URAIAN PEKERJAAN BOBOT %

BULAN LALU BULAN INI S/D BULAN INI TOTAL SETIAP


FISIK BOBOT % FISIK BOBOT % FISIK BOBOT % ITEM AS V/7 (STANDARD)
PEKERJAAN PERSIAPAN 2.89%
1.PENGUKURAN DAN PASANG BOWPLANK 1.31% 100 0.01 0 0.00 100 1.31%
2.89% PROGRES TOTAL 80.31%
2.PEMBUATAN JEMBATAN 1.58 100 1.58 0 0.00 100 1.58%
PEKERJAAN PONDASI 14.05%
3.PEMBESIAN PLAT LAJUR,TAPAK,KOLOM 12/12 5.0% 100 0.05 0 0.00 100 5.00%
4.COR STRAUSS, PLAT TAPAK, SLOOF 8.0% 100 0.08 0 0.00 100 8.00% 14.05%
5.PASANG PEMIPAAN AIR KOTOR 1.05% 70 0.01 30 0.00 100 1.05%
PEKERJAAN PASANG DINDING BATA 25.79%
6.PASANGAN DAN PLESTERAN RATA NOL LANTAI 1.01% 0 0.00 100 0.01 100 1.01%
7.URUGAN LANTAI RATA NOL 5.26% 20 0.01 80 0.04 100 5.26%
8.PEMADATAN DAN RABATAN LANTAI 1.02% 0 0.00 100 0.01 100 1.02%
9.PAS.BATA RATA KUSEN,STEL KUSEN,COR KOLOM 11.00% 0 0.00 100 0.11 100 11.00%
25.79%
10.PAS.BATA GEWEL,COR GEWEL,KPL PELESTERAN 3.87% 80 0.03 20 0.01 100 3.87%
12.COR DEK,LISPLANG DAN KOLOM TERAS 3.63% 40 0.01 60 0.02 100 3.63%
PEKERJAAN PASANG ATAP GENTENG 5.65%
20.PASANG GENTENG DAN BUBUNGAN 5.00% 50 0.03 50 0.03 100 5.00%
21.PASANG BAN PEMBATAS /KOMPRESAN 0.65% 30 0.00 70 0.00 100 0.65%
5.65%
PEKERJAAN PELESTERAN DAN ACIAN DINDING 24.69%
13.PELESTERAN RATA KUSEN LUAR DAN DALAM 6.85% 40 0.03 60 0.04 100 6.85%
14.PELESTERAN RATA RING BALOK LUAR DAN DALAM 4.77% 40 0.02 50 0.02 90 4.29%
15.ACIAN PELESTERAN DALAM BANGUNAN 3.35% 55 0.02 35 0.01 90 3.02%
16.ACIAN PELESTERAN LUAR BANGUNAN 2.73% 10 0.00 0 0.00 10 0.27% 21.13%
17.BENANGAN RUANG DALAM,LUBANG VEN 3.70% 0 0.00 100 0.04 100 3.70%
18.BENANGAN TAMPAK LUAR,DEK TERAS DLL 3.00% 50 0.02 50 0.02 100 3.00%
19.TES PEMIPAAN AIR BERSIH 0.29% 0 0.00 0 0.00 0 0.00%
DINDING BELAKANG BELUM PLESTERAN,BELUM ACIAN
PEKERJAAN TANAH 4.87%
22.URUGAN HAL.DEPAN,BELAKANG,CARPORT 4.87% 50 0.02 50 0.02 100 4.87% 4.87%
PEKERJAAN PASANG KERAMIK DAN STEL PINTU 15.67%
23.PASANG BAK KONTROL DAN TES AIR KOTOR 1.52% 10 0.00 80 0.01 90 1.37%
24.PASANG KERAMIK DINDING DAN PEMB.BAK KONTROL 4.56% 20 0.01 80 0.04 100 4.56%
25.PASANG KERAMIK KM/WC 6.22% 0 0.00 0 0.00 0 0.00% 5.93%
26.PEMBU.KOL'AN 1.43% 0 0.00 0 0.00 0 0.00%
27.PAS.DAUN PINTU,PAS.ANAK KUNCI 1.94% 0 0.00 0 0.00 0 0.00%
PEK.PASANG SANITAIR 1.79%
29.PAS.WASTAFEL,MONOBLOK,KITCHEN SINK ( MEBEL ) 1.50% 0 0.00 0 0.00 0 0.00%
30.TES PEMIPAAN AIR BERSIH 0.29% 0 0.00 0 0.00 0 0.00%
0.00%
PEKERJAAN SARANA LUAR 4.15%
30.PEK.PAGAR DEPAN 3.20% 0 0.00 0 0.00 0 0.00%
31.PEK.PELESTERAN DAN ACIAN PAGAR 0.27% 0 0.00 0 0.00 0 0.00% 0.00%
32.PEK.KEBERSIHAN 0.68% 0 0.00 0 0.00 0 0.00%
CHEKLIST 0.45%
100.00%
80.31%
N/B : PROGRES DI ATAS TIDAK TERMASUK PEKERJAAN, LISTRIK, PLAFOND, CAT
PEKERJAAN LISTRIK : listrik 80%
plafond : progres sedang pemasangan rangka