LARSEN & TOUBRO LIMITED - ECC DIVISION Document No.

ENGINEERING DESIGN AND RESEARCH CENTRE C-BF-WI-16 R0


GUIDELINES FOR CHECKING OVERHEAD TANK WITH STAGING Sheet 1 of 1

S.No ACTIVITY

1 Check if height of staging has been shown


2 Check whether staircase / ladder requirements have been taken care of
3 Check whether ventilation openings in shaft have been provided
4 Check if ightning arrestor detail and aviation light detail have been given
5 Check whether type of water proofing has been mentioned
6 Check if detail of water stops has been furnished
7 Check if detail for Construction joint locations and treatment has been given
8 Check if type of cement used has been specified
9 Check if note on minimum cement content has been given
10 Check if note on special finish on inside, if any, has been given
11 Check for note on addition of waterproofing compound to concrete
12 Check if location of manholes have been marked
13 Check if rung detail has been given
14 Check whether pipe sleeves have been provided as per service rerquirements
15 Check if note on water tightness test, if required, has been mentioned
16 Check if hook provision for maintenance & painting has been made
17 Check if haunch detail , if required, has been given
18 Check if notes on materials, laps, anchorages and cover to reinforcement are given

0 May 15, 2003


Rev. No. Date Prepared by Approved by Issued by