ANNEXURE 1

Date:
Project Title - Hindustan Unilever Ltd. Development Centre

Project Managers - Jones Lang Lasalle Meghraj

MEP Consultants - Spectral Services Ltd. ,Mumbai

Contractor: - Blue Star

Status of Shop Drawings for HVAC works

Sr. Dwg. No. Drawing Title Scheduled Date Submission & Approval of Shop Drawings Remarks
No. of Submission 1st Receipt of 2nd Receipt of Final Final
Submission comments Submission comments Submission Approval
1 BSL/HVAC/01 Chiller Plant Room Schematic 6-Apr-08
2 BSL/HVAC/02 Chilled water Schematic(BlockA,B,D,E) 8-Apr-08
3 BSL/HVAC/03 Ventilation Ducting Riser Schematic for Block A,B,D 12-Apr-08
4 BSL/HVAC/04 Ventilation Ducting Riser Schematic for Block F 15-Apr-08
5 BSL/HVAC/05 HVAC Layout for Basement 1 21-Apr-08
6 BSL/HVAC/06 HVAC Layout for Basement 2 24-Apr-08
Zone A(Block A,B,D)
7 BSL/HVAC/07 HVAC Layout for Ground Floor 26-Apr-08
8 BSL/HVAC/08 HVAC Layout for First floor 29-Apr-08
9 BSL/HVAC/09 HVAC Layout for Second Floor 2-May-08
10 BSL/HVAC/10 HVAC layout for third floor 5-May-08
11 BSL/HVAC/11 HVAC layout for fourth floor 8-May-08
12 BSL/HVAC/12 HVAC layout for Terrace floor 12-May-08
Zone B(Block E)
13 BSL/HVAC/13 HVAC Layout for Ground Floor 15-May-08
14 BSL/HVAC/14 HVAC Layout for First floor 19-May-08
15 BSL/HVAC/15 HVAC Layout for Second Floor 22-May-08
16 BSL/HVAC/16 HVAC layout for third floor 26-May-08
17 BSL/HVAC/17 HVAC layout for Terrace floor 29-May-08
Zone C(Block F)
18 BSL/HVAC/18 HVAC Layout for Ground Floor 2-Jun-08
19 BSL/HVAC/19 HVAC Layout for First floor 5-Jun-08
20 BSL/HVAC/20 HVAC layout for Service floor 9-Jun-08
21 BSL/HVAC/21 HVAC Layout for Second Floor 12-Jun-08
22 BSL/HVAC/22 HVAC layout for third floor 16-Jun-08
23 BSL/HVAC/23 HVAC layout for fourth floor 19-Jun-08
24 BSL/HVAC/24 HVAC layout for fifth floor 23-Jun-08
25 BSL/HVAC/25 HVAC layout for Sixth floor 26-Jun-08
26 BSL/HVAC/26 HVAC layout for Terrace floor 30-Jun-08

Note - The above dates are subject to the availability of reflected ceiling plans for all the floors

(a) Total no. of drawings = … Nos.; (b) Drawings Approved = … Nos.; (c) Approval Awaited = … Nos.; (d) Drawings Under Hold = … Nos.; (e) Drawings to be Submitted = … Nos.
Note: (a) All drawings in A1 size; (b) Floor plans - 1 : 100 (number of sheets as per project); (c) Section - 1 : 50; (d) Plant Room - 1 : 50 or 1 : 100 as per project)
ANNEXURE 1

Project Title - Hindustan Unilever Ltd. Development Centre

Project Managers - Jones Lang Lasalle Meghraj

MEP Consultants - Spectral Services Ltd. ,Mumbai

Contractor: - Blue Star

Status of Technical Submittals


Sr. Submittals Scheduled Date Date of Date of Inspection Samples for Approval
No. of Submission Submission Approval At Site At Works
1 Chillers 8-Apr-08
2 Pumps 7-Apr-08
3 Cooling Tower 10-Apr-08
4 AHU`s 23-Apr-08
5 VRF Units 12-Apr-08
6 Ventilation fans 22-Apr-08
7 Pipes 5-Apr-08
8 Butterfly valves 15-Apr-08
9 Check Valves 15-Apr-08
10 2-way Motorised valve 15-Apr-08
11 Ball valves 15-Apr-08
12 Pot strainer 15-Apr-08
13 Y-strainer 15-Apr-08
14 Duct thermal Insulation 18-Apr-08
15 Pipe Thermal Insulatio 18-Apr-08
16 Scrubber Unit 30-Apr-08
17 Temperature Guages 5-Apr-08
18 Pressure Guages 5-Apr-08

SPECTRAL SERVICES CONSULTANTS PVT. LTD., MUMBAI


ANNEXURE 3

Technical (Product) Submittal

CLIENT :

PROJECT :

SERVICE :

SUBMITTAL REF NO. :

DESCRIPTION OF ITEM :

B.O.Q. REF. NO. :

SPECIFICATION REF. NO. :

CLAUSE NO. :

PROPOSED MAKE :

ENCLOSURES :

CONTRACTOR :

SIGNATURE : DATE:
CONSULTANTS :

APPROVED BY : DATE:
PROJECT MANAGEMENT :
CONSULTANT

APPROVED BY : DATE:
CLIENT :

APPROVED BY : DATE:

SPECTRAL SERVICES CONSULTANTS PVT. LTD., MUMBAI