Government of India (Ministry of Road Transport & Highways)

Through
Government of Andhra Pradesh
Roads & Buildings Department ( National Highways)
AUTHORITY ENGINEER : M/s WADIA TECHNO-ENGINEERING SERVICES LTD.
CONTRACTOR : M/s BSCPL Infrastructure Ltd

RFI Submission Chainage RFI Inspection Type of 


Sl.No RFI NO. Description of Item Side RFI Status Remarks
Structure
Date Time From To Date Time
1 REP/NH‐216/STR/088 25‐07‐18 9.00 AM Check the excavation for Line Drain 160+050 160+100 RHS 25‐07‐18 4.00 PM Drain

Checking and allow to M15 PCC 
2 REP/NH‐216/STR/092 25‐07‐18 5.00 PM 160+050 160+100 RHS 26‐07‐18 4.00 PM Drain
leveling Course for Line Drain

3 REP/NH‐216/STR/093 26‐07‐18 5.00 PM Check the excavation for Line Drain 160+000 160+050 RHS 27‐07‐18 10.00 AM Drain

Checking and allow to M15 PCC 
4 REP/NH‐216/STR/094 26‐07‐18 5.00 PM 160+000 160+050 RHS 27‐07‐18 4.00 PM Drain
leveling Course for Line Drain

5 REP/NH‐216/STR/101 30‐07‐18 5.00 PM Check the excavation for Line Drain 151+800 151+900 LHS 31‐07‐18 10.00 AM Drain

6 REP/NH‐216/STR/102 30‐07‐18 5.00 PM Check the excavation for Line Drain 159+800 160+000 RHS 31‐07‐18 11.00 AM Drain

Checking and allow to M15 PCC 
7 REP/NH‐216/STR/103 30‐07‐18 5.00 PM 151+800 151+900 LHS 31‐07‐18 4.00 PM Drain
leveling Course for Line Drain
Checking and allow to M15 PCC 
8 REP/NH‐216/STR/104 30‐07‐18 5.00 PM 159+900 160+000 RHS 31‐07‐18 5.00 PM Drain
leveling Course for Line Drain

9 REP/NH‐216/STR/107 01‐08‐18 5.00 PM Check the excavation for Line Drain 151+900 152+000 LHS 02‐08‐18 11.30 AM Drain

Checking and allow to M15 PCC 
10 REP/NH‐216/STR/108 01‐08‐18 5.00 PM 151+900 151+950 LHS 02‐08‐18 5.00 PM Drain
leveling Course for Line Drain
Checking and allow to M30 RCC for 
11 REP/NH‐216/STR/111 02‐08‐18 5.00 PM 160+000 160+100 RHS 03‐08‐18 11.30 AM Drain
Drain Raft

12 REP/NH‐216/STR/129 07‐08‐18 5.00 PM Check the excavation for Line Drain 159+900 160+100 LHS 08‐08‐18 11.30 AM Drain

Checking and allow to M15 PCC 
13 REP/NH‐216/STR/130 07‐08‐18 5.00 PM 160+000 160+100 LHS 08‐08‐18 2.00 PM Drain
leveling Course for Line Drain
Checking and allow to M30 RCC for 
14 REP/NH‐216/STR/131 07‐08‐18 5.00 PM 159+900 160+000 RHS 08‐08‐18 4.30 PM Drain
Drain Raft
Checking and allow to M15 PCC 
15 REP/NH‐216/STR/132 08‐08‐18 5.00 PM 159+800 159+900 RHS 09‐08‐18 10.00 AM Drain
leveling Course for Line Drain

16 REP/NH‐216/STR/133 08‐08‐18 5.00 PM Check the excavation for Line Drain 152+000 152+100 LHS 09‐08‐18 11.00 AM Drain

Checking and allow to M15 PCC 
17 REP/NH‐216/STR/134 08‐08‐18 5.00 PM 151+950 152+050 LHS 09‐08‐18 12.00 PM Drain
leveling Course for Line Drain

18 REP/NH‐216/STR/135 08‐08‐18 5.00 PM Check the excavation for Line Drain 159+800 159+900 LHS 09‐08‐18 2.00 PM Drain