Anda di halaman 1dari 13

INDEPENDENT SURVEYOR, NDT & TECHNICAL SERVICES

HYDROTEST PROCEDURE

DOC. NO : 007/HT/ISyP/API/IX/2017 REVISION:


PT. INDOTIMAS DATE : September, 2017
00
SYIFA PERKASA PAGE : Page 1 of 13

TABLE OF CONTENTS

Paragraph Description Page

1. Scope 2
2. Purpose 2
3. Reference Code 2
4. Responsibilities 2
5. General 2
6. Vacuum Test 2
7. Hydrostatic Test 3
8. Air Test 5
9. Safety Precautions 6

PT.INDOTIMAS SYIFA PERKASA


Hydrotest Test Procedure for Storage Tank
INDEPENDENT SURVEYOR, NDT & TECHNICAL SERVICES

HYDROTEST PROCEDURE

DOC. NO : 007/HT/ISyP/API/IX/2017 REVISION:


PT. INDOTIMAS DATE : September, 2017
00
SYIFA PERKASA PAGE : Page 2 of 13
1. Scope: 4.3 Tank Technician
This Procedure specifies the requirements of a. Responsible to carryout pressure testing and
Hydrostatic Test, Vacuum Test and Air Test for other activities in support of pressure testing.
Aboveground Water Storage Tank. b. Ensure that all marking around the thank is done
as per the drawing
2. Purpose c. Ensures the pressure gauges used have current
This Procedure describes the equipment and calibrated stickers.
materials to be used and factors to be d. Complete pressure test record and submit copy
considered during the Pressure Test of Storage to program manager.
Tank, and ensure that this procedure shall be
5. General
done in accordance with the Project
5.1 After the completion of all welding works and non-
Specifications and related Standards and Codes.
destructive examinations of bottom plate welds,
shell plate welds, roof plate welds and reinforced
3. Reference Code:
plate welds of the tank
a. ASME Code Sec. I the applicable 2015 Edition
5.2 The tank shall be pressure tested for the
and Addenda,
identifications of leakage. This pressure shall be
b. ASME Code Sec VIII Div. 1, 2015 the carried out as per the approved drawing, approved
applicable Edition and Addenda, ITP and standard API 650.
c. API 650, 2015 Edition Applicable Code For 5.3 This test will divide into following mentioned
Storage Tank stages:
a. Test preliminaries such as Visual Inspection.
4. Responsibilities b. nspection of Tank Bottom Welds (Vacuum Box
4.1 QA/QC Engineer / Inspector Testing).
a. Shall be responsible to witness the test and c. Testing of the Shell Course and Tank Bottom
judge the suitability of work carried out. Settlement (Hydrostatic- Testing).
b. Responsible to make calculations, prepare d. Inspection of Roof-Plate and Reinforcing Plates
documents and layout systems of work. (Air Testing).
c. Assessing the suitability of the method, 5.4 Ensure that all of the mentioned test must perform
medium and test pressure requested given after controlling all of the N.D.T. test reports.
the design of the item submitted for testing. 5.5 Vacuum test is carried out to find any leakage in the
d. Produce written instructions for the bottom plate by the use the vacuum box testing
supervisor and technicians relating to the equipment.
procedures, equipment and personnel to be 5.6 Hydrostatic test is conducted to find any leakage in
employed in the test. the shell plate weld and to check the elevation of
4.2 Construction Supervisor the tank bottom settlement. Potable water shall be
a. Shall be responsible for organizing the test used to fill the tank.
as per this procedure and approved ITP and 5.7 Air test is conducted to check the gas tight of roof
shall also be responsible for maintaining the and reinforced plates of shell openings of the tank.
records duly signed by all concerns.
b. Responsible to ensure that the technicians 6. Vacuum Test
working under his supervision The Vacuum box test is conducted to check soundness of
c. Shall communicate with his management, annular welded joints and all lap joints of bottom plates
client and other contractors. (long seam and short seam).
d. Shall ensure method statements, risk 6.1 Equipment and Material
assessments and permit to work a. The vacuum box test is performed by using a box
requirements are communicated to the with visible window of fiber glass (i.e. 6’’ Wide by
technicians and other personnel. 30’’ long metallic box with a fiber glass). The
PT.INDOTIMAS SYIFA PERKASA
Hydrotest Test Procedure for Storage Tank
INDEPENDENT SURVEYOR, NDT & TECHNICAL SERVICES

HYDROTEST PROCEDURE

DOC. NO : 007/HT/ISyP/API/IX/2017 REVISION:


PT. INDOTIMAS DATE : September, 2017
00
SYIFA PERKASA PAGE : Page 3 of 13
open bottom is sealed against the tank seconds examination time, stop watch to be
surface by a sponge rubber gasket. used after reaching the 21Kpa /designation
b. The test scheme shall have suitable vacuum.
connections, such as necessary valves and 6.4 Evaluation of Defects
calibrated vacuum gauge. a. Bubbles produced by air sucked through the
c. The gauge shall have a range of 21Kpa (6 in. welded seam can detect the presence of defect.
Hg) to 35Kpa (10 in. Hg) for normal leaks b. The tested areas are accepted only when no
and 56Kpa (16 in. Hg) to 70Kpa (20 in. Hg) continuous bubbles formation is observed.
shall be performed for the detection of very c. A minimum light intensity of 100Lux is required
small leaks. for conducting the examination.
d. The test scheme shall be demonstrated with d. Upon satisfactory inspection, a report shall be
sample test block by application bubble prepared for the further activities.
solution at site before conduction of the test 6.5 Repair and Retest
on the job. a. Defects in welds shall be repaired by chipping,
e. The bubble forming solution shall produce a grinding or melting out the defects from one side
film that does not break away from the area or both sides of the joints as required and re-
to be tested, and the bubbles formed shall welding are done.
not break rapidly due to air drying or low b. Only the cutting out of defective joints that is
surface tension. necessary to correct the defect is required.
f. A vacuum can be drawn on the box by any c. After repairing, retest of vacuum box test of
convenient method, such as connection to a welded joint shall be carried out.
diesel motor intake manifold or special 6.6 Cleaning
vacuum pump. After test the area shall be thoroughly cleaned for
6.2 Surface Preparation the further activities.
a. The surface to be examined and all adjacent
areas shall be cleaned thoroughly and free 7. Hydrostatic Test
from all dirt, grease, lint, scale, welding flux, Hydrostatic test is conducted to carry out the leakage in
weld spatters, paint, oil and other the shell plates and also to carry out elevation
extraneous matter that could obstruct measurement of the bottom foundation of tank by using
surface openings. tank foundation settlement method.
b. Prior to vacuum testing all joints shall be 7.1 General Consideration
checked visually. a. The water for hydro test will be provided by
6.3 Procedure of Vacuum Test SWCC, the initial filling of the first and second
a. The temperature of the surface of the part will come from this pipe system source.
to be examined shall not below 40C (400F) b. After the first tank is tested, the water will be
and nor above 520C (1250F). transferred to the second tank. After the second
b. The weld seam on the test shall be applied tank is tested, the water will be transferred to
with a bubble solution for detecting leaks the third and fourth tank for Testing.
prior to placing vacuum box. c. Contractor will furnish the pipe and pumps
c. The foaming shall be minimized by means of required to move the water from tank to tank.
uniform application of bubble solution. d. After the completion of the hydro testing
d. A vacuum can be drawn on the box by any operations for the first and fourth tank,
convenient method, such as connection to a contractor will dispose of the water on site at
gasoline- or diesel motor intake manifold. the designated point.
e. The gauge shall register a partial vacuum of 7.2 Preparation of Hydrostatic Test
at least 21Kpa for inspection of the joints. a. After the completion of all welding works and
f. The required partial vacuum shall be non-destructive examination of tank and all
maintained for greater or either at least 5 welded joints shall be signed off by QC welding
PT.INDOTIMAS SYIFA PERKASA
Hydrotest Test Procedure for Storage Tank
INDEPENDENT SURVEYOR, NDT & TECHNICAL SERVICES

HYDROTEST PROCEDURE

DOC. NO : 007/HT/ISyP/API/IX/2017 REVISION:


PT. INDOTIMAS DATE : September, 2017
00
SYIFA PERKASA PAGE : Page 4 of 13
inspector prior to commencement of the f. Continue filling the tank until the water level
hydrostatic test. reaches the quarter point of the tank height. At
b. Temporary test gaskets shall be used for all this point discontinue filling while the level
fittings and manholes. readings are taken on the 16 points as described
c. The hydrostatic test of tank shall be in above (7.1- Item no.7) and readings are
conducted before permanent external recorded.
piping is connected to the tank. g. If the differential readings do not exceed 1½ mm
d. Cleaning inside the tank and removal of per meter of circumference, the filling of water
temporary jigs and tools shall be completed. shall continue.
e. All shell openings shall be closed by block h. As water is being pumped into the tank. Observe
valves or by appropriate cover plates. the circumference of the tank for any signs of
f. Roof manholes shall be opened while leak or distortion in each shell course. If any
introducing water into the tank or drawing signs appear immediately discontinue filling and
off water. determine the cause. Repair shall be made with
g. Initial tank level readings shall be taken the water level at least 300mm below the point
using 16 equally spaced points marked on being repaired.
the bottom plate projecting out from the i. Take additional readings when the tank is half
bottom shell around the tank at its base. full, three quarter full and full height. The same
h. The above points will be referenced back to criteria for differential settlement as stated in
a permanent benchmark. above (7.1- Item no.7) shall apply to each of the
i. Install temporary plastic tube to be used as a level readings.
water level indicator during hydrostatic test. j. Filling of water into the tank shall be continue
7.3 Procedure of Hydrostatic Test until the level reaches the maximum desired
a. Proper arrangement shall be carried out for height as shown on approved IFC drawing.
the water filling. Pipe connection from the k. The test water will remain in the tank at the
water resource point and providing valves maximum desired height for a period of 48
wherever required. hours. Final level readings shall be taken prior to
b. Potable water shall be used for hydrostatic removing any water from the tank.
testing. l. Water filling schedule and holding period shall
c. To protect urgent uneven settlement, water be in accordance with API 650 as given in below
filling rate shall be controlled. Therefore the table 2:
maximum filling and discharge rate shall be
as per standard API 650 as given in the
below table 1.

7.4 Tank Foundation Settlement


a. For the adequacy of tank foundation
performance, a staged hydrostatic procedure
and an extensive settlement monitoring
d. Filling shall be done in four stages 25%, 50%,
program is performed as per project
75% and 100%. After each stage a load
specification and API 650.
stabilization period shall be observed.
b. Therefore the following tolerable settlement
e. As water rises in the tank, observe the shell
criteria are adopted as a basis for evaluating
fittings for any signs of leakage around the
tank performance during hydrostatic testing
blind flanges.
PT.INDOTIMAS SYIFA PERKASA
Hydrotest Test Procedure for Storage Tank
INDEPENDENT SURVEYOR, NDT & TECHNICAL SERVICES

HYDROTEST PROCEDURE

DOC. NO : 007/HT/ISyP/API/IX/2017 REVISION:


PT. INDOTIMAS DATE : September, 2017
00
SYIFA PERKASA PAGE : Page 5 of 13
Filling of water shall continue while 10m (32ft). A minimum of four diametrical lines
elevation measurements are being made shall be used.
as long as the change in water elevation for 7.5 Removal of Test Water
a set of reading does not exceed 300 mm. a. After the completion of Hydrostatic test, the
c. Shell elevation measurements shall be tank shall be emptied at a maximum water level
made at equally-spaced intervals around variation rate as per specification.
the tank circumference not exceeding 10 m b. Make sure that roof manholes and vents are
(32 ft). open during empty operation of conical roof
d. Install settlement monitoring markers at tank.
eight equally spaced locations along the c. When the first tank has been tested, make
perimeter of the tanks. connections to the second tank through a gate
e. Observed elevations shall be referred to a valve and extend the piping to the designated
permanent benchmark. The level point.
instrument shall be set up at least 1½ times d. When the second tank has been tested, connect
tank diameter away from the tank when the tested tank to the next tank and water to be
tank elevation readings are taken. filled through the system of temporary valves
f. There are six sets of settlement readings and piping.
are required as follows: e. Prior to starting the pumping operation between
- Before start of the hydrostatic test. two tanks, make sure that roof manholes and
- With tank filled to 1/4 test height (±600 vents are open on both tanks.
mm). f. Transfer to the next tank using gravity and a
- With tank filled to 1/2 test height (±600 temporary pump as required to empty the
mm). tested tank.
- With tank filled to 3/4 test height (±600 g. After all water has been removed from the
mm). tested tank, open all manholes and remove all
- At least 24 hours after the tank has temporary blinds and equipment.
been filled to the maximum test height. h. After final draining and drying, brushing, broom
This period may be increased in or vacuum cleaner shall clean surface of the
accordance to the requirement of the tanks bottoms.
project specification. i. QC Inspectors sign the test data sheet at the
- After tank has been emptied of test completion of hydro test.
water.
g. g. If settlement measurements are 8. Air Test
specified by the Purchaser, any differential Air test is carried out to check the gas tight of the
settlement greater than 13 mm per 10 m. roof plate and reinforced plate of shell openings of
of circumference or a uniform settlement the tank.
over 50 mm shall be reported to 8.1 Equipment and Material
contractor. a. Pressure Gauge or Manometer
h. Filling of the tank shall be stopped until b. Blank/Blind Flange with Safety Relief Valve.
cleared by the contractor. c. Soapsuds
i. Internal bottom elevation measurements d. Air Supply System
shall be made before and after hydrostatic
testing. Measurements shall be made at
maximum intervals of 3m (10ft) measured 8.2 Procedure of Air Test
on diametrical lines across the tank. After final welding and clearing the tank, an air test
j. The diametrical lines shall be spaced at shall be conducted to ensure water tightness and
equal angles, with a maximum separation the integrity of welding according to the procedure
measured at the tank circumference of as follows:
PT.INDOTIMAS SYIFA PERKASA
Hydrotest Test Procedure for Storage Tank
INDEPENDENT SURVEYOR, NDT & TECHNICAL SERVICES

HYDROTEST PROCEDURE

DOC. NO : 007/HT/ISyP/API/IX/2017 REVISION:


PT. INDOTIMAS DATE : September, 2017
00
SYIFA PERKASA PAGE : Page 6 of 13
a. The tank workers shall prepare the test q. Release the air pressure once the test is
equipment and materials such as; pressure completed then put back all components/parts
gauge or manometer, testing piece, supply that have been removed.
air and soapsuds etc.,
b. Before starting the air pressure test, water 9. Safety Precautions
shall be filled to 50mm below the curb a. The safety measures shall be implemented during
angle. testing activities and the contractor shall provide
c. Cleaning and visual inspection of entire the necessary safety equipment, communication
welding of roof plates and all roof equipment, access barriers etc.
accessories shall be carried out prior to test. b. Contractor shall issue a statement to all persons
d. A manometer of suitable range shall be connected with testing, warning of the hazards of
connected to the roof nozzle with ¼’’ failure under pressure.
diameter PVC tube for measurement of c. There is a possibility that workers can take
pressure remedial action once minor leakages are noticed
e. Inlet connection shall be done with ½’’ hose
before total failure occurs.
from the compressor outlet to one of the
d. Hydrostatic tests are conducted under the
roof nozzle.
constraints of projects specifications.
f. To regulate the pressure, valves shall be
e. Air/gas used for Air test is compressible to large
provided on both ends.
extent and has very high potential energy stored
g. Once all nozzles and manhole are closed,
pressure shall be applied slowly inside the when compressed.
roof by controlling the isolation valves. f. Ensure that no any worker shall present inside the
h. Once the required tank prior to pressure test.
i. Set the testing piece to the desired filling g. Use and storage of any compressed gas under high
point of air either on manhole or air vents. pressure can be extremely dangerous if proper gas
j. Fill and press up the tank with compressed handling procedures are not observed.
air until it reaches 2.2 Psi on the pressure h. Where the test system is testing using
gauge or an equivalent water level in the pressurization above its normal working level, it
manometer and hold at this pressure for at follows that the tester should be prepared for the
least for 1 hour. consequences of failure.
k. Observe the pressure gauge or water level i. This means that there may need to be protective
in the manometer if it remains in the barriers or screens, but all such precautions will be
desired test pressure. specifically dedicated to the risk involved in the
l. If this pressure remains the same then apply test.
soapsuds to welding seams or joint and the j. The technician must be conscious at all times of the
areas to be check for leaks. potential for a rise in temperature to significantly
m. If the pressure decreases, re-check the increase pressure.
possible air passage and blank-off or k. Safety officer must be present at site during test.
retighten. l. Tested & certified Lifting equipment shall be used
n. If there are leaks then identify and mark the
for lifting and shifting purpose.
exact location of defects.
m. Safety Precautions shall be followed during
o. Release the air pressure, rectify the leak and
fabrication and erection as per project
retest again until successful passed the test
specification.
in the presence of Client QC Engineer.
n. Welding cables and power cables to be laid
p. The inspection and acceptance report shall
be fully accomplished and signed by the properly as per Instrumentation and Electrical rules
Clients representative, Tank Supervisor and and local state govt. rules and regulation.
QC Engineer. o. Proper housekeeping and clean condition shall be

PT.INDOTIMAS SYIFA PERKASA


Hydrotest Test Procedure for Storage Tank
INDEPENDENT SURVEYOR, NDT & TECHNICAL SERVICES

HYDROTEST PROCEDURE

DOC. NO : 007/HT/ISyP/API/IX/2017 REVISION:


PT. INDOTIMAS DATE : September, 2017
00
SYIFA PERKASA PAGE : Page 7 of 13
maintained in the fabrication shop and site as
per requirement.
p. Wear proper PPE i.e. tall protection harness,
goggles etc.
q. Clean and clear the area and return the used
equipment and materials to the tool room or
shop.
r. Conduct hazard assessment and safety
meeting.
s. Barricading of Tank, First-Aid kit and
emergency phone number shall be available.
t. The contractor shall provide patrols to all
around the tank to watch any special points of
hazards during pressure test of tank.
u. Safety sign boards both in English and
Indonesia language shall be posted at
appropriate locations during tank testing the
display shall be "TANK UNDER PRESSURE TEST
KEEP AWAY".

PT.INDOTIMAS SYIFA PERKASA


Hydrotest Test Procedure for Storage Tank
INDEPENDENT SURVEYOR, NDT & TECHNICAL SERVICES

HYDROTEST PROCEDURE

DOC. NO : 007/HT/ISyP/API/IX/2017 REVISION:


PT. INDOTIMAS DATE : September, 2017
00
SYIFA PERKASA PAGE : Page 8 of 13
REPORT SAMPLE

PT.INDOTIMAS SYIFA PERKASA


Hydrotest Test Procedure for Storage Tank
INDEPENDENT SURVEYOR, NDT & TECHNICAL SERVICES

HYDROTEST PROCEDURE

DOC. NO : 007/HT/ISyP/API/IX/2017 REVISION:


PT. INDOTIMAS DATE : September, 2017
00
SYIFA PERKASA PAGE : Page 9 of 13
0 % TANK SETTLEMENT REPORT

PT.INDOTIMAS SYIFA PERKASA


Hydrotest Test Procedure for Storage Tank
INDEPENDENT SURVEYOR, NDT & TECHNICAL SERVICES

HYDROTEST PROCEDURE

DOC. NO : 007/HT/ISyP/API/IX/2017 REVISION:


PT. INDOTIMAS DATE : September, 2017
00
SYIFA PERKASA PAGE : Page 10 of 13
25 % TANK SETTLEMENT REPORT

PT.INDOTIMAS SYIFA PERKASA


Hydrotest Test Procedure for Storage Tank
INDEPENDENT SURVEYOR, NDT & TECHNICAL SERVICES

HYDROTEST PROCEDURE

DOC. NO : 007/HT/ISyP/API/IX/2017 REVISION:


PT. INDOTIMAS DATE : September, 2017
00
SYIFA PERKASA PAGE : Page 11 of 13
50 % TANK SETTLEMENT REPORT

PT.INDOTIMAS SYIFA PERKASA


Hydrotest Test Procedure for Storage Tank
INDEPENDENT SURVEYOR, NDT & TECHNICAL SERVICES

HYDROTEST PROCEDURE

DOC. NO : 007/HT/ISyP/API/IX/2017 REVISION:


PT. INDOTIMAS DATE : September, 2017
00
SYIFA PERKASA PAGE : Page 12 of 13
75 % TANK SETTLEMENT REPORT

PT.INDOTIMAS SYIFA PERKASA


Hydrotest Test Procedure for Storage Tank
INDEPENDENT SURVEYOR, NDT & TECHNICAL SERVICES

HYDROTEST PROCEDURE

DOC. NO : 007/HT/ISyP/API/IX/2017 REVISION:


PT. INDOTIMAS DATE : September, 2017
00
SYIFA PERKASA PAGE : Page 13 of 13
100% TANK SETTLEMENT REPORT

PT.INDOTIMAS SYIFA PERKASA


Hydrotest Test Procedure for Storage Tank

Anda mungkin juga menyukai