0 C.W.15 Finishing Works v3 51.55 días mié 18/04/18 mié 20/06/18 60%
1 Finishing Works 51.55 días mié 18/04/18 mié 20/06/18 60%
2 GENERAL SERVICES (all areas) 51.55 días mié 18/04/18 mié 20/06/18 70%
3 STUDIES FOR HVAC, ELECTRICAL & FINISHING 51.55 días mié 18/04/18 mié 20/06/18 70%
WORK
4 Execution studies 10 días mié 18/04/18 lun 30/04/18 100%
5 Contractor's Facilities 3 días lun 30/04/18 vie 04/05/18 100% 4
6 Quality Assurance Plan (PAQ) 5 días vie 04/05/18 jue 10/05/18 100% 5
7 As Built Documents folders 4 días jue 14/06/18 mar 19/06/18 20% 9FF,15FF,59FF,80FF,103FF,121FF,148FF,152FF,37FF,175FF
8 Tests and start-up 5 días jue 14/06/18 mié 20/06/18 0% 7CC
9 GENERAL ACTIVITIES (all areas) 21 días lun 14/05/18 jue 07/06/18 50%
10 SANITARY PLUMBING 21 días lun 14/05/18 jue 07/06/18 45%
11 All evacuation system 19 días lun 14/05/18 mar 05/06/18 50%
12 All sanitary equipment (include water supply) 9 días lun 28/05/18 jue 07/06/18 35% 11FF+2 días
13 HOT WATER ZONE 3 3 días lun 14/05/18 mié 16/05/18 100%
14 Electrical hot water tank 3 días lun 14/05/18 mié 16/05/18 100%
15 ZONE 1 (+0.00 1-7&C-G: offices, rooms, feeders, IS 32.75 días mié 18/04/18 mar 29/05/18 83%
mach timers & UPS room)
16 INTERIOR LAYOUT 3.64 días vie 27/04/18 jue 03/05/18 92%
17 Fixed partitions without glass and solid doors 2 días vie 27/04/18 jue 03/05/18 95% 21FC+5 días
18 Fixed partitions with glass and solid doors 3 días vie 27/04/18 mié 02/05/18 90% 17CC
19 COATING 31.75 días mié 18/04/18 lun 28/05/18 79%
20 Removable suspendend ceiling 6 días lun 21/05/18 lun 28/05/18 85%
21 Painted wall 5 días mié 18/04/18 mar 24/04/18 80%
22 Technical raised floor 4 días mar 08/05/18 vie 11/05/18 100%
23 PVC-type floor covering 2 días sáb 12/05/18 mar 15/05/18 15%
24 Epoxy floor covering 2 días sáb 12/05/18 mar 15/05/18 85%
25 HVAC 15 días lun 30/04/18 vie 18/05/18 92%
26 Single flow extractor 6 días lun 30/04/18 mar 08/05/18 90% 21
27 Natural ventilation by air grille 3 días mar 08/05/18 vie 11/05/18 90% 26
28 Ceiling mounted casettes 5 días vie 11/05/18 jue 17/05/18 95% 27
29 Fan coil & redundant production system 1 día jue 17/05/18 vie 18/05/18 95% 28
30 LOW VOLTAGE POWER 23.25 días lun 30/04/18 mar 29/05/18 89%
31 Distribution board 2 días lun 30/04/18 mié 02/05/18 100% 21
32 Single phase outlets (inclued cabling) 1 día jue 03/05/18 jue 03/05/18 90% 31
33 Three phase outlets (inclued cabling) 1 día vie 04/05/18 vie 04/05/18 90% 32
34 LED-type recessed in suspended ceiling 1 día lun 28/05/18 mar 29/05/18 65% 20
35 NETWORK 2 días vie 04/05/18 lun 07/05/18 0%
36 Switch & outlet 2 días vie 04/05/18 lun 07/05/18 0% 32
37 Batch plant 25.25 días jue 03/05/18 sáb 02/06/18 92%
38 INTERIOR LAYOUT 2 días vie 11/05/18 lun 14/05/18 100%
39 Water resistance 2 días vie 11/05/18 lun 14/05/18 100% 42
40 COATING 17 días jue 03/05/18 mié 23/05/18 100%
41 Tile wall covering 4 días jue 03/05/18 mar 08/05/18 100%
42 Painted wall & ceiling 3 días mar 08/05/18 vie 11/05/18 100% 41
43 Technical raised floor 5 días vie 11/05/18 jue 17/05/18 100% 41,42
44 Removable suspendend ceiling 3 días jue 17/05/18 lun 21/05/18 100% 43
45 Epoxy floor covering 2 días lun 21/05/18 mié 23/05/18 100% 44
46 HVAC 11 días vie 11/05/18 jue 24/05/18 96%
47 Single flow extractor 4 días vie 11/05/18 mié 16/05/18 90% 42
48 Natural ventilation by air grille 2 días mié 16/05/18 vie 18/05/18 100% 47

Página 1
xx xx
Id Nombre de tarea Duración Comienzo Fin % completado Predecesoras
abril 2018 mayo 2018 junio 2018
17 20 23 26 29 02 05 08 11 14 17 20 23 26 29 01 04 07 10 13 16 19
49 Ceiling mounted casettes 2 días vie 18/05/18 lun 21/05/18 100% 48
50 Fan coil, air handler & redundant production system 3 días lun 21/05/18 jue 24/05/18 100% 49
51 LOW VOLTAGE POWER 13 días jue 03/05/18 vie 18/05/18 100%
52 Distribution board 2 días vie 11/05/18 lun 14/05/18 100% 42
53 Single phase outlets (inclued cabling) 3 días mar 15/05/18 vie 18/05/18 100% 52
54 LED-type recessed in suspended ceiling 4 días jue 03/05/18 mar 08/05/18 100%
55 NETWORK 3 días vie 18/05/18 mar 22/05/18 100%
56 Switch & outlet 3 días vie 18/05/18 mar 22/05/18 100% 53
57 STEEL WORK 3 días mié 30/05/18 sáb 02/06/18 0%
58 Mesh partition (doors incl.) 3 días mié 30/05/18 sáb 02/06/18 0% 174
59 ZONE 2 (+0.00 11-16&C-D: offices&rooms & sanitary 25 días mar 08/05/18 jue 07/06/18 75%
22-23&C-D)
60 INTERIOR LAYOUT 5 días mié 30/05/18 mar 05/06/18 85%
61 Fixed partitions without glass and solid doors 2 días mié 30/05/18 vie 01/06/18 85% 67
62 Fixed partitions with glass and solid doors 2 días vie 01/06/18 lun 04/06/18 80% 61
63 Water resistance 1 día mar 05/06/18 mar 05/06/18 95% 62
64 COATING 21.8 días mar 08/05/18 lun 04/06/18 73%
65 Removable suspendend ceiling 4 días jue 24/05/18 mar 29/05/18 35% 19CC+3 días
66 Tile wall covering 3 días mié 30/05/18 sáb 02/06/18 98%
67 Painted wall & ceiling 2 días mar 08/05/18 mié 30/05/18 90% 66CC
68 Epoxy floor covering 2 días vie 11/05/18 lun 04/06/18 95% 66,67
69 HVAC 3 días lun 04/06/18 jue 07/06/18 1%
70 Single flow extractor 2 días lun 04/06/18 mié 06/06/18 1% 66,67,68
71 Fan coil 1 día mié 06/06/18 jue 07/06/18 0% 70
72 LOW VOLTAGE POWER 18 días mié 16/05/18 jue 07/06/18 82%
73 Distribution board 1 día mié 06/06/18 jue 07/06/18 0%
74 Single phase outlets (inclued cabling) 18 días mié 16/05/18 jue 07/06/18 100% 73
75 Three phases outlets (inclued cabling) 2 días mié 16/05/18 vie 18/05/18 100% 74CC
76 LED-type recessed in suspended ceiling 2 días mié 30/05/18 vie 01/06/18 25% 65
77 LED-type fixed on concrete 3 días lun 28/05/18 jue 31/05/18 25%
78 NETWORK 2 días vie 18/05/18 lun 21/05/18 85%
79 Switch & outlet 2 días vie 18/05/18 lun 21/05/18 85% 75
80 ZONE 3 (+0.00 1-7&K-O: electrical rooms&sanitary) 50.55 días mié 18/04/18 mar 19/06/18 57%
81 INTERIOR LAYOUT 2 días mié 06/06/18 jue 07/06/18 60%
82 Water resistance 2 días mié 06/06/18 jue 07/06/18 60%
83 COATING 16.9 días lun 21/05/18 sáb 09/06/18 66%
84 Removable suspendend ceiling 6 días lun 28/05/18 lun 04/06/18 30% 65CC+3 días
85 Painted wall & ceiling 4 días mar 29/05/18 sáb 02/06/18 70% 84CC+1 día
86 Tile wall covering 4 días lun 04/06/18 vie 08/06/18 100% 84,85
87 Technical raised floor 13.9 días lun 21/05/18 mié 06/06/18 100%
88 PVC-type floor covering 3 días mié 06/06/18 sáb 09/06/18 0% 87
89 Floor covering with epoxy 3 días mié 06/06/18 sáb 09/06/18 0% 87
90 HVAC 11 días mié 23/05/18 mar 05/06/18 79%
91 Ceiling mounted casettes 2 días mié 23/05/18 jue 24/05/18 100%
92 Fan coil 2 días vie 25/05/18 lun 28/05/18 50% 91
93 Air handler 1 día lun 28/05/18 mar 29/05/18 50% 92
94 Single flow system all included station, ducts, grid… 4 días mar 29/05/18 sáb 02/06/18 100% 93
95 Natural ventilation by grid included filter 2 días sáb 02/06/18 mar 05/06/18 60% 94
96 LOW VOLTAGE POWER 46.55 días mié 18/04/18 jue 14/06/18 36%
97 Distribution board 3 días mié 18/04/18 vie 20/04/18 0%
98 Single phase outlets (inclued cabling) 4 días sáb 09/06/18 jue 14/06/18 70% 97

Página 2
xx xx
Id Nombre de tarea Duración Comienzo Fin % completado Predecesoras
abril 2018 mayo 2018 junio 2018
17 20 23 26 29 02 05 08 11 14 17 20 23 26 29 01 04 07 10 13 16 19
99 LED-type recessed in suspended ceiling 5 días lun 04/06/18 sáb 09/06/18 65% 84
100 LED-type fixed on concrete 5 días sáb 02/06/18 vie 08/06/18 0% 85
101 NETWORK 4 días jue 14/06/18 mar 19/06/18 0%
102 Switch & outlet 4 días jue 14/06/18 mar 19/06/18 0% 98,97
103 ZONE 4 (+0.00 12-17&N-O: laboratory, office&rooms) 33.25 días mié 02/05/18 lun 11/06/18 99%
104 INTERIOR LAYOUT 4 días mié 23/05/18 lun 28/05/18 100%
105 Fixed partition & solid doors 2 días mié 23/05/18 jue 24/05/18 100% 110
106 Water resistance 2 días vie 25/05/18 lun 28/05/18 100% 105
107 COATING 32.45 días mié 02/05/18 sáb 09/06/18 99%
108 Removable suspendend ceiling 4 días lun 04/06/18 vie 08/06/18 98% 84
109 Tile wall covering 18.2 días vie 18/05/18 sáb 09/06/18 100% 108CC+3 días
110 Painted wall 3 días vie 18/05/18 mar 22/05/18 90% 109CC
111 Floor covering with epoxy 12 días mié 02/05/18 mié 16/05/18 100%
112 HVAC 5 días mié 23/05/18 mar 29/05/18 100%
113 Ceiling mounted casettes 2 días sáb 26/05/18 mar 29/05/18 100% 114
114 Single flow system all included station, ducts, grid… 3 días mié 23/05/18 vie 25/05/18 100% 110
115 LOW VOLTAGE POWER 16 días mié 23/05/18 lun 11/06/18 100%
116 Distribution board 2 días mié 23/05/18 jue 24/05/18 100% 110
117 Single phase outlets (inclued cabling) 2 días vie 25/05/18 lun 28/05/18 100% 116
118 LED-type recessed in suspended ceiling 2 días vie 08/06/18 lun 11/06/18 100% 108
119 NETWORK 2 días mar 29/05/18 jue 31/05/18 100%
120 Switch & outlets 2 días mar 29/05/18 jue 31/05/18 100% 117,116
121 ZONE 5 (-5.50 18-19&H-N: rooms, offices&sanitary/ 30 días vie 11/05/18 sáb 16/06/18 41%
14-17&H-N: LVSB room, transformer area&offices/
3-7&K-L: transformer&boosting area)
122 INTERIOR LAYOUT 8 días mar 29/05/18 jue 07/06/18 27%
123 Fixed partitions without glass and solid doors 4 días mar 29/05/18 sáb 02/06/18 25% 130
124 Fixed partitions with glass and solid doors 4 días lun 04/06/18 jue 07/06/18 0% 123
125 Water resistance 2 días jue 31/05/18 sáb 02/06/18 85% 123CC+2 días
126 COATING 30 días vie 11/05/18 sáb 16/06/18 73%
127 Removable suspended ceiling 2 días vie 11/05/18 lun 14/05/18 33%
128 Painted ceiling 10 días sáb 12/05/18 jue 24/05/18 20% 127CC+1 día
129 Tile wall covering 4 días mié 16/05/18 lun 21/05/18 95% 127CC+3 días,128CC+3 días
130 Painted wall 10 días jue 17/05/18 mar 29/05/18 85% 129CC+1 día
131 Technical raised floor 2 días mar 29/05/18 jue 31/05/18 100% 129,130
132 Floor covering with epoxy 13 días jue 31/05/18 sáb 16/06/18 100% 131
133 HVAC 13 días mar 29/05/18 jue 14/06/18 0%
134 Single flow system all included station, ducts, grid… 10 días mar 29/05/18 lun 11/06/18 0% 130
135 Natural ventilation by grid included filter 1 día lun 11/06/18 mar 12/06/18 0% 134
136 Fan coil 8 días vie 01/06/18 mar 12/06/18 0% 134CC+3 días
137 Ceiling mounted cassetes 2 días mar 12/06/18 jue 14/06/18 0% 135
138 LOW VOLTAGE POWER 20 días lun 14/05/18 mié 06/06/18 23%
139 Distribution board 4 días mar 29/05/18 sáb 02/06/18 0% 130
140 Single phase outlets (inclued cabling) 5 días mar 29/05/18 lun 04/06/18 90% 139CC
141 Three phases outlets (inclued cabling) 2 días mar 05/06/18 mié 06/06/18 0% 140
142 LED-type recessed in suspended ceiling 4 días lun 14/05/18 vie 18/05/18 0% 127
143 LED-type fixed on concrete 5 días jue 24/05/18 mié 30/05/18 0% 128
144 NETWORK 6 días jue 07/06/18 jue 14/06/18 10%
145 Switch & outlets 6 días jue 07/06/18 jue 14/06/18 10% 140,141,139
146 STEEL WORK 6 días lun 21/05/18 lun 28/05/18 85%
147 Mesh partition (doors incl.) 6 días lun 21/05/18 lun 28/05/18 85%

Página 3
xx xx
Id Nombre de tarea Duración Comienzo Fin % completado Predecesoras
abril 2018 mayo 2018 junio 2018
17 20 23 26 29 02 05 08 11 14 17 20 23 26 29 01 04 07 10 13 16 19
148 ZONE 6 (-5.50 22-23&H-K: IS machine training room ) 3 días mar 29/05/18 vie 01/06/18 97%
149 COATING 3 días mar 29/05/18 vie 01/06/18 97%
150 Painted wall 2 días mar 29/05/18 jue 31/05/18 95% 130
151 Floor covering with epoxy 1 día jue 31/05/18 vie 01/06/18 100% 150
152 ZONE 7 (-5.50 phase 4 areas) 33 días vie 27/04/18 jue 07/06/18 52%
153 INTERIOR LAYOUT 3 días vie 11/05/18 mar 15/05/18 25%
154 Water resistance 3 días vie 11/05/18 mar 15/05/18 25% 158
155 COATING 33 días vie 27/04/18 jue 07/06/18 64%
156 Removable suspendend ceiling 7 días mar 15/05/18 mié 23/05/18 0% 127CC+3 días
157 Tile wall covering 4 días mié 23/05/18 lun 28/05/18 0% 156
158 Painted wall & ceiling 10 días vie 27/04/18 jue 10/05/18 95% 157CC-20 días
159 Technical raised floor (40-42&P-Q LVSB room) 5 días lun 28/05/18 sáb 02/06/18 100% 157,158
160 Floor covering with epoxy 6 días jue 31/05/18 jue 07/06/18 100% 159CC+3 días
161 HVAC 9 días vie 11/05/18 mar 22/05/18 23%
162 Ceiling mounted casettes 2 días vie 11/05/18 lun 14/05/18 90% 158
163 Fan coil 1 día lun 14/05/18 mar 15/05/18 25% 162
164 Single flow system all included station, ducts, grid… 2 días mar 15/05/18 jue 17/05/18 0% 163
165 Natural ventilation by grid included filter 4 días jue 17/05/18 mar 22/05/18 0% 164CC+2 días
166 LOW VOLTAGE POWER 13 días vie 11/05/18 sáb 26/05/18 40%
167 Distribution board 2 días vie 11/05/18 lun 14/05/18 0% 158
168 Single phase outlets (inclued cabling) 3 días mié 16/05/18 sáb 19/05/18 85% 167
169 LED-type recessed in suspended ceiling 3 días mié 23/05/18 sáb 26/05/18 35% 156
170 LED-type fixed on concrete 1 día mié 23/05/18 jue 24/05/18 0% 156
171 NETWORK 3 días sáb 19/05/18 mié 23/05/18 47%
172 Switch & outlets 3 días sáb 19/05/18 mié 23/05/18 47% 167,168
173 STEEL WORK 2 días lun 28/05/18 mié 30/05/18 100%
174 Mesh partition (doors incl.) 2 días lun 28/05/18 mié 30/05/18 100% 147
175 FPB 27.5 días mié 18/04/18 mar 22/05/18 27%
176 INTERIOR LAYOUT & FITTINGS 4 días mar 15/05/18 vie 18/05/18 20%
177 Fixed partition & solid doors 2 días mar 15/05/18 mié 16/05/18 0% 183
178 Fixed partitions without glass, and solid doors 2 días mar 15/05/18 mié 16/05/18 60% 177CC
179 Water resistance 2 días jue 17/05/18 vie 18/05/18 0% 177,178
180 COATING 21 días mié 18/04/18 lun 14/05/18 23%
181 Removable suspendend ceiling 4 días lun 07/05/18 jue 10/05/18 25%
182 Tile wall covering 5 días lun 30/04/18 lun 07/05/18 60% 183CC+10 días
183 Painted wall & ceiling 21 días mié 18/04/18 lun 14/05/18 30%
184 PVC-type floor covering & epoxy 15 días mié 18/04/18 lun 07/05/18 0%
185 HVAC 7 días jue 26/04/18 sáb 05/05/18 51%
186 Single flow system all included station, ducts, grid… 6 días jue 26/04/18 vie 04/05/18 0% 183CC+7 días
187 Ceiling mounted casettes 7 días jue 26/04/18 sáb 05/05/18 95% 186CC
188 LOW VOLTAGE POWER 14.75 días lun 30/04/18 vie 18/05/18 28%
189 Distribution board 5 días lun 30/04/18 lun 07/05/18 0% 183CC+3 días
190 Single phase outlets (inclued cabling) 8 días lun 07/05/18 mié 16/05/18 70% 189
191 LED-type recessed in suspended ceiling 6 días vie 11/05/18 vie 18/05/18 0% 181
192 LED-type fixed on concrete 1 día vie 11/05/18 vie 11/05/18 0% 181
193 NETWORK 5 días mié 16/05/18 mar 22/05/18 0%
194 Switch & outlets 5 días mié 16/05/18 mar 22/05/18 0% 190,189
195 Activites closure 0 días mar 19/06/18 mar 19/06/18 0% 9,15,59,80,103,121,148,152,37,175 19/0