plan 1. Expert judgment 1. Activity resource requirements Planning
estimating the type & quantity of 2. Activity list 2. Alternative analysis 2. Resource breakdown
resources needed. 3. Activity attributes 3. Published estimating data structure (RBS)
4. Resource calendars 4. Bottom-up estimating 3. Project documents updates
5. Risk register 5. Project management software
6. Activity cost estimates
7. Enterprise environmental factors
8. Organizational process assets
6.5 Estimate Activity Durations: 1. Schedule management plan 1. Expert judgment 1. Activity duration estimates Planning
estimating durations of individual 2. Activity list 2. Analogous estimating 2. Project documents updates
activities. 3. Activity attributes 3. Parametric estimating
4. Activity resource requirements 4. Three-point estimating
5. Resource calendars 5. Group decision-making
6. Project scope statement techniques
7. Risk register 6. Reserve analysis
8. Resource breakdown structure
9. Enterprise environmental factors
10. Organizational process assets
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 14-3
Process Inputs Tools Outputs Process
Group
6.6 Develop Schedule: analyzing 1. Schedule management plan 1. Schedule network analysis 1. Schedule baseline Planning
sequences, durations, resource 2. Activity list 2. Critical path method 2. Project schedule
requirements, and constraints to 3. Activity attributes 3. Critical chain method 3. Schedule data
create the project schedule 4. Project schedule network 4. Resource optimization 4. Project calendars
baseline. diagrams techniques 5. Project management plan
5. Activity resource requirements 5. Modeling techniques updates
6. Resource calendars 6. Leads and lags 6. Project documents updates
7. Activity duration estimates 7. Schedule compression
8. Project scope statement 8. Scheduling tool
9. Risk register
10. Project staff assignments
11. Resource breakdown structure
12. Enterprise environmental factors
13. Organizational process assets
6.7 Control Schedule: monitoring 1. Project management plan 1. Performance reviews 1. Work performance information Monitoring
status and managing changes to 2. Project schedule 2. Project management software 2. Schedule forecasts &
the schedule baseline. 3. Work performance data 3. Resource optimization 3. Change requests Controlling
4. Project calendars techniques 4. Project management plan
5. Schedule data 4. Modeling techniques updates
6. Organizational process assets 5. Leads & lags 5. Project documents updates
6. Schedule compression 6. OPA updates
7. Scheduling tool
14-4 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Cost Management: processes for estimating, budgeting, & controlling costs so the project can be completed within budget.
Process Inputs Tools Outputs Process
Group
7.1 Plan Cost Management: 1. Project management plan 1. Expert judgment 1. Cost management plan Planning
planning, managing, expending, 2. Project charter 2. Analytical techniques
and controlling project costs. 3. Enterprise environmental factors 3. Meetings
4. Organizational process assets
7.2 Estimate Costs: estimating 1. Cost management plan 1. Expert judgment 1. Activity cost estimates Planning
the costs of resources needed to 2. Human resource management 2. Analogous estimating 2. Basis of estimates
complete project activities. plan 3. Parametric estimating 3. Project documents updates
3. Scope baseline 4. Bottom-up estimating
4. Project schedule 5. Three-point estimating
5. Risk register 6. Reserve analysis
6. Enterprise environmental factors 7. Cost of quality
7. Organizational process assets 8. Project management software
9. Vendor bid analysis
10. Group decision-making
techniques
7.3 Determine Budget: 1. Cost management plan 1. Cost aggregation 1. Cost baseline Planning
aggregating estimated costs to 2. Scope baseline 2. Reserve analysis 2. Project funding requirements
establish a cost baseline. 3. Activity cost estimates 3. Expert judgment 3. Project documents updates
4. Basis of estimates 4. Historical relationships
5. Project schedule 5. Funding limit reconciliation
6. Resource calendars
7. Risk register
8. Agreements
9. Organizational process assets
7.4 Control Costs: monitoring 1. Project management plan 1. Earned value management 1. Work performance Monitoring &
status and managing changes to 2. Project funding requirements 2. Forecasting information Controlling
the cost baseline. 3. Work performance data 3. To-complete performance index 2. Cost forecasts
4. Organizational process assets 4. Performance reviews 3. Change requests
5. Project management software 4. Project management plan
6. Reserve analysis updates
5. Project documents updates
6. OPA updates
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 14-5
Quality Management: processes to ensure the project will satisfy the needs for which it was undertaken & implement a quality management system.
Process Inputs Tools Outputs Process
Group
8.1 Plan Quality Management: 1. Project management plan 1. Cost-benefit analysis 1. Quality management plan Planning
identifying relevant quality 2. Stakeholder register 2. Cost of quality 2. Process improvement plan
requirements/standards & 3. Risk register 3. Seven basic quality tools 3. Quality metrics
documenting how the project will 4. Requirements documentation 4. Benchmarking 4. Quality checklists
demonstrate compliance. 5. Enterprise environmental factors 5. Design of experiments 5. Project documents updates
6. Organizational process assets 6. Statistical sampling
7. Additional quality planning
tools
8. Meetings
8.2 Perform Quality Assurance: 1. Quality management plan 1. Quality management and 1. Change requests Executing
ensuring the project uses all 2. Process improvement plan control tools 2. Project management plan
processes needed to meet 3. Quality metrics 2. Quality audits updates
requirements. The ultimate purpose 4. Quality control measurements 3. Process analysis 3. Project documents updates
of QA is quality improvement. 5. Project documents 4. OPA updates
8.3 Control Quality: monitoring 1. Project management plan 1. Seven basic quality tools 1. Quality control measurements Monitoring &
results for compliance & 2. Quality metrics 2. Statistical sampling 2. Validated changes Controlling
recommending necessary changes. 3. Quality checklists 3. Inspection 3. Validated deliverables
4. Work performance data 4. Approved change requests 4. Work performance information
+/- 1 sigma = 68.3% 5. Approved change requests review 5. Change requests
+/- 2 sigma = 95.5% 6. Deliverables 6. Project management plan
+/- 3 sigma = 99.7% 7. Project documents updates
+/- 6 sigma = 99.9997% 8. Organizational process assets 7. Project documents updates
8. OPA updates
14-6 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Human Resource Management: processes that organize and manage the project team.
Process Inputs Tools Outputs Process
Group
9.1 Plan HR Management: 1. Project management plan 1. Organization charts and 1. Human resource Planning
establishing roles, responsibilities, 2. Activity resource requirements position descriptions management plan
reporting relationships, & creating a 3. Enterprise environmental factors 2. Networking
staffing management plan. 4. Organizational process assets 3. Organizational theory
4. Expert judgment
5. Meetings
9.2 Acquire Project Team: getting 1. Human resource management 1. Pre-assignment 1. Project staff assignments Executing
the human resources needed to plan 2. Negotiation 2. Resource calendars
complete the project. 2. Enterprise environmental factors 3. Acquisition 3. Project management plan
3. Organizational process assets 4. Virtual teams updates
5. Multi-criteria decision analysis
9.3 Develop Project Team: 1. Human resource management 1. Interpersonal skills 1. Team performance Executing
improving competencies, interaction plan 2. Training assessments
of the team, & overall team 2. Project staff assignments 3. Team-building activities 2. EEF updates
environment. 3. Resource calendars 4. Ground rules
5. Colocation
6. Recognition and rewards
7. Personnel assessment tools
9.4 Manage Project Team: tracking 1. Human resource management 1. Observation and conversation 1. Change requests Executing
performance, providing feedback, plan 2. Project performance appraisals 2. Project management plan
resolving issues, & coordinating 2. Project staff assignments 3. Conflict management updates
changes. 3. Team performance assessments 4. Interpersonal skills 3. Project documents updates
4. Issue log 4. EEF updates
5. Work performance reports 5. OPA updates
6. Organizational process assets
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 14-7
Communication Management: processes to ensure the timely & appropriate generation, collection, distribution, storage, & ultimate disposition of project
information.
Process Inputs Tools Outputs Process
Group
10.1 Plan Communications 1. Project management plan 1. Communication 1. Communications Planning
Management: developing a 2. Stakeholder register requirements analysis management plan
communication approach to meet the 3. Enterprise environmental factors 2. Communication technology 2. Project documents updates
information needs of stakeholders. 4. Organizational process assets 3. Communication models
4. Communication methods
5. Meetings
10.2 Manage Communications: 1. Communications management 1. Communication technology 1. Project communications Executing
managing information using the plan 2. Communication models 2. Project management plan
communications management plan. 2. Work performance reports 3. Communication methods updates
3. Enterprise environmental factors 4. Information management 3. Project documents updates
4. Organizational process assets systems 4. OPA updates
5. Performance reporting
10.3 Control Communications: 1. Project management plan 1. Information management 1. Work performance Monitoring &
monitoring and controlling 2. Project communications systems information Controlling
communications to ensure 3. Issue log 2. Expert judgment 2. Change requests
information needs of stakeholders are 4. Work performance data 3. Meetings 3. Project management plan
met. 5. Organizational process assets updates
4. Project documents updates
5. OPA updates
14-8 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Risk Management: processes concerned with planning, identifying, analyzing, responding, and controlling project risks.
Process Inputs Tools Outputs Process
Group
11.1 Plan Risk Management: 1. Project management plan 1. Analytical techniques 1. Risk management Planning
how to conduct risk 2. Project charter 2. Expert judgment plan
management activities. 3. Stakeholder register 3. Meetings
4. Enterprise environmental factors
5. Organizational process assets
11.2 Identify Risks: determining 1. Risk management plan 1. Documentation reviews 1. Risk register Planning
which risks might affect the 2. Cost management plan 2. Information gathering techniques
project. 3. Schedule management plan 3. Checklist analysis
4. Quality management plan 4. Assumptions analysis
5. HR management plan 5. Diagramming techniques
6. Scope baseline 6. SWOT analysis
7. Activity cost estimates 7. Expert judgment
8. Activity duration estimates
9. Stakeholder register
10. Project documents
11. Procurement documents
12. Enterprise environmental factors
13. Organizational process assets
11.3 Perform Qualitative Risk 1. Risk management plan 1. Risk probability and impact assessment 1. Project documents Planning
Analysis: prioritizing risks for 2. Scope baseline 2. Probability and impact matrix updates
further analysis or action 3. Risk register 3. Risk data quality assessment
(probability vs. impact). 4. Enterprise environmental factors 4. Risk categorization
5. Organizational process assets 5. Risk urgency assessment
6. Expert judgment
11.4 Perform Quantitative Risk 1. Risk management plan 1. Data gathering and representation 1. Project documents Planning
Analysis: numerically analyzing 2. Cost management plan techniques updates
the potential effect of identified 3. Schedule management plan 2. Quantitative risk analysis and modeling
risks. 4. Risk register techniques
5. Enterprise environmental factors 3. Expert judgment
6. Organizational process assets
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 14-9
Process Inputs Tools Outputs Process
Group
11.5 Plan Risk Responses: 1. Risk management plan 1. Strategies for negative risks or threats 1. Project management Planning
how to enhance opportunities & 2. Risk register 2. Strategies for positive risks or opportunities plan updates
reduce threats. 3. Contingent response strategies 2. Project documents
4. Expert judgment updates
11.6 Control Risks: monitoring 1. Project management plan 1. Risk reassessment 1. Work performance Monitoring
identified risks, identifying new 2. Risk register 2. Risk audits information &
risks, & evaluating risk 3. Work performance data 3. Variance and trend analysis 2. Change requests Controlling
response plans. 4. Work performance reports 4. Technical performance measurement 3. Project management
5. Reserve analysis plan updates
6. Meetings 4. Project documents
updates
5. OPA updates
14-10 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Procurement Management: processes to acquire products, services, or results from outside the project team.
Process Inputs Tools Outputs Process
Group
12.1 Plan Procurement 1. Project management plan 1. Make-or-buy analysis 1. Procurement management plan Planning
Management: documenting 2. Requirements documentation 2. Expert judgment 2. Procurement statement of work
purchasing decisions, specifying 3. Risk register 3. Market research 3. Procurement documents
the approach, and identifying 4. Activity resource requirements 4. Meetings 4. Source selection criteria
potential sellers. 5. Project schedule 5. Make-or-buy decisions
6. Activity cost estimates 6. Change requests
7. Stakeholder register 7. Project documents updates
8. Enterprise environmental factors
9. Organizational process assets
12.2 Conduct Procurements: 1. Procurement management plan 1. Bidder conference 1. Selected sellers Executing
obtaining seller responses, 2. Procurement documents 2. Proposal evaluation techniques 2. Agreements
selecting a seller, and awarding 3. Source selection criteria 3. Independent estimates 3. Resource calendars
a contract. 4. Seller proposals 4. Expert judgment 4. Change requests
5. Project documents 5. Advertising 5. Project management plan
6. Make-or-buy decisions 6. Analytical techniques updates
7. Procurement statement of work 7. Procurement negotiations 6. Project documents updates
8. Organizational process assets
12.3 Control Procurements: 1. Project management plan 1. Contract change control system 1. Work performance information Monitoring
managing procurement 2. Procurement documents 2. Procurement performance 2. Change requests &
relationships, monitoring contract 3. Agreements reviews 3. Project management plan Controlling
performance, and making 4. Approved change requests 3. Inspections and audits updates
changes as appropriate. 5. Work performance reports 4. Performance reporting 4. Project documents updates
6. Work performance data 5. Payment systems 5. OPA updates
6. Claims administration
7. Records management system
12.4 Close Procurements: 1. Project management plan 1. Procurement audits 1. Closed procurements Closing
completing each project 2. Procurement documents 2. Procurement negotiations 2. OPA updates
procurement. 3. Records management system
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 14-11
Stakeholder Management: processes required to identify stakeholders, their expectations, and appropriate management strategies.
Process Inputs Tools Outputs Process
Group
13.1 Identify Stakeholders: identifying 1. Project charter 1. Stakeholder analysis 1. Stakeholder register Initiating
the interests, involvement, & 2. Procurement documents 2. Expert judgment
influence of people & organizations 3. Enterprise environmental factors 3. Meetings
impacted by the project. 4. Organizational process assets
13.2 Plan Stakeholder Management: 1. Project management plan 1. Expert judgment 1. Stakeholder management Planning
developing appropriate stakeholder 2. Stakeholder register 2. Meetings plan
management strategies. 3. Enterprise environmental factors 3. Analytical techniques 2. Project documents updates
4. Organizational process assets
13.3 Manage Stakeholder 1. Stakeholder management plan 1. Communication methods 1. Issue log Executing
Engagement: communicating and 2. Communications management 2. Interpersonal skills 2. Change requests
working with stakeholders to meet plan 3. Management skills 3. Project management plan
their needs and resolve issues. 3. Change log updates
4. Organizational process assets 4. Project documents updates
5. OPA updates
13.4 Control Stakeholder 1. Project management plan 1. Information management 1. Work performance Monitoring &
Engagement: monitoring stakeholder 2. Issue log systems information Controlling
relationships, & adjusting strategies if 3. Work performance data 2. Expert judgment 2. Change requests
appropriate. 4. Project documents 3. Meetings 3. Project management plan
updates
4. Project documents updates
5. OPA updates
14-12 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Unit 15: Exercises
Exercise 1: Instructions
Your instructor may assign these exercises to small groups during class. Alternatively, you may work on them as
homework, either individually or in small study groups.
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 15-1
Exercise 1: Instructions
1. Using the blank template on the next page, fill in the ten knowledge areas in column one. Alternatively, you
may draw the template separately if you prefer.
2. Fill in the five process groups in the column headings for columns two through six.
3. The correct answers for each exercise can be found at the beginning of the following exercise.
15-2 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Exercise 1: Blank Template
Process Groups
Knowledge Areas
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 15-3
Exercise 2: Instructions and Template
Use the template below to fill in the processes that belong to Integration Management and Scope Management. As
a hint for this first exercise, there should be a total of twelve. You will complete a similar process for other
knowledge areas in the exercises which follow.
Process Groups
Integration
Scope
15-4 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Exercise 3: Instructions and Template
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 15-5
Process Groups
Monitor &
Knowledge Areas Initiate Plan Execute Close
Control
Time
15-6 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Exercise 4: Instructions and Template
Cost
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 15-7
Process Groups
Monitoring &
Knowledge Areas Initiating Planning Executing Closing
Controlling
Quality
15-8 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Exercise 5: Instructions and Template
Fill in the processes for Human Resource, Communication, Risk, Procurement, and Stakeholder Management:
Process Groups
Monitoring &
Knowledge Areas Initiating Planning Executing Closing
Controlling
Develop project Develop project Direct and Monitor and Close project or
Integration charter management plan manage project control project phase
work work
Perform integrated
change control
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 15-9
Process Groups
Monitoring &
Knowledge Areas Initiating Planning Executing Closing
Controlling
Plan quality Perform quality Control quality
Quality management assurance
Human Resource
Communication
Risk
Procurement
Stakeholder
15-10 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Complete Template for Exercises 1-5
Process Groups
Monitoring &
Knowledge Areas Initiating Planning Executing Closing
Controlling
Develop project Develop project Direct and Monitor and Close project or
Integration charter management plan manage project control project phase
work work
Perform integrated
change control
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 15-11
Process Groups
Monitoring &
Knowledge Areas Initiating Planning Executing Closing
Controlling
Plan quality Perform quality Control quality
Quality management assurance
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 15-13
2. What does a Gantt chart show exceptionally well?
a. dependency
b. dummy task
c. variance
d. float
15-14 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Exercise 6: Review of Scheduling Concepts Solution
1. Which of the following terms is not associated with a precedence diagram?
a. critical path
b. slack
c. lag
d. bar chart
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 15-15
Exercise 7: Network Diagram Practice
Use the following problems to practice the conventions of network diagramming. Solutions follow each problem.
Network 1: Finish-to-Finish
15-16 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Network 1: Finish-to-Finish Solution
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 15-17
Network 2: Start-to-Start with Lag
15-18 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Network 2: Start-to-Start with Lag Solution
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 15-19
Network 3: Finish-to-Start
15-20 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Network 3: Finish-to-Start Solution
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 15-21
Network #4
15-22 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Network #4 Solution
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 15-23
Exercise 8: Crashing Practice
Use the following problems to practice the conventions of crashing. Solutions follow each problem.
Crashing Problem 1
15-24 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Crashing Problem 1 Solution
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 15-25
Crashing Problem 2
15-26 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Crashing Problem 2 Solution
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 15-27
Crashing Problem 3
15-28 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Crashing Problem 3 Solution
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 15-29
Exercise 9: Cost Practice
Assume an interest rate of 10%. Use the data provided in the following table and then answer the questions posed
below. Solutions are on the following page.
15-30 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Exercise 9: Cost Practice Solution
1. What is the PV for time period 2? $6,611.57: Divide the cash flow of $8,000 by the time adjustment factor
which is (1+i)t = (1.1)2 = 1.1 x 1.1 = 1.21. Therefore, $8,000/1.21 = $6,611.57
2. What is the payback period? Time period 2 (first period in which the cumulative cash flow is positive; $2,000
total profit considering all revenues and costs to date)
3. What is the BCR (Benefit Cost Ratio)? BCR = Revenue/Cost = $44,000/$18,000 = 2.44. Interpretation: The
project will return $2.44 for every dollar invested.
4. What is the NPV (Net Present Value)? The sum of all PVs, which is totaled at the bottom of the PV column as
$16,689.93 (which is the expected profit after adjusting for the time value of all cash flows).
5. What is the ROI (Return on Investment)? (Benefit-Cost)/Cost = (44-18)/18 = 1.44 (as a percentage: 144%).
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 15-31
Exercise 10: Math for the PMP Exam
General Advice:
The number of math questions ranges from 3 or 4 to as many as 25. For most people, the heaviest focus
has been on earned value management.
Do not skip the math preparation! Historically, most of the math is straightforward and is “low hanging fruit”.
There is an easily calculated “right answer”.
The key on the math is: practice, practice, practice
This guide covers the types of questions most frequently seen on the exam (the quick and dirty guide)
rather than every possible math question that could ever theoretically appear.
Solutions are found at the end of each knowledge area exercise set.
Index of Topics:
1. You have completed $40,000 worth of work as measured by work packages. The actual cost of this work has
totaled $50,000 and the project plan called for $32,000 worth of work to be competed at this point.
a. What is the cost variance and what does it mean about performance thus far?
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 15-33
2. The first status report on your $100,000 facility clean-up project shows that you have completed $20,000 worth of
work and have spent $25,000. At the first status report, you should have accomplished $22,000 worth of work.
15-34 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Forecasting
1. The first status report on your $100,000 facility clean-up project shows that you have completed $20,000 worth of
work and have spent $25,000. At the first status report, you should have accomplished $22,000 worth of work.
c. What is the EAC if current performance trends continue for the remaining work?
d. What is the EAC if current variances do not apply to the remaining work?
e. Generally speaking, does the CPI for the rest of the project need to be above 1.0 or below 1.0 if you wish to finish
on the original budget?
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 15-35
2. The original project budget was $1,000,000 total. You just measured current status and found that $400,000
work has been completed at an actual cost of $500,000.
a. What is the EAC if current variances are considered typical for the remaining work?
b. What is the EAC if current variances are not considered typical for the remaining work?
15-36 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Other EV Questions and Exercises
1. Using earned value management, answer the questions related to the following table:
Month PV EV AC
Jan $500 $450 $550
Feb $600 $600 $600
Mar $500 $475 $475
Apr $450 $450 $450
May $550 $500 $500
Total =
a. How much work should have been done as of the end of March?
b. How much work had actually been completed as of the end of March?
e. In most circumstances, would you expect this project to finish on budget, with a cost overrun, or with a cost
underrun?
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 15-37
2. Michael and Angelo are working on a dinosaur reconstruction project and they have been assigned the teeth.
Specifically, they have been assigned to reconstruct the mouth of hydrasaur containing 2,000 teeth. Each tooth has
a planned budget of $150 and they are EACH supposed to complete 10 teeth a day.
It is the end of the 12th day and they have completed a total of 300 teeth thus far. They have spent $48,000 on this
work. Answer the following questions using earned value management.
15-38 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
f. What is the SPI?
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 15-39
3. Using the diagram below, what is the cost and schedule status for the work shown, i.e. a) cost overrun or
underrun b) ahead of or behind schedule?
a)
AC
b)
EV
PV
4. A colleague dropped the following information on your desk and asked for your help. The colleague stated that
the information represented the data used in the latest calculation of TCPI. The information looked like this:
1,000,000-400,000
1,000,000-500,000
c. What would the CPI need to be for the rest of the project if you expect to finish on budget?
15-40 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Cost (Earned Value) Problems Solutions
Variances and Indexes
1. You have completed $40,000 worth of work as measured by work packages. The actual cost of this work has
totaled $50,000 and the project plan called for $32,000 worth of work to be competed at this point.
a. What is the cost variance and what does it mean about performance thus far?
CV = EV-AC = 40k-50k = -$10,000 which means that the project has a $10,000 cost overrun at this point.
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 15-41
2. The first status report on your $100,000 facility clean-up project shows that you have completed $20,000 worth of
work and have spent $25,000. At the first status report, you should have accomplished $22,000 worth of work.
15-42 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Forecasting
1. The first status report on your $100,000 facility clean-up project shows that you have completed $20,000 worth of
work and have spent $25,000. At the first status report, you should have accomplished $22,000 worth of work.
a. What is the BAC, EV, AC, and PV? BAC = $100,000. EV = $20,000. AC = $25,000. PV = $22,000.
b. How much work remains to be done? Work remaining = BAC-EV = 100k-20k = $80,000 worth of work
remaining.
c. What is the EAC if current performance trends continue for the remaining work? EAC (typical) = BAC/CPI =
100k/.80 = $125,000 (expecting an overrun at completion of $25,000).
d. What is the EAC if current variances do not apply to the remaining work? EAC (atypical) = AC + (BAC-EV) = 25k
+ (100k-20k) = $105,000 (expecting an overrun at completion of $5,000).
e. Generally speaking, does the CPI for the rest of the project need to be above 1.0 or below 1.0 if you wish to finish
on the original budget? The current CPI is .80 (below 1.0; cost overrun) so the CPI for the rest of the project
would need to be above 1.0 (cost underrun) to balance out the spending and finish on budget.
f. What is the formula for calculating TCPI? Work Remaining divided by Budget Remaining = (BAC-EV)/(BAC-
AC)
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 15-43
2. The original project budget was $1,000,000 total. You just measured current status and found that $400,000
work has been completed at an actual cost of $500,000.
a. What is the EAC if current variances are considered typical for the remaining work?
EAC (typical) = BAC/CPI = 1,000,000/.80 = $1,250,000 (expecting an overrun at completion of $250,000).
b. What is the EAC if current variances are not considered typical for the remaining work?
EAC (atypical) = AC + (BAC-EV) = 500k + (1,000,000-400k) = $1,100,000 (expecting an overrun at completion
of $100,000).
15-44 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Other EV Questions and Exercises
1. Using earned value management, answer the questions related to the following table:
Month PV EV AC
Jan $500 $450 $550
Feb $600 $600 $600
Mar $500 $475 $475
Apr $450 $450 $450
May $550 $500 $500
Total = $2600 $2475 $2575
a. How much work should have been done as of the end of March? $1600 (the total PV for Jan, Feb, and Mar)
b. How much work had actually been completed as of the end of March? $1525 (the total EV for Jan, Feb, Mar)
c. What is the project cost variance as of the end of May? CV = EV-AC = 2475-2575 = -$100 (cost overrun)
d. What is the project schedule variance as of the end of May? SV = EV-PV = 2475-2600 = -$125 (behind
schedule)
e. In most circumstances, would you expect this project to finish on budget, with a cost overrun, or with a cost
underrun? The most likely trend on cost overruns is that they tend to continue. The most likely outcome in
this case would be a cost overrun at completion.
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 15-45
2. Michael and Angelo are working on a dinosaur reconstruction project and they have been assigned the teeth.
Specifically, they have been assigned to reconstruct the mouth of hydrasaur containing 2,000 teeth. Each tooth has
a planned budget of $150 and they are EACH supposed to complete 10 teeth a day.It is the end of the 12th day and
they have completed a total of 300 teeth thus far. They have spent $48,000 on this work.
15-46 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
f. What is the SPI?
1.25 = EV/PV = 45k/36k (ahead of schedule)
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 15-47
3. Using the diagram below, what is the cost and schedule status for the work shown, i.e. a) cost overrun or
underrun b) ahead of or behind schedule?
AC
EV
PV
15-48 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
4. A colleague dropped the following information on your desk and asked for your help. The colleague stated that
the information represented the data used in the latest calculation of TCPI. The information looked like this:
1,000,000-400,000
1,000,000-500,000
c. What would the CPI need to be for the rest of the project if you expect to finish on budget?
1.20 (Calculating the TCPI formula using the numbers shown above yields 1.20. This indicates that the
project has experienced an overrun thus far and needs an underrun for the remaining work if you expect to
finish on budget.).
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 15-49
Cost and Schedule (PERT Basics) Problems
PERT was developed in the 1950’s by the U.S. Navy to help manage their Polaris Submarine Program. The
concept is useful when attempting to estimate durations or costs when the outcomes are highly uncertain. Instead
of giving a single estimate, three estimates are created which establish a potential range. The range extends from
an optimistic outcome to a most likely outcome and finally to a pessimistic outcome. Again, the technique can be
applied to duration estimates (the original concept) but also equally well to cost estimates.
1. Using PERT, the following three estimates were created: the optimistic cost estimate is $200,000; the most likely
cost was estimated at $250,000; and the pessimistic estimate was given as $450,000.
b. Compared to the most likely estimate, the PERT calculated average is usually believed to be more optimistic or
pessimistic?
15-50 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
2. Using PERT, the following three duration estimates were created: optimistically the work will take 4 days, the
most likely duration is 6 days, and the pessimistic duration is 10 days.
c. An estimate using Monte Carlo simulation would probably be more optimistic or pessimistic than the PERT
estimate?
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 15-51
Cost and Schedule (PERT Basics) Problems Solutions
1. Using PERT, the following three estimates were created: the optimistic cost estimate is $200,000; the most likely
cost was estimated at $250,000; and the pessimistic estimate was given as $450,000.
b. Compared to the most likely estimate, the PERT calculated average is usually believed to be more optimistic or
pessimistic?
PERT is considered more pessimistic than a single most likely estimate. In “a” above, the most likely was
$250,000 whereas PERT calculated an expected average of $275,000.
15-52 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
2. Using PERT, the following three duration estimates were created: optimistically the work will take 4 days, the
most likely duration is 6 days, and the pessimistic duration is 10 days.
c. An estimate using Monte Carlo simulation would probably be more optimistic or pessimistic than the PERT
estimate?
More pessimistic. To summarize, PERT is more pessimistic than CPM and Monte Carlo simulation is the
most pessimistic of the three types of estimates.
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 15-53
Cost (Accuracy of Estimates) Problem
a. If the estimate was done for project approval as part of initiating, what would be the expected range of accuracy
and what name would you give it?
b. If you believe actual outcomes would range from $90,000 to as much as $125,000; what type of estimate do you
have?
c. What type of estimate would you want if you need the greatest possible accuracy? What would be the timing of
such an estimate?
15-54 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Cost (Accuracy of Estimates) Problem Solution
a. If the estimate was done for project approval as part of initiating, what would be the expected range of accuracy
and what name would you give it?
Range of accuracy is from -25% to +75% and is referred to as an order of magnitude estimate. Also called a
ROM and another example in the PMBOK is the analogous estimate.
b. If you believe actual outcomes would range from $90,000 to as much as $125,000; what type of estimate do you
have?
A budget estimate, which has a range of accuracy of -10% to +25% (which is the range of the numbers given
in the question).
c. What type of estimate would you want if you need the greatest possible accuracy? What would be the timing of
such an estimate?
A definitive estimate (also called bottom-up) would be done at the end of planning when you are ready to
establish a cost baseline. The range of accuracy is -5% to +10%.
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 15-55
Procurement Problems
Incentive Fees and Prices
1. You are using a cost plus incentive fee (CPIF) contract with the following negotiated terms:
a. If the final, actual cost is $300 million, what fee will the contractor earn?
b. Again, with a final, actual cost of $300 million, what price will the buyer pay?
15-56 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Point of Total Assumption
2. You are using a fixed price incentive fee (FPIF) contract with the following negotiated terms:
b. If the final, actual cost is $350,000; what fee will the contractor earn?
c. If the final, actual cost is $350,000; what price will the buyer pay?
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 15-57
Procurement (Incentive Fees and Prices) Problems Solutions
1. You are using a cost plus incentive fee (CPIF) contract with the following negotiated terms:
a. If the final, actual cost is $300 million, what fee will the contractor earn?
First, calculate the adjustment to the target fee as follows:
(Target cost-Actual cost) x Seller’s Share
(250 mil-300 mil) x .40 = -50 mil x .40 = -$20 mil
Second, calculate the actual seller fee as follows:
Target fee + Adjustment
$30 mil - $20 mil = $10 mil (Fee calculated by the formula)
Third, check the minimum guaranteed fee
The minimum fee is guaranteed at $18 million
Since the formula calculated a lower amount, the actual fee paid will be $18 million
b. Again, with a final, actual cost of $300 million, what price will the buyer pay?
Price = Actual cost + Actual Fee $300 mil + $18 mil = $318 mil
15-58 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
2. You are using a fixed price incentive fee (FPIF) contract with the following negotiated terms:
Target cost = $370 thousand Target Fee = $40 thousand
Ceiling Price = $500 thousand Share Ratio = 80:20
b. If the final, actual cost is $350,000; what fee will the contractor earn?
As before, calculate the fee adjustment and the actual fee to be paid.
Adjustment = (Target cost-Actual cost) x Seller’s share
(370k-350k) x .20 = 20k x .20 = +$4,000
Now calculate the actual fee
Actual fee = Target fee + Adjustment = $40k + $4k = $44,000
Contractor got $4,000 added to the target fee
c. If the final, actual cost is $350,000; what price will the buyer pay?
Price = Actual cost + Actual fee $350,000 + $44,000 = $394,000
The buyer got $16,000 subtracted from the target price
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 15-59
Risk Problems
Expected Monetary Value
1. You have arrived at Calamity Acres Gambling Resort. The above ground swimming pool and broken diving board
immediately caught your eye but you decided to make some money first. You have chosen to play a game that
works as follows. You provide $100 cash in return for one of three outcomes: 1) you win $5,000; 2) you win $200;
or 3) you win $0 (lose your money). It turns out that the probabilities for each potential outcome are 1%, 10%, and
89% respectively.
2. Your stock broker has suggested an investment with the following supporting data. There is a 60% chance the
investment will yield a net worth of $10,000. There is a 25% chance the investment will yield a net worth of $6,000.
However, there is a 15% chance the investment will yield a net worth of $0 (you could lose your investment). What
is the EMV of this investment?
3. What is the EMV of a $50,000 profit if there is a 45% chance of that particular outcome?
15-60 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Probability
1. You have 2 statistically independent and mutually exclusive events. Event A has a 70% chance of occurring.
Event B has an 80% chance of occurring. What is the probability that events A and B will both occur?
a. What is the probability that event A will not occur during both of the last 2 months?
b. What is the probability that event A will occur during both of the first 2 months?
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 15-61
Risk Problems Solutions
Expected Monetary Value
1a. What is the expected monetary value (EMV) of playing this game?
You must calculate the EMV for each of the 3 outcomes and then add them:
$5,000 x 1% = $50
$200 x 10% = $20
$0 x 89% = $0
The total EMV is $70
15-62 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
2. Your stock broker has suggested an investment with the following supporting data. There is a 60% chance the
investment will yield a net worth of $10,000. There is a 25% chance the investment will yield a net worth of $6,000.
However, there is a 15% chance the investment will yield a net worth of $0 (you could lose your investment). What
is the EMV of this investment?
Follow the same procedure by calculating the EMV of each possible outcome and then add them up:
$10,000 x 60% = $6,000
$6,000 x 25% = $1,500
$0 x 15% = $0
The total EMV is $7,500
3. What is the EMV of a $50,000 profit if there is a 45% chance of that particular outcome?
$50,000 x 45% = $22,500
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 15-63
Probability
1. You have 2 statistically independent and mutually exclusive events. Event A has a 70% chance of occurring.
Event B has an 80% chance of occurring. What is the probability that events A and B will both occur?
56% (multiply the probabilities of each event)
a. What is the probability that event A will not occur during both of the last 2 months?
16% (the probability of not occurring during any single month is 40%; the probability of not occurring twice
in a row is 40% x 40%)
b. What is the probability that event A will occur during both of the first 2 months?
36% = 60% x 60%
15-64 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Miscellaneous Problems
Communication Channels
1. You are the project manager with 5 team members working for you. You just gained 2 new team members. How
many additional communication channels must you now manage?
2. You are the project manager with 11 team members working for you. You just lost 3 team members to another
project. How many fewer communication channels need to be maintained?
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 15-65
Generic Variances
1. Task A had a planned duration of 6 days. It actually took 9 days. What is the variance for this task?
2. Task B was supposed to cost $3,000 and actually cost $2,800. What is the variance for this task?
15-66 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Lease vs. Buy
1. You need a special piece of equipment for your energy research project. Your engineer has indicated that the
equipment will be needed for about 25 days. You must decide whether to buy the equipment or lease it for the time
needed. The following data has been collected:
If you buy, the purchase price is $2,750; a shipping fee of $1,000 and a set-up cost of another $1,000 will be
incurred; and finally the operating cost per day is $75.
If you lease, there is an installation fee of $1,250 and a daily usage fee of $250 (per day).
a. At how many days of usage would the cost of buying vs. leasing be the same?
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 15-67
Miscellaneous Problems Solutions
Communication Channels
1. You are the project manager with 5 team members working for you. You just gained 2 new team members. How
many additional communication channels must you now manage?
You must remember to count yourself in the numbers. You started with a total of 6 people (including
yourself) and ended as a team of 8. Therefore, you initially had 15 channels [(n x (n-1))/2]. You ended with
28 channels [(n x (n-1))/2]. The number of additional channels is 28-15 = 13.
2. You are the project manager with 11 team members working for you. You just lost 3 team members to another
project. How many fewer communication channels need to be maintained?
Use the same formula and logic. You started with a team of 12 (including yourself) and ended as a team of
9. So, you initially had 66 channels and ended with only 36. You ended with 30 fewer channels than you
had at the outset.
15-68 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
Generic Variances
1. Task A had a planned duration of 6 days. It actually took 9 days. What is the variance for this task?
Variance = Plan-Actual. Therefore, the variance here is -3 days (6-9). The task took 3 days longer than
planned.
2. Task B was supposed to cost $3,000 and actually cost $2,800. What is the variance for this task?
Again, Plan-Actual yields 3,000-2800 = +$200. This task cost $200 less than planned (cost underrun).
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 15-69
Lease vs. Buy
1. You need a special piece of equipment for your energy research project. Your engineer has indicated that the
equipment will be needed for about 25 days. You must decide whether to buy the equipment or lease it for the time
needed. The following data has been collected:
If you buy, the purchase price is $2,750; a shipping fee of $1,000 and a set-up cost of another $1,000 will be
incurred; and finally the operating cost per day is $75.
If you lease, there is an installation fee of $1,250 and a daily usage fee of $250 (per day).
a. At how many days of usage would the cost of buying vs. leasing be the same?
15-70 PMC:DJ4:EN:000 ver.3.0 | © 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved.
© 2015 CMF Solutions and TwentyEighty Strategy Execution. All Rights Reserved. | PMC:DJ4:EN:000 ver.3.0 15-71