PLANTATION ESTABLISHMENT
Brushing (2 m wide, 200 sqm/md) sqm 3333 11.11 270 2999.7 2,999.70 1.80
Staking (500 spots/md) stake 1667 3.33 270 899.1 899.10 0.54
Hole digging (150 spots/md) hole 1667 11.11 270 2999.7 2,999.70 1.80
Seedling transport/hauling (240 seedlings/md) seedlings 1833 7.64 270 2062.8 2,062.80 1.24
Planting (150 seedlings/manday) seedlings 1667 11.11 270 2999.7 2,999.70 1.80
Tools and materials 2,000.00 2,000.00
SUB TOTAL 2,000.00 44.3 11,961.00 13,961.00 7.18
PERCENTAGE
INFRASTRUCTURE
Nursery facility (1 nursery/400 HA)* 1,250.00 1 270 270.00 1,520.00 0.91
Graded trail (1m, 50m/ha) meter 50 0.33 270 89.10 89.10 0.05
Footpath (1m, 50m/ha) meter 50 0.33 270 89.10 89.10 0.05
Fireline construction (10m, 120m/md) sqm 500 4.17 270 1,125.90 1,125.90 0.68
Fireline maintenance (200 sqm/md) sqm 500 2.5 270 675.00 675.00 0.40
Bunkhouse (1 unit/200 HA) 500 0.55 270 148.50 648.50 0.39
Lookout tower (1 unit/200 HA) 150 0.1 270 27.00 177.00 0.11
SUBTOTAL 1,900.00 8.98 2,424.60 4,324.60 2.59
PERCENTAGE 43.93 56.07