Anda di halaman 1dari 4

PANEL SIDE JB SIDE

NO ZONE BUILDING NO PANEL NO. JUNCTION BOX NO. Glanding Termination Glanding Termination
1 ZONE 2 FAR515 FAR515-MDF-301 5150-JE-3002 PLSB PLSB
2 ZONE 2 FAR515 FAR515-MDF-201 5150-JE-2004 PLSB PLSB
3 ZONE 3 FAR515 FAR515-MDF-123 5190-JEI-1016 PLSB PLSB
4 ZONE 3 FAR515 FAR515-MDF-224 5190-JEI-2016 PLSB PLSB
5 ZONE 4 FAR515 FAR515-MDF-223 5150-JEI-2041 PLSB PLSB DONE
6 ZONE 4 FAR515 FAR515-MDF-221 5150-JEI-2012 PLSB PLSB DONE
7 ZONE 4 FAR515 FAR515-MDF-121 5150-JEI-1012 PLSB PLSB DONE
8 ZONE 4 FAR515 FAR515-MDF-124 5100-JEI-1061
9 ZONE 4 FAR511 FAR511-MDF-223 5190-JEI-2009
10 ZONE 4 FAR515 FAR515-MDF-124 5190-JEI-1015 PLSB PLSB
11 ZONE 4 FAR515 FAR515-MDF-224 5190-JEI-2015 DONE DONE
12 ZONE 4 FAR515 FAR515-MDF-121 5150-JEI-1019 PLSB PLSB
13 ZONE 4 FAR515 FAR515-MDF-331 5150-JEI-3008 DONE DONE
14 ZONE 4 FAR515 FAR515-MDF-201 5150-E-2020 DONE DONE
15 ZONE 5 FAR515 FAR515-MDF-301 5150-JE-3012 PLSB PLSB
16 ZONE 5 FAR515 FAR515-MDF-124 5190-JEI-1006 PLSB PLSB
17 ZONE 5 FAR515 FAR515-MDF-121 5150-JEI-1018 PLSB PLSB
18 ZONE 5 FAR515 FAR515-MDF-222 5150-JEI-2018 PLSB PLSB DONE DONE
19 ZONE 5 FAR515 FAR515-MDF-302 5150-JE-3014 PLSB PLSB
20 ZONE 5 FAR515 FAR515-MDF-301 5150-JE-3013 DONE DONE DONE DONE
21 ZONE 5 FAR515 FAR515-MDF-121 5150-JEI-1033 PLSB PLSB
22 ZONE 5 FAR515 FAR515-MDF-331 5150-JE-3048 PLSB PLSB
23 ZONE 5 FAR515 FAR515-MDF-122 5900-JEI-1011 DONE
24 ZONE 6 FAR511 FAR511-MDF-225 5190-JEI-2019
25 ZONE 6 FAR511 FAR511-MDF-223 5190-JEI-2008 DONE DONE
26 ZONE 6 FAR511 FAR511-MDF-123 5190-JEI-1008 DONE DONE
27 ZONE 7 FAR511 FAR511-MDF-121 5170-JEI-1010 PLSB PLSB
28 ZONE 7 FAR511 FAR511-MDF-122 5170-JEI-1009 PLSB PLSB
29 ZONE 7 FAR511 FAR511-MDF-121 5170-JEI-1012 PLSB PLSB
30 ZONE 7 FAR511 FAR511-MDF-122 5170-JEI-1011 PLSB PLSB
31 ZONE 7 FAR511 FAR511-MDF-221 5170-JEI-2012 DONE DONE
32 ZONE 7 FAR511 FAR511-MDF-122 5170-JEI-1008 PLSB PLSB
33 ZONE 7 FAR511 FAR511-MDF-202 5170-JE-2008 PLSB PLSB
34 ZONE 7 FAR511 FAR511-MDF-221 5170-JEI-2008 DONE DONE
35 ZONE 7 FAR511 FAR511-MDF-123 5900-JEI-1002 DONE DONE
36 ZONE 7 FAR511 FAR511-MDF-225 5900-JEI-2005
37 ZONE 7 FAR511 FAR511-MDF-203 5900-JE-2004 PLSB PLSB
38 ZONE 7 FAR511 FAR511-MDF-202 5170-JE-2006 PLSB PLSB
39 ZONE 7 FAR511 FAR511-MDF-225 5170-JEI-2006 PLSB PLSB DONE
40 ZONE 7 FAR511 FAR511-MDF-121 5170-JEI-1004 PLSB PLSB DONE
41 ZONE 7 FAR511 FAR511-MDF-221 5170-JEI-2005 PLSB PLSB DONE
42 ZONE 7 FAR511 FAR511-MDF-301 5150-JE-3050
43 ZONE 7 FAR511 FAR511-MDF-302 5170-JE-3002 DONE
44 ZONE 7 FAR515 FAR515-MDF-123 5900-JEI-1010
45 ZONE 8 FAR519 FAR519-MDF-131 5190-JEI-1007 DONE DONE
46 ZONE 8 FAR519 FAR519-MDF-331 5150-JEI-3025 DONE DONE

Note: For futher details of primary and secondary cable's number, please refer to PLSB Pulling Cable Schedule or field site check.
REMARKS
1) Cable have gland located outside JB. 2) Primary cable is in short length. 3) JB relocate required (action by PLSB)
1) Cable have gland located outside JB. 2) Primary cable is in short length. 3) JB relocate required (action by PLSB)
1) Primary cable not found.
1) Primary cable not found.
1) Piping still in process pressure testing.
1) Piping still in process pressure testing.
1) Piping still in process pressure testing.
1) Primary cable not found. 2) Secondary cable not found.
1) Cable not found.
1) Primary cable & 3 secondary cables no found to JB side. 2) Cable tray no cable.
1) Primary cable & 3 secondary cables no found to JB side. 2) Cable tray no cable.
1) Secondary cable no found.
1) Secondary cable no found.
1) Secondary cable no found.
1) JB have no cable.
1) JB have no cable. 2) Primary cable not found.
1) JB side cable routine need a trench or duct band (due under pipe line).
1) JB side cable routine need a trench or duct band (due under pipe line).
1) JB side cable routine need a trench or duct band (due under pipe line).
1) JB side cable routine need a trench or duct band (due under pipe line).
1) JB side cable routine need a trench or duct band (due under pipe line).
1) JB side cable cannot reach due no trench.
1) JB side cable cannot reach due no trench. 2) No TS/no drawing for this cable.
1) JB side cable cannot gland due of excavation incomplete.
1) JB side cable cannot gland due of excavation incomplete.
1) JB side cable cannot gland due of excavation incomplete.
1) Primary & secondary not found and cable routine need a trench or duct band (due under pipe line).
1) Primary & secondary not found and cable routine need a trench or duct band (due under pipe line).
1) Primary & secondary not found and cable routine need a trench or duct band (due under pipe line).
1) Primary & secondary not found and cable routine need a trench or duct band (due under pipe line).
1) Primary & secondary not found and cable routine need a trench or duct band (due under pipe line).
1) Primary & secondary not found and cable routine need a trench or duct band (due under pipe line).
1) JB gland plate hole too small for cable glanding (adapter required).
1) Primary & secondary cable not found due obstructions.
1) Relocate JB location (PLSB advised).
1) Relocate JB location (PLSB advised). 2) Cable & drawing not found.
1) Relocate JB location (PLSB advised).
1) JB gland plate hole too small for cable glanding (adapter required).
1) Secondary cable not found due obstructions.
1) Secondary cable not found due obstructions.
1) Secondary cable not found due obstructions.
1) Primary & secondary cable not found due obstructions.
1) Primary cable not found at panel side. 2) JB primary & secondary cable not found.
1) Primary cable not found at panel side. 2) JB primary & secondary cable not found.
1) JB secondary cable cannot reached to JB location.
1) JB secondary cable cannot reached to JB location.