Activity ID Activity Name Original Remaining Total Start October 2017 November 2017 December 2017 January 2018 February 2018 March 2018 April 2018 May 2018 June 2018 July 2018 August 2018
Duration Duration Float 05
01 08 15 22 29 05 12 19 26 03 10 17 24 31 07 14 21 28 04 11 18 25 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 01 08 15 22 29
156.0d 156.0d 72.0d 02-Oct-17 08:00 07-Apr-18 08:00 AM, STF PALONG TIMUR REV.00 CS ONLY RUN FOLLOW MIP REV.00
STF PALONG TIMUR REV.00 CS ONLY RUN FOLLOW MIP REV.00
AM
156.0d 156.0d 72.0d 02-Oct-17 08:00 AM 07-Apr-18 08:00 AM, Milestone
Milestone
ML-001-100 Milestone Start STF 0.0d 0.0d 72.0d 02-Oct-17 08:00 AM*
ML-001-110 Milestone Finish STF 0.0d 0.0d 72.0d 07-Apr-18 08:00 AM*
32.0d 32.0d 72.0d 02-Oct-17 08:00 AM 07-Nov-17 05:00 PM, General & Preliminaries
General & Preliminaries
Documentation 32.0d 32.0d 72.0d 02-Oct-17 08:00 AM 07-Nov-17 05:00 PM, Documentation

Preparation & Submission 32.0d 32.0d 72.0d 02-Oct-17 08:00 AM 07-Nov-17 05:00 PM, Preparation & Submission
STF1000 Preparation of Performance Bond 14.0d 14.0d 72.0d 02-Oct-17 08:00 AM
STF1010 Preparation of Insurances Policies / Public Liability / Workmen's Compensation 14.0d 14.0d 72.0d 02-Oct-17 08:00 AM
STF1020 Preparation & Submission of Levy of CIDB 14.0d 14.0d 72.0d 02-Oct-17 08:00 AM
STF1030 Site Registration of JKKP (DOSH) 14.0d 14.0d 72.0d 02-Oct-17 08:00 AM
STF1040 Submission Copy of SPAN Certificate 14.0d 14.0d 72.0d 02-Oct-17 08:00 AM
STF1050 Preparation & Submission of Lithography Expenses 14.0d 14.0d 72.0d 02-Oct-17 08:00 AM
STF1060 Preparation & Submission of PQP / Method Statements 14.0d 14.0d 72.0d 02-Oct-17 08:00 AM
STF1070 Preparation of Works (Contractor Requirements) 18.0d 18.0d 72.0d 18-Oct-17 08:00 AM
STF1080 Preparation of Works (Engineers / S.O / PD's Requirements) 18.0d 18.0d 72.0d 18-Oct-17 08:00 AM
STF1090 Preparation of Works (General Obligation, Project Requirements) 18.0d 18.0d 72.0d 18-Oct-17 08:00 AM
STF1100 Preparation of Works (Authorities Requirements) 18.0d 18.0d 72.0d 18-Oct-17 08:00 AM
STF1110 Preparation of Works (Environmental Protection & Enhancement) 18.0d 18.0d 72.0d 18-Oct-17 08:00 AM
124.0d 124.0d 72.0d 08-Nov-17 08:00 AM 05-Apr-18 05:00 PM, Civil & Structures
Civil & Structures
Underground Tank & Building 124.0d 124.0d 72.0d 08-Nov-17 08:00 AM 05-Apr-18 05:00 PM, Underground Tank & Building

Preliminary Works 24.0d 24.0d 72.0d 08-Nov-17 08:00 AM 05-Dec-17 05:00 PM, Preliminary Works

Site Measurement & Site Preparation 24.0d 24.0d 72.0d 08-Nov-17 08:00 AM 05-Dec-17 05:00 PM, Site Measurement & Site Preparation
STF1120 Site survey 12.0d 12.0d 72.0d 08-Nov-17 08:00 AM
STF1130 Site clearance 12.0d 12.0d 72.0d 22-Nov-17 08:00 AM
Wash Water Collection & Sludge Balancing Tank 100.0d 100.0d 72.0d 06-Dec-17 08:00 AM 05-Apr-18 05:00 PM, Wash Water Collection & Sludge Balancing Tank

Slab for All excluding Drywells 29.0d 29.0d 72.0d 06-Dec-17 08:00 AM 10-Jan-18 05:00 PM, Slab for All excluding Drywells
STF1140 Excavation, levelling & compaction works 12.0d 12.0d 72.0d 06-Dec-17 08:00 AM
STF1150 Install formwork 3.0d 3.0d 72.0d 20-Dec-17 08:00 AM
STF1160 Lay of 75mm thick lean concrete 1.0d 1.0d 72.0d 24-Dec-17 08:00 AM
STF1170 Erect formwork, install reinforcement, kicker & waterstop 9.0d 9.0d 72.0d 26-Dec-17 08:00 AM*
STF1180 Inspection 1.0d 1.0d 72.0d 07-Jan-18 08:00 AM*
STF1190 Concreting & curing works 2.0d 2.0d 72.0d 08-Jan-18 08:00 AM*
STF1200 Dismantle formwork 1.0d 1.0d 72.0d 10-Jan-18 08:00 AM*
Slab for Drywells 9.0d 9.0d 72.0d 11-Jan-18 08:00 AM 21-Jan-18 05:00 PM, Slab for Drywells
STF1210 To excavate, level & compact 1.0d 1.0d 72.0d 11-Jan-18 08:00 AM*
STF1220 Lay of 75mm thick lean concrete 1.0d 1.0d 72.0d 13-Jan-18 08:00 AM*
STF1230 Erect formwork, install reinforcement, kicker & waterstop 3.0d 3.0d 72.0d 14-Jan-18 08:00 AM*
STF1240 Inspection 1.0d 1.0d 72.0d 17-Jan-18 08:00 AM*
STF1250 Concreting & curing works 2.0d 2.0d 72.0d 18-Jan-18 08:00 AM*
STF1260 Dismantle formwork 1.0d 1.0d 72.0d 21-Jan-18 08:00 AM*
Wall '1' - 1st Lift (1.5m) 11.0d 11.0d 72.0d 22-Jan-18 08:00 AM 03-Feb-18 05:00 PM, Wall '1' - 1st Lift (1.5m)
STF1270 Erect scaffold & stagging 1.0d 1.0d 72.0d 22-Jan-18 08:00 AM*
STF1280 Erect formwork, install reinforcement, kicker & waterstop 4.0d 4.0d 72.0d 23-Jan-18 08:00 AM*
STF1290 Inspection 1.0d 1.0d 72.0d 28-Jan-18 08:00 AM*
STF1300 Concreting works 1.0d 1.0d 72.0d 29-Jan-18 08:00 AM*
STF1310 Curing works 3.0d 3.0d 72.0d 30-Jan-18 08:00 AM*
STF1320 Dismantle formwork, scaffold & stagging 1.0d 1.0d 72.0d 03-Feb-18 08:00 AM*
Wall '2' - 1st Lift (1.5m & 2.4m) 13.0d 13.0d 72.0d 04-Feb-18 08:00 AM 20-Feb-18 05:00 PM, Wall '2' - 1st Lift (1.5m & 2.4m)
STF1330 Erect scaffold & stagging 1.0d 1.0d 72.0d 04-Feb-18 08:00 AM*
STF1340 Erect formwork, install reinforcement, kicker & waterstop 4.0d 4.0d 72.0d 05-Feb-18 08:00 AM*
STF1350 Install 4 units of 100mm dia. Pipes 2.0d 2.0d 72.0d 10-Feb-18 08:00 AM*
STF1360 Inspection 1.0d 1.0d 72.0d 12-Feb-18 08:00 AM*
STF1370 Concreting works 1.0d 1.0d 72.0d 13-Feb-18 08:00 AM*
STF1380 Curing works 3.0d 3.0d 72.0d 14-Feb-18 08:00 AM*
STF1390 Dismantle formwork, scaffold & stagging 1.0d 1.0d 72.0d 20-Feb-18 08:00 AM*
Wall '1' - 2nd Lift (2.1m) 12.0d 12.0d 72.0d 21-Feb-18 08:00 AM 06-Mar-18 05:00 PM, Wall '1' - 2nd Lift (2.1m)
STF1400 Erect scaffold & stagging 1.0d 1.0d 72.0d 21-Feb-18 08:00 AM*
STF1410 Erect formwork, install reinforcement 4.0d 4.0d 72.0d 22-Feb-18 08:00 AM*
STF1420 Install 2 units of 300mm dia. of pipes (level - 22.50) 1.0d 1.0d 72.0d 27-Feb-18 08:00 AM*
STF1430 Inspection 1.0d 1.0d 72.0d 28-Feb-18 08:00 AM*
STF1440 Concreting works 1.0d 1.0d 72.0d 01-Mar-18 08:00 AM*
STF1450 Curing works 3.0d 3.0d 72.0d 03-Mar-18 08:00 AM*
STF1460 Dismantle formwork, scaffold & stagging 1.0d 1.0d 72.0d 06-Mar-18 08:00 AM*
Wall '2' - 2nd Lift (2.1m, 1.45m, 2.15m) 12.0d 12.0d 72.0d 07-Mar-18 08:00 AM 20-Mar-18 05:00 PM, Wall '2' - 2nd Lift (2.1m, 1.45m, 2.15m)
STF1470 Erect scaffold & stagging 1.0d 1.0d 72.0d 07-Mar-18 08:00 AM*
STF1480 Erect formwork, install reinforcement 5.0d 5.0d 72.0d 08-Mar-18 08:00 AM*
STF1490 Inspection 1.0d 1.0d 72.0d 14-Mar-18 08:00 AM*
STF1500 Concreting works 1.0d 1.0d 72.0d 15-Mar-18 08:00 AM*
STF1510 Curing works 3.0d 3.0d 72.0d 17-Mar-18 08:00 AM*
STF1520 Dismantle formwork, scaffold & stagging 1.0d 1.0d 72.0d 20-Mar-18 08:00 AM*
Cantilever Beam, Walkway Slab & Overflow Slab/Wall 12.0d 12.0d 72.0d 07-Mar-18 08:00 AM 20-Mar-18 05:00 PM, Cantilever Beam, Walkway Slab & Overflow Slab/Wall
STF1530 Erect scaffold & stagging 1.0d 1.0d 72.0d 07-Mar-18 08:00 AM*
STF1540 Erect & install formwork, t-props, soffit and reinforcement 4.0d 4.0d 72.0d 08-Mar-18 08:00 AM*
STF1550 Install 2 units of 200mm dia. of pipes at Overflow Wall A & C 1.0d 1.0d 72.0d 13-Mar-18 08:00 AM*
STF1560 Inspection 1.0d 1.0d 72.0d 14-Mar-18 08:00 AM*
STF1570 Concreting works 1.0d 1.0d 72.0d 15-Mar-18 08:00 AM*
STF1580 Curing works 3.0d 3.0d 72.0d 17-Mar-18 08:00 AM*
STF1590 Dismantle formwork, t-props, soffit, scaffold & stagging 1.0d 1.0d 72.0d 20-Mar-18 08:00 AM*
Partial Backfilling (Drywells Area) 6.0d 6.0d 75.0d 21-Mar-18 08:00 AM 27-Mar-18 05:00 PM, Partial Backfilling (Drywells Area)
STF1600 Repair of cold joints & honeycomb at affected area 1.0d 1.0d 72.0d 21-Mar-18 08:00 AM*
STF1610 Partial backfilling & compaction (1st stage) 1.0d 1.0d 75.0d 22-Mar-18 08:00 AM*
STF1620 Reinstate existing sump 2.0d 2.0d 75.0d 24-Mar-18 08:00 AM*
STF1630 Reinstate existing sewer pipes 1.0d 1.0d 75.0d 26-Mar-18 08:00 AM*
STF1640 Partial backfilling & compaction (2nd stage) 1.0d 1.0d 75.0d 27-Mar-18 08:00 AM*
Repair of Cold Joints, Waterproofing & Painting 4.0d 4.0d 72.0d 22-Mar-18 08:00 AM 26-Mar-18 05:00 PM, Repair of Cold Joints, Waterproofing & Painting
STF1650 Repair of cold joints & honeycomb 2.0d 2.0d 72.0d 22-Mar-18 08:00 AM*
STF1660 Waterproofing of internal wall 1.0d 1.0d 72.0d 25-Mar-18 08:00 AM*
STF1670 Painting (1 coat resistant primer & 2 coats anti-fungus) 1.0d 1.0d 72.0d 25-Mar-18 08:00 AM*
STF1680 Cleanup site 1.0d 1.0d 72.0d 26-Mar-18 08:00 AM*
Water Tighness Testing & Backfilling 9.0d 9.0d 72.0d 27-Mar-18 08:00 AM 05-Apr-18 05:00 PM, Water Tighness Testing & Backfilling
STF1690 To fill up WWCT & SBT with water 1.0d 1.0d 72.0d 27-Mar-18 08:00 AM*
STF1700 Monitoring 3.0d 3.0d 72.0d 28-Mar-18 08:00 AM*
STF1710 To backfill & compact outer perimeter of WWCT & SBT 5.0d 5.0d 72.0d 01-Apr-18 08:00 AM*
Dewatering Platform (Geotube) 94.0d 94.0d 78.0d 06-Dec-17 08:00 AM 29-Mar-18 05:00 PM, Dewatering Platform (Geotube)

Excavation Works & Hardcore 10.0d 10.0d 78.0d 06-Dec-17 08:00 AM 17-Dec-17 05:00 PM, Excavation Works & Hardcore
STF1720 Site measurement & marking 2.0d 2.0d 78.0d 06-Dec-17 08:00 AM*
STF1730 To excavate, level & compact ground 5.0d 5.0d 78.0d 09-Dec-17 08:00 AM*
STF1740 To lay, spread & compact Crusher-run as hardcore (0.3m Thk) 3.0d 3.0d 78.0d 14-Dec-17 08:00 AM*
Drain (Base) 16.0d 16.0d 78.0d 18-Dec-17 08:00 AM 07-Jan-18 05:00 PM, Drain (Base)
STF1750 Install formwork, lay of 50mm thick lean concrete 2.0d 2.0d 78.0d 18-Dec-17 08:00 AM*
STF1760 Erect formwork, install reinforcement 7.0d 7.0d 78.0d 20-Dec-17 08:00 AM*
STF1770 Inspection 1.0d 1.0d 78.0d 30-Dec-17 08:00 AM*
STF1780 Concreting works 2.0d 2.0d 78.0d 31-Dec-17 08:00 AM*
STF1790 Curing works 2.0d 2.0d 78.0d 03-Jan-18 08:00 AM*
STF1800 Dismantle formwork 2.0d 2.0d 78.0d 06-Jan-18 08:00 AM*
Drain (Wall - 2 sides) 17.0d 17.0d 78.0d 08-Jan-18 08:00 AM 27-Jan-18 05:00 PM, Drain (Wall - 2 sides)
STF1810 Erect formwork, install reinforcement 10.0d 10.0d 78.0d 08-Jan-18 08:00 AM*
STF1820 Inspection 1.0d 1.0d 78.0d 20-Jan-18 08:00 AM*
STF1830 Concreting works 2.0d 2.0d 78.0d 21-Jan-18 08:00 AM*
STF1840 Curing works 2.0d 2.0d 78.0d 23-Jan-18 08:00 AM*
STF1850 Dismantle formwork & backfilling works 2.0d 2.0d 78.0d 25-Jan-18 08:00 AM*

Primary Baseline Remaining Work Baseline Milestone Page 1 of 2 TASK filter: All Activities
Actual Work Critical Remaining Work Summary © Oracle Corporation
STF PALONG TIMUR REV.00 CS ONLY RUN FOLLOW MIP REV.00 Classic Schedule Layout 22-Apr-18 11:11 AM
Activity ID Activity Name Original Remaining Total Start October 2017 November 2017 December 2017 January 2018 February 2018 March 2018 April 2018 May 2018 June 2018 July 2018 August 2018
Duration Duration Float 05
01 08 15 22 29 05 12 19 26 03 10 17 24 31 07 14 21 28 04 11 18 25 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 01 08 15 22 29
Ground Slab 21.0d 21.0d 78.0d 28-Jan-18 08:00 AM 22-Feb-18 05:00 PM, Ground Slab
STF1860 Install formwork, lay of 50mm thick lean concrete 2.0d 2.0d 78.0d 28-Jan-18 08:00 AM*
STF1870 Erect formwork, install reinforcement 12.0d 12.0d 78.0d 30-Jan-18 08:00 AM*
STF1880 Inspection 1.0d 1.0d 78.0d 13-Feb-18 08:00 AM*
STF1890 Concreting works 2.0d 2.0d 78.0d 14-Feb-18 08:00 AM*
STF1900 Curing works 2.0d 2.0d 78.0d 19-Feb-18 08:00 AM*
STF1910 Dismantle formwork 2.0d 2.0d 78.0d 21-Feb-18 08:00 AM*
Ramp 20.0d 20.0d 78.0d 24-Feb-18 08:00 AM 18-Mar-18 05:00 PM, Ramp
STF1920 Install formwork, lay of 50mm thick lean concrete 2.0d 2.0d 78.0d 24-Feb-18 08:00 AM*
STF1930 Erect formwork, install reinforcement 7.0d 7.0d 78.0d 26-Feb-18 08:00 AM*
STF1940 Inspection 1.0d 1.0d 78.0d 06-Mar-18 08:00 AM*
STF1950 Concreting works 2.0d 2.0d 78.0d 07-Mar-18 08:00 AM*
STF1960 Curing works 2.0d 2.0d 78.0d 10-Mar-18 08:00 AM*
STF1970 Dismantle formwork 2.0d 2.0d 78.0d 12-Mar-18 08:00 AM*
STF1980 Install cheuque plate covers 2.0d 2.0d 78.0d 14-Mar-18 08:00 AM*
STF1990 To clean up site condition including levelling & compaction 2.0d 2.0d 78.0d 17-Mar-18 08:00 AM*
Geotube 30.0d 30.0d 78.0d 24-Feb-18 08:00 AM 29-Mar-18 05:00 PM, Geotube
STF2000 Delivery of 30 units of geotube to site 5.0d 5.0d 93.0d 24-Feb-18 08:00 AM*
STF2010 Setting of site ready for installation works 1.0d 1.0d 78.0d 19-Mar-18 08:00 AM*
STF2020 Installation of geotube and necessarry works 7.0d 7.0d 78.0d 20-Mar-18 08:00 AM*
STF2030 Cleanup site 2.0d 2.0d 78.0d 28-Mar-18 08:00 AM*
Polymer Building 94.0d 94.0d 78.0d 06-Dec-17 08:00 AM 29-Mar-18 05:00 PM, Polymer Building

Footing (1m x 1m - 0.3m Thk) & Stump (0.3m x 0.3m - 0.45m Thk) 11.0d 11.0d 78.0d 06-Dec-17 08:00 AM 18-Dec-17 05:00 PM, Footing (1m x 1m - 0.3m Thk) & Stump (0.3m x 0.3m - 0.45m Thk)
STF2040 To excavate, level & compact ground to receive foundation 1.0d 1.0d 78.0d 06-Dec-17 08:00 AM*
STF2050 Install formwork, lay of 50mm thick lean concrete 1.0d 1.0d 78.0d 07-Dec-17 08:00 AM*
STF2060 Erect formwork & install reinforcement 3.0d 3.0d 78.0d 09-Dec-17 08:00 AM*
STF2070 Inspection 1.0d 1.0d 78.0d 12-Dec-17 08:00 AM*
STF2080 Concreting works 1.0d 1.0d 78.0d 13-Dec-17 08:00 AM*
STF2090 Curing works 2.0d 2.0d 78.0d 14-Dec-17 08:00 AM*
STF2100 Dismantle formwork 1.0d 1.0d 78.0d 17-Dec-17 08:00 AM*
STF2110 Backfilling & compaction works to the level of top stump 1.0d 1.0d 78.0d 18-Dec-17 08:00 AM*
Ground Beam (0.3m x 0.6m) & Ground Slab (0.2m Thk) 12.0d 12.0d 78.0d 19-Dec-17 08:00 AM 03-Jan-18 05:00 PM, Ground Beam (0.3m x 0.6m) & Ground Slab (0.2m Thk)
STF2120 Erect formwork surround the outer of stump 1.0d 1.0d 78.0d 19-Dec-17 08:00 AM*
STF2130 Backfilling & compaction works to the level of bottom slab 2.0d 2.0d 78.0d 20-Dec-17 08:00 AM*
STF2140 Install formwork, lay of 50mm thick lean concrete 1.0d 1.0d 78.0d 23-Dec-17 08:00 AM*
STF2150 Install reinforcement both ground beam & slab 3.0d 3.0d 78.0d 24-Dec-17 08:00 AM*
STF2160 Inspection 1.0d 1.0d 78.0d 28-Dec-17 08:00 AM*
STF2170 Concreting works 1.0d 1.0d 78.0d 30-Dec-17 08:00 AM*
STF2180 Curing works 2.0d 2.0d 78.0d 31-Dec-17 08:00 AM*
STF2190 Dismantle formwork 1.0d 1.0d 78.0d 03-Jan-18 08:00 AM*
Column - 5.5m (0.25mm x 0.25mm) 11.0d 11.0d 78.0d 03-Jan-18 08:00 AM 15-Jan-18 05:00 PM, Column - 5.5m (0.25mm x 0.25mm)
STF2200 Install reinforcement 2.0d 2.0d 78.0d 03-Jan-18 08:00 AM*
STF2210 Erect formwork & bracing 2.0d 2.0d 78.0d 06-Jan-18 08:00 AM*
STF2220 Inspection 1.0d 1.0d 78.0d 08-Jan-18 08:00 AM*
STF2230 Concreting works 2.0d 2.0d 78.0d 09-Jan-18 08:00 AM*
STF2240 Curing works 3.0d 3.0d 78.0d 11-Jan-18 08:00 AM*
STF2250 Dismantle formwork & bracing 1.0d 1.0d 78.0d 15-Jan-18 08:00 AM*
Intermediate Beam (0.25mm x 0.5mm) 10.0d 10.0d 78.0d 15-Jan-18 08:00 AM 25-Jan-18 05:00 PM, Intermediate Beam (0.25mm x 0.5mm)
STF2330 Erect scaffold, stagging, t-prox & soffit 1.0d 1.0d 78.0d 15-Jan-18 08:00 AM*
STF2340 Install reinforcement 2.0d 2.0d 78.0d 16-Jan-18 08:00 AM*
STF2350 Erect formwork 1.0d 1.0d 78.0d 18-Jan-18 08:00 AM*
STF2360 Inspection 1.0d 1.0d 78.0d 20-Jan-18 08:00 AM*
STF2370 Concreting works 1.0d 1.0d 78.0d 21-Jan-18 08:00 AM*
STF2380 Curing works 3.0d 3.0d 78.0d 22-Jan-18 08:00 AM*
STF2390 Dismantle scaffold, stagging, t-prox, soffit & formwork 1.0d 1.0d 78.0d 25-Jan-18 08:00 AM*
Roof Beam (0.25mm x 0.5mm) 10.0d 10.0d 129.0d 16-Jan-18 08:00 AM 27-Jan-18 05:00 PM, Roof Beam (0.25mm x 0.5mm)
STF2260 Erect scaffold, stagging, t-prox & soffit 1.0d 1.0d 129.0d 16-Jan-18 08:00 AM*
STF2270 Install reinforcement including L-Plates for roof truss 2.0d 2.0d 129.0d 17-Jan-18 08:00 AM*
STF2280 Erect formwork 1.0d 1.0d 129.0d 20-Jan-18 08:00 AM*
STF2290 Inspection 1.0d 1.0d 129.0d 21-Jan-18 08:00 AM*
STF2300 Concreting works 1.0d 1.0d 129.0d 22-Jan-18 08:00 AM*
STF2310 Curing works 3.0d 3.0d 129.0d 23-Jan-18 08:00 AM*
STF2320 Dismantle scaffold, stagging, t-prox, soffit & formwork 1.0d 1.0d 129.0d 27-Jan-18 08:00 AM*
Roof Truss, Covering & Accessories 12.0d 12.0d 118.0d 27-Jan-18 08:00 AM 08-Feb-18 05:00 PM, Roof Truss, Covering & Accessories
STF2400 Deliver prefabricated light gauge MS roof truss on-site 1.0d 1.0d 78.0d 27-Jan-18 08:00 AM*
STF2410 Install prefabricated light gauge MS roof truss & bracing 2.0d 2.0d 78.0d 28-Jan-18 08:00 AM*
STF2420 Install purlins 2.0d 2.0d 78.0d 30-Jan-18 08:00 AM*
STF2430 Inspection 1.0d 1.0d 78.0d 01-Feb-18 08:00 AM*
STF2440 Install concrete roof tiles & ridge cap 4.0d 4.0d 78.0d 03-Feb-18 08:00 AM*
STF2450 Install fascia board & bracket for gutter 1.0d 1.0d 118.0d 07-Feb-18 08:00 AM*
STF2460 Inspection 1.0d 1.0d 118.0d 08-Feb-18 08:00 AM*
Floor, Wall, Ceiling & Accessories 27.0d 27.0d 78.0d 03-Feb-18 08:00 AM 07-Mar-18 05:00 PM, Floor, Wall, Ceiling & Accessories
STF2470 Install 225mm thk. brickwall, tie with mortar - Team A & B 4.0d 4.0d 78.0d 03-Feb-18 08:00 AM*
STF2480 Install roller shutter & frame for door and window 3.0d 3.0d 78.0d 07-Feb-18 08:00 AM*
STF2490 Electrical wiring works - carry out by specialist team 4.0d 4.0d 78.0d 11-Feb-18 08:00 AM*
STF2500 External plastering - Team A 3.0d 3.0d 78.0d 15-Feb-18 08:00 AM*
STF2510 Internal plastering - Team B 3.0d 3.0d 78.0d 15-Feb-18 08:00 AM*
STF2520 Install frame & ceiling (external) - Team A 3.0d 3.0d 78.0d 21-Feb-18 08:00 AM*
STF2530 Install frame & ceiling (internal) - Team B 3.0d 3.0d 78.0d 21-Feb-18 08:00 AM*
STF2540 Install gutter & UPVC downpipes 1.0d 1.0d 78.0d 25-Feb-18 08:00 AM*
STF2550 Rendering of floor, install tiles & skirting 4.0d 4.0d 78.0d 25-Feb-18 08:00 AM*
STF2560 Painting of wall (external & internal) & ceiling - undercoat - Team A 4.0d 4.0d 78.0d 01-Mar-18 08:00 AM*
STF2570 Painting of wall (external & internal) & ceiling - finish coat - Team B 4.0d 4.0d 78.0d 01-Mar-18 08:00 AM*
STF2580 Install door & windows 1.0d 1.0d 78.0d 06-Mar-18 08:00 AM*
STF2590 Install GI tray / condiut 1.0d 1.0d 78.0d 07-Mar-18 08:00 AM*
U-Shaped Drain - Team C 11.0d 11.0d 78.0d 08-Mar-18 08:00 AM 20-Mar-18 05:00 PM, U-Shaped Drain - Team C
STF2600 Excavation & levelling works 2.0d 2.0d 78.0d 08-Mar-18 08:00 AM*
STF2610 Erect formwork 1.0d 1.0d 78.0d 11-Mar-18 08:00 AM*
STF2620 Install reinforcement 3.0d 3.0d 78.0d 12-Mar-18 08:00 AM*
STF2630 Inspection 1.0d 1.0d 78.0d 15-Mar-18 08:00 AM*
STF2640 Concreting works 1.0d 1.0d 78.0d 17-Mar-18 08:00 AM*
STF2650 Curing works 2.0d 2.0d 78.0d 18-Mar-18 08:00 AM*
STF2660 Dismantle formwork 1.0d 1.0d 78.0d 20-Mar-18 08:00 AM*
Apron & Ramp - Team C 8.0d 8.0d 78.0d 21-Mar-18 08:00 AM 29-Mar-18 05:00 PM, Apron & Ramp - Team C
STF2670 Backfilling, levelling & compaction works 1.0d 1.0d 78.0d 21-Mar-18 08:00 AM*
STF2680 Erect formwork, install reinforcement 3.0d 3.0d 78.0d 22-Mar-18 08:00 AM*
STF2690 Inspection 1.0d 1.0d 78.0d 26-Mar-18 08:00 AM*
STF2700 Concreting works 1.0d 1.0d 78.0d 27-Mar-18 08:00 AM*
STF2710 Curing works 1.0d 1.0d 78.0d 28-Mar-18 08:00 AM*
STF2720 Dismantle formwork & cleanup site 1.0d 1.0d 78.0d 29-Mar-18 08:00 AM*

Primary Baseline Remaining Work Baseline Milestone Page 2 of 2 TASK filter: All Activities
Actual Work Critical Remaining Work Summary © Oracle Corporation