2018
Estimasi Aspal Minyak Pemakaian Aspal Minyak dan Aspal
e
Panjang Jalan Pemakaian Tack Coat Buton
No Nama Paket/Ruas No Mata Pembayaran Pekerjaan Satuan Volume
Efektif Kadar Aspal Prime Coat
Optimum (%). (LTR) Aspal Minyak Aspal Buton
Divisi 6. Perkerasan Aspal
1 37.31 Km PELEBARAN JALAN BTS. PROP. SULBAR ‐ BTS. KOTA 6.1 (1)(a) Lapis resap pengikat ‐ aspal cair liter 72,801.21 80:100 72,801.21
PINRANG ‐ 1 6.1 (2)(a) Lapis perekat ‐ aspal cair liter 152,547.63 30:100 152,547.63
6.3 (5a) Laston Lapis Aus (AC‐WC) ton 25,508.85 6.00 25,508.85
6.3 (5c) Laston Lapis Aus (AC‐WC L) ton 2,311.02 6.00 2,311.02
6.3 (6a) Laston Lapis Antara (AC‐BC) ton 17,731.49 5.80 17,731.49
6.3 (6c) Laston Lapis Antara (AC‐BC L) ton 25,942.66 5.80 25,942.66
6.3 (7a) Laston Lapis Pondasi (AC Base) ton 15,082.29 5.50 15,082.29
LTBA Kasar ton 5,421.45 5,421.45
Divisi 6. Perkerasan Aspal
2 19.93 Km PELEBARAN JALAN BTS. PROP. SULBAR ‐ BTS. KOTA 6.1 (1)(a) Lapis resap pengikat ‐ aspal cair liter 44,829.00 80:100 44,829.00
PINRANG ‐ 2 6.1 (2)(a) Lapis perekat ‐ aspal cair liter 74,870.78 30:100 74,870.78
6.3 (5a) Laston Lapis Aus (AC‐WC) ton 14,143.48 6.00 14,143.48
6.3 (5c) Laston Lapis Aus (AC‐WC L) ton 1,674.43 6.00 1,674.43
6.3 (6a) Laston Lapis Antara (AC‐BC) ton 4,459.93 5.80 4,459.93
6.3 (6c) Laston Lapis Pondasi (AC Bc L) ton 16,744.46 5.50 16,744.46
6.3 (7a) Laston Lapis Pondasi (AC Base) ton 9,966.75 9,966.75
LTBA Kasar ton 1,554.37 1,554.37
Divisi 6. Perkerasan Aspal
3 4.0 Km PRESERVASI DAN PELEBARAN JALAN PANGKAJENE 6.1 (1)(a) Lapis resap pengikat ‐ aspal cair liter 21,060.00 80:100 21,060.00
SIDRAP ‐ ANABANUA 6.1 (2)(a) Lapis perekat ‐ aspal cair liter 8,489.25 30:100 8,489.25
6.3 (5a) Laston Lapis Aus (AC‐WC) ton 314.32 6.00 314.32
6.3 (6a) Laston Lapis Antara (AC‐BC) ton 394.68 5.80 394.68
6.3 (7a) Laston Lapis Pondasi (AC Base) ton 527.07 5.50 527.07
SKh‐5.6.3.1.(1a) CBA‐Asblawele Lapis Aus (AC‐WC ASbLawele) ton 1,996.70
SKh‐5.6.3.1.(2a) CBA‐Asblawele Lapis Antara (AC‐BC ASbLawele) ton 3,016.82
SKh‐5.6.3.1.(3a) CBA‐Asblawele Lapis Base (AC‐Base ASbLawele) ton 4,034.02
SKh‐5.6.3.1.(4) Aspal Keras ton 332.92 332.92
SKh‐5.6.3.1.(5) Asbuton Lawele Butir ton 1,042.27 1,042.27
Divisi 6. Perkerasan Aspal
4 4.6 Km PRESERVASI DAN PELEBARAN JALAN TARUMPAKAE ‐ 6.1 (1)(a) Lapis resap pengikat ‐ aspal cair liter 32,681.25 80:100 32,681.25
BTS. LUWU 6.1 (2)(a) Lapis perekat ‐ aspal cair liter 13,072.50 30:100 13,072.50
6.3 (5a) Laston Lapis Aus (AC‐WC) ton 400.89 6.00 400.89
6.3 (6a) Laston Lapis Antara (AC‐BC) ton 601.34 5.80 601.34
6.3 (7a) Laston Lapis Pondasi (AC Base) ton 801.78 5.50 801.78
SKh‐5.6.3.1.(1a) CBA‐Asblawele Lapis Aus (AC‐WC ASbLawele) ton 3,117.32
SKh‐5.6.3.1.(2a) CBA‐Asblawele Lapis Antara (AC‐BC ASbLawele) ton 4,694.92
SKh‐5.6.3.1.(3a) CBA‐Asblawele Lapis Base (AC‐Base SbLawele) ton 6,277.94
SKh‐5.6.3.1.(4) Aspal Keras ton 522.26 522.26
SKh‐5.6.3.1.(5) Asbuton Lawele Butir ton 1,623.60 1,623.60
Divisi 6. Perkerasan Aspal
5 2.5 Km PRESERVASI REKONSTRUKSI JALAN BTS. KOTA 6.1 (1)(a) Lapis resap pengikat ‐ aspal cair liter 13,496.00 80:100 13,496.00
TAKALAR ‐ JENEPONTO ‐ 6.1 (2)(a) Lapis perekat ‐ aspal cair liter 4,346.18 30:100 4,346.18
6.3 (5a) Laston Lapis Aus (AC‐WC) ton 182.27 6.00 182.27
6.3 (6a) Laston Lapis Antara (AC‐BC) ton 267.72 5.80 267.72
6.3 (7a) Laston Lapis Pondasi (AC Base) ton 22.08 5.50 22.08
SKh‐5.6.3.1.(1a) CBA‐Asblawele Lapis Aus (AC‐WC ASbLawele) ton 856.48
SKh‐5.6.3.1.(2a) CBA‐Asblawele Lapis Antara (AC‐BC ASbLawele) ton 1,636.76
SKh‐5.6.3.1.(3a) Campuran Beraspal Panas(Laston) Lapis Aus (AC‐WCP) ton 276.00
SKh‐5.6.3.1.(4) Aspal Keras ton 100.06 100.06
SKh‐5.6.3.1.(5) Asbuton Lawele Butir ton 288.14 288.14
SKh‐....6.3.1.(2c) Campuran Beraspal Panas(Laston) Lapis Aus (AC‐WCP)(L) ton 276.00 276.00
SKh‐1.6.3.3.(1) Campuran CPHMA Asbuton Lapis Aus (AC ‐ WC Asb CPHMA) ton 2.70 2.70
RENCANA KEBUTUHAN ASPAL JALAN NASIONAL PROVINSI SULAWESI SELATAN TA.2018
Estimasi Aspal Minyak Pemakaian Aspal Minyak dan Aspal
e
Panjang Jalan Pemakaian Tack Coat Buton
No Nama Paket/Ruas No Mata Pembayaran Pekerjaan Satuan Volume
Efektif Kadar Aspal Prime Coat
Optimum (%). (LTR) Aspal Minyak Aspal Buton
Divisi 6. Perkerasan Aspal
6 2.9 Km PELEBARAN JALAN MAROS ‐ BTS. BONE 6.1 (1)(a) Lapis resap pengikat ‐ aspal cair liter 14,335.00 80:100 14,335.00
6.1 (2)(a) Lapis perekat ‐ aspal cair liter 5,509.14 30:100 5,509.14
6.3 (5a) Laston Lapis Aus (AC‐WC) ton 342.08 6.00 342.08
6.3 (6a) Laston Lapis Antara (AC‐BC) ton 309.04 5.80 309.04
6.3 (7c) Laston Lapis Pondasi (AC Base L) ton 418.45 5.50 418.45
SKh‐5.6.3.1.(1a) CBA‐Asblawele Lapis Aus (AC‐WC ASbLawele) ton 1,450.56
SKh‐5.6.3.1.(2a) CBA‐Asblawele Lapis Antara (AC‐BC ASbLawele) ton 2,212.19
SKh‐5.6.3.1.(3a) CBA‐Asblawele Lapis Base (AC‐Base SbLawele) ton 3,008.22
SKh‐5.6.3.1.(4) Aspal Keras ton 248.80 248.80
SKh‐5.6.3.1.(5) Asbuton Lawele Butir ton 768.86 768.86
Divisi 6. Perkerasan Aspal
7 2.0 Km PELEBARAN JALAN TOPOKA ( BELOPA ) 6.1 (1)(a) Lapis resap pengikat ‐ aspal cair liter 14,400.00 80:100 14,400.00
6.1 (2)(a) Lapis perekat ‐ aspal cair liter 8,700.00 30:100 8,700.00
6.3 (5a) Laston Lapis Aus (AC‐WC) ton 533.60 6.00 533.60
6.3 (6a) Laston Lapis Antara (AC‐BC) ton 800.40 5.80 800.40
6.3 (7c) Laston Lapis Pondasi (AC Base L) ton 588.00 5.50 588.00
6.3 (7a) Laston Lapis Pondasi (AC Base ) ton 706.56 5.50 706.56
SKh‐5.6.3.1.(1a) CBA‐Asblawele Lapis Aus (AC‐WC ASbLawele) ton 1,841.99
SKh‐5.6.3.1.(2a) CBA‐Asblawele Lapis Antara (AC‐BC ASbLawele) ton 2,777.39
SKh‐5.6.3.1.(3a) CBA‐Asblawele Lapis Base (AC‐Base SbLawele) ton 2,458.83
SKh‐5.6.3.1.(4) Aspal Keras ton 267.81 267.81
SKh‐5.6.3.1.(5) Asbuton Lawele Butir ton 816.22 816.22
Divisi 6. Perkerasan Aspal
8 6.5 Km AKSES BANDARA PONGTIKU 6.1 (1)(a) Lapis resap pengikat ‐ aspal cair liter 80:100 ‐
6.1 (2)(a) Lapis perekat ‐ aspal cair liter 9,100.00 30:100 9,100.00
6.3 (5c) Laston Lapis Aus (AC‐WC L) ton 2,820.00 6.00 2,820.00
6.3 (6a) Laston Lapis Antara (AC‐BC) ton 5.80 ‐
6.3 (7c) Laston Lapis Pondasi (AC Base L) ton 5.50 ‐
SKh‐....6.3.1.(2c) Campuran Beraspal Panas(Laston) Lapis Aus (AC‐WCP)(L) ton 235.00 235.00
Divisi 6. Perkerasan Aspal
9 2.0 Km AKSES MALILI 6.1 (1)(a) Lapis resap pengikat ‐ aspal cair liter 13,500.00 80:100 7,500.00
6.1 (2)(a) Lapis perekat ‐ aspal cair liter 7,147.45 30:100 7,147.45
6.3 (5a) Laston Lapis Aus (AC‐WC ) ton 532.09 6.00 532.09
6.3 (6a) Laston Lapis Antara (AC‐BC) ton 320.71 5.80 18.60
6.3 (7a) Laston Lapis Pondasi (AC Base ) ton 110.45 5.50 6.07
SKh‐5.6.3.1.(1a) CBA‐Asblawele Lapis Aus (AC‐WC ASbLawele) ton 2,858.26
SKh‐5.6.3.1.(2a) CBA‐Asblawele Lapis Antara (AC‐BC ASbLawele) ton 2,011.21
SKh‐5.6.3.1.(4) Aspal Keras ton 197.89 197.89
SKh‐5.6.3.1.(5) Asbuton Lawele Butir ton 563.04 563.04
SKh‐....6.3.1.(2c) Campuran Beraspal Panas(Laston) Lapis Aus (AC‐WCP)(L) ton 235.00 235.00
Ket: Semua volume sesuai dengan dokumen Engineer Estimate P2JN Sulsel