BS 2654: 1989
3 Typical tank foundation pad
A.3.1_ A typical tank foundation pad, an exemple of which
is lustrated in figure 25, is described in A.3.2 to A.3.6.
A3.2 The matarial ina typical foundation snd to raplaca
‘any unsatisctory underlying soft spots, should be sound,
clean and durable. It should bind to form a densa surface
when laid in 180 rom layers ard rolled with # 6 tonnes
to 10 tonnes roller, The top surfece of the pad should
incorporate stable permeable granular drainage layer
‘The core ofthe pad cart be constructed from any highly
‘comoactable, chemically inert, lccally available material
‘that it not susceptibisto frost heave, is non-corrosive and
is of low compressibility end sufficient strength, An annular
ng of coarse granular material may be required to provid
igh edge oad resistance when the locally available mates
has low strength except when confined, e., most sands,
‘The annular ring may alto be required to prevent weshrout
Of fine soils in the event of a bottom leak and provide
protection against erosion ground the tank perimeter
‘A.3.3 Iv is suggested that the surface upon whieh the tank
bottom will rest be constructed to @ height of a minima
‘oF 300 mm plus the expacted settlament above the
surrounding ground level, The surface of the completed
‘foundation should be sloped up from the periahary to the
entre: a slope of 1 in 120 Is recommended es ¢rlnimum,
‘On poor soils, this slope should be increased to compensete
tor extra settlement at the tank centre (For ‘coneddown’
bottoms, s90 4.4.2).
A.3.4 When the profile of the surface is complete it should
‘be covered with a smooth situmensand mix that i 80mm
thick to weatherproof the foundation and provide layer
sufficiantly firm to eaery the necessary traffi and facilitate
walding of the bottom plates, This layer will also retard
corrosion of the tank bottom, Mill see should hava both
removed from the underside ef the bottom plates to
‘inimize corrosion (see 3.2111). This bitumen-sand surface
ing should extend outside the tank periphery to protect
the external surface of the foundation and may need
Festrlmming after the water test and from time to time
during operation to maintain suitable water drainage away
from the tank, Bitumen-sand surfacing should be omitted
where eathodie protection of the tank bottom Is adonted.
50 thick bitum
sand mix
O75 mm PYC pipes oF
equal at not wore than
5m between centres
around periphery, plastic
mesh seraen over inside
open end
All imarsions arn limowes, unless otherwie sated,
Figure 36, Typical tank foundation
Ks
4g 120 min. stope
Zilli lille
Stable permeable compacted
granular drainage layer
‘approximately 150 thick
Thoroughly compacted
chemically inert Fill of
granular or other stable,
heave fee,tow compressibility
eval
¥
%...A.36 A tuiteblo b/tumensand can be produced by hot:
‘mixing in the following proportions by mats:
(a) 8 £ 0.5 % (m/m) non-toxic out back bitumen
‘luxed with kerosina end not creosote"),
(0) 40 1.0% {mm/m) filler: either limestone dust passing
{a sleve of nominal aperture size 75 ym complying with
185410, oF Portidnd cement;
(o} 81 £ 1.5 % (ov/m) clean dry washed send with tha
Bropertios given in table 2 of BS 882, 1201 ; Part 2
1973,
A$ an alternative to the send, crushed rack types 1 to 7,
tag oF limestone in accordance with table 63 of 8S 4987
1973 may be used, fs
‘Some variation of these proportions may be necessary to
suitambont temperature conditions, loceliy aveilable
‘materials, etc,, and it Is recommended that tral mixes be
‘made in order to achieve the correct proportions to sult
‘the particular case,
A.36 A series of 75 mm diameter PVC pipes should bo
placed around the perimetar of the drainage layer and
rotrude through the bitsand facing to the berm to give
warning of any bottom plate leaeage, The pipes should be
ft not more than 5 m intervals and the inst should be
‘covered with @ mesh screen to prevent elogging by mat
‘rom the drainage layer, In special casey it may be
/ecassary to Intraciuce an impermeable layer below the
‘basa of the foundation pad {see figure 35},
A4 Modifications and alternatives to.
typical foundation pads
A.4.1 Where poor subrsail conditions necessitate the use
of a ceinforced concrete raf ard piled foundations, the raft
should be designed in accordance with normal rainforeed
‘concrete practice (see CP 114 or CP 170) and surfaced
with a reduced thickness of bitumen-sand mix as desoribed
nas,
A.B Where a tank with a central itera bottom drainage
sump is required:
(a) on hard ground where ltto settlement Is expected,
may be given a slight fall to the
(b) on poor ground where considerable settlement is
expected, special consideration should be givan tw the
possiblity of unacceptable tensile stresses developing
{n the bottom plates and in such cases e foundation
constructed as recommended In A.4.1 should be used,
A4.3 For high-pressure tanks, it may be nacestary to
_Brevent uplift of the shall due to the combined effects of
vapour pressure and wind movement by means of an
anchorage around the shall bullt into # suitable concrate
ring oF raft,
*Crecaote Maxed bitumen snot considera 1 be aceeptabie in view of
BS 2664: 1989
Where the foundation design inco-pox
care should be taken to ensure that thee
characteristics of the ring wall and the In
495 to result in excessive differential seta
the inner wall ofthe ring beam. Consideration may need
10 be given to the provision of a hinged transition slab in
this trea, A minimum thickness of 60 mm of bitumencand
should be maintained over the conerete
AS Water testing
Whila it is normal prectice to tast aft tanks by filing with
water before commissioning, this filing should be done
under controtied conditions to enaure that foundation
failure does not occur during filing. The water text pressure
is an intogral pert of the foundation design and should be
agreed with a soli mechanics specialist
All tank tests will be carried aut to provide adequate
measured toad/settlemant records.
‘Tae firet tank In @ new area will be the most critical and
fubsequent testing arrangements on other tanks should be
adjusted in the light of the first test results whe
4af0 on similar eub-tll conditions
‘A minimum of four points on tanks under 25 m diameter
{and eight points on tanks ever 25 m diameter thoule be
‘marked around the base of the tank for subsequent levelling
reference, & grester number of points may be required for
large tanks and/or where @ complex settlement pattern is
expected, Bofore wetar Is added to the tank, the levels et
ach reference point should be recorded. Permanent rafe-
Fence levels have to be established in locations unalfected
by tank loading.
AAs o guide, when ground conditions are good and settle-
‘ment is expected to be nesigibe, the tank may be halt.
filed with watar as quickly as practicable, having regerd to
{te size, the pumping facities and water supply available.
‘No ‘urther filling should proceed until levels have been
‘eken and checked ageinst the readings when empty to
{ngure that no uneven settlement is occurring in which cose
filing ean proceed until tho tank is three-quarters full, when
‘evel reacings should be taken again. Provided the tenke
omains level with only slight settlement due to load, filling
{cen then proceed until the tenk is full, when level readings
‘gnin repeated, The full weter lone should be maine
tzind for 48 h and provided levels remain sensibly consi
tent, the tank can be oftloaded prior to ealibration for
service, Provided this tank is satisfactory and subsequent
{enks are founded similarly, the level roadinge at one-half
tnd three-quarters eapacity may be omittad for smell tanks
Of less than 25 m diameter. On weak ground where signti-
ant sottlemonts may be expected or where the initial
fector of safety agains sip feilure Is low, the rate of fling
should be greatly reduced, Somme guidance on the sefe
heights for Initial fling and where pauses in fling are
It ot comtant,
%
63
*