Anda di halaman 1dari 1

CONTRACTING FOR CAPITAL PROJECTS AACE INTERNATIONAL

this project; in order to perform the work, a potential bidder deter-


• current financial capability; mine whether ther have or can acquire the equipment
• safety ratings on past projects; and through purchase, lease, or rental arrangements.
• experienced project team, etc.
• Specialized Knowledge—Along with all of the above, a
Some owners (particularly in the design-build arena) have potential bidder should review pre-bid information to
held open competitions to prequalify potential contractors determine whether their organization has the requisite
followed by preliminary design competitions among pre- skills and knowledge to successfully perform the work
qualified contractors (with limited remuneration for those under the known terms and conditions.
invited to the design competition).
• Risk Analysis—A contractor considering bidding on a
potential project should review the general and supple-
DECISION TO BID mental or special provisions of the contract to determine
how project risk is allocated under the contract. For
Perhaps one of the toughest decisions in contracting is the example, if there is a no damage for delay clause in the
bid/no bid decision that every contractor must make once an contract, or if the contract has no differing site condition
opportunity to bid on a project is identified. The contractor clause, then the contractor’s risk if increased substantial-
needs to carefully examine each potential bidding opportu- ly in the event of delay or it encounters materially differ-
nity. Some of the factors the contractor must consider include ent conditions. This being the case, a potential bidder
the following: needs to determine if their company can survive if such
situations occur during performance of the work.
• Expertise—When considering submitting a bid, a con-
tractor has to determine whether its organization has the • Workload and Other Potential Projects—Finally, a con-
expertise to perform the work. A review of past projects tractor considering bidding on a project needs to think
will determine whether the contractor has done anything about their current workload to see how that may impact
like this project in the past. If not, some thought should equipment, key personnel, logistics, bonding and finan-
be given to whether they are truly capable of performing cial capabilities. Further, a contractor needs to consider
the work. In the alternative, a contractor might consider what other projects are likely to be bid in the same time-
teaming with another through a joint venture, in order to frame that they may want to bid on. A potential problem
assure sufficient expertise to perform the work and to faced by many contractors is multiple projects being bid
spread the risk of the project. at the same time. If a contractor bids on three projects
simultaneously, serious consideration must be given to
• Financial Capability—A contractor considering a bid what happens if they are the successful bidder on all
must look at insurance and bonding requirements, pay- three projects. If this event occurs, can they perform?
ment provisions, and potential project cash flow scenarios
to determine if they have the necessary financial capability
to perform the work and successfully complete the project. KEY CONTRACT CLAUSES

• Bonding Capacity—Many capital projects require both In the administration of contracts, all clauses in the contact
performance and payment bonds to protect the interests are important and must be adhered to to avoid breach of con-
of the owner in the event of contractor failure to com- tract situations. However, some clauses are more important
plete the work or failure to pay subcontractors and ven- than others. Among the more important clauses, in alphabet-
dors. In such cases, part of the contractor’s decision to ical order, are the following:
bid involves their bonding capacity. If a contractor has a • Audit—This clause typically outlines an owner’s right to
bonding capacity of $100 million and already has $85 perform reviews (audits) of contractor costs or records.
million in active projects underway, the contractor may Such clauses ordinarily outline what costs or records are
not be able to bid a new $50 million capital project unless subject to audit, when, and under what circumstances.
they can successfully convince their surety (bonding
company) to increase their bonding coverage limits. • Changes—This clause is critical. This is the clause that
allows the owner to direct changes to the work, including
• Personnel—A contractor considering as bid must look to plans, specifications, time of performance, means, and
its own staffing to determine whether it has sufficient methods. Absent a change clause, an owner is precluded
experienced personnel to perform the work during the from making changes to the work. Of particular impor-
period of anticipated performance. tance in this clause is whether the clause allows the owner
to unilaterally direct changes to the work (in which case,
• Equipment—If a project requires specialized equipment if the contractor refuses to comply with the directive, they

25.12

Anda mungkin juga menyukai