PR’s answers received on 05 Jan 2018 in response to my 19 Nov 2017 Section 20 Observations
21 July 2017
Dear Madam/Sir
Potter Raper have provided the tenants of Salisbury Estate with three cost analyses for heating works about
which I have some queries. The documents will be referred to as follows:
CBA1: dated Dec 2015 Appendix ‘C’ of the “Feasibility and Budget Costs Report and Option
Appraisal for Renewal for Underground Heating and Pipework at Salisbury Estate. London, SE17”
dated December 2017
CBA2: issued Feb 2017 ‘Salisbury Estate Life Cycle Cost Comparison’ issued February 2017
CBA3: issued Jun 2017 ‘Life Cycle Cost Comparison Rev H Salisbury Estate issued June 2017.
1. In CBA1 there are 34 items detailed totalling £2,990,562.00. This appears to equate to ‘Capital Cost
Assessment’ for Option 1-Whole Communal Heating System in CBA2 where there are 5 items totalling
£1,886,621 and CBA3 where there are 4 items totalling £2,000,000.00. Please provide a breakdown
for the CBA2 and CBA3 totals by the 34 original items from CBA1 and an explanation of how a saving
of 33% relative to CBA1 has been achieved.
The document dated December 2015 is not a CBA but a feasibility estimate. And such was split into
sections based on the Mechanical Consultants findings. The document Ms Barwell refers to as CBA2
(actually should be called CBA1) is based on tenders received from contractors. The saving
mentioned is achieved as based on actual tendered figures not an estimate also for a different
scope of works . Also because when tendered the works were split into different sections/headings.
To try and split out into sections from original feasibility estimate would be subjective as to where
costs went, therefore a futile exercise.
2. CBA2 and CBA3 have a maintenance/Running Cost figure for Year 1 for the individual boiler option but
this is considered to be “included” in Year 1 for the District Heating System (DHS) option. Please
explain why the assumption is difference between the two CBAs and why there is no maintenance or
running costs for the DHS in Year 1 but there is for individual boilers.
No maintenance in 1st year as would be carried out by contractor and therefore included within
capital costs.(this is the case on all schemes)
3. Both CBA2 and CBA3 calculate the Net Present Value (NPV) for Year 1 of the Individual Boilers using
the same discount rate as for Year 2:
Please explain why the following typical yield curve calculation was not used:
Year 1: Annual cost x 1/1.03^1 (CBA2 = £26,857; CBA3 = £127,009)
Year 2: Annual cost x 1/1.03^2 (CBA2 = £26,596; CBA3 = £125,776)
1
Year 3: Annual cost x 1/1.03^3 (CBA2 = £26,338; CBA3 = £124,555)
Costs are taken at present value Year 0 then adjusted year on year up to year 40 by the
stated inflation figure of 2% in line with the Bank of England’s target inflation rate. Costs in
future years are then adjusted by a discount rate of 3% for the calculation of NPV. (3% is the
value stated by the Cabinet Office for long term discount rates period 31-75 years) to a net
present value figure to allow comparison taking into account when future payments over the
This is the definition of a standard yield curve, and that which I used in my initial analysis above.
Potter Raper have not followed this methodology as you will see in the highlighted number above
and this is what I am trying to get an answer to- why have they used a different Year 1 formula to
the norm? They still have not answered this question, they have simply given me the definition of
a yield curve, which they have not followed
4. In CBA2 an undiscounted allowance of £300,528 is made in the DHS option in Year 5 for “Internal
works to properties” (£280,633 if the Year 5 maintenance costs of £19,894 is deducted). Please
explain where this is accounted for in CBA3.
In CBA 2 (actually CBA1) internal works to properties were included, for both options, as at the
time we were going to be doing so. In CBA3 (Actually CBA2 ) there is no allowance for internal
works in the individual or shown for communal. (However FYI there is an allowance for limited
remedial internal works within capital costs for communal)
5. Please provide details of how the undiscounted CBA3 Year 2 running costs for the DHS of £138,312.51
and the Year 1 running costs for individual boilers of £130,819.76 were derived.
Costs for both options were based on supplied running costs, submitted and requested from
Salisbury Estate, Tenants and Residents Association for 4 Salisbury Close and 22 Chatham Street.
These were then extrapolated (using bed weighting and typical internal areas) to take account of
size and type of property and properties that are disconnected.
6. The undiscounted figure provided for Individual Boilers in Year 13 of CBA3 is £725,713.01 (see table
below). The Year 12 running cost figure adjusted for inflation gives a Year 13 running cost of
£165,911.09, meaning the cost for the boiler replacement in Year 13 is £559,801.92. ie:
If the Year 13 boiler replacement figure is inflation-adjusted to Year 26 then the boiler replacement
cost is £724,163.48. The Year 25 running cost figure adjusted for inflation gives a Year 26 figure of
£214,623.68, meaning the total for Year 26 should be £938,787.16. ie
Please explain why CBA3 gives a Year 26 total of £953,270.43, as this appears to be the Year 27
2
Boiler replacement figure plus the Year 26 Running Costs for the total Year 26 figure (see purple
figures below).
Answer 6,7,8 noted there was a formula error within 1 cell picking up the year 12 replacement
costs rather than year 13. Once adjusted correctly it increases the overall cost of the individual
boiler option by 0.098%
7. Similarly, please explain why the Year 39 total includes the Year 39 running costs but the Year 40
boiler costs (see blue figures below) instead of £1,190,609.11
See answer to 6
8. Extrapolating the Year 13 boiler replacement cost of £559,801.92 back to the Year 0 pre-inflation
figure (green figures below) results in a unit price of £1,940.56. Please explain how this relates to the
stated allowance of £1800 per unit (pink figures below).
See answer to 6
Ms Barwell’s questions the accuracy and suggest the 0.098% error identified makes the cost for
individual boilers lower rather than higher. As in our previous response it was duly noted that one
cell formula (year 13 replacement) was linked to the year 12 replacement costs rather than year
13.
Once corrected this leads to an increase. The replacement costs are calculated from the base date
year, then a yearly inflation figure is applied, to calculate the future figure. For that reason, the
costs increase each year, so year 13 would be more than year 12. Therefore by correcting this
discrepancy, it would overall increase the costs of the individual boiler option.
Note - Potter Raper’s 05 Jan 2018 answer is now that the starting cost for the boilers is £1,940.56
in order to include access costs (from their response to my 19 November Section 20 Observations.
My original question above asked how the their £1,940.56 starting figure related to the stated
allowance of £1800 but they did not mention the inclusion of access costs until 05 Jan 2018 )
9. The BCIS component life schedules do not seem to be publicly available. In the Potter Raper
document to which CBA1 was appended page 3 states: “…such long life assets as the district heating
pipework, if correctly specified, should be suitable to deliver heat without issue now considered with a
life expectancy of between 35 and 50 year period.” Please explain why the most optimistic maximum
life span of 50 years is used for the DHS option in CBA2 and CBA3 rather than the average of 42.5
years.
The CIBSE District Heating Manual for London [GLA] it is expected that with modern installation
materials and techniques new installations are expected to “achieve life-times in excess of 50
years”. The 35-50 years mentioned is the estimate life span of the existing underground pipework.
Improvements in materials, installation and manufacturing mean a longer lifespan is expected.
pipework. This would put the communal system life cycle cost at £6,384,391. This is lower
This excludes Evora's incorrectly stated costing for Value Engineered GFCH, which doesn't
allow for access scaffold and multiple building height flue replacements and additional fire
protection measures, and is incorrectly stated within figure 2. Pg 19 GFCH (Value Engineered)
£6,729,198.93.
Not sure why they are bringing the Evora LCC costings into this - I have never mentioned them.
10. Please explain how credit taken for components with remaining lifespan was calculated in all CBAs.
Residual value at year 40 is calculated by, number of years lifespan pro rata'd to find yearly cost.
Then that yearly cost is applied to lifespan remaining at year 40 to calculate residual value.
Residual value at year 40 is calculated by the number of year’s lifespan remaining, divided by
the total lifespan of the component. This gives a percentage of value remaining at year 40. costs
with interest applied. This can be adjusted using the discount rate method as before to
4
Inflation = 2% Discount rate = 3% Properties= 223
Running costs Boiler cost Annual cost NPV
Yours faithfully,
*********************************************************************************
After receiving Potter Raper’s response in green I emailed this to Bola on 28 Jul 2017 and received the
5
purple response on 28 Aug 2017. Note: part of the response is under question 8 above in order that
the discussion about each point is kept together.)
Thank your for forwarding the responses from Potter Raper. I have not yet reviewed them fully but
will respond fully when I have. However, in the meantime, you will note that their response to my
questions 6. 7., and 8. below was that the calculations they have provided are not correct (I need to
review fully, but on first glance they also appear to have made another error in their response since
the correct calculation reduces the cost for individual boilers rather than increasing it). Since Potter
Raper has repeated calculation errors in all the CBAs provided to the council and tenants (they have
stated that the report dated Dec 2015 is not a CBA) I would like to know who in the council has
reviewed these figures and what their qualifications to do so are?
See also Q8 above.
Also maybe in the interest of explaining why a communal system would likely be more cost
effective, if you list out the works involved in each scheme side by side it becomes in my mind clear
which scheme would likely have a lower initial cost.
Individual Communal
Trenching for upgrade of gas mains Trenching for district heating pipework
Potter Raper make our point for us here as to why costing for immersion heating is required - only 3
items on the ‘Individual’ list are required for non-gas options. The table would look like this:
Individual Communal
Installing 200+ Electrical Boilers in existing hot water Trenching for district heating pipework
tank cupboards
Electrical works to 200+ properties to connect boilers Replacing district heating pipes
I received no response from the council regarding who reviewed the figures and what their
qualifications to do so are.