Author(s)
i
ABSTRACT
Pakistan has vast resources of energy potential. there's estimated 1,540 MTOE of coal within
is a choice that Pakistan is exploring, and this report recommends that ultra-
super critical plants be installed within the country to realize bigger units of power generated,
in respect to fuel consumed, once more underscoring the principle of efficiency that forms the
plants so as to curtail environmental footprint and guarantee most utilization of fuel. The
advice is to maneuver towards higher efficiency and lower emissions (HELE), and ultra-
super crucial power plants would be the approach forward. This report
shall cover the upcoming coal fired power plants of the country until 2035.
Keywords:
Ultra-super critical
HELE
Coal fired
Resources
1
UNDERTAKING
I certify that project titled “ Future Coal Power Plants Projects Till 2035”
is my own work. The work has not been presented elsewhere for assessment. Where material
has been used from other sources it has been properly acknowledged / referred.
Abdul Matin
15-ME-166
2
ACKNOWLEDGEMENTS
We are thankful to our honorable Professor Dr. Abid Hussain Who provided us a chance to
enhance our knowledge, gave us the opportunity and guided us during our project assignment. We
really praise to his great efforts. We again extended our deep gratitude and heartiest thanks to all
of them whose creativity, experience, wisdom, skill, constructive criticism, scholastic approach
3
TABLE OF CONTENTS
ABSTRACT ………………………………………………………………………………...…….ii
UNDERTAKING…………………………………………………………………...……iii
ACKNOWLEDGEMENT……………………………………………………………………...…...iv
ABBREVATIONS……………………………………………………………………………...…..x
4
2.8 Siddiqsons Energy Ltd ......................................................................................................... 15
Conclusion ..................................................................................................................................... 20
REFERENCES .............................................................................................................................. 21
5
LIST OF FIGURES
Number Page
6
LIST OF TABLES
Number Page
7
ABBREVIATIONS:
HP : High Pressure
8
CHAPTER 1
Energy
in the Plan as ensuring energy security is one of the important themes of the Vision. Pakistan is
facing a formidable challenge of energy shortages with the demand outweighing its supply. The
energy shortage has adversely affected all sectors of the economy resulting in an annual loss of up
to three per cent of the GDP. Pakistan’s existing energy mix is highly dependent on expensive
fuels, like oil and gas, instead of coal and hydel. In this context, gas accounts for 48 per cent,
followed by oil 33 per cent, hydel 11 per cent, coal six per cent, nuclear two per cent and a small
fraction from imported electricity. Disproportionate reliance on the imported oil, that is 85 per cent
of the total supply, is exerting a strain on the balance of payments besides making the energy mix
unfavourable. The total commercial primary energy mix for 2012-13 was 64.59 MTOE of which
26.5 per cent was from imports and 73.5 per cent was from local indigenous resources. The current
energy mix is heavily based on the subsidised indigenous gas, which is depleting and is left with
useful life of 17 years at the current consumption level. The future demand of primary energy is
9
TABLE 1.1 Primary Energy Mix of Pakistan
power.
10
Sitara Chemical Industries Ltd. Power Plant, located in Faisalabad, Punjab. It is capable
of producing 40 MW of power.
Fauji Fertilizer Power Plant, located in Karachi, Sindh. It is capable of producing 118
MW of power.
Sahiwal Coal Power Plant, located in Sahiwal, Punjab. It is capable of producing 1320
MW of power.
of power.
Port Qasim Coal Power Plant, located in Karachi, Sindh. It is capable of producing 1320
MW of power.
of power.
11
CHAPTER 2
Pakistan Atomic Energy Commission (PAEC) has submitted an application to the National
Electric Power Regulatory Authority (Nepra) seeking power generation licence for the said
power plant.
12
K-Electric signed an agreement with Chinese companies to set up 700 megawatts of coal-fired
power plants. China Datang Overseas Investment Corporation (CDTO) and China Machinery
Engineering Corporation (CMEC) entered into a joint development agreement to develop two
350MW of coal-based power plant with a cost of one billion dollars at Port Qasim. The energy
generated by this project shall be sold to KE under a long term contractual arrangement as allowed
It is located in Mithi, Thar. Seventy per cent work on both mining and power projects have been
completed ahead of schedule and the first electron from Thar Coal Block-II will start generating
power by the end of this year, according to Sindh Engro Coal Mining Company (SECMC) chief
executive officer. The company is just 20 meters away from the first steam coal to supply coal to
660MW mine-mouth power plant. SECMC is a joint venture between Sindh government and
Engro Powergen Ltd. The power plant will be operational in May, 2019.
The second coal-fired power plant of Hubco will generate 1,320 megawatts from two 660MW
units. Coal will be imported from Indonesia and South Korea.
Hub Power Company (Hubco) will have a 24% stake in the power plant while a Chinese
company will have 74% shareholding. Additionally, 2% stake has been reserved for the
13
Balochistan government. Most of the finances are offered by Chinese banks. It is expected to be
operational by August, 2019.
ThalNova Power Thar Private Ltd (TNPTL) has signed the Engineering, Procurement, Construction
(EPC) contract with China Machinery & Engineering Corporation (CMEC) in Beijing recently to develop
the 330 MW Power project in Thar, Sindh. ThalNova is a CPEC power project based on Thar lignite
coal to be located at the power park site within Block II, Thar Coalfields, District Tharparkar, Sindh.
Plant construction will involve site clearing, preparation, grading, excavations and construction
of foundations, excavation of water storage and evaporation pond, construction of roads and other
structures. Power plant turbine’s main equipment and associated parts will be imported to Pakistan
14
and shipped to site on flat bed trailers. Auxiliary machinery, components and structures from
Pakistan will be manufactured and fabricated outside the plant and shipped to the site on flat bed
trailers. These parts will be fabricated and installed on site. Typical activities during the plant
fabrication will include, site preparation and erection of equipment, machinery and structures.
Placement of the vessels and equipment on the foundations, laying of pipes, welding, joining,
Port Qasim Lucky power station is a 660-megawatt (MW) coal-fired power station proposed by
Lucky Electric Power Company Limited in Port Qasim, Pakistan. In March 2016, the Pakistan
Power Infrastructure Board approved the project. The project would cost $1 billion, and would be
financed on a 75:25 debt:equity ratio. Construction work would be performed by SEPCO III
Electric Power Construction. In November 2016, Lucky Electric announced that the plant would
run on domestic coal from the Thar lignite mine, rather than imported coal, in line with government
policy to increase reliance on domestic coal. At the time, Lucky stated that it planned to achieve
financial close by March 2017, and to begin commercial operations by the end of 2019; as of June
2017, however, there had been no announcement of financial close. In December 2016, Lucky
signed an engineering, procurement, and construction (EPC) contract with SEPCO III. In July
2018 it was reported GE Power will provide the boiler and steam turbine technology for the plant,
which is ultra-supercritical.
15
Energy Limited is a special purpose vehicle (SPV) established to develop around 330 megawatts
of Thar coal-fired power generation facility in Block II, district Tharparkar Sindh on a build,
operate and own basis. the company was carrying cash amount of Rs65bn (USD 565mn) as of Mar
2018 and it has also applied for “letter of intent and rights” to develop 350MW of wind and solar
It is an imported coal based power project, situated at Gwadar, in the province of Balochistan,
Pakistan. The primary energy input will be imported coal. It is to have an installed capacity of 300
MW. The estimated cost will be 600 Million USD. China Communications Construction Company
(CCCC) is the project executing company. Gwadar port authority and Gwadar Development authority are
The idea behind Oracle’s 4Mtpa mine and a first stage 660MW power plant at the mouth is based
going to rise.
The cost of realising this project is expected to be US$1.6bn, of which US$1bn will be debt.
16
The firm has agreements and contracts, including an EPC (engineering, procurement
and construction) term sheet and contracts with its Chinese partner SEPCO for both mine and
plant.
A ‘no objection’ letter from the Central Power Purchasing Agency Guarantee Limited (CPPA)
- which buys electricity on behalf of Pakistan’s state-owned electricity grid operator NTDC means
power from the Thar project can be transmitted into the grid. Oracle’s site was recently put on the
priority list on the China-Pakistan Economic Corridor (CPEC), which should result in the fast-
17
CHAPTER 3
Coal is prepared for use by crushing the rough coal to pieces less than 2 inches (5 cm) in size. The
coal is then transported from the storage yard to in-plant storage silos by conveyor belts at rates
In plants that burn pulverized coal, silos feed coal to pulverizers (coal mills) that take the larger 2-
inch (51 mm) pieces, grind them to the consistency of talcum powder, sort them, and mix them
with primary combustion air which transports the coal to the boiler furnace and preheats the coal
in order to drive off excess moisture content. A 500 MWe plant may have six such pulverizers,
five of which can supply coal to the furnace at 250 tons per hour under full load.
In plants that do not burn pulverized coal, the larger 2-inch (51 mm) pieces may be directly fed
into the silos which then feed either mechanical distributors that drop the coal on a traveling grate
or the cyclone burners, a specific kind of combustor that can efficiently burn larger pieces of fuel.
3.2 Working
Coal-fired plants produce electricity by burning coal in a boiler to produce steam. The steam
produced, under tremendous pressure, flows into a turbine, which spins a generator to create
electricity. The steam is then cooled, condensed back into water and returned to the boiler to start
18
Fig 3.2 Working of a Coal- Fired Power Plant
19
Conclusion
From the above analysis and my working experiences in coal-fired power plants. I can easily say
that the power plant is modern day techniques in operation and in working. As we know that
renewable energy is the result to our crisis in electrical power sector. The last government has
achieved a lot, yet there’s a long way to go. If we need to end this power crisis, we all has to play
our part and each government has to dedicate itself to eliminating the crisis. No power plant in the
world is free from problem. It is the responsibility of management to cope with the problems and
resolve them for the growth of the power plant. Sometimes, the management of power plant
realizes the problems but they have not given proper opportunity to implement their strategies in
their respective departments. China collaboration and CPEC proves as a golden opportunity for us
20
REFERENCES
Web Links:
21