Anda di halaman 1dari 39

PROJECT: CONSTRUCTION OF 2 X 20 MVA,

33/11 kV PRIMARY SUB STATION DESIGNATED Rev No 0


AS JARZIZ (DPC/TENDER/2016/201) Rev Date 07.05.2017

Project CONSTRUCTION OF 33/11K,2X20MVA PSS DESIGNATED AS JARZIZ


Project Company DHOFAR POWER COMPANY
Owner’s Engineer HAMED ENGINEERING SERVICES LLC
Contractor SHARIKAT FANNIYA OMANIYA LLC

METHOD STATEMENT FOR CIVIL ACTIVITIES:

1
PROJECT: CONSTRUCTION OF 2 X 20 MVA,
33/11 kV PRIMARY SUB STATION DESIGNATED Rev No 0
AS JARZIZ (DPC/TENDER/2016/201) Rev Date 07.05.2017

Project CONSTRUCTION OF 33/11K,2X20MVA PSS DESIGNATED AS JARZIZ


Project Company DHOFAR POWER COMPANY
Owner’s Engineer HAMED ENGINEERING SERVICES LLC
Contractor SHARIKAT FANNIYA OMANIYA LLC

DOCUMENT REFERENCE NUMBER: SFO/CO498/MS/C/01

EXCAVATION

TITLE Prepared /Reviewed by SFO Approved by SFO Approved by HES


Civil/ QAQC Engineer Site Manager Civil Engineer
NAME
SIGNATURE

DATE

2
PROJECT: CONSTRUCTION OF 2 X 20 MVA,
33/11 kV PRIMARY SUB STATION DESIGNATED Rev No 0
AS JARZIZ (DPC/TENDER/2016/201) Rev Date 07.05.2017

Project CONSTRUCTION OF 33/11K,2X20MVA PSS DESIGNATED AS JARZIZ


Project Company DHOFAR POWER COMPANY
Owner’s Engineer HAMED ENGINEERING SERVICES LLC
Contractor SHARIKAT FANNIYA OMANIYA LLC

The following activities shall be ensured by the Civil Engineer and QC Engineer at site

1.0 Purpose

The purpose of this instruction is to provide sequence of events and responsibilities for excavation and
associated activities and measures adopted for safe and systematic work method to satisfy all the relevant
specifications and requirements.

2.0 Applicable Specifications, Reference, Standards and Approved Drawings

Scope Of work
Volume -2, Section – 12.6.1
Issued Method Statement

3.0 Job Safety Plan

3.1Hazard Identification

Falling Of Equipment
Human Injury
Dust Hazard
Falling of Equipment in to the excavated pits.

3.2Action by the Execution Team

Proper approach and area demarcated by proper barricading of 1.6 M away of excavated area.
To avoid any collapse sides of all excavation will be sloped to safe angles to prevent collapse/caving. Proper
shoring shall be done to avoid earth sliding wherever sandy soils encountered.
Before excavation cable/pipe location shall be detected with detectors.
Before deploying work force safety induction shall be provided, identify associated hazards and precautionary
measures shall be briefed
Provide banksmen along with equipments vehicle movements.
Check the area to be back filled and remove all unwanted materials.
Ensure all the earth moving Equipment are inspected properly and driven by authorised operator.

3
PROJECT: CONSTRUCTION OF 2 X 20 MVA,
33/11 kV PRIMARY SUB STATION DESIGNATED Rev No 0
AS JARZIZ (DPC/TENDER/2016/201) Rev Date 07.05.2017

Project CONSTRUCTION OF 33/11K,2X20MVA PSS DESIGNATED AS JARZIZ


Project Company DHOFAR POWER COMPANY
Owner’s Engineer HAMED ENGINEERING SERVICES LLC
Contractor SHARIKAT FANNIYA OMANIYA LLC

Provide adequate illumination.


Provide appropriate PPE’s.

4.0Responsibilty

Civil Engineer / supervisor shall be the responsible person in supervising the above said activities.
Quality Control Engineer shall monitor the activities for the compliance of the specifications if any,
traceability, non conformance and compilation and maintenance of records.
Safety Co-ordinator shall be all time available at site to check all the safety aspects during execution of work and
liaison with all necessary authorities and obtain required work permits. Surveyor shall establish the control points
as per survey plan.

5.0 Procedure
5.1 Excavations for substructures/ trenches/ boundary wall
a) Datum and setting out:
 Before work commences survey has to be carried out to establish the levels of the work site on approval
from HES/DPC.
 Levels shown on the contract document shall relate to a local datum established by S.F.O/ HES/DPC.
 Levels shall be taken on grid approved by HES/DPC, spot levels to be submitted to HES/DPC for
records and retaining the same.
 The site shall be prepared by cutoff shrubs trees and bush roots of all vegetations as directed by HES/DPC.
 The top soil shall be removed from the area of excavation.
b) Excavation permits
 Before commencing excavation permit should be obtained from local authorities in which the routes of
existing services and new routes services are to be shown clearly and get it approved as an when required.
 Trial pits/ hand excavation has to be carried out for locating possessions of underground cables. If any
exiting services/ obstruction has been found should immediately be informed to HES/DPC.
 After setting and laying out based on approved drawings, excavation has been carried out with appropriate
tools and machineries and safe equipments.

4
PROJECT: CONSTRUCTION OF 2 X 20 MVA,
33/11 kV PRIMARY SUB STATION DESIGNATED Rev No 0
AS JARZIZ (DPC/TENDER/2016/201) Rev Date 07.05.2017

Project CONSTRUCTION OF 33/11K,2X20MVA PSS DESIGNATED AS JARZIZ


Project Company DHOFAR POWER COMPANY
Owner’s Engineer HAMED ENGINEERING SERVICES LLC
Contractor SHARIKAT FANNIYA OMANIYA LLC

 On attaining the required level, surface has been prepared for formation which includes dressing, leveling
with ground surface.
 Excavated soil to be kept as stock piles near site as approved by HES/DPC if necessary or unless otherwise
it shall be carried away from site.
 While Excavation if it encounters any unsuitable strain which will adversely affect any structure it shall be
notified to client. As per client discretion it shall be rectified /replaced with any other suitable approved
soil.

6.0Records:
Quality Records (Approved Drawings & shop drawings)
Inspection Form (RFI /Checklist)

5
PROJECT: CONSTRUCTION OF 2 X 20 MVA,
33/11 kV PRIMARY SUB STATION DESIGNATED Rev No 0
AS JARZIZ (DPC/TENDER/2016/201) Rev Date 07.05.2017

Project CONSTRUCTION OF 33/11K,2X20MVA PSS DESIGNATED AS JARZIZ


Project Company DHOFAR POWER COMPANY
Owner’s Engineer HAMED ENGINEERING SERVICES LLC
Contractor SHARIKAT FANNIYA OMANIYA LLC

LIST OF METHOD STATEMENTS FOR CIVIL ACTIVITIES

VOL-1
S. No. Document Number Description Page No.
1 SFO/NAQ/MS/C/01 Excavation 3
2 SFO/NAQ/MS/C/02 Backfilling & Compaction 7
3 SFO/NAQ/MS/C/03 Concreting 11
4 SFO/NAQ/MS/C/04 Curing 19
5 SFO/NAQ/MS/C/05 Masonry 22
6 SFO/NAQ/MS/C/06 Plastering 26
7 SFO/NAQ/MS/C/07 Roof slab Water proofing 31
8 SFO/NAQ/MS/C/08 Painting 34
9 SFO/NAQ/MS/C/09 Wall/ floor Tile fixing 37
10 SFO/NAQ/MS/C/10 Anti-termite treatment 40

VOL-II

1 SFO/ALSD/MS/C/11 Road Work 3


2 SFO/ALSD/MS/C/12 False Ceiling 8
3 SFO/ALSD/MS/C/13 Raised Floor 13
4 SFO/ALSD/MS/C/14 Floor Screed 18
5 SFO/ALSD/MS/C/15 Installation of Fencing 23
6 SFO/ALSD/MS/C/16 Mechanical Installation 29

6
PROJECT: CONSTRUCTION OF 2 X 20 MVA,
33/11 kV PRIMARY SUB STATION DESIGNATED Rev No 0
AS JARZIZ (DPC/TENDER/2016/201) Rev Date 07.05.2017

Project CONSTRUCTION OF 33/11K,2X20MVA PSS DESIGNATED AS JARZIZ


Project Company DHOFAR POWER COMPANY
Owner’s Engineer HAMED ENGINEERING SERVICES LLC
Contractor SHARIKAT FANNIYA OMANIYA LLC

DOCUMENT REFERENCE NUMBER: SFO/NAQ/MS/C/02

BACKFILLING AND COMPACTION

TITLE Prepared /Reviewed by SFO Approved by SFO Approved by HES


Civil/ QAQC Engineer Site Manager Civil Engineer
NAME
SIGNATURE

DATE

7
PROJECT: CONSTRUCTION OF 2 X 20 MVA,
33/11 kV PRIMARY SUB STATION DESIGNATED Rev No 0
AS JARZIZ (DPC/TENDER/2016/201) Rev Date 07.05.2017

Project CONSTRUCTION OF 33/11K,2X20MVA PSS DESIGNATED AS JARZIZ


Project Company DHOFAR POWER COMPANY
Owner’s Engineer HAMED ENGINEERING SERVICES LLC
Contractor SHARIKAT FANNIYA OMANIYA LLC

The following activities shall be ensured by the Civil Engineer and QC Engineer at site
1.0 Purpose
The purpose of this instruction is to provide the guidelines for backfilling and compaction and
associated activities to satisfy all the relevant specifications and requirements.

2.0 Applicable Specifications, Reference, Standards and Approved Drawings


Scope Of work
Volume -2, Section – 12.6.11
Issued Method Statement

3.0 Job Safety Plan

3.1Hazard Identification

Falling Of Equipment
Human Injury
Dust Hazard
Falling of Equipment in to the excavated pits.

3.2Action by the Execution Team

Proper approach and area demarcated by proper barricading of excavated area.


Provide banksmen along with equipments vehicle movements.
Check the area to be back filled and remove all unwanted materials.
Ensure all the earth moving Equipment are inspected properly and driven by authorised operator.
Provide adequate illumination.
Provide appropriate PPE’s.

4.0Responsibilty

Civil Engineer / supervisor shall be the responsible person in supervising the above said activities.
Quality Control Engineer shall monitor the activities for the compliance of the specifications if any. Safety Co-
ordinator shall be all time available at site to check all the safety aspects during execution of work.
5.0 Procedure
8
PROJECT: CONSTRUCTION OF 2 X 20 MVA,
33/11 kV PRIMARY SUB STATION DESIGNATED Rev No 0
AS JARZIZ (DPC/TENDER/2016/201) Rev Date 07.05.2017

Project CONSTRUCTION OF 33/11K,2X20MVA PSS DESIGNATED AS JARZIZ


Project Company DHOFAR POWER COMPANY
Owner’s Engineer HAMED ENGINEERING SERVICES LLC
Contractor SHARIKAT FANNIYA OMANIYA LLC

Clearing of site in order to remove any existing steel, concrete, debris, loose windblown sand and other foreign
materials.
All soft spots left shall be filled with suitable material and compacted.
Excavated material, if any, and suitable and approved by Client/ Consultant for backfilling shall be
transported and placed in fill areas within the limits.

Site Preparation

After clearing, grubbing and removal of all unsuitable material from the surface excavated from the existing
ground shall be scarified, watered, leveled and compacted
Back filling material is a natural well-graded sand/gravel material. The characteristic of back filling material to
be used shall be in accordance with Tender Specification.
Rock fragments or gravel exceeding 150 mm, which may exist in natural fill material, shall be removed by
screening at site or by other appropriate method in order to comply with the gradation limits.

Mixing, Spreading and Compaction:

Fill materials shall be transported to site, stacked in heap. Water from QP approved source is to be added and
mixed thoroughly such that the moisture content of the filling material is within ±3% of the Optimum Moisture
Content. The mixed filling material shall then be spread in layers on the fill area by means of shovels and
graders. In order to compensate for the evaporation loss of moisture additional quantities of water shall be
sprinkled while compacting. The subsequent layers shall be of 150 mm compacted thicknesses. The spreaded
back filled material is compacted by single drum
vibrating roller, Portable vibratory compactors with adequate number of passes to achieve the required
compaction and should be free from undulations, soft spots and within allowable tolerances for evenness of
Surfaces. The compacted area shall then be tested for required Field Dry Density. Back fill shall be compacted
to a maximum density equal to 95% of Maximum Dry Density as determined by BS 1377 part 13.

Inspection and Testing Frequency:

Field tests shall be carried out at the following frequency:


Density and moisture content (as determined by BS 1377 test 15B or 15C) one test per 200 cu.m of compacted fill.

9
PROJECT: CONSTRUCTION OF 2 X 20 MVA,
33/11 kV PRIMARY SUB STATION DESIGNATED Rev No 0
AS JARZIZ (DPC/TENDER/2016/201) Rev Date 07.05.2017

Project CONSTRUCTION OF 33/11K,2X20MVA PSS DESIGNATED AS JARZIZ


Project Company DHOFAR POWER COMPANY
Owner’s Engineer HAMED ENGINEERING SERVICES LLC
Contractor SHARIKAT FANNIYA OMANIYA LLC

No individual value of density shall be acceptable, if %Compaction is less than 95%

Records:

Quality Records (Lab results for Field Dry Density, Moisture Content Test, Maximum Dry Density,

Percentage Compaction)

Inspection Form (RFI /Checklist)

10
PROJECT: CONSTRUCTION OF 2 X 20 MVA,
33/11 kV PRIMARY SUB STATION DESIGNATED Rev No 0
AS JARZIZ (DPC/TENDER/2016/201) Rev Date 07.05.2017

Project CONSTRUCTION OF 33/11K,2X20MVA PSS DESIGNATED AS JARZIZ


Project Company DHOFAR POWER COMPANY
Owner’s Engineer HAMED ENGINEERING SERVICES LLC
Contractor SHARIKAT FANNIYA OMANIYA LLC

DOCUMENT REFERENCE NUMBER: SFO/NAQ/MS/C/03

CONCRETING

TITLE Prepared /Reviewed by SFO Approved by SFO Approved by HES


Civil/ QAQC Engineer Site Manager Civil Engineer
NAME
SIGNATURE

DATE

11
PROJECT: CONSTRUCTION OF 2 X 20 MVA,
33/11 kV PRIMARY SUB STATION DESIGNATED Rev No 0
AS JARZIZ (DPC/TENDER/2016/201) Rev Date 07.05.2017

Project CONSTRUCTION OF 33/11K,2X20MVA PSS DESIGNATED AS JARZIZ


Project Company DHOFAR POWER COMPANY
Owner’s Engineer HAMED ENGINEERING SERVICES LLC
Contractor SHARIKAT FANNIYA OMANIYA LLC

The following activities shall be ensured by the Civil Engineer and QC Engineer at site

1.0 Purpose
The purpose of this instruction is to provide methodology for production, transportation, pouring, compacting,
finishing and curing for structures.

2.0 Applicable Specifications, Reference, Standards and Approved Drawings


Scope Of work
Volume -2, Section –12.7.1
Issued Method Statement
3.0 Job Safety Plan

3.1Hazard Identification
Road Accidents, Batching plant breakdown
Traffic Problems.
Access risk
Bodily Injury
Respiratory hazards
Electric Shock
Falls, Trips, Bodily Injury

3.2Action by the Execution Team


Proper inspection of machineries shall be carried out.
Workers shall be briefed for plan.
Banks man should be provided
Suitable footwear and appropriate PPE shall be provided.
Access / egress to the work area should be properly made by means of approved scaffolds, platforms, ladders and
stairs for concreting at heights.

4.0Responsibilty

12
PROJECT: CONSTRUCTION OF 2 X 20 MVA,
33/11 kV PRIMARY SUB STATION DESIGNATED Rev No 0
AS JARZIZ (DPC/TENDER/2016/201) Rev Date 07.05.2017

Project CONSTRUCTION OF 33/11K,2X20MVA PSS DESIGNATED AS JARZIZ


Project Company DHOFAR POWER COMPANY
Owner’s Engineer HAMED ENGINEERING SERVICES LLC
Contractor SHARIKAT FANNIYA OMANIYA LLC

Civil Engineer / supervisor shall be the responsible person in supervising the above said activities.
Quality Control Engineer shall monitor the activities for the compliance of the specifications if any,
traceability, non-conformance and compilation and maintenance of records.
Safety Co-ordinator shall be all time available at site to check all the safety aspects during execution of work
and liaison with all necessary authorities and obtain required work permit.
Surveyor shall establish the control points as per survey plan.

5.0 Materials
Ordinary Portland cement
Coarse aggregate conforming to BS 882
Fine aggregate conforming to BS 882
Water conforming to BS 3148-1980.
Source
Material shall be procured from the approved supplier
Coarse Aggregate
Aggregates shall be supplied from approved supplier. The test report from the supplier shall be submitted to
HES/DPC as required. If required samples shall be tested at laboratory and results shall be submitted.
Mix Proportion
Necessary laboratory Trials shall be carried out at factory to arrive at a mix proportion for different grades of
concrete. Concrete shall be workable in nature and meet the requirement of strength criteria along work
durability in addition to determination of mix proportion, particular attention shall be given to physical
properties such as work ability cohesiveness, plasticity and slump and the compressive strength.

Concrete production
The requisition for the concrete shall be placed only when the pour is ready in all respects. Mix all the
ingredients in the mixer machine as per the proportion of approved mix design in situ. concrete shall be
mixed in site shall be mixed in batching machines with sufficient water storage capacity and with a gauge
for all grades of concrete. The mixing time shall be 2 minutes after adding water to the try mix, the mix
details will be recorded in the batch sheet .

13
PROJECT: CONSTRUCTION OF 2 X 20 MVA,
33/11 kV PRIMARY SUB STATION DESIGNATED Rev No 0
AS JARZIZ (DPC/TENDER/2016/201) Rev Date 07.05.2017

Project CONSTRUCTION OF 33/11K,2X20MVA PSS DESIGNATED AS JARZIZ


Project Company DHOFAR POWER COMPANY
Owner’s Engineer HAMED ENGINEERING SERVICES LLC
Contractor SHARIKAT FANNIYA OMANIYA LLC

Transportation
All concrete shall be conveyed from the mixture machine to the concrete pour basement with all precaution
to prevent loss of water by evaporation in hot weather and heat loss in cold weather conditions. No concrete
shall be transported and placed in open while it is raining.

6.0 Procedure
Placing of concrete
After adequate mixing concrete shall be immediately transported to the pouring point with damper / shovel
before start setting without any time delay. Care shall be taken while pouring to avoid any segregation of
ingredients necessary chutes to be used wherever required to reach the concrete to the appropriate place with
care. For transporting the concrete greater care shall be taken by providing adequate manpower and
machinery to avoid any delay. Concrete shall be placed in position and sequences as indicated in the drawing,
placing methods shall depend on rate of concrete plan type structures and quantity , rate placement of
concrete to be poured, the equipment available for compacting and placing the concrete formwork design and
initial setting time of concrete. Once all reinforcements are positioned and aligned, embedded parts and form
work are securely held in position and is duly inspected prior commence of work. Information shall be given
by submission of RFI's before concreting starts. Concrete shall be laid continuously in uniform layers of
thickness approximately 450 mm where internal vibrators are used or 300 mm in all other cases. Concrete
shall not be dropped through a height more than 2 meter. For locations where direct placement is not possible
and in particular through narrow work form suitable drop chutes shall be provided. Long Troughs, chutes and
pipes shall be kept free from coatings of hardened concrete or any spillages. Concrete shall be poured with
utmost care to avoid any displacement of reinforcements and anchor bolts, sleeves, PVC water stopper if any.
Pouring of concrete in supported structures shall not start until concrete previously poured in structures is no
longer plastic and has been intact for at least two hours. Concrete poured in individual members shall be
continued without stoppage up to the construction joint or at the end of the member.

Bulk concreting shall be carried out in sections and each section has to be concreted without interval. While
pouring concrete temperature shall be maintained to reach not below 5 Celsius and not more than 30 degree
Celsius.

14
PROJECT: CONSTRUCTION OF 2 X 20 MVA,
33/11 kV PRIMARY SUB STATION DESIGNATED Rev No 0
AS JARZIZ (DPC/TENDER/2016/201) Rev Date 07.05.2017

Project CONSTRUCTION OF 33/11K,2X20MVA PSS DESIGNATED AS JARZIZ


Project Company DHOFAR POWER COMPANY
Owner’s Engineer HAMED ENGINEERING SERVICES LLC
Contractor SHARIKAT FANNIYA OMANIYA LLC

Shuttering & de-shuttering


Shuttering materials shall be properly cleaned by appliying proper deshutterin chemical and then used for
shuttering to achieve proper finishing of concrete.
De-shuttering shall be done only after the concrete has achieved its desired strength for slabs and vertical
sides for columns and beam. De-shuttering shall be carried out with proper deshuttering tools to cause
minimum damage to concrete edges.

Binding of steel
Steel shall be stacked properly away from water contact and moisture to avoid rusting. Steel shall be cut and
bend with proper cutting and bending machines.
Steel shall be binded by binding wire with minimum of 20 SWG thickness, tied properly with the binding
tool. While erection of any vertical steel for column etc should be provided with supports before concreting to
avoid bending of steel.

Compaction of Concrete
Each layer of fresh concrete shall be compacted by vibrators to the minimum practicable compacted
consolidated volume. Compacted concrete shall be free from pockets of coarse aggregates and shall flush
tightly against all form materials. Mechanical vibration shall be supplemented by hand spreading and
tampering especially at the corners.
Immersion Type vibrators shall be inserted in vertical positions at various points approximately 450 mm
apart and area of the vibrating point is 10 times of its cross sectional area,60 mm dia vibrator shall be mostly
used except in the areas of congested reinforcement where 40 mm shall be used. Vibrators shall be allowed to
penetrate down by its own weight and duration shall be
sufficient to consolidate the concrete but not sufficient to cause segregation generally from 5 to 15 seconds.
Vibrator shall fully penetrated into the layer being located and also 50 mm into the previous layer while the
layer beneath is still plastic to ensure good bond and homogenous between the two layers and prevention of
any cold joints. vibrator shall not be used for dragging or spreading of concrete and spare should be used for
any critical application.
On pouring of concrete it shall be continued until the level of structure has been attained and or construction
joint has been reached.

15
PROJECT: CONSTRUCTION OF 2 X 20 MVA,
33/11 kV PRIMARY SUB STATION DESIGNATED Rev No 0
AS JARZIZ (DPC/TENDER/2016/201) Rev Date 07.05.2017

Project CONSTRUCTION OF 33/11K,2X20MVA PSS DESIGNATED AS JARZIZ


Project Company DHOFAR POWER COMPANY
Owner’s Engineer HAMED ENGINEERING SERVICES LLC
Contractor SHARIKAT FANNIYA OMANIYA LLC

Concreting In adverse weather


Concrete cannot be done during storms and thunder rains without proper arrangements and protection.
Concreting is not allowed when shaded temperature is more than 37 degree Celcius.
Concrete finishes
Formed surfaces to view shall be smooth form finish. Finished surface shall be sound solid and free from
honeycombing protuberances and blemishes. Dusting of surfaces with dry cement to absorb access water shall
not be permitted.

Curing
Before initial setting concrete shall be protected against the evaporation losses due to harmful effect of
sunshine drying wind, rain and running water. Upon the completion of concreting the exposed surface has to
be covered with any material which can keep the surface damp. Immediately upon the removal of form work
the newly exposed surface has to be protected from water loss. Bund shall be made all around the pour, of
sand -cement lean mortar, to facilitate the same. Curing of concrete shall start after final setting time of
concrete for finished surface. Curing shall be continued till 14 days after placing the concrete. Curing of sides
of construction joints shall be aided by wet burlap. This shall be maintained moist by spraying water. Curing
compounds to be applied after removing the sides of substructure and shall be in accordance with the
manufacturer recommendations.

Test and Inspection


During the progress of construction batches of concrete shall be constantly monitored for temperature, slump,
and strength at various ages etc at frequencies as per the inspection and test plan.
Cube sampling and testing
Cubes shall be made from sample of concrete taken from the mixture as directed by client/consultant. 6 cubes
per pouring shall be taken for cube test. The cubes shall be sent to test to outside laboratory approved by the
consultant. Test certificate shall be submitted accordingly.
For slump test the slump cone should be properly cleaned with water before use. Concrete shall be then
poured into the cone till 40 % of total filling then conctere shall be tapped to level with the use of minimum
16mm dia tapping rod, then concrete is filled till top and tapped to level. Slump value shall be checked.

16
PROJECT: CONSTRUCTION OF 2 X 20 MVA,
33/11 kV PRIMARY SUB STATION DESIGNATED Rev No 0
AS JARZIZ (DPC/TENDER/2016/201) Rev Date 07.05.2017

Project CONSTRUCTION OF 33/11K,2X20MVA PSS DESIGNATED AS JARZIZ


Project Company DHOFAR POWER COMPANY
Owner’s Engineer HAMED ENGINEERING SERVICES LLC
Contractor SHARIKAT FANNIYA OMANIYA LLC

Additional requirement in hot weather


Necessary precautions shall be taken when the atmospheric temperature rises more than 40 degree Celsius.
The maximum permissible temp of concrete being placed shall be determined by the owner/ engineer
according to the nature and location of the work and shall not be more than 30 degree Celsius and the
following precautions has to be taken:
Shading aggregate and cement stockpile
Usage of cold water for mixing
Spraying aggregate stock piles with water.
Usage of recommended and approved admixture to retard the setting time and or enhance work ability.
Shading of form work and reinforcement bars.
Pouring shall be done during low temperature( pouring shall be done preferably after sunset)
In hot weather concrete shall be deposited in horizontal layers to a depth not less exceeding 300mm and
internal mechanical vibrators has to be used. All concrete has to be cured for at least 14 days after placing and
kept continuously wet for all days. The quality of the curing water shall be same as that used for making
concrete.
Storage of materials
Aggregate: aggregate shall be stocked separately without mixing each other as stock piling. Aggregates
shall be stock piled in separated grading with concrete/ block wall boundary as directed by site engineer.
1. 20mm aggregate
2. 10mm aggregate
3. Fine aggregate
More care shall be taken for handling the aggregate to avoid mixing each other and foreign particles

Protection of mixture machine


Equipment shall be covered with polythene/ tarpaulin while not in use to protect from dust and weather

7.0 Quality Records:


Quality Records (Approved Drawings, Shop drawings, Mix design reports, Concrete batch delivery note)
Inspection Form (RFI /Checklist) includes concrete pour card, air temperature, weather conditions.
Cube test register and As built drawings.

17
PROJECT: CONSTRUCTION OF 2 X 20 MVA,
33/11 kV PRIMARY SUB STATION DESIGNATED Rev No 0
AS JARZIZ (DPC/TENDER/2016/201) Rev Date 07.05.2017

Project CONSTRUCTION OF 33/11K,2X20MVA PSS DESIGNATED AS JARZIZ


Project Company DHOFAR POWER COMPANY
Owner’s Engineer HAMED ENGINEERING SERVICES LLC
Contractor SHARIKAT FANNIYA OMANIYA LLC

DOCUMENT REFERENCE NUMBER: SFO/NAQ/MS/C/04


CURING

TITLE Prepared /Reviewed by SFO Approved by SFO Approved by HES


Civil/ QAQC Engineer Site Manager Civil Engineer
NAME
SIGNATURE

DATE

18
PROJECT: CONSTRUCTION OF 2 X 20 MVA,
33/11 kV PRIMARY SUB STATION DESIGNATED Rev No 0
AS JARZIZ (DPC/TENDER/2016/201) Rev Date 07.05.2017

Project CONSTRUCTION OF 33/11K,2X20MVA PSS DESIGNATED AS JARZIZ


Project Company DHOFAR POWER COMPANY
Owner’s Engineer HAMED ENGINEERING SERVICES LLC
Contractor SHARIKAT FANNIYA OMANIYA LLC

The following activities shall be ensured by the Civil Engineer and QC Engineer at site.
1.0 Purpose
The purpose of this instruction is to provide methodology for curing of structures at construction of substation
proper curing of concrete is essential for promoting the hydration of cement. Curing
consists of control of concrete temperature and moisture loss from the concrete .The object of curing is to keep
concrete saturated for certain period before the maximum possible hydration take place. it can be achieved either
by watering and or curing compounds.
2.0 Applicable Specifications, Reference, Standards and Approved Drawings
Scope Of work
Volume -2, Section –12.7.15
Issued Method Statement
3.0 Job Safety Plan
3.1Hazard Identification
Access risk
Electric Shock
Falls, Trips
3.2Action by the Execution Team
Suitable footwear and appropriate PPE shall be provided.
Access / egress to the work area should be properly made by means of approved scaffolds, platforms, ladders and
stairs for curing at heights.
All Electrical wirings and connections secured properly.

4.0 Procedure
Water shall be provided from approved source for curing of concrete. Slab concreting shall be done by spraying
or sprinkling water immediately after finishing. Measures shall be adopted to prevent evaporation loss before
initial setting of concrete. Once the concrete surface becomes hard it is preferred to do ponding and water shall
be filled and maintained for the seven days period. To avoid rapid evaporation of water from the surface
polythene sheet shall be provide above the wet Hessian cloth wherever required. Cement /sand bund shall be

19
PROJECT: CONSTRUCTION OF 2 X 20 MVA,
33/11 kV PRIMARY SUB STATION DESIGNATED Rev No 0
AS JARZIZ (DPC/TENDER/2016/201) Rev Date 07.05.2017

Project CONSTRUCTION OF 33/11K,2X20MVA PSS DESIGNATED AS JARZIZ


Project Company DHOFAR POWER COMPANY
Owner’s Engineer HAMED ENGINEERING SERVICES LLC
Contractor SHARIKAT FANNIYA OMANIYA LLC

made to avoid flow of water from the surface. For vertical surfaces like walls and columns, Hessian cloth will be
wrapped and water shall be sprinkled regularly for 14 days to cure the elements.

5.0Records
Post pour concrete inspection.

20
PROJECT: CONSTRUCTION OF 2 X 20 MVA,
33/11 kV PRIMARY SUB STATION DESIGNATED Rev No 0
AS JARZIZ (DPC/TENDER/2016/201) Rev Date 07.05.2017

Project CONSTRUCTION OF 33/11K,2X20MVA PSS DESIGNATED AS JARZIZ


Project Company DHOFAR POWER COMPANY
Owner’s Engineer HAMED ENGINEERING SERVICES LLC
Contractor SHARIKAT FANNIYA OMANIYA LLC

DOCUMENT REFERENCE NUMBER: SFO/NAQ/MS/C/05

MASONRY

TITLE Prepared /Reviewed by SFO Approved by SFO Approved by HES


Civil/ QAQC Engineer Site Manager Civil Engineer
NAME
SIGNATURE

DATE

21
PROJECT: CONSTRUCTION OF 2 X 20 MVA,
33/11 kV PRIMARY SUB STATION DESIGNATED Rev No 0
AS JARZIZ (DPC/TENDER/2016/201) Rev Date 07.05.2017

Project CONSTRUCTION OF 33/11K,2X20MVA PSS DESIGNATED AS JARZIZ


Project Company DHOFAR POWER COMPANY
Owner’s Engineer HAMED ENGINEERING SERVICES LLC
Contractor SHARIKAT FANNIYA OMANIYA LLC

The following activities shall be ensured by the Civil Engineer and QC Engineer at site
1.0 Purpose
The purpose of this instruction is to define general sequence of events and responsibilities for carrying out Block
Masonry and the measures adopted for safe and systematic completion of the same.
2.0 Applicable Specifications, Reference, Standards and Approved Drawings
Scope Of work
Volume -2, Section –12.10
Issued Method Statement
3.0 Job Safety Plan
3.1Hazard Identification
Working at Height
Falls Trips, Bodily Injury
Access Risk, Respiratory Hazards

3.2Action by the Execution Team


1. All the manpower involved in the job shall wear appropriate PPE.
2. Proper approach to the work spot, good housekeeping and proper illuminations shall be provided.
3. Appropriate scaffolding shall be provided as needed to allow safe and finishing of the masonry.

4.0 Procedure
Material
As per approved MAS Submitted to Consultant.
Set out
All the works shall be set out and checked with reference to the certified survey/points/lines/axis. The
dimensions of each element shall be as per the AFC drawings and the same shall be verified and recorded.

Laying Of Masonry
Preparation of Mortar

22
PROJECT: CONSTRUCTION OF 2 X 20 MVA,
33/11 kV PRIMARY SUB STATION DESIGNATED Rev No 0
AS JARZIZ (DPC/TENDER/2016/201) Rev Date 07.05.2017

Project CONSTRUCTION OF 33/11K,2X20MVA PSS DESIGNATED AS JARZIZ


Project Company DHOFAR POWER COMPANY
Owner’s Engineer HAMED ENGINEERING SERVICES LLC
Contractor SHARIKAT FANNIYA OMANIYA LLC

Mortar proportion shall be (1:4) cement and of fine aggregates for load bearing wall and (1:6) cement and of
sand for non load bearing units.
Ingredients for mortars shall be measured by gauge boxes/Weigh Batcher.
Mortar shall be thoroughly mixed till uniform mixer is attained.
Sufficient potable water shall be added and mixed until a homogenous mix is obtained.
Mortar shall be applied within 30 minutes after mixing .Hardened mortar or stiffened due to hydration of the
cement shall not be used.
Laying
Concrete surface in contact with masonry shall be hacked and surface roughened for proper bonding.
All concrete blocks shall be soaked with water before being used and the surface of the base shall be wetted
before laying.
Block work shall be done as per dimensions in accordance with approved drawings.
On laying of first course of masonry units one layer of mortar shall be placed on the base covering the bottom
surface. Masonry units shall be laid on a full bed of mortar and gently pressed so that mortar can get into the
space between the blocks to ensure good adhesion. On laying of each unit excess mortar from the joints shall be
wiped off cleanly with the trowel
Cross –joints and wall joints shall be flushed and packed with mortar to prevent formation of hollow pockets.
Blocks shall be laid in stretcher bond on a full bed of mortar and the joints shall be uniform not exceeding 10
mm.
Where wall faces are to be rendered the joints shall be racked out to form keys. No half cut blocks shall not be
used to form a bond. Variations to standard block width shall be as per indications in drawings.
The maximum height of block work built in a day shall be 1.6 M
Verticality of the wall faces and horizontality of the courses shall be checked with plumb bob and spirit level
respectively. All alignment and verticality of each masonry unit to final position shall be done while the mortar is
soft.
Walls shall be carried up regularly any part more than 1m lower than other unless the permission of the
consultant received.
Curing shall be carried out by using lightly spraying fresh water for 5 days.

Stacking and storage of blocks

23
PROJECT: CONSTRUCTION OF 2 X 20 MVA,
33/11 kV PRIMARY SUB STATION DESIGNATED Rev No 0
AS JARZIZ (DPC/TENDER/2016/201) Rev Date 07.05.2017

Project CONSTRUCTION OF 33/11K,2X20MVA PSS DESIGNATED AS JARZIZ


Project Company DHOFAR POWER COMPANY
Owner’s Engineer HAMED ENGINEERING SERVICES LLC
Contractor SHARIKAT FANNIYA OMANIYA LLC

All blocks are to be stored on plain ground surfaces and the stacks of the blocks are to be protected by splashing
by mud or contamination by other materials.
5.0Records
Specifications, approved drawings and shop drawing.

24
PROJECT: CONSTRUCTION OF 2 X 20 MVA,
33/11 kV PRIMARY SUB STATION DESIGNATED Rev No 0
AS JARZIZ (DPC/TENDER/2016/201) Rev Date 07.05.2017

Project CONSTRUCTION OF 33/11K,2X20MVA PSS DESIGNATED AS JARZIZ


Project Company DHOFAR POWER COMPANY
Owner’s Engineer HAMED ENGINEERING SERVICES LLC
Contractor SHARIKAT FANNIYA OMANIYA LLC

DOCUMENT REFERENCE NUMBER: SFO/NAQ/MS/C/06

PLASTERING

TITLE Prepared /Reviewed by SFO Approved by SFO Approved by HES


Civil/ QAQC Engineer Site Manager Civil Engineer
NAME
SIGNATURE

DATE

25
PROJECT: CONSTRUCTION OF 2 X 20 MVA,
33/11 kV PRIMARY SUB STATION DESIGNATED Rev No 0
AS JARZIZ (DPC/TENDER/2016/201) Rev Date 07.05.2017

Project CONSTRUCTION OF 33/11K,2X20MVA PSS DESIGNATED AS JARZIZ


Project Company DHOFAR POWER COMPANY
Owner’s Engineer HAMED ENGINEERING SERVICES LLC
Contractor SHARIKAT FANNIYA OMANIYA LLC

The following activities shall be ensured by the Civil Engineer and QC Engineer at site
1.0 Purpose
The purpose of this procedure is to cover all basic requirements to be carried out for plastering work.
1.1 Applicable Specifications, Reference, Standards and Approved Drawings
Scope Of work
Volume -2, Section –12.11.3
Issued Method Statement.

3.0 Job Safety Plan


3.1Hazard Identification
Working at Height
Falls Trips, Bodily Injury
Access Risk, Respiratory Hazards, Electric Shock.

3.2Action by the Execution Team


1. All the manpower involved in the job shall wear appropriate PPE.
2. Proper approach to the work spot, good housekeeping and proper illuminations shall be provided.
3. Appropriate scaffolding shall be provided as needed to allow safe and finishing of the masonry.
4. All the electrical installations shall be enclosed properly and ELCB shall be installed to prevent danger of
electric shock.
5. Safety induction shall be given before commencing work and all workmen shall be briefed about
associated hazards and necessary precautionary measures involved and evacuation procedures.
6. Trained workmen shall be provided and competent person shall inspect before commencing site activities.

4.0 Procedure
Material
Cement Conforming To BS -12
Sand Conforming To BS 1199
Water Conforming To BS 3148.
Before rendering the block work, surface shall be brushed to remove efflorescence and loose dust.
26
PROJECT: CONSTRUCTION OF 2 X 20 MVA,
33/11 kV PRIMARY SUB STATION DESIGNATED Rev No 0
AS JARZIZ (DPC/TENDER/2016/201) Rev Date 07.05.2017

Project CONSTRUCTION OF 33/11K,2X20MVA PSS DESIGNATED AS JARZIZ


Project Company DHOFAR POWER COMPANY
Owner’s Engineer HAMED ENGINEERING SERVICES LLC
Contractor SHARIKAT FANNIYA OMANIYA LLC

Before rendering commences, all surfaces are to be wetted with water


Plaster level /thickness buttons shall be made before starting the plaster.
All Surfaces of concrete shall be roughened to provide a good key.
Corner beads shall be fixed to all external corners and exposed edges of plaster work.
Material shall be OPC Cement, sand as per BS -1199 and water from approved source.
Cement and sand shall be dry mixed thoroughly in the ratio of 1:4 by Volume. Water shall be added gradually
and mixed further till the mortar attains consistency.
Mixed plaster shall be used within 30 Minutes of time and partially set plaster shall not be used.
Rendering coat shall be two coats, Base or spatter coat and final coat
Base coat shall be 2-3 mm thick and shall be moist for two days and then allowed to dry out.
Expanded metal lath mesh of minimum 200 mm width shall be fixed over all joints between block work and
concrete surface including all chases made in the block work.
Before starting the second (Final) coat plaster, base coat shall be wet.
The second coat shall be 12-13 mm thick and floated to a true, even smooth surface.
Internal, External and ceiling (As per drawing) Plaster (Base and Final) will be 15 mm thick.
Plastering between two corners, lintels shall be carried out in one operation.
For External plastering stress relieving joints shall be provided at each storey height.
The rendering must be kept damp by lightly spraying with fresh water for 7 days after application.
External rendered surfaces shall be covered with hessian Cloth.
Curing for the vertical plastering shall be carried by using light water spray for 4 days after application.
External rendering shall be done as described in the scope of work and with recommendations of BS 5262.

5.0Records
All material shall be conformed to specifications and approved drawings.
Records shall be reviewed to ensure completion as per specification.
Applicable measuring instruments shall have current valid calibration certificate

27
PROJECT: CONSTRUCTION OF 2 X 20 MVA,
33/11 kV PRIMARY SUB STATION DESIGNATED Rev No 0
AS JARZIZ (DPC/TENDER/2016/201) Rev Date 07.05.2017

Project CONSTRUCTION OF 33/11K,2X20MVA PSS DESIGNATED AS JARZIZ


Project Company DHOFAR POWER COMPANY
Owner’s Engineer HAMED ENGINEERING SERVICES LLC
Contractor SHARIKAT FANNIYA OMANIYA LLC

DOCUMENT REFERENCE NUMBER: SFO/NAQ/MS/C/07

ROOF SLAB WATER PROOFING WORK

TITLE Prepared /Reviewed by SFO Approved by SFO Approved by HES


Civil/ QAQC Engineer Site Manager Civil Engineer
NAME
SIGNATURE

DATE

28
PROJECT: CONSTRUCTION OF 2 X 20 MVA,
33/11 kV PRIMARY SUB STATION DESIGNATED Rev No 0
AS JARZIZ (DPC/TENDER/2016/201) Rev Date 07.05.2017

Project CONSTRUCTION OF 33/11K,2X20MVA PSS DESIGNATED AS JARZIZ


Project Company DHOFAR POWER COMPANY
Owner’s Engineer HAMED ENGINEERING SERVICES LLC
Contractor SHARIKAT FANNIYA OMANIYA LLC

The following activities shall be ensured by the Civil Engineer and QC Engineer at site
1.0 Purpose
The purpose of this procedure is to cover all basic requirements to be carried out for water proofing work.
1.1 Applicable Specifications, Reference, Standards and Approved Drawings
Scope Of work
Volume -2, Section –12.14
Issued Method Statement.

3.0 Job Safety Plan


3.1Hazard Identification
Working at Height
Falls Trips, Bodily Injury
Access Risk, Respiratory Hazards, Electric Shock.

3.2Action by the Execution Team


1. All the manpower involved in the job shall wear appropriate PPE.
2. Proper approach to the work spot, good housekeeping and proper illuminations shall be provided.
3. Appropriate scaffolding shall be provided as needed to allow safe and finishing of the masonry.
4. All the electrical installations shall be enclosed properly and ELCB shall be installed to prevent danger of
electric shock.
5. Safety induction shall be given before commencing work and all workmen shall be briefed about associated
hazards and necessary precautionary measures involved and evacuation procedures.
6. Trained workmen shall be provided and competent person shall inspect before commencing site activities.

4.0 Procedure
Material
Cement Conforming To BS -12
Sand Conforming To BS 1199
Water Conforming To BS 3148.

29
PROJECT: CONSTRUCTION OF 2 X 20 MVA,
33/11 kV PRIMARY SUB STATION DESIGNATED Rev No 0
AS JARZIZ (DPC/TENDER/2016/201) Rev Date 07.05.2017

Project CONSTRUCTION OF 33/11K,2X20MVA PSS DESIGNATED AS JARZIZ


Project Company DHOFAR POWER COMPANY
Owner’s Engineer HAMED ENGINEERING SERVICES LLC
Contractor SHARIKAT FANNIYA OMANIYA LLC

After the light weight screed concrete is finished and proper curing shall be done by sprinkling and spraying water.
Before commencing the water proofing work ensure that the concrete surface is cleaned and the surface shall be
moisture free.
Apply the bitumen paint on top of the concrete and let it dry for 24 hours. The bitumen surface shall be made dust
free before commencing the waterproofing membrane application.
The bottom side of the membrane shall heated up slightly with the help of gas torch and shall be sticked to the
bitumen paint. Proper care shall be taken heating and sticking the membrane.
After the waterproof membrane is fixed the 4mm thick geo-textile membrane shall be laid above it. One layer of 50
mm thick roof insulation is laid above the geo textile membrane. Proper care shall be taken while laying the roof
insulation while cutting and fixing adjacent pieces. 30mm thick Roof tiles are then fixed above the roof insulation.
The gaps between the tiles is finished with the cement mix. Proper care shall be taken for providing slope and rain
water drain pipe.

5.0Records
All material shall be conformed to specifications and approved drawings.
Records shall be reviewed to ensure completion as per specification.
Applicable measuring instruments shall have current valid calibration certificate

30
PROJECT: CONSTRUCTION OF 2 X 20 MVA,
33/11 kV PRIMARY SUB STATION DESIGNATED Rev No 0
AS JARZIZ (DPC/TENDER/2016/201) Rev Date 07.05.2017

Project CONSTRUCTION OF 33/11K,2X20MVA PSS DESIGNATED AS JARZIZ


Project Company DHOFAR POWER COMPANY
Owner’s Engineer HAMED ENGINEERING SERVICES LLC
Contractor SHARIKAT FANNIYA OMANIYA LLC

DOCUMENT REFERENCE NUMBER: SFO/NAQ/MS/C/08

PAINTING WORK

TITLE Prepared /Reviewed by SFO Approved by SFO Approved by HES


Civil/ QAQC Engineer Site Manager Civil Engineer
NAME
SIGNATURE

DATE

31
PROJECT: CONSTRUCTION OF 2 X 20 MVA,
33/11 kV PRIMARY SUB STATION DESIGNATED Rev No 0
AS JARZIZ (DPC/TENDER/2016/201) Rev Date 07.05.2017

Project CONSTRUCTION OF 33/11K,2X20MVA PSS DESIGNATED AS JARZIZ


Project Company DHOFAR POWER COMPANY
Owner’s Engineer HAMED ENGINEERING SERVICES LLC
Contractor SHARIKAT FANNIYA OMANIYA LLC

The following activities shall be ensured by the Civil Engineer and QC Engineer at site
1.0 Purpose
The purpose of this procedure is to cover all basic requirements to be carried out for internal and external painting
works.
1.1 Applicable Specifications, Reference, Standards and Approved Drawings
Scope Of work
Issued Method Statement.

3.0 Job Safety Plan


3.1Hazard Identification
Working at Height
Falls Trips, Bodily Injury
Access Risk, Respiratory Hazards, Electric Shock.

3.2Action by the Execution Team


1. All the manpower involved in the job shall wear appropriate PPE.
2. Proper approach to the work spot, good housekeeping and proper illuminations shall be provided.
3. Appropriate scaffolding shall be provided as needed to allow safe and finishing of the masonry.
4. All the electrical installations shall be enclosed properly and ELCB shall be installed to prevent danger of
electric shock.
5. Safety induction shall be given before commencing work and all workmen shall be briefed about associated
hazards and necessary precautionary measures involved and evacuation procedures.
6. Trained workmen shall be provided and competent person shall inspect before commencing site activities.

4.0 Procedure
After curing of plastering is finished the surface shall be be made dust free and moisture free.
In the internal wall finishes apply 2 coats of putty to get a smooth surface for paining. Sufficient time shall be given
for drying of putty for applying paint. Apply 2 coats of approved shade of paint to get proper finish. Final coat of

32
PROJECT: CONSTRUCTION OF 2 X 20 MVA,
33/11 kV PRIMARY SUB STATION DESIGNATED Rev No 0
AS JARZIZ (DPC/TENDER/2016/201) Rev Date 07.05.2017

Project CONSTRUCTION OF 33/11K,2X20MVA PSS DESIGNATED AS JARZIZ


Project Company DHOFAR POWER COMPANY
Owner’s Engineer HAMED ENGINEERING SERVICES LLC
Contractor SHARIKAT FANNIYA OMANIYA LLC

paint can be done after all the internal activities like panel installation, door fixing is finished or clearance from
client/ consultant.
For external painting the plastering finish shall rough finish and after cleaning apply 2 coats of approved shade of
paint. Final coat of paint shall be done after all the Civil and civil activities have been completed.

5.0Records
All material shall be conformed to specifications and approved drawings.
Records shall be reviewed to ensure completion as per specification.
Applicable measuring instruments shall have current valid calibration certificate

33
PROJECT: CONSTRUCTION OF 2 X 20 MVA,
33/11 kV PRIMARY SUB STATION DESIGNATED Rev No 0
AS JARZIZ (DPC/TENDER/2016/201) Rev Date 07.05.2017

Project CONSTRUCTION OF 33/11K,2X20MVA PSS DESIGNATED AS JARZIZ


Project Company DHOFAR POWER COMPANY
Owner’s Engineer HAMED ENGINEERING SERVICES LLC
Contractor SHARIKAT FANNIYA OMANIYA LLC

DOCUMENT REFERENCE NUMBER: SFO/NAQ/MS/C/09

WALL AND FLOOR TILE WORK

34
PROJECT: CONSTRUCTION OF 2 X 20 MVA,
33/11 kV PRIMARY SUB STATION DESIGNATED Rev No 0
AS JARZIZ (DPC/TENDER/2016/201) Rev Date 07.05.2017

Project CONSTRUCTION OF 33/11K,2X20MVA PSS DESIGNATED AS JARZIZ


Project Company DHOFAR POWER COMPANY
Owner’s Engineer HAMED ENGINEERING SERVICES LLC
Contractor SHARIKAT FANNIYA OMANIYA LLC

The following activities shall be ensured by the Civil Engineer and QC Engineer at site
1.0 Purpose
The purpose of this procedure is to cover all basic requirements to be carried out for wall and floor tiles fixing work.
1.1 Applicable Specifications, Reference, Standards and Approved Drawings
Scope Of work
Issued Method Statement.

3.0 Job Safety Plan


3.1Hazard Identification
Working at Height
Falls Trips, Bodily Injury
Access Risk, Respiratory Hazards, Electric Shock.

3.2Action by the Execution Team


1. All the manpower involved in the job shall wear appropriate PPE.
2. Proper approach to the work spot, good housekeeping and proper illuminations shall be provided.
3. Appropriate scaffolding shall be provided as needed to allow safe and finishing of the masonry.
4. All the electrical installations shall be enclosed properly and ELCB shall be installed to prevent danger of
electric shock.
5. Safety induction shall be given before commencing work and all workmen shall be briefed about associated
hazards and necessary precautionary measures involved and evacuation procedures.
6. Trained workmen shall be provided and competent person shall inspect before commencing site activities.

4.0 Procedure
The area shall be cleaned properly and final finish level and slope of floor shall be properly checked and marked
before commencing the work. The grout of approved make and type shall be mixed according to the instruction in
the manufacturer’s catalogue. The mixed grout is applied on the levelled and cleaned surface using proper tools and
tiles are fixed matching the marked horizontal and vertical line. Tile spacers shall be fixed at each corner of the tile
for getting proper finish and equal spacing between the tiles. After 24 hrs of drying of tile the gap between the tiles
are then filled up with the white cement grout for wall tile and grout of matching colour for floor tiles shall be

35
PROJECT: CONSTRUCTION OF 2 X 20 MVA,
33/11 kV PRIMARY SUB STATION DESIGNATED Rev No 0
AS JARZIZ (DPC/TENDER/2016/201) Rev Date 07.05.2017

Project CONSTRUCTION OF 33/11K,2X20MVA PSS DESIGNATED AS JARZIZ


Project Company DHOFAR POWER COMPANY
Owner’s Engineer HAMED ENGINEERING SERVICES LLC
Contractor SHARIKAT FANNIYA OMANIYA LLC

applied for proper finish. Care shall be taken to apply the grout in level with the tile surface and the tiles surface.
Clean the tiles surface properly after application of grout.

5.0Records
All material shall be conformed to specifications and approved drawings.
Records shall be reviewed to ensure completion as per specification.
Applicable measuring instruments shall have current valid calibration certificate

36
PROJECT: CONSTRUCTION OF 2 X 20 MVA,
33/11 kV PRIMARY SUB STATION DESIGNATED Rev No 0
AS JARZIZ (DPC/TENDER/2016/201) Rev Date 07.05.2017

Project CONSTRUCTION OF 33/11K,2X20MVA PSS DESIGNATED AS JARZIZ


Project Company DHOFAR POWER COMPANY
Owner’s Engineer HAMED ENGINEERING SERVICES LLC
Contractor SHARIKAT FANNIYA OMANIYA LLC

DOCUMENT REFERENCE NUMBER: SFO/NAQ/MS/C/10

ANTITERMITE TREATMENT

TITLE Prepared /Reviewed by SFO Approved by SFO Approved by HES


Civil/ QAQC Engineer Site Manager Civil Engineer
NAME
SIGNATURE

DATE

37
PROJECT: CONSTRUCTION OF 2 X 20 MVA,
33/11 kV PRIMARY SUB STATION DESIGNATED Rev No 0
AS JARZIZ (DPC/TENDER/2016/201) Rev Date 07.05.2017

Project CONSTRUCTION OF 33/11K,2X20MVA PSS DESIGNATED AS JARZIZ


Project Company DHOFAR POWER COMPANY
Owner’s Engineer HAMED ENGINEERING SERVICES LLC
Contractor SHARIKAT FANNIYA OMANIYA LLC

The following activities shall be ensured by the Civil Engineer and QC Engineer at site
1.0 Purpose
The purpose of this procedure is to cover all basic requirements to be carried out for anti-termite treatment for
compacted soil.
1.1 Applicable Specifications, Reference, Standards and Approved Drawings
Scope Of work
Volume -2, Section –12.22
Issued Method Statement.

3.0 Job Safety Plan


3.1Hazard Identification
Working at Height
Falls Trips, Bodily Injury
Access Risk, Respiratory Hazards, Electric Shock.

3.2Action by the Execution Team


1. All the manpower involved in the job shall wear appropriate PPE.
2. Proper approach to the work spot, good housekeeping and proper illuminations shall be provided.
3. Appropriate scaffolding shall be provided as needed to allow safe and finishing of the masonry.
4. All the electrical installations shall be enclosed properly and ELCB shall be installed to prevent danger of
electric shock.
5. Safety induction shall be given before commencing work and all workmen shall be briefed about associated
hazards and necessary precautionary measures involved and evacuation procedures.
6. Trained workmen shall be provided and competent person shall inspect before commencing site activities.

4.0 Procedure
Termite treatment in pre-construction stages includes several procedures that must be done to ensure an area of
termite-free construction. Treating before any slab placement with insecticides is the most common method of
termite treatment. This will form a chemical barrier between ground slab that will prevent the insects to approach
the building. The chemical mixing and application shall be done by approved chemist or under in his supervision.

38
PROJECT: CONSTRUCTION OF 2 X 20 MVA,
33/11 kV PRIMARY SUB STATION DESIGNATED Rev No 0
AS JARZIZ (DPC/TENDER/2016/201) Rev Date 07.05.2017

Project CONSTRUCTION OF 33/11K,2X20MVA PSS DESIGNATED AS JARZIZ


Project Company DHOFAR POWER COMPANY
Owner’s Engineer HAMED ENGINEERING SERVICES LLC
Contractor SHARIKAT FANNIYA OMANIYA LLC

The chemical is mixed with water and shall be applied all over the compacted soil by sparying or pouring at the rate
of 6 litres /sq m. The chemical mixing and application shall be done by approved chemist or under in his
supervision.

5.0Records
All material shall be conformed to specifications and approved drawings.
Records shall be reviewed to ensure completion as per specification.
Applicable measuring instruments shall have current valid calibration certificate

39

Anda mungkin juga menyukai