Phase 1 :
- PLN Standard - Limitation
i. Study Preparation
ii. Design /Technology
iii. Interconnection requirement
(ex: updating grid code)
iv. Standardized PPA Phase 3
- Gov. RE dev. plan
i. RUEN/RUKN • COD
ii. RE penetration study Phase 2
iii. Local content • Feed-In-Tariff
Regulation
• Direct
Phase 1
Procurement Phase 2 :
• PLN Standard - Feed-In-Tariff
• Gov. RE dev. plan i. RE Quota
ii. Subsidy policy
- Direct Procurement
i. Tender Process
ii. Negotiated Tariff
RE INTEGRATION PROCESS & CHALLENGES
(PROJECT LEVEL)
System Stability
• Power varies with Wind/Solar Resource
• Require Reactive Power Control
• Trip of large Wind/Solar Farm is harm for Voltage Stability.
• Sensitive Area connected to large Wind/Solar Farm can have Impact on
Voltage/Frequency Stability.
• No Contribution of System Inertia from Doubly-Fed Induction Generator
and Fully Rated Converter Generator -> Frequency Stability -> Required
Additional Control
SPECIFIC CHALLENGES FOR INTERMITTENT REGP (2)
System Security
• Wind and large Solar Farm must have ability to control Voltage and
Frequency
• Fault Ride Through Capability
• Require Reactive Power Control for proper Voltage Profile
Power Quality
• Doubly-Fed Induction Generator, Fully Rated Converter Generator and
Inverter System can be the Source of Harmonic, especially connect to
weak Network.
• Voltage Fluctuation -> Flicker, Voltage Imbalance.
• Voltage Dips cause the Disconnection of Wind/Solar Farm and
consequently cause large Inrush Current during Recovery.
Case Study :
PeakPuncak
Beban Load vs Wind Speed
vs Wind Speed
1600 8
1400 7
1200 6
1000 5
800 4
600 3
400 2
200 1
0 0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Peak Puncak
Beban Load Wind
Wind Speed
Speed
Southern Sulawesi Grid : WPP Penetration
Case 1:
Wind power supply drop maximum until 60 MW
Simulation Result:
Frequency = 49,197 Hz
(Frequency relay operate)
Case Study :
1. Peak Load : 58 MW
2. Day Load : 51 MW
3. PV install capacity : 5 MW
4. Connection : 20 kV
5. Percentage of PV install capacity compare to day load: 8.6%
• If full PV (5 MW) operated, there is frequency fluctuation, and load
shedding.
• The maximum capacity of PV, that grid still can operated normally, is 3
MW or 5-6% from day load.
1. Generation with higher ramp rate mostly peak power plant (Gas PP, Hydro PP
with reservoir). To accommodate PV fluctuation, we need to make sure this
generation type configuration enough or system reliability will be worse.
2. If PV operated, peaking generation should be operated too with small
capacity factor, even not at the peaking time. The effect of this condition is
inefficiency and higher operational cost.
3. PLN need to make a standard and regulation (grid code) to accommodate the
renewable energy development.
CONCLUSION
“Integrating Intermittent Renewable Energy Generation Plant (REGP)
the Perspective from System Planning”