WOODEN BLOCKS

DEMAG CC2000 300mt Crawler


1 x 5m Grommet in concrete
crane with 48m main boom in
beam 20mm sling
SH mode at 14.00m radius
Chain Block capacity 5 ton

1 x 22m Sling of 32mm

9821 9821 9821


Jacking at four corners

3250

3250

3250
Final position of job, from
here crane shall be used
during dismantling & erection.

Temporary Structure for Jacking Temporary Saddle Temporary Saddle

Temporary Structure for Jacking 4mm Steel Rollers Temporary Structure for Sliding
Temporary Structure for Jacking
Temporary Structure for Sliding
5000

5000

GROUND LEVEL

K1 L1
0 12-03-2018 ISSUED FOR COMMENTS. GURUDEV SINGH S.G. R.K.C.
REV. DATE REVISION BY CHK APPROVED REMARKS

CLIENT:- CHAMBAL FERTILSERS AND CHEMICALS LIMITED

DRAWING TITLE:-
DISMANTLING & ERECTION SCHEME FOR AMMONIA RECEIVER
(11V-01 ) & RECOVERY TOWER ( 11C-05)

PROJECT :- DISMANTLING AND ERECTION WORK FOR REPLACEMENT OF


FOLLOWING EQUIPMENT: CFCL

CONTRACTOR :-
SATNAM GLOBAL INFRAPROJECT LTD, DELHI

JOB NO. UNIT SCALE DRAWING NO. SHEET REV.


- - - SGIL - CFCL-ATR19-002 1 OF 2 0