ATP

1 ()
Prepared (Subject resp) No.
EGUAAMB/EMAZEDO
Approved (Document resp) Checked Date Rev Reference

2018/02/22 PA1

IP Switches Acceptance Test Procedure ITLA

– Republica Dominicana

Contents 1 General
..................................................................................................................... 1 2 Scope
........................................................................................................................ 2 3
Acceptance Test Procedure .................................................................................... 3
3.1 Prerequisites ................................................................................................ 3
3.1.1 Hardware Tools ............................................................................................ 3
3.1.2 Software Tools ............................................................................................. 3
4 Delivery Acceptance ................................................................................................ 3
4.1 IP Switches .................................................................................................. 3
4.1.1 Hardware Acceptance .................................................................................. 3
4.1.2 Configuration Acceptance ............................................................................ 5
4.1.3 Document Acceptance ............................................................................... 11
5 Integration Acceptance ......................................................................................... 12
5.1 Connectivity ................................................................................................ 12
5.1.1 IP List reachability ...................................................................................... 12
5.1.2 IP Connectivity ........................................................................................... 12
5.2 Redundancy Test Acceptance .................................................................... 13
5.2.1 Intra-switch link failures ................................. Error! Bookmark not defined.
5.2.2 IP Switch to Switch Link Failures ................... Error! Bookmark not defined.
6 Sign off Acceptance ............................................................................................... 14
DocuSign Envelope ID: 37DEBD3B-F025-4ADE-B6C2-892B62325492

ATP
Prepared (Subject resp) No.

Approved (Document resp) Checked Reference


Date 2014-08-2122
Rev

PA1
2 (19)

1 General
This document outlines the acceptance test procedure for a new IP Switches integration in
ITLA Dominican network.

2 Scope
This document covers customer acceptance for the IP Switches delivery and configuration
for traffic. All acceptance tests will be carried out at the customer site. Depending on time
constraints, licensing, and mutual agreement, a sub-set of these test cases may be performed
instead, or additional, customer-specific test cases may be added.

This document also serves as a test report. Each test case contains fields for reporting (notes,
signatures, etc.). If a node has passed certain test case, appropriate field should be signed.
Not performed tests, or tests that have failed for any reasons are noted in this test report and
the reason is explained in Notes..

Overall integration is considered signed-off when Final Site Acceptance has been signed off.
ATP needs to be distributed as per agreed on distribution list.

Network Element Information

Site Name: ITLA Comunicaciones CXA

ED1-SWA
ED2-SWB
Node Name:

Hardware Level
Site Switches:
EBE Comunicaciones S.R.L Personnel

1. Test Leader Name: Anderson Santos

1. Test Leader Email: 20163460@itla.edu.do

2. Test Leader Name:


Francisco Soriano

2. Test Leader Email:


20163445@itla.edu.do
DocuSign Envelope ID: 37DEBD3B-F025-4ADE-B6C2-892B62325492

ATP
Prepared (Subject resp) No.

Approved (Document resp) Checked Reference


Date 2014-08-2122
Rev

PA1
3 (19)

3. Test Leader Name:


Jeffry Rafael Pérez

3. Test Leader Email: 20152821@itla.edu.do

4. Test Leader Name: Jose Romero

4. Test Leader Email:


20163451@itla.edu.do

5. Test Leader Name:


Juan Marmolejos

5. Test Leader Email:


20131926@itla.edu.do
Customer Personnel

1. Test Leader Name: Manuel Kadafi Guerrero Rojas

1. Test Leader Email: mguerrero@itla.edu.do

2. Test Leader Name:

2. Test Leader Email:

3 Acceptance Test Procedure


The ATP consists of several groups of tests:

a. Delivery Acceptance: Selected cases, which serve as verification of delivery of


SW, HW, configuration.

b. Integration Acceptance: These tests reflect the services provided by the solution,
including operation, maintenance, etc.

c. Final Site Acceptance: These test cases serve as verification of finalized


integration of the new node.
DocuSign Envelope ID: 37DEBD3B-F025-4ADE-B6C2-892B62325492

ATP
Prepared (Subject resp) No.

Approved (Document resp) Checked Reference


Date 2014-08-2122
Rev

PA1
4 (19)

3.1 Prerequisites

This chapter describes the network configuration and tools necessary for the tests.

3.1.1 Hardware Tools

• PC/Workstation to connect to the switches and monitor the traffic


• Serial cable to connect to the switches

3.1.2 Software Tools

Secure CRT | Putty | MobaXterm

4 Delivery Acceptance
The scope of this chapter is to verify the configuration and connectivity of the solution.

4.1 IP Switches

4.1.1 Hardware Acceptance

Description
This check will verify that the delivery is complete and without damage. This procedure must be repeated for each Site
Switch individually.
Expected Result

Actual delivered material should match materials list.


Delivered material should be in excellent condition and without visual damage
Precondition
Ethernet Switch installed.
Test Procedure Notes
DocuSign Envelope ID: 37DEBD3B-F025-4ADE-B6C2-892B62325492

ATP
Prepared (Subject resp) No.

Approved (Document resp) Checked Reference


Date 2014-08-2122
Rev

PA1
5 (19)

Visually check the delivered Passed


Ethernet switch, including
power supply, cables,
cards, and spare parts
against materials list.

Visually check the delivered


components for damage.

1) Make sure the console


access port is
operating. (Serial port
settings are: 9600bps,
8 data bits, no parity, 1
stop)
2) Connect using console
o SSH protocol details
provided earlier.
3) Make sure all cable is
inserted into correct
interface according to
design.

4) Save the configuration


and reboot the switch.
Wait for switch to
recover then login as
user “admin”. Check
the configuration is
retained.

command: copy
running-config
startupconfig
command: save

5) Fan and Power


verifications

Verify the Fan Operation:

command: Show env


fan
command:
Display fan
DocuSign Envelope ID: 37DEBD3B-F025-4ADE-B6C2-892B62325492

ATP
Prepared (Subject resp) No.

Approved (Document resp) Checked Reference


Date 2014-08-2122
Rev

PA1
6 (19)

Verify the Power Operation:

command:
Show env power
command: Display
power-supply

6) Check system
memory. Ensure no
excessive memory
usage exists.
Command: Show
file systems
Command: dir flash:/
DocuSign Envelope ID: 37DEBD3B-F025-4ADE-B6C2-892B62325492

ATP
Prepared (Subject resp) No.

Approved (Document resp) Checked Reference


Date 2014-08-2122
Rev

PA1
7 (19)

Date Name: Signature Notes


Passed

4.1.2 Configuration Acceptance

Description
This test case will ensure that the customer, before execution of integration acceptance test cases starts, accepts the
configuration of the Site Switches. The configuration file and a series of printouts will be retrieved and delivered to the
customer for acceptance. This procedure must be repeated for each Site Switch individually.
Expected Result
Configuration reflects the customer’s requirements.
Precondition
Ethernet Switch configured.
Test Procedure Notes
DocuSign Envelope ID: 37DEBD3B-F025-4ADE-B6C2-892B62325492

ATP
Prepared (Subject resp) No.

Approved (Document resp) Checked Reference


Date 2014-08-2122
Rev

PA1
8 (19)

1. Via inbound management, open one session to the Passed


Switch:

ED1-SWA

command: ssh –l username <ip address>

2. Verify that the correct software revision is displayed.

command: Show version

3. Verify the configuration:

command: show running-config


DocuSign Envelope ID: 37DEBD3B-F025-4ADE-B6C2-892B62325492

ATP
Prepared (Subject resp) No.

Approved (Document resp) Checked Reference


Date 2014-08-2122
Rev

PA1
9 (19)
DocuSign Envelope ID: 37DEBD3B-F025-4ADE-B6C2-892B62325492

ATP
Prepared (Subject resp) No.

Approved (Document resp) Checked Reference


Date 2014-08-2122
Rev

PA1
10 (19)

4. Verify the following configuration:


• Vlan tag
• Assigned port
• System IP address

command: Show vlan brief


Show running-config
Show ip interface brief

For all vlans having L3 activated, check that IP


forwarding is enabled. IP enables L3 capabilities.

5. Verify the ports configuration:

command: show ip interfaces


brief
DocuSign Envelope ID: 37DEBD3B-F025-4ADE-B6C2-892B62325492

ATP
Prepared (Subject resp) No.

Approved (Document resp) Checked Reference


Date 2014-08-2122
Rev

PA1
11 (19)
DocuSign Envelope ID: 37DEBD3B-F025-4ADE-B6C2-892B62325492

ATP
Prepared (Subject resp) No.

Approved (Document resp) Checked Reference


Date 2014-08-2122
Rev

PA1
12 (19)
ED2-SWB

command: ssh –l username <ip address

6. Verify that the correct software revision is displayed.

command: Display version

7. Verify the configuration:

command: Display current-configuration

8. Verify the following configuration:


• Vlan tag
• Assigned port
DocuSign Envelope ID: 37DEBD3B-F025-4ADE-B6C2-892B62325492

ATP
Prepared (Subject resp) No.

Approved (Document resp) Checked Reference


Date 2014-08-2122
Rev

PA1
13 (19)

System IP address command:


display vlan all
Display current-configuration
Display interface brief

For all vlans having L3 activated, check that IP forwarding


is enabled. IP enables L3 capabilities.

9. Verify the ports configuration:

command: Display ip interface


DocuSign Envelope ID: 37DEBD3B-F025-4ADE-B6C2-892B62325492

ATP
Prepared (Subject resp) No.

Approved (Document resp) Checked Reference


Date 2014-08-2122
Rev

PA1
14 (19)
DocuSign Envelope ID: 37DEBD3B-F025-4ADE-B6C2-892B62325492

ATP
Prepared (Subject resp) No.

Approved (Document resp) Checked Reference


Date 2014-08-2122
Rev

PA1
15 (19)
DocuSign Envelope ID: 37DEBD3B-F025-4ADE-B6C2-892B62325492

ATP
Prepared (Subject resp) No.

Approved (Document resp) Checked Reference


Date 2014-08-2122
Rev

PA1
16 (19)

Date Name: Signature Notes

Customer Passed | Fail

4.1.3 Document Acceptance

Description
This check will verify that the delivered documentation is complete.

Expected Result

All documentation shall be delivered.

Precondition

N/A

Test Procedure Notes


Passed | Fail
All Documentation shall be delivered by Solution Architect.
- HLD
- LLD
- Physical & logical diagrams
- IP addressing
- Physical connectivity

Date Name: Signature Notes


Passed | Fail
Customer
DocuSign Envelope ID: 37DEBD3B-F025-4ADE-B6C2-892B62325492

ATP
Prepared (Subject resp) No.

Approved (Document resp) Checked Reference


Date 2014-08-2122
Rev

PA1
17 (19)

5 Integration Acceptance
This section verifies the successful operation of the Solution for traffic. The log file for this
session should be saved, which should be backed up and removed before leaving site.

5.1 Connectivity

The scope of these tests is to verify that the nodes have connectivity to all connected network
elements.

5.1.1 IP List reachability

IP address from document about OSPF, last week.

5.1.2 IP Connectivity

Description

Expected Result

There is IP connectivity to all nodes in networks.

Precondition

Nodes connected and configured in the networks.

Test Procedure Notes


Make a list of all adjacent nodes (e.g. server, routers) connected to each network
interface
Passed | Fail
Ping network elements connected via this switch board:

ED1-SWA 192.168.1.2
ED2-SWB 192.168.1.3

Command: ping dst-ip_addr


Commando for cisco : show ip interface brief
DocuSign Envelope ID: 37DEBD3B-F025-4ADE-B6C2-892B62325492

ATP
Prepared (Subject resp) No.

Approved (Document resp) Checked Reference


Date 2014-08-2122
Rev

PA1
18 (19)

In case certain ports are


Customer should verify status of the connection from remote ends. blocked in the firewall,
these test scenarios should
be omitted.

Date Name: Signature Notes

Customer Passed | Fail

5.2 Redundancy Test Acceptance

ç
DocuSign Envelope ID: 37DEBD3B-F025-4ADE-B6C2-892B62325492

ATP

19 (19)

Prepared (Subject resp) No.

Approved (Document resp) Checked Date Rev Reference

2014-08-2122 PA1

6 Sign off Acceptance

Date

martes, 31 de julio de 2018