Anda di halaman 1dari 4

J048 - CADANGAN MEMBINA KEMUDAHAN PENGURUSAN ENAPCEMAR DI LRA PALONG TIMUR, SEGAMAT, JOHOR.

PAKEJ 1 - CADANGAN MEMBINA, MENYIAP DAN MENTAULIAH KEMUDAHAN PENGURUSAN ENAPCEMAR, BANGUNAN POLIMER DAN PELANTAR GEOTUBE SERTA
KERJA-KERJA BERKAITAN.

NO LOCATION Description of Work Progress This Week Actual (%) Schedule (%) Variance
(From 1st
April 2018 - 7th April 2018)
A WASH WATER COLLECTION & SLUDGE Weekly percentage 1.33 0.31 +1.02
BALANCING TANK (WWCT & SBT) Overall civil works percentage as at 07.04.2018 79.08 69.13 +9.95
Overall project percentage as at 07.04.2018 11.79 10.31 +1.48
A1 WALL '2' - 1st Lift (1.5m & 2.4m) Continue curing works
*Refer 'Attachment B' in the email Continue dismantle formwork & scaffold
A2 WALL '1' - 2nd Lift (2.4m) Continue install reinforcement bar (Y12 & Y16)
*Refer 'Attachment C' in the email Continue install scaffold & stagging
Continue install 2 units of 300mm dia. puddle flange pipes
Erect & install formwork
Inspection works
Concreting works (V = 35m3)
Curing works
A3 WALL '2' - 2nd Lift (2.1m, 1.45m & 2.15m) Install reinforcement bar (Y12 & Y16)
*Refer 'Attachment C' in the email Install scaffold & stagging
A4 Cantilever Beam, Walkway Slab & Overflow Install reinforcement bar (Y12 & Y16)
Slab/Wall
*Refer 'Attachment D' in the email Erect & install formwork, t-props & soffit
Install scaffold & stagging
J048 - CADANGAN MEMBINA KEMUDAHAN PENGURUSAN ENAPCEMAR DI LRA PALONG TIMUR, SEGAMAT, JOHOR.

PAKEJ 1 - CADANGAN MEMBINA, MENYIAP DAN MENTAULIAH KEMUDAHAN PENGURUSAN ENAPCEMAR, BANGUNAN
POLIMER DAN PELANTAR GEOTUBE SERTA KERJA-KERJA BERKAITAN.

***All data obtained from Primavera P6 15.2


***Weightage = 14.91 for WWCT & SBT

Cumulative Weekly
NO DATE Schedule % Complete Remarks
Weightage Weightage
1 3/10/2018 54.93 8.19
2 3/17/2018 58.44 8.71 0.52
3 3/24/2018 63.45 9.46 0.75
4 3/31/2018 67.08 10.00 0.54
5 4/7/2018 69.13 10.31 0.31

Cumulative Weekly
NO DATE Units % Complete Remarks
Weightage Weightage
1 3/10/2018 56.7 8.45
2 3/17/2018 63.48 9.46 1.01
3 3/24/2018 65.69 9.79 0.33
4 3/31/2018 70.17 10.46 0.67
5 4/7/2018 79.08 11.79 1.33
J048 - CADANGAN MEMBINA KEMUDAHAN PENGURUSAN ENAPCEMAR DI LRA PALONG TIMUR, SEGAMAT, JOHOR.

PAKEJ 1 - CADANGAN MEMBINA, MENYIAP DAN MENTAULIAH KEMUDAHAN PENGURUSAN ENAPCEMAR, BANGUNAN
POLIMER DAN PELANTAR GEOTUBE SERTA KERJA-KERJA BERKAITAN.

***All data obtained from Primavera P6 15.2


***Weightage = 13.51 for PIPEWORKS

Cumulative Weekly
NO DATE Schedule % Complete Remarks
Weightage Weightage
1 3/24/2018 98.89 13.36
2 3/31/2018 100 13.51 0.15

Cumulative Weekly
NO DATE Units % Complete Remarks
Weightage Weightage
1 3/24/2018 12 1.62
2 3/31/2018 20 2.70 1.08
J048 - CADANGAN MEMBINA KEMUDAHAN PENGURUSAN ENAPCEMAR DI LRA PALONG TIMUR, SEGAMAT, JOHOR.

PAKEJ 1 - CADANGAN MEMBINA, MENYIAP DAN MENTAULIAH KEMUDAHAN PENGURUSAN ENAPCEMAR, BANGUNAN
POLIMER DAN PELANTAR GEOTUBE SERTA KERJA-KERJA BERKAITAN.

***All data obtained from Primavera P6 15.2


***Weightage = 38.68 for MECHANICAL

Cumulative Weekly
NO DATE Schedule % Complete Remarks
Weightage Weightage
1 3/24/2018 78.04 30.19
2 3/31/2018 82.07 31.74 1.55

Cumulative Weekly
NO DATE Units % Complete Remarks
Weightage Weightage
1 3/24/2018 36.71 14.20
2 3/31/2018 41.79 16.16 1.96