1 PERENCANAAN KONTSTRUKSI REHAB BERAT GEDUNG KANTOR 140 days
2 (TAHAP II)
PEKERJAAN BANGUNAN KANTOR 89 days
3 PEKERJAAN PERSIAPAN 2 days
4 PEKERJAAN TANAH DAN PONDASI BATU KALI 14 days
5 PEKERJAAN BESI DAN BETON 11 days
6 PEKERJAAN DINDING DAN LANTAI 12 days
7 PEKERJAAN LANGIT-LANGIT 12 days
8 PEKERJAAN KUSEN PINTU DAN JENDELA 14 days
9 PEKERJAAN LISTRIK 14 days
10 PEKERJAAN SANITASI 14 days
11 PEKERJAAN ATAP 14 days
12 PEKERJAAN LAIN-LAIN 7 days
13 PEKERJAAN BANGUNAN PENDUKUNG KOPERASI DAN 103 days
14 PENJARA
PEKERJAAN PERSIAPAN 2 days
15 PEKERJAAN TANAH DAN PONDASI BATU KALI 14 days
16 PEKERJAAN BESI DAN BETON 11 days
17 PEKERJAAN DINDING DAN LANTAI 12 days
18 PEKERJAAN LANGIT-LANGIT 12 days
19 PEKERJAAN KUSEN PINTU DAN JENDELA 14 days
20 PEKERJAAN LISTRIK 14 days
21 PEKERJAAN SANITASI 14 days
22 PEKERJAAN ATAP 14 days
23 PEKERJAAN LAIN-LAIN 7 days
24 PEKERJAAN BANGUNAN PENDUKUNG GARASI 92 days
25 PEKERJAAN PERSIAPAN 2 days
26 PEKERJAAN TANAH DAN PONDASI BATU KALI 10 days
27 PEKERJAAN BESI DAN BETON 7 days
28 PEKERJAAN DINDING DAN LANTAI 7 days
29 PEKERJAAN LANGIT-LANGIT 12 days
30 PEKERJAAN LISTRIK 14 days
31 PEKERJAAN DRAINASE 14 days
32 PEKERJAAN ATAP 12 days
33 PEKERJAAN LAIN-LAIN 14 days
34 PEKERJAAN PAGAR 56 days
35 PEKERJAAN PERSIAPAN 2 days
36 PEKERJAAN TANAH DAN PONDASI BATU KALI 14 days
37 PEKERJAAN BESI DAN BETON 7 days
38 PEKERJAAN DINDING PAGAR 14 days
39 PEKERJAAN PINTU GERBANG 14 days
40 PEKERJAAN HALAMAN PARKIR DAN RUANG SATPAM 81 days
41 PEKERJAAN HALAMAN 7 days
42 PEKERJAAN TAMAN 18 days
43 PEKERJAAN LISTRIK 14 days
44 PEKERJAAN POS SATPAM 21 days
45 PEKERJAAN DRAINASE 19 days
46 PEKERJAAN TIANG BENDERA 10 days