Anda di halaman 1dari 3

STF PALONG TIMUR REV.

04 ALL NON-RUN Classic Schedule Layout 16-Apr-18 05:03 PM


Activity ID Activity Name Original Remaining Total Start Finish October 2017 November 2017 December 2017 January 2018 February 2018 March 2018 April 2018 May 2018 June 2018 July 2018 August 2018
Duration Duration Float 05
01 08 15 22 29 05 12 19 26 03 10 17 24 31 07 14 21 28 04 11 18 25 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 01 08 15 22 29
268.6d 268.6d 3.4d 02-Oct-17 08:00 AM 27-Jun-18 01:00 27-Jun-18 01:00 PM, STF PALONG TIMUR REV.04 ALL NON-RUN
STF PALONG TIMUR REV.04 ALL NON-RUN
PM
225.5d 225.5d 2.5d 02-Oct-17 08:00 AM 27-Jun-18 01:00 PM 27-Jun-18 01:00 PM, Milestone
Milestone
STF1000 Milestone Start STF 0.0d 0.0d 3.0d 02-Oct-17 08:00 AM* 02-Oct-17 08:00 AM
STF1010 Milestone Finish STF 0.0d 0.0d 2.5d 27-Jun-18 01:00 PM* 27-Jun-18 01:00 PM
32.0d 32.0d 3.0d 02-Oct-17 08:00 AM 07-Nov-17 05:00 PM 07-Nov-17 05:00 PM, General & Preliminaries
General & Preliminaries
Documentation 32.0d 32.0d 3.0d 02-Oct-17 08:00 AM 07-Nov-17 05:00 PM 07-Nov-17 05:00 PM, Documentation

Preparation & Submission 32.0d 32.0d 3.0d 02-Oct-17 08:00 AM 07-Nov-17 05:00 PM 07-Nov-17 05:00 PM, Preparation & Submission
STF1020 Preparation of Performance Bond 14.0d 14.0d 3.0d 02-Oct-17 08:00 AM 17-Oct-17 05:00 PM
STF1030 Preparation of Insurances Policies / Public Liability / Workmen's Compensation
14.0d 14.0d 3.0d 02-Oct-17 08:00 AM 17-Oct-17 05:00 PM
STF1040 Preparation & Submission of Levy of CIDB 14.0d 14.0d 3.0d 02-Oct-17 08:00 AM 17-Oct-17 05:00 PM
STF1050 Site Registration of JKKP (DOSH) 14.0d 14.0d 3.0d 02-Oct-17 08:00 AM 17-Oct-17 05:00 PM
STF1060 Submission Copy of SPAN Certificate 14.0d 14.0d 3.0d 02-Oct-17 08:00 AM 17-Oct-17 05:00 PM
STF1070 Preparation & Submission of Lithography Expenses 14.0d 14.0d 3.0d 02-Oct-17 08:00 AM 17-Oct-17 05:00 PM
STF1080 Preparation & Submission of PQP / Method Statements 14.0d 14.0d 3.0d 02-Oct-17 08:00 AM 17-Oct-17 05:00 PM
STF1090 Preparation of Works (Contractor Requirements) 18.0d 18.0d 3.0d 18-Oct-17 08:00 AM 07-Nov-17 05:00 PM
STF1100 Preparation of Works (Engineers / S.O / PD's Requirements) 18.0d 18.0d 3.0d 18-Oct-17 08:00 AM 07-Nov-17 05:00 PM
STF1110 Preparation of Works (General Obligation, Project Requirements) 18.0d 18.0d 3.0d 18-Oct-17 08:00 AM 07-Nov-17 05:00 PM
STF1120 Preparation of Works (Authorities Requirements) 18.0d 18.0d 3.0d 18-Oct-17 08:00 AM 07-Nov-17 05:00 PM
STF1130 Preparation of Works (Environmental Protection & Enhancement)18.0d 18.0d 3.0d 18-Oct-17 08:00 AM 07-Nov-17 05:00 PM
188.5d 188.5d 12.5d 11-Dec-17 08:00 AM 17-Jun-18 12:00 PM 17-Jun-18 12:00 PM, Civil & Structures
Civil & Structures
Underground Tank & Building 188.5d 188.5d 12.5d 11-Dec-17 08:00 AM 17-Jun-18 12:00 PM 17-Jun-18 12:00 PM, Underground Tank & Building

Wash Water Collection & Sludge Balancing Tank 145.0d 145.0d 56.0d 11-Dec-17 08:00 AM 04-May-18 05:00 PM 04-May-18 05:00 PM, Wash Water Collection & Sludge Balancing Tank

Site Measurement & Site Preparation 55.0d 55.0d 3.0d 11-Dec-17 08:00 AM 03-Feb-18 05:00 PM 03-Feb-18 05:00 PM, Site Measurement & Site Preparation
STF1140 Site survey 11.0d 11.0d 3.0d 11-Dec-17 08:00 AM* 21-Dec-17 05:00 PM
STF1150 Site clearance 14.0d 14.0d 3.0d 22-Dec-17 08:00 AM* 04-Jan-18 05:00 PM
STF1160 Excavation, levelling & compaction works 26.0d 26.0d 3.0d 05-Jan-18 08:00 AM* 30-Jan-18 05:00 PM
STF1170 Install formwork 3.0d 3.0d 3.0d 31-Jan-18 08:00 AM* 02-Feb-18 05:00 PM
STF1180 Lay of 75mm thick lean concrete 1.0d 1.0d 3.0d 03-Feb-18 08:00 AM* 03-Feb-18 05:00 PM
Slab for All excluding Drywells 19.0d 19.0d 3.0d 04-Feb-18 08:00 AM 22-Feb-18 05:00 PM 22-Feb-18 05:00 PM, Slab for All excluding Drywells
STF1190 Erect formwork, install reinforcement, kicker & waterstop 15.0d 15.0d 3.0d 04-Feb-18 08:00 AM* 18-Feb-18 05:00 PM
STF1200 Inspection 1.0d 1.0d 3.0d 19-Feb-18 08:00 AM* 19-Feb-18 05:00 PM
STF1210 Concreting & curing works 2.0d 2.0d 3.0d 20-Feb-18 08:00 AM* 21-Feb-18 05:00 PM
STF1220 Dismantle formwork 1.0d 1.0d 3.0d 22-Feb-18 08:00 AM* 22-Feb-18 05:00 PM
Slab for Drywells 9.0d 9.0d 3.0d 23-Feb-18 08:00 AM 03-Mar-18 05:00 PM 03-Mar-18 05:00 PM, Slab for Drywells
STF1230 To excavate, level & compact 1.0d 1.0d 3.0d 23-Feb-18 08:00 AM* 23-Feb-18 05:00 PM
STF1240 Lay of 75mm thick lean concrete 1.0d 1.0d 3.0d 24-Feb-18 08:00 AM* 24-Feb-18 05:00 PM
STF1250 Erect formwork, install reinforcement, kicker & waterstop 3.0d 3.0d 3.0d 25-Feb-18 08:00 AM* 27-Feb-18 05:00 PM
STF1260 Inspection 1.0d 1.0d 3.0d 28-Feb-18 08:00 AM* 28-Feb-18 05:00 PM
STF1270 Concreting & curing works 2.0d 2.0d 3.0d 01-Mar-18 08:00 AM* 02-Mar-18 05:00 PM
STF1280 Dismantle formwork 1.0d 1.0d 3.0d 03-Mar-18 08:00 AM* 03-Mar-18 05:00 PM
Wall '1' - 1st Lift (1.5m) 11.0d 11.0d 3.0d 04-Mar-18 08:00 AM 14-Mar-18 05:00 PM 14-Mar-18 05:00 PM, Wall '1' - 1st Lift (1.5m)
STF1290 Erect scaffold & stagging 1.0d 1.0d 3.0d 04-Mar-18 08:00 AM* 04-Mar-18 05:00 PM
STF1300 Erect formwork, install reinforcement, kicker & waterstop 4.0d 4.0d 3.0d 05-Mar-18 08:00 AM* 08-Mar-18 05:00 PM
STF1310 Inspection 1.0d 1.0d 3.0d 09-Mar-18 08:00 AM* 09-Mar-18 05:00 PM
STF1320 Concreting works 1.0d 1.0d 3.0d 10-Mar-18 08:00 AM* 10-Mar-18 05:00 PM
STF1330 Curing works 3.0d 3.0d 3.0d 11-Mar-18 08:00 AM* 13-Mar-18 05:00 PM
STF1340 Dismantle formwork, scaffold & stagging 1.0d 1.0d 3.0d 14-Mar-18 08:00 AM* 14-Mar-18 05:00 PM
Wall '2' - 1st Lift (1.5m & 2.4m) 13.0d 13.0d 3.0d 15-Mar-18 08:00 AM 27-Mar-18 05:00 PM 27-Mar-18 05:00 PM, Wall '2' - 1st Lift (1.5m & 2.4m)
STF1350 Erect scaffold & stagging 1.0d 1.0d 3.0d 15-Mar-18 08:00 AM* 15-Mar-18 05:00 PM
STF1360 Erect formwork, install reinforcement, kicker & waterstop 4.0d 4.0d 3.0d 16-Mar-18 08:00 AM* 19-Mar-18 05:00 PM
STF1370 Install 4 units of 100mm dia. Pipes 2.0d 2.0d 3.0d 20-Mar-18 08:00 AM* 21-Mar-18 05:00 PM
STF1380 Inspection 1.0d 1.0d 3.0d 22-Mar-18 08:00 AM* 22-Mar-18 05:00 PM
STF1390 Concreting works 1.0d 1.0d 3.0d 23-Mar-18 08:00 AM* 23-Mar-18 05:00 PM
STF1400 Curing works 3.0d 3.0d 3.0d 24-Mar-18 08:00 AM* 26-Mar-18 05:00 PM
STF1410 Dismantle formwork, scaffold & stagging 1.0d 1.0d 3.0d 27-Mar-18 08:00 AM* 27-Mar-18 05:00 PM
Wall '1' - 2nd Lift (2.1m) 12.0d 12.0d 3.0d 28-Mar-18 08:00 AM 08-Apr-18 05:00 PM 08-Apr-18 05:00 PM, Wall '1' - 2nd Lift (2.1m)
STF1420 Erect scaffold & stagging 1.0d 1.0d 3.0d 28-Mar-18 08:00 AM* 28-Mar-18 05:00 PM
STF1430 Erect formwork, install reinforcement 4.0d 4.0d 3.0d 29-Mar-18 08:00 AM* 01-Apr-18 05:00 PM
STF1440 Install 2 units of 300mm dia. of pipes (level - 22.50) 1.0d 1.0d 3.0d 02-Apr-18 08:00 AM* 02-Apr-18 05:00 PM
STF1450 Inspection 1.0d 1.0d 3.0d 03-Apr-18 08:00 AM* 03-Apr-18 05:00 PM
STF1460 Concreting works 1.0d 1.0d 3.0d 04-Apr-18 08:00 AM* 04-Apr-18 05:00 PM
STF1470 Curing works 3.0d 3.0d 3.0d 05-Apr-18 08:00 AM* 07-Apr-18 05:00 PM
STF1480 Dismantle formwork, scaffold & stagging 1.0d 1.0d 3.0d 08-Apr-18 08:00 AM* 08-Apr-18 05:00 PM
Wall '2' - 2nd Lift (2.1m, 1.45m, 2.15m) 12.0d 12.0d 3.0d 09-Apr-18 08:00 AM 20-Apr-18 05:00 PM 20-Apr-18 05:00 PM, Wall '2' - 2nd Lift (2.1m, 1.45m, 2.15m)
STF1490 Erect scaffold & stagging 1.0d 1.0d 3.0d 09-Apr-18 08:00 AM* 09-Apr-18 05:00 PM
STF1500 Erect formwork, install reinforcement 5.0d 5.0d 3.0d 10-Apr-18 08:00 AM* 14-Apr-18 05:00 PM
STF1510 Inspection 1.0d 1.0d 3.0d 15-Apr-18 08:00 AM* 15-Apr-18 05:00 PM
STF1520 Concreting works 1.0d 1.0d 3.0d 16-Apr-18 08:00 AM* 16-Apr-18 05:00 PM
STF1530 Curing works 3.0d 3.0d 3.0d 17-Apr-18 08:00 AM* 19-Apr-18 05:00 PM
STF1540 Dismantle formwork, scaffold & stagging 1.0d 1.0d 3.0d 20-Apr-18 08:00 AM* 20-Apr-18 05:00 PM
Cantilever Beam, Walkway Slab & Overflow Slab/Wall 12.0d 12.0d 3.0d 09-Apr-18 08:00 AM 20-Apr-18 05:00 PM 20-Apr-18 05:00 PM, Cantilever Beam, Walkway Slab & Overflow Slab/Wall
STF1550 Erect scaffold & stagging 1.0d 1.0d 3.0d 09-Apr-18 08:00 AM* 09-Apr-18 05:00 PM
STF1560 Erect & install formwork, t-props, soffit and reinforcement 4.0d 4.0d 3.0d 10-Apr-18 08:00 AM* 13-Apr-18 05:00 PM
STF1570 Install 2 units of 200mm dia. of pipes at Overflow Wall A & C 1.0d 1.0d 3.0d 14-Apr-18 08:00 AM* 14-Apr-18 05:00 PM
STF1580 Inspection 1.0d 1.0d 3.0d 15-Apr-18 08:00 AM* 15-Apr-18 05:00 PM
STF1590 Concreting works 1.0d 1.0d 3.0d 16-Apr-18 08:00 AM* 16-Apr-18 05:00 PM
STF1600 Curing works 3.0d 3.0d 3.0d 17-Apr-18 08:00 AM* 19-Apr-18 05:00 PM
STF1610 Dismantle formwork, t-props, soffit, scaffold & stagging 1.0d 1.0d 3.0d 20-Apr-18 08:00 AM* 20-Apr-18 05:00 PM
Partial Backfilling (Drywells Area) 6.0d 6.0d 3.0d 21-Apr-18 08:00 AM 26-Apr-18 05:00 PM 26-Apr-18 05:00 PM, Partial Backfilling (Drywells Area)
STF1620 Repair of cold joints & honeycomb at affected area 1.0d 1.0d 3.0d 21-Apr-18 08:00 AM* 21-Apr-18 05:00 PM
STF1630 Partial backfilling & compaction (1st stage) 1.0d 1.0d 3.0d 22-Apr-18 08:00 AM* 22-Apr-18 05:00 PM
STF1640 Reinstate existing sump 2.0d 2.0d 3.0d 23-Apr-18 08:00 AM* 24-Apr-18 05:00 PM
STF1650 Reinstate existing sewer pipes 1.0d 1.0d 3.0d 25-Apr-18 08:00 AM* 25-Apr-18 05:00 PM
STF1660 Partial backfilling & compaction (2nd stage) 1.0d 1.0d 3.0d 26-Apr-18 08:00 AM* 26-Apr-18 05:00 PM
Repair of Cold Joints, Waterproofing & Painting 4.0d 4.0d 56.0d 22-Apr-18 08:00 AM 25-Apr-18 05:00 PM 25-Apr-18 05:00 PM, Repair of Cold Joints, Waterproofing & Painting
STF1670 Repair of cold joints & honeycomb 2.0d 2.0d 56.0d 22-Apr-18 08:00 AM* 23-Apr-18 05:00 PM
STF1680 Waterproofing of internal wall 1.0d 1.0d 56.0d 24-Apr-18 08:00 AM* 24-Apr-18 05:00 PM
STF1690 Painting (1 coat resistant primer & 2 coats anti-fungus) 1.0d 1.0d 56.0d 24-Apr-18 08:00 AM* 24-Apr-18 05:00 PM
STF1700 Cleanup site 1.0d 1.0d 56.0d 25-Apr-18 08:00 AM* 25-Apr-18 05:00 PM
Water Tighness Testing & Backfilling 9.0d 9.0d 56.0d 26-Apr-18 08:00 AM 04-May-18 05:00 PM 04-May-18 05:00 PM, Water Tighness Testing & Backfilling
STF1710 To fill up WWCT & SBT with water 1.0d 1.0d 56.0d 26-Apr-18 08:00 AM* 26-Apr-18 05:00 PM
STF1720 Monitoring 3.0d 3.0d 56.0d 27-Apr-18 08:00 AM* 29-Apr-18 05:00 PM
STF1730 To backfill & compact outer perimeter of WWCT & SBT 5.0d 5.0d 56.0d 30-Apr-18 08:00 AM* 04-May-18 05:00 PM
Dewatering Platform (Geotube) 48.0d 48.0d 11.0d 22-Apr-18 08:00 AM 08-Jun-18 05:00 PM 08-Jun-18 05:00 PM, Dewatering Platform (Geotube)

Excavation Works & Hardcore 5.0d 5.0d 10.1d 22-Apr-18 08:00 AM 26-Apr-18 05:00 PM 26-Apr-18 05:00 PM, Excavation Works & Hardcore
STF1740 Site measurement & marking 1.0d 1.0d 10.1d 22-Apr-18 08:00 AM* 22-Apr-18 05:00 PM
STF1750 To excavate, level & compact ground 3.0d 3.0d 10.1d 23-Apr-18 08:00 AM* 25-Apr-18 05:00 PM
STF1760 To lay, spread & compact Crusher-run as hardcore (0.3m Thk) 1.0d 1.0d 10.1d 26-Apr-18 08:00 AM* 26-Apr-18 05:00 PM
Drain (Base) 10.0d 10.0d 10.9d 27-Apr-18 08:00 AM 06-May-18 05:00 PM 06-May-18 05:00 PM, Drain (Base)
STF1770 Install formwork, lay of 50mm thick lean concrete 2.0d 2.0d 10.1d 27-Apr-18 08:00 AM* 28-Apr-18 05:00 PM
STF1780 Erect formwork, install reinforcement 5.0d 5.0d 15.5d 28-Apr-18 07:00 PM* 01-May-18 11:00 PM
STF1790 Inspection 1.0d 1.0d 10.8d 02-May-18 08:00 AM* 02-May-18 05:00 PM
STF1800 Concreting works 2.0d 2.0d 10.8d 03-May-18 08:00 AM* 04-May-18 05:00 PM
STF1810 Curing works 1.0d 1.0d 10.8d 05-May-18 08:00 AM* 05-May-18 05:00 PM
STF1820 Dismantle formwork 1.0d 1.0d 10.8d 06-May-18 08:00 AM* 06-May-18 05:00 PM
Drain (Wall - 2 sides) 10.5d 10.5d 10.9d 06-May-18 07:00 PM 17-May-18 12:00 PM 17-May-18 12:00 PM, Drain (Wall - 2 sides)
STF1830 Erect formwork, install reinforcement 7.0d 7.0d 16.1d 06-May-18 07:00 PM* 11-May-18 12:00 PM
STF1840 Inspection 1.0d 1.0d 10.9d 11-May-18 01:00 PM* 12-May-18 12:00 PM
STF1850 Concreting works 2.0d 2.0d 10.9d 12-May-18 01:00 PM* 14-May-18 12:00 PM
STF1860 Curing works 1.0d 1.0d 10.9d 14-May-18 01:00 PM* 15-May-18 12:00 PM
STF1870 Dismantle formwork & backfilling works 2.0d 2.0d 10.9d 15-May-18 01:00 PM* 17-May-18 12:00 PM
Ground Slab 11.4d 11.4d 12.0d 17-May-18 01:00 PM 28-May-18 05:00 PM 28-May-18 05:00 PM, Ground Slab

Primary Baseline Remaining Work Baseline Milestone Page 1 of 3 TASK filter: All Activities
Actual Work Critical Remaining Work Summary © Oracle Corporation
STF PALONG TIMUR REV.04 ALL NON-RUN Classic Schedule Layout 16-Apr-18 05:03 PM
Activity ID Activity Name Original Remaining Total Start Finish October 2017 November 2017 December 2017 January 2018 February 2018 March 2018 April 2018 May 2018 June 2018 July 2018 August 2018
Duration Duration Float 05
01 08 15 22 29 05 12 19 26 03 10 17 24 31 07 14 21 28 04 11 18 25 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 01 08 15 22 29
STF1880 Install formwork, lay of 50mm thick lean concrete 2.0d 2.0d 11.9d 17-May-18 01:00 PM* 19-May-18 12:00 PM
STF1890 Erect formwork, install reinforcement 7.0d 7.0d 17.8d 19-May-18 01:00 PM* 23-May-18 11:00 PM
STF1900 Inspection 1.0d 1.0d 12.0d 24-May-18 08:00 AM* 24-May-18 05:00 PM
STF1910 Concreting works 2.0d 2.0d 12.0d 25-May-18 08:00 AM* 26-May-18 05:00 PM
STF1920 Curing works 1.0d 1.0d 12.0d 27-May-18 08:00 AM* 27-May-18 05:00 PM
STF1930 Dismantle formwork 1.0d 1.0d 12.0d 28-May-18 08:00 AM* 28-May-18 05:00 PM
Ramp 12.4d 12.4d 11.0d 17-May-18 01:00 PM 29-May-18 05:00 PM 29-May-18 05:00 PM, Ramp
STF1940 Install formwork, lay of 50mm thick lean concrete 2.0d 2.0d 10.9d 17-May-18 01:00 PM* 19-May-18 12:00 PM
STF1950 Erect formwork, install reinforcement 4.0d 4.0d 16.3d 19-May-18 01:00 PM* 21-May-18 11:00 PM
STF1960 Inspection 1.0d 1.0d 11.0d 22-May-18 08:00 AM* 22-May-18 05:00 PM
STF1970 Concreting works 2.0d 2.0d 11.0d 23-May-18 08:00 AM* 24-May-18 05:00 PM
STF1980 Curing works 1.0d 1.0d 11.0d 25-May-18 08:00 AM* 25-May-18 05:00 PM
STF1990 Dismantle formwork 1.0d 1.0d 11.0d 26-May-18 08:00 AM* 26-May-18 05:00 PM
STF2000 Install cheuque plate covers 1.0d 1.0d 11.0d 27-May-18 08:00 AM* 27-May-18 05:00 PM
STF2010 To clean up site condition including levelling & compaction 2.0d 2.0d 11.0d 28-May-18 08:00 AM* 29-May-18 05:00 PM
Geotube 10.0d 10.0d 11.0d 30-May-18 08:00 AM 08-Jun-18 05:00 PM 08-Jun-18 05:00 PM, Geotube
STF2020 Delivery of 30 units of geotube to site 3.0d 3.0d 11.0d 30-May-18 08:00 AM* 01-Jun-18 05:00 PM
STF2030 Setting of site ready for installation works 1.0d 1.0d 11.0d 02-Jun-18 08:00 AM* 02-Jun-18 05:00 PM
STF2040 Installation of geotube and necessarry works 5.0d 5.0d 11.0d 03-Jun-18 08:00 AM* 07-Jun-18 05:00 PM
STF2050 Cleanup site 1.0d 1.0d 11.0d 08-Jun-18 08:00 AM* 08-Jun-18 05:00 PM
Polymer Building 51.5d 51.5d 12.5d 27-Apr-18 08:00 AM 17-Jun-18 12:00 PM 17-Jun-18 12:00 PM, Polymer Building

Footing (1m x 1m - 0.3m Thk) & Stump (0.3m x 0.3m - 0.45m Thk) 9.0d 9.0d 3.0d 27-Apr-18 08:00 AM 05-May-18 05:00 PM 05-May-18 05:00 PM, Footing (1m x 1m - 0.3m Thk) & Stump (0.3m x 0.3m - 0.45m Thk)
STF2060 To excavate, level & compact ground to receive foundation 1.0d 1.0d 3.0d 27-Apr-18 08:00 AM* 27-Apr-18 05:00 PM
STF2070 Install formwork, lay of 50mm thick lean concrete 1.0d 1.0d 3.0d 28-Apr-18 08:00 AM* 28-Apr-18 05:00 PM
STF2080 Erect formwork & install reinforcement 3.0d 3.0d 4.5d 28-Apr-18 07:00 PM* 30-Apr-18 05:00 PM
STF2090 Inspection 1.0d 1.0d 3.0d 30-Apr-18 08:00 AM* 30-Apr-18 05:00 PM
STF2100 Concreting works 1.0d 1.0d 3.0d 01-May-18 08:00 AM* 01-May-18 05:00 PM
STF2110 Curing works 2.0d 2.0d 3.0d 02-May-18 08:00 AM* 03-May-18 05:00 PM
STF2120 Dismantle formwork 1.0d 1.0d 3.0d 04-May-18 08:00 AM* 04-May-18 05:00 PM
STF2130 Backfilling & compaction works to the level of top stump 1.0d 1.0d 3.0d 05-May-18 08:00 AM* 05-May-18 05:00 PM
Ground Beam (0.3m x 0.6m) & Ground Slab (0.2m Thk) 10.0d 10.0d 3.0d 06-May-18 08:00 AM 15-May-18 05:00 PM 15-May-18 05:00 PM, Ground Beam (0.3m x 0.6m) & Ground Slab (0.2m Thk)
STF2140 Erect formwork surround the outer of stump 1.0d 1.0d 3.0d 06-May-18 08:00 AM* 06-May-18 05:00 PM
STF2150 Backfilling & compaction works to the level of bottom slab 2.0d 2.0d 3.0d 07-May-18 08:00 AM* 08-May-18 05:00 PM
STF2160 Install formwork, lay of 50mm thick lean concrete 1.0d 1.0d 3.0d 09-May-18 08:00 AM* 09-May-18 05:00 PM
STF2170 Install reinforcement both ground beam & slab 3.0d 3.0d 4.4d 09-May-18 07:00 PM* 11-May-18 08:00 PM
STF2180 Inspection 1.0d 1.0d 3.0d 11-May-18 08:00 AM* 12-May-18 08:00 AM
STF2190 Concreting works 1.0d 1.0d 3.0d 12-May-18 08:00 AM* 12-May-18 05:00 PM
STF2200 Curing works 2.0d 2.0d 3.0d 13-May-18 08:00 AM* 14-May-18 05:00 PM
STF2210 Dismantle formwork 1.0d 1.0d 3.0d 15-May-18 08:00 AM* 15-May-18 05:00 PM
Column - 5.5m (0.25mm x 0.25mm) 8.0d 8.0d 5.0d 15-May-18 08:00 AM 22-May-18 05:00 PM 22-May-18 05:00 PM, Column - 5.5m (0.25mm x 0.25mm)
STF2220 Install reinforcement 2.0d 2.0d 4.4d 15-May-18 08:00 AM* 16-May-18 12:00 PM
STF2230 Erect formwork & bracing 1.0d 1.0d 4.4d 16-May-18 01:00 PM* 16-May-18 11:00 PM
STF2240 Inspection 1.0d 1.0d 5.0d 16-May-18 08:00 AM* 17-May-18 08:00 AM
STF2250 Concreting works 2.0d 2.0d 5.0d 17-May-18 08:00 AM* 18-May-18 05:00 PM
STF2260 Curing works 3.0d 3.0d 5.0d 19-May-18 08:00 AM* 21-May-18 05:00 PM
STF2270 Dismantle formwork & bracing 1.0d 1.0d 5.0d 22-May-18 08:00 AM* 22-May-18 05:00 PM
Roof Beam (0.25mm x 0.5mm) 8.0d 8.0d 3.0d 17-May-18 08:00 AM 24-May-18 05:00 PM 24-May-18 05:00 PM, Roof Beam (0.25mm x 0.5mm)
STF2280 Erect scaffold, stagging, t-prox & soffit 1.0d 1.0d 4.4d 17-May-18 08:00 AM* 17-May-18 05:00 PM
STF2290 Install reinforcement including L-Plates for roof truss 2.0d 2.0d 4.4d 17-May-18 07:00 PM* 19-May-18 09:00 AM
STF2300 Erect formwork 1.0d 1.0d 4.4d 19-May-18 09:00 AM* 19-May-18 08:00 PM
STF2310 Inspection 1.0d 1.0d 3.0d 19-May-18 08:00 AM* 20-May-18 08:00 AM
STF2320 Concreting works 1.0d 1.0d 3.0d 20-May-18 08:00 AM* 20-May-18 05:00 PM
STF2330 Curing works 3.0d 3.0d 3.0d 21-May-18 08:00 AM* 23-May-18 05:00 PM
STF2340 Dismantle scaffold, stagging, t-prox, soffit & formwork 1.0d 1.0d 3.0d 24-May-18 08:00 AM* 24-May-18 05:00 PM
Intermediate Beam (0.25mm x 0.5mm) 8.0d 8.0d 3.0d 17-May-18 08:00 AM 24-May-18 05:00 PM 24-May-18 05:00 PM, Intermediate Beam (0.25mm x 0.5mm)
STF2350 Erect scaffold, stagging, t-prox & soffit 1.0d 1.0d 4.4d 17-May-18 08:00 AM* 17-May-18 05:00 PM
STF2360 Install reinforcement 2.0d 2.0d 4.4d 17-May-18 07:00 PM* 19-May-18 09:00 AM
STF2370 Erect formwork 1.0d 1.0d 4.4d 19-May-18 09:00 AM* 19-May-18 08:00 PM
STF2380 Inspection 1.0d 1.0d 3.0d 19-May-18 08:00 AM* 20-May-18 08:00 AM
STF2390 Concreting works 1.0d 1.0d 3.0d 20-May-18 08:00 AM* 20-May-18 05:00 PM
STF2400 Curing works 3.0d 3.0d 3.0d 21-May-18 08:00 AM* 23-May-18 05:00 PM
STF2410 Dismantle scaffold, stagging, t-prox, soffit & formwork 1.0d 1.0d 3.0d 24-May-18 08:00 AM* 24-May-18 05:00 PM
Roof Truss, Covering & Accessories 10.0d 10.0d 26.0d 24-May-18 08:00 AM 02-Jun-18 05:00 PM 02-Jun-18 05:00 PM, Roof Truss, Covering & Accessories
STF2420 Deliver prefabricated light gauge MS roof truss on-site 1.0d 1.0d 12.0d 24-May-18 08:00 AM* 24-May-18 05:00 PM
STF2430 Install prefabricated light gauge MS roof truss & bracing 2.0d 2.0d 12.0d 25-May-18 08:00 AM* 26-May-18 05:00 PM
STF2440 Install purlins 2.0d 2.0d 12.0d 27-May-18 08:00 AM* 28-May-18 05:00 PM
STF2450 Inspection 1.0d 1.0d 12.0d 28-May-18 08:00 AM* 28-May-18 05:00 PM
STF2460 Install concrete roof tiles & ridge cap 4.0d 4.0d 12.0d 29-May-18 08:00 AM* 01-Jun-18 05:00 PM
STF2470 Install fascia board & bracket for gutter 1.0d 1.0d 12.0d 02-Jun-18 08:00 AM* 02-Jun-18 05:00 PM
STF2480 Inspection 1.0d 1.0d 26.0d 02-Jun-18 08:00 AM* 02-Jun-18 05:00 PM
Floor, Wall, Ceiling & Accessories 19.0d 19.0d 4.6d 24-May-18 07:00 PM 06-Jun-18 03:00 PM 06-Jun-18 03:00 PM, Floor, Wall, Ceiling & Accessories
STF2490 Install 225mm thk. brickwall, tie with mortar - Team A & B 3.0d 3.0d 4.6d 24-May-18 07:00 PM* 26-May-18 08:00 PM
STF2500 Install roller shutter & frame for door and window 2.0d 2.0d 4.6d 26-May-18 08:00 PM* 28-May-18 09:00 AM
STF2510 Electrical wiring works - carry out by specialist team 4.0d 4.0d 4.6d 26-May-18 08:00 PM* 29-May-18 02:00 PM
STF2520 External plastering - Team A 3.0d 3.0d 4.6d 29-May-18 02:00 PM* 31-May-18 02:00 PM
STF2530 Internal plastering - Team B 3.0d 3.0d 4.6d 29-May-18 02:00 PM* 31-May-18 02:00 PM
STF2540 Install frame & ceiling (external) - Team A 2.0d 2.0d 4.6d 31-May-18 02:00 PM* 01-Jun-18 09:00 PM
STF2550 Install frame & ceiling (internal) - Team B 2.0d 2.0d 4.6d 31-May-18 02:00 PM* 01-Jun-18 09:00 PM
STF2560 Install gutter & UPVC downpipes 1.0d 1.0d 4.6d 01-Jun-18 09:00 PM* 02-Jun-18 03:00 PM
STF2570 Rendering of floor, install tiles & skirting 4.0d 4.0d 4.6d 01-Jun-18 09:00 PM* 04-Jun-18 03:00 PM
STF2580 Painting of wall (external & internal) & ceiling - undercoat - Team A3.0d 3.0d 4.6d 04-Jun-18 03:00 PM* 06-Jun-18 03:00 PM
STF2590 Painting of wall (external & internal) & ceiling - finish coat - Team B3.0d 3.0d 4.6d 04-Jun-18 03:00 PM* 06-Jun-18 03:00 PM
STF2600 Install door & windows 1.0d 1.0d 4.6d 04-Jun-18 03:00 PM* 05-Jun-18 10:00 AM
STF2610 Install GI tray / condiut 1.0d 1.0d 4.6d 05-Jun-18 10:00 AM* 05-Jun-18 09:00 PM
U-Shaped Drain - Team C 8.5d 8.5d 12.5d 03-Jun-18 08:00 AM 11-Jun-18 12:00 PM 11-Jun-18 12:00 PM, U-Shaped Drain - Team C
STF2620 Excavation & levelling works 2.0d 2.0d 12.0d 03-Jun-18 08:00 AM* 04-Jun-18 05:00 PM
STF2630 Erect formwork 1.0d 1.0d 18.3d 04-Jun-18 07:00 PM* 05-Jun-18 12:00 PM
STF2640 Install reinforcement 3.0d 3.0d 18.3d 05-Jun-18 01:00 PM* 07-Jun-18 12:00 PM
STF2650 Inspection 1.0d 1.0d 12.5d 06-Jun-18 01:00 PM* 07-Jun-18 12:00 PM
STF2660 Concreting works 1.0d 1.0d 12.5d 07-Jun-18 01:00 PM* 08-Jun-18 12:00 PM
STF2670 Curing works 2.0d 2.0d 12.5d 08-Jun-18 01:00 PM* 10-Jun-18 12:00 PM
STF2680 Dismantle formwork 1.0d 1.0d 12.5d 10-Jun-18 01:00 PM* 11-Jun-18 12:00 PM
Apron & Ramp - Team C 5.9d 5.9d 12.5d 11-Jun-18 01:00 PM 17-Jun-18 12:00 PM 17-Jun-18 12:00 PM, Apron & Ramp - Team C
STF2690 Backfilling, levelling & compaction works 1.0d 1.0d 12.5d 11-Jun-18 01:00 PM* 12-Jun-18 12:00 PM
STF2700 Erect formwork, install reinforcement 3.0d 3.0d 18.3d 12-Jun-18 01:00 PM* 14-Jun-18 12:00 PM
STF2710 Inspection 1.0d 1.0d 12.5d 13-Jun-18 01:00 PM* 14-Jun-18 12:00 PM
STF2720 Concreting works 1.0d 1.0d 12.5d 14-Jun-18 01:00 PM* 15-Jun-18 12:00 PM
STF2730 Curing works 1.0d 1.0d 12.5d 15-Jun-18 01:00 PM* 16-Jun-18 12:00 PM
STF2740 Dismantle formwork & cleanup site 1.0d 1.0d 12.5d 16-Jun-18 01:00 PM* 17-Jun-18 12:00 PM
85.0d 85.0d 73.0d 22-Jan-18 08:00 AM 16-Apr-18 05:00 PM 16-Apr-18 05:00 PM, Pipeworks (200mm & 300mm Dia. Pipe)
Pipeworks (200mm & 300mm Dia. Pipe)
Procurement & Installation Works 85.0d 85.0d 73.0d 22-Jan-18 08:00 AM 16-Apr-18 05:00 PM 16-Apr-18 05:00 PM, Procurement & Installation Works

STF2750 To procure & deliver 100mm & 300mm Pipes to site 24.0d 24.0d 62.0d 22-Jan-18 08:00 AM 20-Feb-18 05:00 PM
STF2760 Excavation & backfilling works 24.0d 24.0d 74.0d 21-Feb-18 08:00 AM 16-Mar-18 05:00 PM
STF2770 Pipe laying & jointing 24.0d 24.0d 74.0d 21-Feb-18 08:00 AM 16-Mar-18 05:00 PM
STF2780 Connection to existing Chamber / Pipes 24.0d 24.0d 74.0d 17-Mar-18 08:00 AM 09-Apr-18 05:00 PM
STF2790 Miscellaneous works 18.0d 18.0d 80.0d 17-Mar-18 08:00 AM 03-Apr-18 05:00 PM
STF2800 Cleaning & testing works 6.0d 6.0d 62.0d 10-Apr-18 08:00 AM 16-Apr-18 05:00 PM
172.0d 172.0d 16.0d 23-Dec-17 08:00 AM 12-Jun-18 05:00 PM 12-Jun-18 05:00 PM, Mechanical Works
Mechanical Works
Drawing & Material Approval 24.0d 24.0d 14.0d 23-Dec-17 08:00 AM 21-Jan-18 05:00 PM 21-Jan-18 05:00 PM, Drawing & Material Approval

STF2810 Submission of Drawing / Material for approval 12.0d 12.0d 14.0d 23-Dec-17 08:00 AM 07-Jan-18 05:00 PM
STF2820 Review & approval for Drawing / Material 12.0d 12.0d 14.0d 08-Jan-18 08:00 AM 21-Jan-18 05:00 PM
Tank & Plant 156.0d 156.0d 16.0d 08-Jan-18 08:00 AM 12-Jun-18 05:00 PM 12-Jun-18 05:00 PM, Tank & Plant

Primary Baseline Remaining Work Baseline Milestone Page 2 of 3 TASK filter: All Activities
Actual Work Critical Remaining Work Summary © Oracle Corporation
STF PALONG TIMUR REV.04 ALL NON-RUN Classic Schedule Layout 16-Apr-18 05:03 PM
Activity ID Activity Name Original Remaining Total Start Finish October 2017 November 2017 December 2017 January 2018 February 2018 March 2018 April 2018 May 2018 June 2018 July 2018 August 2018
Duration Duration Float 05
01 08 15 22 29 05 12 19 26 03 10 17 24 31 07 14 21 28 04 11 18 25 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 01 08 15 22 29
Wash Water Collection & Sludge Balancing Tank 143.0d 143.0d 22.0d 08-Jan-18 08:00 AM 30-May-18 05:00 PM 30-May-18 05:00 PM, Wash Water Collection & Sludge Balancing Tank

Procurement & Delivery 109.0d 109.0d 14.0d 08-Jan-18 08:00 AM 17-May-18 05:00 PM 17-May-18 05:00 PM, Procurement & Delivery
STF2830 Horizontal Screw Pump & Subermisble Supernatant Pump 79.0d 79.0d 14.0d 08-Jan-18 08:00 AM 11-Apr-18 05:00 PM
STF2840 FAT Wash Water Recovery Pumpset 6.0d 6.0d 14.0d 12-Apr-18 08:00 AM 18-Apr-18 05:00 PM
STF2850 Pipes, Fittings & Valves 30.0d 30.0d 14.0d 12-Apr-18 08:00 AM 17-May-18 05:00 PM
STF2860 Submersible Mixer 30.0d 30.0d 14.0d 12-Apr-18 08:00 AM 17-May-18 05:00 PM
STF2870 Crane / Lifting Equipment, High Pressure Rubber Hose 30.0d 30.0d 14.0d 12-Apr-18 08:00 AM 17-May-18 05:00 PM
Installation Works 42.0d 42.0d 22.0d 19-Apr-18 08:00 AM 30-May-18 05:00 PM 30-May-18 05:00 PM, Installation Works
STF2880 Construction of Horizontal Screw Pump Pit 24.0d 24.0d 22.0d 19-Apr-18 08:00 AM 12-May-18 05:00 PM
STF2890 Horizontal Screw Pump & Submersible Supernatant Pump 18.0d 18.0d 22.0d 13-May-18 08:00 AM 30-May-18 05:00 PM
STF2900 Pipeworks, Fittings & Valves 18.0d 18.0d 22.0d 13-May-18 08:00 AM 30-May-18 05:00 PM
STF2910 Submersible Mixer 12.0d 12.0d 22.0d 13-May-18 08:00 AM 24-May-18 05:00 PM
STF2920 Crane / Lifting Equipment, High Pressure Rubber Hose 12.0d 12.0d 17.0d 18-May-18 08:00 AM 29-May-18 05:00 PM
Existing Sedimentation Tank / Basin 121.0d 121.0d 38.0d 08-Jan-18 08:00 AM 08-May-18 05:00 PM 08-May-18 05:00 PM, Existing Sedimentation Tank / Basin

Procurement & Delivery 61.0d 61.0d 52.0d 08-Jan-18 08:00 AM 21-Mar-18 05:00 PM 21-Mar-18 05:00 PM, Procurement & Delivery
STF2930 Submersible Sludge Pump 61.0d 61.0d 32.0d 08-Jan-18 08:00 AM 21-Mar-18 05:00 PM
STF2940 Pipes, Fittings & Valves 30.0d 30.0d 83.0d 08-Jan-18 08:00 AM 11-Feb-18 05:00 PM
Installation Works 48.0d 48.0d 38.0d 22-Mar-18 08:00 AM 08-May-18 05:00 PM 08-May-18 05:00 PM, Installation Works
STF2950 Submersible Sludge Pump 24.0d 24.0d 38.0d 22-Mar-18 08:00 AM 14-Apr-18 05:00 PM
STF2960 Pipes, Fittings & Valves 24.0d 24.0d 38.0d 15-Apr-18 08:00 AM 08-May-18 05:00 PM
Polymer Plant 156.0d 156.0d 3.0d 08-Jan-18 08:00 AM 12-Jun-18 05:00 PM 12-Jun-18 05:00 PM, Polymer Plant

Procurement & Delivery 60.0d 60.0d 67.0d 08-Jan-18 08:00 AM 20-Mar-18 05:00 PM 20-Mar-18 05:00 PM, Procurement & Delivery
STF2970 Engineering Design for Polymer Plant & Dosing System 18.0d 18.0d 31.0d 08-Jan-18 08:00 AM 28-Jan-18 05:00 PM
STF2980 Metering pumps (Diaphragm type) 60.0d 60.0d 31.0d 08-Jan-18 08:00 AM 20-Mar-18 05:00 PM
STF2990 Crane / Lifting Equipment 30.0d 30.0d 97.0d 08-Jan-18 08:00 AM 11-Feb-18 05:00 PM
STF3000 Static Mixer & Sludge Blender 30.0d 30.0d 97.0d 08-Jan-18 08:00 AM 11-Feb-18 05:00 PM
Fabrication Works 36.0d 36.0d 37.0d 21-Mar-18 08:00 AM 02-May-18 05:00 PM 02-May-18 05:00 PM, Fabrication Works
STF3010 Mixing & Service Tank 36.0d 36.0d 31.0d 21-Mar-18 08:00 AM 02-May-18 05:00 PM
STF3020 Hopper, Feeder & Pump Skid 36.0d 36.0d 37.0d 21-Mar-18 08:00 AM 02-May-18 05:00 PM
STF3030 Local Control Panel 30.0d 30.0d 37.0d 21-Mar-18 08:00 AM 24-Apr-18 05:00 PM
Installation Works 7.0d 7.0d 3.0d 06-Jun-18 08:00 AM 12-Jun-18 05:00 PM 12-Jun-18 05:00 PM, Installation Works
STF3040 Mixing & Service Tank 7.0d 7.0d 3.0d 06-Jun-18 08:00 AM 12-Jun-18 05:00 PM
STF3050 Hopper, Feeder & Pump Skid 7.0d 7.0d 3.0d 06-Jun-18 08:00 AM 12-Jun-18 05:00 PM
STF3060 Dosing Pipeworks 7.0d 7.0d 3.0d 06-Jun-18 08:00 AM 12-Jun-18 05:00 PM
STF3070 Local Control Panel 7.0d 7.0d 3.0d 06-Jun-18 08:00 AM 12-Jun-18 05:00 PM
STF3080 Crane / Lifting Equipment 7.0d 7.0d 3.0d 06-Jun-18 08:00 AM 12-Jun-18 05:00 PM
STF3090 Static Mixer & Sludge Blender 7.0d 7.0d 3.0d 06-Jun-18 08:00 AM 12-Jun-18 05:00 PM
Pipeworks (100mm Dia. Pipe & Below) 85.0d 85.0d 73.0d 22-Jan-18 08:00 AM 16-Apr-18 05:00 PM 16-Apr-18 05:00 PM, Pipeworks (100mm Dia. Pipe & Below)

Procurement & Installation Works 85.0d 85.0d 73.0d 22-Jan-18 08:00 AM 16-Apr-18 05:00 PM 16-Apr-18 05:00 PM, Procurement & Installation Works
STF3100 Procurement & Delivery of Pipes 24.0d 24.0d 83.0d 22-Jan-18 08:00 AM 20-Feb-18 05:00 PM
STF3110 Excavation, Backfilling Works 24.0d 24.0d 74.0d 17-Mar-18 08:00 AM 09-Apr-18 05:00 PM
STF3120 Pipe Laying, Jointing 24.0d 24.0d 74.0d 17-Mar-18 08:00 AM 09-Apr-18 05:00 PM
STF3130 Cleaning & Testing works 6.0d 6.0d 62.0d 10-Apr-18 08:00 AM 16-Apr-18 05:00 PM
Miscellaneous Works 124.0d 124.0d 21.0d 22-Jan-18 08:00 AM 25-May-18 05:00 PM 25-May-18 05:00 PM, Miscellaneous Works

Procurement & Delivery 79.0d 79.0d 15.0d 22-Jan-18 08:00 AM 25-Apr-18 05:00 PM 25-Apr-18 05:00 PM, Procurement & Delivery
STF3140 Engineering Design for Motive Water System & Air Compressor 18.0d 18.0d 15.0d 22-Jan-18 08:00 AM 11-Feb-18 05:00 PM
STF3150 Booster Pump 30.0d 30.0d 15.0d 12-Feb-18 08:00 AM 20-Mar-18 05:00 PM
STF3160 Air Compressor Set 30.0d 30.0d 15.0d 12-Feb-18 08:00 AM 20-Mar-18 05:00 PM
STF3170 Submersible Pump (Portable & Gasoline Engine) 30.0d 30.0d 15.0d 12-Feb-18 08:00 AM 20-Mar-18 05:00 PM
STF3180 Portable Water Jet 12.0d 12.0d 15.0d 12-Feb-18 08:00 AM 27-Feb-18 05:00 PM
STF3190 Penstock & Valve 60.0d 60.0d 15.0d 12-Feb-18 08:00 AM 24-Apr-18 05:00 PM
STF3200 FAT Penstock / Valve 1.0d 1.0d 15.0d 25-Apr-18 08:00 AM 25-Apr-18 05:00 PM
Installation Works 66.0d 66.0d 21.0d 21-Mar-18 08:00 AM 25-May-18 05:00 PM 25-May-18 05:00 PM, Installation Works
STF3210 Booster Pump 18.0d 18.0d 39.0d 21-Mar-18 08:00 AM 07-Apr-18 05:00 PM
STF3220 Air Compressor Set 18.0d 18.0d 39.0d 21-Mar-18 08:00 AM 07-Apr-18 05:00 PM
STF3230 Penstock & Valve 30.0d 30.0d 21.0d 26-Apr-18 08:00 AM 25-May-18 05:00 PM
176.0d 176.0d 11.0d 11-Dec-17 08:00 AM 04-Jun-18 05:00 PM 04-Jun-18 05:00 PM, Electrical Works
Electrical Works
Drawing & Material Approval 24.0d 24.0d 10.0d 11-Dec-17 08:00 AM 09-Jan-18 05:00 PM 09-Jan-18 05:00 PM, Drawing & Material Approval

STF3240 Submission Drawing/Material for Approval 12.0d 12.0d 10.0d 11-Dec-17 08:00 AM 24-Dec-17 05:00 PM
STF3250 Review & Approval for Drawing/Material 12.0d 12.0d 10.0d 26-Dec-17 08:00 AM 09-Jan-18 05:00 PM
Panel & Cabling Works 161.0d 161.0d 11.0d 26-Dec-17 08:00 AM 04-Jun-18 05:00 PM 04-Jun-18 05:00 PM, Panel & Cabling Works

Switchboard / MCC Panel 152.0d 152.0d 20.0d 26-Dec-17 08:00 AM 26-May-18 05:00 PM 26-May-18 05:00 PM, Switchboard / MCC Panel
STF3260 Procurement & Fabrication of Panel 84.0d 84.0d 10.0d 26-Dec-17 08:00 AM 05-Apr-18 05:00 PM
STF3270 FAT Electrical Control and Switchboards 1.0d 1.0d 15.0d 26-Apr-18 08:00 AM 26-Apr-18 05:00 PM
STF3280 Installation Works 30.0d 30.0d 20.0d 27-Apr-18 08:00 AM 26-May-18 05:00 PM
Submain Cabling Works for MCC-SDP-Palong 59.0d 59.0d 11.0d 07-Apr-18 08:00 AM 04-Jun-18 05:00 PM 04-Jun-18 05:00 PM, Submain Cabling Works for MCC-SDP-Palong
STF3290 Procurement & Delivery of Cable 24.0d 24.0d 10.0d 07-Apr-18 08:00 AM 05-May-18 05:00 PM
STF3300 Installation & Cabling Works 30.0d 30.0d 11.0d 06-May-18 08:00 AM 04-Jun-18 05:00 PM
Distribution & Earthing System 59.0d 59.0d 11.0d 07-Apr-18 08:00 AM 04-Jun-18 05:00 PM 04-Jun-18 05:00 PM, Distribution & Earthing System
STF3310 Procurement & Delivery of Cable 24.0d 24.0d 10.0d 07-Apr-18 08:00 AM 05-May-18 05:00 PM
STF3320 Installation Works 30.0d 30.0d 11.0d 06-May-18 08:00 AM 04-Jun-18 05:00 PM
Compund Lighting System 59.0d 59.0d 11.0d 07-Apr-18 08:00 AM 04-Jun-18 05:00 PM 04-Jun-18 05:00 PM, Compund Lighting System
STF3330 Procurement & Delivery 24.0d 24.0d 10.0d 07-Apr-18 08:00 AM 05-May-18 05:00 PM
STF3340 Installation & Cabling Works 30.0d 30.0d 11.0d 06-May-18 08:00 AM 04-Jun-18 05:00 PM
Miscellaneous Works 30.0d 30.0d 11.0d 06-May-18 08:00 AM 04-Jun-18 05:00 PM 04-Jun-18 05:00 PM, Miscellaneous Works
STF3350 Relocations Existing Cabling Works 30.0d 30.0d 11.0d 06-May-18 08:00 AM 04-Jun-18 05:00 PM
STF3360 Miscellaneous Works 30.0d 30.0d 11.0d 06-May-18 08:00 AM 04-Jun-18 05:00 PM
169.0d 169.0d 18.0d 11-Dec-17 08:00 AM 28-May-18 05:00 PM 28-May-18 05:00 PM, Instrumentation Works
Instrumentation Works
Drawing & Material Approval 24.0d 24.0d 33.0d 11-Dec-17 08:00 AM 09-Jan-18 05:00 PM 09-Jan-18 05:00 PM, Drawing & Material Approval

STF3370 Submission Drawing/Material for Approval 12.0d 12.0d 33.0d 11-Dec-17 08:00 AM 24-Dec-17 05:00 PM
STF3380 Review & Approval for Drawing/Material 12.0d 12.0d 33.0d 26-Dec-17 08:00 AM 09-Jan-18 05:00 PM
Panel & Cabling Works 154.0d 154.0d 18.0d 26-Dec-17 08:00 AM 28-May-18 05:00 PM 28-May-18 05:00 PM, Panel & Cabling Works

Procurement & Installation Works 154.0d 154.0d 18.0d 26-Dec-17 08:00 AM 28-May-18 05:00 PM 28-May-18 05:00 PM, Procurement & Installation Works
STF3390 Procurement & Fabrication of Instrument Panel 84.0d 84.0d 33.0d 26-Dec-17 08:00 AM 05-Apr-18 05:00 PM
STF3400 FAT 1.0d 1.0d 15.0d 28-Apr-18 08:00 AM 28-Apr-18 05:00 PM
STF3410 Installation & Signal Cabling Works 30.0d 30.0d 18.0d 29-Apr-18 08:00 AM 28-May-18 05:00 PM
10.0d 10.0d 11.0d 09-Jun-18 08:00 AM 18-Jun-18 05:00 PM 18-Jun-18 05:00 PM, Infrastructure Works
Infrastructure Works
Reinstatement of Damaged Existing Road 10.0d 10.0d 11.0d 09-Jun-18 08:00 AM 18-Jun-18 05:00 PM 18-Jun-18 05:00 PM, Reinstatement of Damaged Existing Road

STF3420 Site clearance, levelling & compaction 7.0d 7.0d 11.0d 09-Jun-18 08:00 AM 15-Jun-18 05:00 PM
STF3430 Lay & compact crusher-run & premix (binder and wearing coarse)10.0d 10.0d 11.0d 09-Jun-18 08:00 AM 18-Jun-18 05:00 PM
14.5d 14.5d 3.5d 13-Jun-18 08:00 AM 27-Jun-18 12:00 PM 27-Jun-18 12:00 PM, Site Handover Works
Site Handover Works
Project Completions 14.5d 14.5d 3.5d 13-Jun-18 08:00 AM 27-Jun-18 12:00 PM 27-Jun-18 12:00 PM, Project Completions

Training, Testing, Commissioning & Maintenance 14.5d 14.5d 3.5d 13-Jun-18 08:00 AM 27-Jun-18 12:00 PM 27-Jun-18 12:00 PM, Training, Testing, Commissioning & Maintenance
STF3440 Preparation of Testing & Report 8.0d 8.0d 2.0d 13-Jun-18 08:00 AM 21-Jun-18 05:00 PM
STF3450 Pre-commissioning 4.0d 4.0d 2.0d 13-Jun-18 08:00 AM 17-Jun-18 05:00 PM
STF3460 Setting to Work 3.0d 3.0d 2.0d 18-Jun-18 08:00 AM 20-Jun-18 05:00 PM
STF3470 Commissioning & Training of Works 5.0d 5.0d 2.0d 21-Jun-18 08:00 AM 26-Jun-18 05:00 PM
STF3480 Handing Over to Client 1.0d 1.0d 4.9d 26-Jun-18 07:00 PM 27-Jun-18 12:00 PM

Primary Baseline Remaining Work Baseline Milestone Page 3 of 3 TASK filter: All Activities
Actual Work Critical Remaining Work Summary © Oracle Corporation