Treatment project Roadmap – Control and Automation

Start Project

Basic Engg. Basin Level Decanter P&ID


Package - BEP Calculation Summary Author: Mechanical Engg.
Author: Process Engg. Author: Mechanical Author: Mechanical
Engg. Engg.

Control Panel BOM


Operational Author: Vendor reviews the
Description - OD technical specs sent by xylem and
Author: Process Engg. prepares BOM. Xylem reviews the
BOM and gives approval to
vendor.

IO List
Author: Electrical Engg.

Control Panel Wiring


Diagram
Author: Electrical Engg.

PLC Programming SCADA Development HMI Development Control Panel Building


Responsible: Control Responsible: Control Engg. Responsible: Control Responsible: Panel to be made
Engg. Engg. at panel builder’s workshop.
FAT needs to be done after
panel has been fully built at
Panel Builder’s workshop. After
successful completion of FAT,
Testing and Xylem can give approval to
Panel builder to ship the panel
Validation
at Site.
Responsible: Control
Engg.

Control Panel – Factory


Acceptance Test
Responsible: Control Engg. /
Electrical Engg. From Xylem
will perform FAT at Panel
Builder’s workshop.
After successful completion of
FAT, Xylem can give approval
to Panel builder to ship the
panel at Site.

Pre-Commissioning Start UP
Checklist to be filled and signed
Responsible: Project Manager / Site In-charge
will fill the Pre Commissioning Checklists
ensure that site is ready for Electrical &
Control Commissioning.

On Site Commissioning
Responsible: Control Engg./ Site Engg.for
Electrical and Controls.

Page 1 of 1