One Week Look Ahead Schedule2013.11.19~2013.11.

23
Working alread target
项目名称 施工项目Construction Starting Completion time y Up to date Total Qty. Cumulativ
location/room name Unit
Name item time time limitation alread Qty e%
(Day) y
air duct with flange 24/Nov/13 30/Nov/13 7 % 30 40 70 100 70%
1 roof fabrication
fire damper 24/Nov/13 30/Nov/13 7 % 0 60 60 100 60%
2 roof installation
air duct supports
3 roof fabrication and 24/Nov/13 30/Nov/13 7 % 10 40 50 100 50%
installation
12.6m wash
exhaust fan
4 and installation fan with 24/Nov/13 25/Nov/13 2 % 0 100 100 100 100%
cleaner's duct joint
room
CCB fire damper
5 12.6m CCR installation
24/Nov/13 28/Nov/13 5 % 0 100 100 100 100%

6 12.6m CCR duct test 26/Nov/13 30/Nov/13 5 % 0 100 100 100 100%
and corridor

battery room
main duct &fire
7 to AC damper fabrication 25/Nov/13 30/Nov/13 6 % 0 25 25 100 25%
equipment and installation
room

8 0m wash room ductinstallation


and exhaust fan 24/Nov/13 25/Nov/13 2 % 0 100 100 100 100%

relay room 24/Nov/13 30/Nov/13 7 % 80 20 100 100 100%


9
substati and outside duct install
on
relay room 1install
control 10 NO fire damper 24/Nov/13 30/Nov/13 7 % 0 100 100 100 100%
room
duct and exhaust fan 24/Nov/13 30/Nov/13 7 % 0 100 100 100 100%
11 wash room installation
MV
switch supply and return
gear 12 0m to roof main duct with fire 24/Nov/13 30/Nov/13 7 % 0 40 40 100 40%
damper installation
room
comprehe pipe supports
nsive pipe rack 24/Nov/13 30/Nov/13 7 % 80 20 100 100 100%
13 installation
pipe top
rack pipe sfitting 24/Nov/13 30/Nov/13 7 % 0 40 40 100 40%
exhaust fan with
hydrogen 14 wash room duct installation 24/Nov/13 27/Nov/13 4 % 0 100 100 100 100%
fan
admin 15 first floor 24/Nov/13 30/Nov/13 7 %
pipe fitting
fire pump house
pump switchgear flow fan 24/Nov/13 30/Nov/13 7 % 0 0 0 150 0%
house 16 room installation
Chemical flow fan 24/Nov/13 30/Nov/13 7 % 0 3 3 150 2%
flow fan 17 Building installation
material 18 wood piad for pipe 24/Nov/13 30/Nov/13 7 % 20 20 100 20%
purchase
arrive 24/Nov/13 25/Nov/13 2 % 100 100 100 100%
19 damper sample
备注Remark

total 82m 60m


complete

total 5 NO.S

total 24 piece

1 NO

to AC
equipment
room total 24m
2*12m up
to roor

320m

next week
all
complete

Saturday
arrive