16
26 THE PARTIES
27 1. Plaintiff is, and at all relevant times herein was, a community services district
28 organized and existing under the laws of the State of California.
-1-
2091/031966-0002
12522442.3 a09/20/18 COMPLAINT
1 2. Defendant CDM SMITH, INC. (“CDM”) is, and at all relevant times herein was, a
2 corporation organized and existing under the laws of the State of Massachusetts.
3 3. Plaintiff is unaware of the true names and capacities of Defendants named herein as
4 Does 1 through 25, inclusive, and for that reason has sued such Defendants by such fictitious
5 names pursuant to Code of Civil Procedure section 474. Plaintiff is informed and believes and, on
6 that basis alleges, that each fictitiously-named Defendant is responsible or liable in some manner
7 for the events referred to herein. Plaintiff will amend this Complaint to show the true names and
9 4. For purposes of this Complaint, CDM and DOES 1 through 25, inclusive, are
11 5. Plaintiff is informed and believes, and based thereon alleges, that Defendants, and
12 each of them, are responsible, in whole or in part, for each of the acts or omissions alleged herein,
13 and that, at all times herein mentioned, Defendants, and each of them, were acting as agents,
14 servants, and/or employees of each other, and were acting within the course and scope of their
15 agency and employment with the full knowledge and consent, either express or implied, of each of
16 the other Defendants. As such, Defendants, and each of them, were and are jointly and severally
17 responsible with each of the other named Defendants herein for those acts or omissions alleged
18 herein.
19 VENUE
20 6. The San Luis Obispo County Superior Court is the proper venue for this action
21 pursuant to Section 6.06 of the Engineering Services Agreement at issue in this case, and because
22 the contract, property and nexus of facts arose in the County of San Luis Obispo.
23 FACTUAL BACKGROUND
24 7. Plaintiff is an independent community services district that provides water,
25 wastewater, fire protection and other community services to its customers within its jurisdictional
26 boundaries in San Luis Obispo County. Plaintiff provides water service to approximately 6,200
27 residents in the unincorporated area of Cambria, and draws from the San Simeon and Santa Rosa
-2-
2091/031966-0002
12522442.3 a09/20/18 COMPLAINT
1 8. By January 2014, drought conditions which had ravaged the State of California
2 (and in particular the Central Coast) since 2011 had severely reduced the availability of water
3 from the Aquifers. Despite the fact that the District had already imposed stringent conservation
4 measures on its customers, the District was in danger of running out of water. On January 30,
5 2014, the District declared a “Stage 3 Water Shortage Emergency,” and imposed even more
6 stringent conservation measures, including surcharges on excessive water use and a complete
7 prohibition on outdoor use of potable water. On the same date, the District’s Board of Directors
8 authorized the District’s General Manager to enter into any necessary agreements to develop and
10 9. Because the District did not have the in-house expertise to develop such a project
11 on its own, Plaintiff looked to and relied on Defendants to investigate, design and construct a
12 water treatment facility that could address Plaintiff’s emergency water supply crisis. On or about
13 February 7, 2014, the District entered into an Engineering Services Agreement (“Agreement”)
14 with CDM for the design and construction of an emergency water supply project intended to
15 produce an additional 400,000 to 600,000 gallons per day of potable water (the “Project”). The
17 10. The District intended that the Project—which ultimately cost in excess of $10
18 million—would not only address the immediate emergency, but would provide a reliable
19 emergency source of water going forward, to insulate the District against anticipated continued
20 water shortages and drought conditions in the coming years. Due, in part, to climate change
21 impacts, the District anticipated it was likely to need use of the emergency water supply facilities
23 11. The Project called for the extraction and treatment of a mixture of deep brackish
24 water from a saltwater wedge, treated wastewater, and lost aquifer underflow, while avoiding or
25 mitigating potential impacts to the nearby San Simeon and Van Gordon Creeks (as well as a
26 downstream lagoon area). Defendants, who asserted expertise in the services required to design
27 and construct the Project, were tasked with undertaking the “hydrogeological modeling, design,
-3-
2091/031966-0002
12522442.3 a09/20/18 COMPLAINT
1 12. As mandated by Section 1.02 of the Agreement, the specific services to be
2 performed by Defendants under the Agreement were to be set forth in “Task Orders” identifying
3 and defining each phase and activity contemplated under the Project. Among other things,
4 Defendants were to “confer with regulatory agencies, resource agencies, and [the District] to
5 complete the necessary studies and design,” and were to “construct the Project services.”
6 Defendants were to “apply professional judgment in determining the method, details and means of
8 13. At the time the parties entered into the Agreement on February 7, 2014, the Parties
9 also executed the initial Task Order (“Task Order 1”), which called for the preparation of a geo-
10 hydrological model to support the environmental analyses and design needs for the Project. The
11 results from the Task Order 1 analyses would then allow for the refinement of the Project
12 description, with an emphasis on mitigating potential impacts to the nearby creeks and
13 downstream lagoon.
14 14. In connection with CDM’s initial modeling and analyses, CDM proposed the
15 construction of an “evaporation pond” for the Project, which could be used to store and dispose of
16 the brine and related material generated from the water treatment facility. On or about May 2,
17 2014, the District and CDM executed Task Order 3, which, among other things, called for
18 technical reports supporting the design, permitting, and construction of the evaporation pond.
19 Task Order 3 is attached hereto as Exhibit “B” and is incorporated herein by this reference.
20 15. Critical to the feasibility of the evaporation pond was whether it could be designed
21 in a manner that satisfied the legal prerequisites for such “surface impoundments.” The California
22 Code of Regulations and the Regional Water Quality Control Board for the Central Coast Region
23 (“Regional Board”) impose strict requirements for such facilities. As relevant here, any surface
24 impoundment like the evaporation pond, must be “operated to ensure that wastes will be a
25 minimum of five feet (5 ft.) above the highest anticipated elevation of underlying ground water.”
26 (27 CCR § 20240(c) [emph. add.].) That is, a minimum five-foot separation would have to be
27 maintained at all times between the bottom of the proposed evaporation pond and the “highest
28 anticipated” groundwater elevation underlying the pond floor. In addition, to ensure that water
-4-
2091/031966-0002
12522442.3 a09/20/18 COMPLAINT
1 within the evaporation pond would never escape, the Regional Board required the pond to be
2 designed such that during a 1,000-year storm over a 24-hour period, water inside the pond would
3 not reach an elevation higher than 2 feet below the lowest point of the berm enclosing the pond
4 (i.e., during a 1,000-year storm over the course of 24 hours, the pond would need to maintain a
5 minimum 2-foot “freeboard” at all times). Because a 1,000-year storm over a 24-hour period
6 would increase the water level in the pond by 10.2-inches (without any inundation of storm runoff
7 from outside the pond), the Regional Board required a minimum 34.2-inch freeboard to be
8 maintained at all times (2 feet of freeboard plus a 10.2-inch rise in water level during 1,000-year
9 storm = 34.2-inch freeboard). To maintain this requirement, the Regional Board prohibited any
11 16. In order to properly evaluate whether the proposed evaporation pond could meet
12 these strict requirements, Task Order 3 required CDM to thoroughly investigate the existing
13 available data and field conditions needed to design a compliant pond or to determine that a
14 compliant pond would not be feasible. This included data compilation and geo-hydrological and
15 hydraulic analyses, as well as field investigations needed to determine the highest anticipated
16 elevation of groundwater underlying the pond, and the extent to which the relevant watersheds in
17 the area would generate storm flows that might overtop and inundate the pond during a 1,000-year
18 storm event over a 24-hour period. Because the 34.2-inch “freeboard” requirement was based on
19 the assumption that no stormwater runoff from outside the pond would inundate the pond,
20 CDM’s hydrologic and hydraulic analyses of the relevant watersheds was critically important to
21 provide the assurance that the massive stormwater runoff generated by a “worst case scenario”
22 storm would never inundate the evaporation pond proposed by CDM. The analyses undertaken by
23 CDM were presented in technical reports ultimately used to obtain the necessary permitting for the
24 Project and the Regional Board’s Waste Discharge Requirements Order for CDM’s proposed
26 17. To evaluate the requirement that the bottom of the pond remain at least five feet
27 above the highest anticipated elevation of groundwater, CDM drilled a few wells in the area to
28 determine the actual groundwater level that existed at the time, and determined that existing
-5-
2091/031966-0002
12522442.3 a09/20/18 COMPLAINT
1 groundwater levels were approximately 20 feet below the bottom of the pond. Because those
2 wells were “new” and there was no historical reporting on groundwater levels from those wells,
3 however, CDM’s analysis of the extent to which groundwater levels beneath the pond were likely
4 to fluctuate relied solely on historical data from a pre-existing well located approximately 1,200
5 feet south of the proposed pond (“Well 16D-1”). Data from Well 16D-1 showed a water level
6 fluctuation of only 6 feet. Looking only at the historical measurements from Well 16D-1, CDM
7 asserted that groundwater beneath the proposed pond would similarly fluctuate no more than 6
8 feet, i.e., would never rise to more than approximately 14 feet below bottom of the pond. CDM
9 thus concluded the “regulation criteria of a separation of a minimum of 5 feet between the base of
10 the reservoir and the high water table” would easily be met.
11 18. Reliance solely on data from Well 16D-1 was problematic for a number of reasons,
12 including, but not limited to, the fact the geologic conditions of the area in which Well 16D-1 is
13 located are vastly different than the area where the pond is located. For example, Well 16D-1 is
14 located right next to San Simeon Creek, in soil composed mostly of sand and gravel, while the
15 pond is located at a higher elevation, away from the creek, in an area where the soil has a much
16 higher concentration of silts and clays. Accordingly, CDM’s assumption that data from Well
17 16D-1 indicated the extent to which groundwater beneath the proposed pond would fluctuate was
18 deeply flawed.
19 19. In addition, CDM’s analysis ignored red flags that should have reinforced the folly
20 of relying on a single well located 1,200 feet away from the proposed pond in dissimilar
21 conditions. Other reports prepared by CDM before the assessment described above included
22 historical groundwater data from numerous other wells in the vicinity showing much greater
23 fluctuations in groundwater levels. Indeed, the data available to CDM showed Well 16D-1 was an
24 outlier in that its levels fluctuated much less than nearly all of the other wells for which data was
25 available. Thus, CDM inexplicably either ignored or improperly discounted the historical
26 measurements of other wells nearby that showed much higher fluctuations in groundwater
27 elevations and that did not support CDM’s conclusion regarding the “highest anticipated”
-6-
2091/031966-0002
12522442.3 a09/20/18 COMPLAINT
1 20. With regard to the requirement that a 2-foot freeboard be maintained during a
2 1000-year storm event over a 24-hour period, CDM conducted hydrological and hydraulic
3 analyses to determine whether surface waters from outside the pond would overtop the pond
4 during a 1000-year flood. Although CDM recognized a high risk that storm flows from the
5 applicable watershed might not be diverted by the culvert at the nearby San Simeon Creek Road,
6 and could find “a path” to the pond, CDM provided assurance that such a result would not occur.
7 In reaching this conclusion, CDM improperly and without basis assumed that no stormwater
8 would flow across San Simeon Road. As a result of that assumption, CDM’s calculations of
9 potential stormwater flows were based on an artificially small watershed, and ignored potential
10 flows from a vast area north of the road that sloped upward from the Project site.
11 21. Based on CDM’s analyses, CDM provided assurances in its technical reports that:
12 1) a 5-foot separation between the bottom of the pond and the “highest anticipated” groundwater
13 level would be maintained; and 2) there would be “no anticipated” stormwater inundation in the
14 pond and that the pond could maintain the 2-foot freeboard requirement during a 1,000-year storm
15 event.
16 22. Based on CDM’s analyses and assurances, the Regional Board ultimately issued its
17 WDR Order No. R3-2014-0047 (“WDR Order”) authorizing the construction and operation of the
18 evaporation pond. The WDR Order contained numerous prohibitions and conditions, including
19 the requirement that surface waters not overtop the pond enclosure, that a minimum 2-foot
20 freeboard be maintained during a 1,000-year storm event over a 24-hour period, and that a 5-foot
21 separation be maintained between the bottom of the pond and the highest groundwater elevation.
22 23. In January 2017, the region experienced a relatively heavy rain event for the first
23 time since construction of the evaporation pond and implementation of the Project, and the flaws
24 in CDM’s analyses and conclusions quickly became apparent. Significantly, it became apparent
25 that CDM erroneously determined that stormwater would not flow from surrounding areas into the
26 pond, and massively underestimated the extent to which groundwater levels in the vicinity of the
28 24. On or about January 9, 2017, during its routine daily inspection, Plaintiff’s staff
-7-
2091/031966-0002
12522442.3 a09/20/18 COMPLAINT
1 discovered that storm flows from the north side of San Simeon Road had “overtopped” the road
2 and entered District property. As a result of CDM’s flawed design, the District had to take
3 emergency action to prevent the evaporation pond from overflowing. This action required
4 hundreds of man-hours and included extensive hand trenching and sandbagging around the pond
6 channel. But for the emergency action taken by the District’s staff, the pond would not only have
7 further violated the freeboard requirements, but would have overflowed and allowed water to
9 25. Unfortunately, although immediate action was taken upon discovery of the
10 problem, the emergency measures taken by the District’s staff could not prevent all storm runoff
11 from entering the pond. District staff found that the surface elevation of the pond had risen by
12 two-feet between the January 8 and January 9 inspections, indicating that surface water from
13 outside the pond had in fact inundated the pond, in contravention of the WDR Order which
14 prohibited all stormwater runoff from entering the pond. As a result, on February 9, 2017, the
16 detailing the basis for the violation and the District’s liability for its failure “to construct and
17 maintain the surface impoundment and related containment structures to prevent inundation,
18 erosion, slope failure, washout, and overtopping under 1,000-year, 24-hour precipitation
19 conditions.”
20 26. Notwithstanding CDM’s assurance that no stormwater would inundate or enter the
21 evaporation pond during the worst case 1,000-year storm, the Regional Board determined that
22 stormwater flowed across San Simeon Creek Road and entered the pond in January 2017. The
23 January 2017 rain event did not come close to reaching the intensities associated with a 1,000-year
24 storm; nevertheless, stormwater did penetrate the pond, increasing the water elevation to well
25 above the 34.2-inch freeboard needed to maintain the required 2-foot freeboard in the event of a
26 1,000-year storm.
27 27. In order to bring the pond into compliance, Plaintiff retained Terrain Group LLC to
28 survey and oversee completion of an impermeably lined drainage channel on District property that
-8-
2091/031966-0002
12522442.3 a09/20/18 COMPLAINT
1 would handle storm flows from a 1,000-year storm in the event stormwater runoff escaped the
3 28. Unfortunately, the District soon discovered that CDM had committed even more
4 significant errors in the analysis it conducted to satisfy the requirement that a 5-foot separation
5 between the bottom of the pond and the “highest anticipated” groundwater elevation be
6 maintained at all times. Beginning on January 30, 2017, the District observed groundwater
7 elevations that were within five feet of the bottom of the pond at two of the three monitoring wells
8 that were constructed in connection with the evaporation pond. At one of the monitoring wells, on
9 February 27, 2017, groundwater was observed at an elevation two feet higher than the bottom of
10 the pond, indicating that the groundwater had actually breached the pond.
11 29. In July 2017, the Regional Board issued a cease and desist order detailing
12 numerous violations of the WDR Order. Based on the groundwater measurements from the
13 monitoring wells in March and April 2017, the Regional Board determined that the 5-foot
14 separation requirement had been violated, and that groundwater had actually breached the bottom
16 The March 14, 2017 and April 11, 2017 reported groundwater elevations
17 demonstrate that the Discharger failed to estimate the rise of the groundwater
18 surface effectively during site evaluation and impoundment design processes, which
19 resulted in the continued failure to maintain 5 feet of separation between the bottom
22 30. The Regional Board emphasized the inadequacy of the analyses and conclusions
23 CDM presented in an effort to obtain the authorization from the Regional Board to construct the
24 pond:
25 The failure to anticipate and maintain 5 feet of separation from the bottom of the
26 surface impoundment to the top of the groundwater surface highlights a flaw in the
-9-
2091/031966-0002
12522442.3 a09/20/18 COMPLAINT
1 July 15, 2014 and in “Technical Memorandum: Evaluation of Brine Evaporation
2 Pond for Inundation from the 0.1- Percent Annual Exceedance Probability Storm
3 Event” dated November 11, 2014, which were submitted as part of the ROWD
5 31. The cease and desist order required the District to either correct the design of the
6 pond to accommodate the discharge requirements and conditions of the WDR Order or
7 discontinue use of the evaporation pond for its intended purpose. Although the District has
8 explored potential methods for salvaging the pond, in order to mitigate its damages, the remedial
9 efforts needed to bring the pond into compliance with the WDR Order are not feasible, as there is
10 no cost-effective way to ensure compliance with the 5-foot separation requirement, given the
12 32. The District would not have proceeded with the Project in the same form, but for
13 CDM’s analyses and assurances. Had CDM accurately predicted the extent to which groundwater
14 levels would rise, the Project would have been designed from the start to utilize another means of
15 disposing of waste brine, e.g., to discharge such waste into Baker tanks. Instead, as a direct result
16 of CDM’s flawed reports, the District spent in excess of $2.5 million constructing a pond that is
17 now unusable for its intended purpose and which now must be emptied and decommissioned at
21 33. Plaintiff repeats, re-alleges, and hereby incorporates by reference each and every
22 allegation contained in Paragraphs 1 through 32 above, as though fully set forth herein.
23 34. Plaintiff has fully performed each and every covenant and condition of the
24 Agreement.
25 35. The Agreement required Defendants to, inter alia, (a) conduct the appropriate
26 analyses, investigations, and research to ensure that their proposed Project would meet certain
27 requirements, and (b) to otherwise indemnify, protect, defend and/or hold harmless District for any
28 damages flowing from Defendants’ breach of the Agreement or failure to meet its standard of care.
-10-
2091/031966-0002
12522442.3 a09/20/18 COMPLAINT
1 36. The Agreement also expressly requires CDM to, among other applicable
2 indemnities, “indemnify, protect, defend and hold harmless District . . . from and against any and
3 all losses, liabilities, damages, costs and expenses, including attorney’s fees and costs to the extent
4 same are caused in whole or in part by any negligent or wrongful act, error or omission of
6 37. CDM was required to properly investigate and analyze the potential conversion of
7 an existing percolation pond into a brine evaporation pond that would receive waste brine from a
8 water treatment plant, and was also required to conduct the investigation and analysis necessary to
9 demonstrate that the proposed evaporation pond would satisfy the stringent technical requirements
10 for such a pond. The Agreement also required CDM to provide the necessary technical
11 information required in support of the permit needed from the Regional Board to operate the
13 38. CDM breached the Agreement by failing to properly investigate, analyze and
14 research whether the proposed evaporation pond would maintain a 5-foot separation between the
15 bottom of the pond and highest anticipated groundwater level, and whether the pond would be
16 inundated with outside stormwater flows, thereby intruding on the 34.2-inch freeboard
17 requirement.
18 39. In reaching its conclusion that the 5-foot minimum separation between the bottom
19 of pond and highest anticipated groundwater level would be maintained, CDM improperly relied
20 on the historical readings from one well located 1,200 feet away from the proposed pond in
21 dissimilar conditions that showed relatively small fluctuations in groundwater levels. That data
22 could not and did not support CDM’s conclusion that the groundwater underlying the proposed
23 pond would not fluctuate significantly. Further, CDM ignored historical groundwater readings
24 from other nearby wells that showed dramatic fluctuations in groundwater levels. CDM’s reliance
25 on insufficient data, as well as its failure to consider other available data (including data CDM
26 itself had already compiled) constitutes a breach of the Agreement and a clear failure to meet its
27 standard of care.
28 40. In reaching its conclusion that no stormwater runoff would inundate the
-11-
2091/031966-0002
12522442.3 a09/20/18 COMPLAINT
1 evaporation pond, CDM improperly assumed that the massive amount of water within the
2 watershed during a 1,000-year storm would somehow be barricaded by San Simeon Road. The
3 District is informed and believes, and based thereon alleges, that CDM did not verify the
4 assumptions underlying its stormwater flow projections were supported by actual conditions in the
5 field and incorrectly failed to account for changes in flow patterns upstream from the culvert at
6 San Simeon Road. On information and belief, the District further alleges CDM also incorrectly
7 assumed the existence of a ditch along San Simeon Road that would collect excess water in the
8 event stormwater runoff escaped the San Simeon Road culvert, when no such ditch existed.
9 CDM’s incorrect analyses and assumptions, along with its failure to conduct an adequate field
10 inspection to verify the assumptions it made concerning flow patterns, constitute a breach of the
12 41. CDM’s conclusions were proven false by actual conditions after the rains began in
13 January 2017. Groundwater levels in March not only intruded into the required 5 feet of
14 separation, but rose above the bottom of the evaporation pond liner—a full 16 feet higher than
15 predicted by CDM. Had CDM accurately gauged the extent to which groundwater levels would
16 rise, the pond would have never been a part of the Project, since it does not appear that any viable
17 (remotely cost-effective) way to maintain the required 5-foot separation exists, now that the true
20 expended in excess of $2,500,000 constructing an evaporation pond that cannot be used for its
21 intended purpose. The District has also incurred its own response costs, as well as costs related to
22 responding to the Notices of Violation and Cease and Desist Order issued by the Regional Board.
23 The District is also required to expend resources to empty and decommission the pond.
24 43. As a proximate result of Defendants’ contractual breaches, the District has been
25 damaged in an amount according to proof at the time of trial. To date, District has incurred
27 44. Pursuant to Section 6.04 of the Agreement, the District is entitled to recover its
-12-
2091/031966-0002
12522442.3 a09/20/18 COMPLAINT
1 SECOND CAUSE OF ACTION
2 (Professional Negligence Against All Defendants)
3 45. Plaintiff hereby repeats, re-alleges, and incorporates by reference each and every
4 allegation contained in Paragraphs 1 through 44 above, as though fully set forth herein.
6 because Defendants had a duty to use the “skill, prudence and diligence” expected from members
9 professional negligence, because Defendants had a duty to, inter alia, (a) competently, and with
10 the usual “skill, prudence and diligence” expected from members of their profession, perform their
11 obligations under the Agreement, including making the appropriate investigations, analyses, and
12 calculations, (b) competently ensure that the designed and completed Project, and evaporation
13 pond, would meet the requirements of the Agreement, including all requirements imposed by the
14 Regional Board, and (c) otherwise ensure that their calculations, conclusions, investigations, and
15 reports were correct. Defendants, however, failed to comply with these and other duties.
16 48. In reaching its conclusion that the 5-foot minimum separation between the bottom
17 of pond and highest anticipated groundwater level would be maintained, CDM improperly relied
18 on the historical readings from one well located 1,200 feet away from the proposed pond in
19 dissimilar conditions that showed relatively small fluctuations in groundwater levels. That data
20 could not and did not support CDM’s conclusion that the groundwater underlying the proposed
21 pond would not fluctuate significantly. Further, CDM completely ignored historical groundwater
22 readings from other nearby wells that showed dramatic fluctuations in groundwater levels.
23 CDM’s reliance on insufficient data, as well as its failure to consider other available data
24 (including data CDM itself had already compiled) constitutes a breach of CDM’s duty to use
26 49. In reaching its conclusion that no stormwater runoff would inundate the
27 evaporation pond, CDM improperly assumed that the massive amount of water within the
28 applicable watershed during a 1,000-year storm would somehow be barricaded by San Simeon
-13-
2091/031966-0002
12522442.3 a09/20/18 COMPLAINT
1 Road. The District is informed and believes, and based thereon alleges, that CDM did not verify
2 the assumptions underlying its stormwater flow projections were supported by actual conditions in
3 the field and incorrectly failed to account for changes in flow patterns upstream from the culvert at
4 San Simeon Road. On information and belief, CDM also incorrectly assumed the existence of a
5 ditch along San Simeon Road that would collect excess water in the event storm flows overtopped
6 the San Simeon Road culvert, when no such ditch existed. CDM’s incorrect analyses and
7 assumptions, along with its failure to conduct an adequate field inspection to verify the
8 assumptions it made concerning flow patterns, constitute a breach of CDM’s duty to use “skill,
10 50. Based on these failures, the District has received Notices of Violation and a Cease
11 and Desist Order from the Regional Board due to the failure of the evaporation pond, and
12 therefore the Project, to operate in accordance with the WDR issued by the Regional Board.
14 amount according to proof at the time of trial. Among other things, the District expended in
15 excess of $2,500,000 constructing an evaporation pond that cannot be used for its intended
16 purpose. The District has also incurred its own response costs, as well as costs related to
17 responding to the Notices of Violation and Cease and Desist Order issued by the Regional Board.
18 The District is also required to expend resources to empty and decommission the pond. To date,
21 52. Plaintiff’s counsel has executed the appropriate certificate of merit pursuant to
26 2. For interest on the foregoing at the legal rate, including prejudgment interest, from
28 3. For attorneys’ fees and expert witness fees as allowed by the Agreement and/or law;
-14-
2091/031966-0002
12522442.3 a09/20/18 COMPLAINT
1 4. For costs of suit; and
2 5. For such other and further relief as the Court deems just and proper.
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
-15-
2091/031966-0002
12522442.3 a09/20/18 COMPLAINT
EXHIBIT “A”
Exhibit A, page 16
Exhibit A, page 17
Exhibit A, page 18
Exhibit A, page 19
Exhibit A, page 20
Exhibit A, page 21
Exhibit A, page 22
Exhibit A, page 23
Exhibit A, page 24
Exhibit A, page 25
Exhibit A, page 26
Exhibit A, page 27
Exhibit A, page 28
Exhibit A, page 29
Exhibit A, page 30
Exhibit A, page 31
Exhibit A, page 32
Exhibit A, page 33
Exhibit A, page 34
Exhibit A, page 35
Exhibit A, page 36
Exhibit A, page 37
EXHIBIT “B”
Exhibit B, page 38
Exhibit B, page 39
Exhibit B, page 40
Exhibit B, page 41
Exhibit B, page 42
Exhibit B, page 43
Exhibit B, page 44
Exhibit B, page 45
Exhibit B, page 46
Exhibit B, page 47
Exhibit B, page 48
Exhibit B, page 49
Exhibit B, page 50
Exhibit B, page 51
Exhibit B, page 52
Exhibit B, page 53
Exhibit B, page 54
Exhibit B, page 55
Exhibit B, page 56
Exhibit B, page 57