Anda di halaman 1dari 9

EFREN L. ALVAREZ, G.R. No.

G.R. No. 192591 Assessor, old Post Office, Commission on Elections and Department of Social Welfare and Development. These structures were
Petitioner, demolished at the instance of petitioner to give way to the construction project. Thereafter, API proceeded with excavation on the
Present:
area (3-meter deep) and a billboard was put up informing the public about the project and its contractor. However, no mall was
CORONA, C.J.,
constructed as API stopped work within just a few months.
- versus - Chairperson,
LEONARDO-DE CASTRO,
BERSAMIN,
DEL CASTILLO, and On August 10, 2006, petitioner was charged before the Sandiganbayan for violation of Section 3(e) of R.A. No. 3019 (SB-06-CRM-
VILLARAMA, JR., JJ.
0389), under the following Information:
PEOPLE OF THE PHILIPPINES, Promulgated:
Respondent. That on or about 12 September 1996, and sometime prior or subsequent thereto, in the then
June 29, 2011 Municipality (now Science City) of Muoz, Nueva Ecija, and within the jurisdiction of this Honorable Court,
x- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - x the above-named accused EFREN L. ALVAREZ, a high ranking public official, being then the Mayor of
Muoz, Nueva Ecija, taking advantage of his official position and while in the discharge of his official or
DECISION administrative functions, and committing the offense in relation to his office, acting with evident bad faith or
gross inexcusable negligence or manifest partiality did then and there willfully, unlawfully and criminally give
VILLARAMA, JR., J.: the Australian-Professional Incorporated (API) unwarranted benefits, advantage or preference, by awarding to
the latter the contract for the construction of Wag-Wag Shopping Mall in the amount of Two Hundred Forty
Million Pesos (Php 240,000,000.00) under a Buil[d]-Operate-Transfer Agreement, notwithstanding the fact
that API was and is not a duly-licensed construction company as per records of the Philippine Construction
Before us is a petition for review on certiorari under Rule 45 of the 1997 Rules of Civil Procedure, as amended, seeking to reverse Accreditation Board (PCAB), which construction license is a pre-requisite for API to engage in construction
of works for the said municipal government and that API does not have the experience and financial
and set aside the Decision[1] dated November 16, 2009 and Resolution[2] dated June 9, 2010 of the Sandiganbayans Fourth Division qualifications to undertake such costly project among others, to the damage and prejudice of the public service.
finding the petitioner guilty beyond reasonable doubt of violation of Section 3(e) of Republic Act (R.A.) No. 3019, otherwise known
CONTRARY TO LAW.[5]
as the Anti-Graft and Corrupt Practices Act.

Petitioner Efren L. Alvarez, at the time of the subject transaction, was the Mayor of the Municipality (now Science City) of Muoz,
On September 22, 2006, petitioner was duly arraigned, pleading not guilty to the charge.
Nueva Ecija. In July 1995, the Sangguniang Bayan (SB) of Muoz under Resolution No. 136, S-95 invited Mr. Jess Garcia, President
of the Australian-Professional, Inc. (API) in connection with the municipal governments plan to construct a four-storey shopping
mall (Wag-wag Shopping Mall), a project included in its Multi-Development Plan. Subsequently, it approved the adoption of the At the trial, petitioner testified that during his term as Mayor of Muoz, the municipal government planned to borrow

project under the Build-Operate-Transfer (BOT) arrangement in the amount of P240 million, to be constructed on a 4,000-square- money from GSIS to finance the proposed Wag-Wag Shopping Mall project. He learned about API when then Vice-Mayor Romeo

meter property of the municipal government which is located at the back of the Municipal Hall. API submitted its proposal on Ruiz and other SB members showed him a copy of publication/advertisement in the Manila Bulletin and Business Bulletin showing

November 7, 1995.[3] that API was then building similar BOT projects for construction of shopping malls in Lemery, Batangas (P150 million) and in
Calamba, Laguna (P300 million). Because it will not entail government funds and is an alternative to availment of GSIS loan,
petitioner appointed Vice-Mayor Ruiz and other SB members to study the matter. A resolution was subsequently passed by the SB
On February 9, 1996, an Invitation for proposals to be submitted within thirty (30) days, was published in Pinoy tabloid. On April
inviting API for detailed information on their mall projects. Thereafter, the SB approved the construction of Wag-Wag Shopping
12, 1996, the Pre-qualification, Bids and Awards Committee (PBAC) recommended the approval of the proposal submitted by the
Mall under BOT scheme, which was favorably endorsed by the Municipal Development Council. A public hearing was also
lone bidder, API. On April 15, 1996, the SB passed a resolution authorizing petitioner to enter into a Memorandum of Agreement
conducted by Municipal Engineer Armando E. Miranda. On November 8, 1995, the municipal government received the unsolicited
(MOA) with API for the project. Consequently, on September 12, 1996, petitioner signed the MOA with API, represented by its
proposal of API for the construction of Wag-Wag Shopping Mall. For three weeks, an Invitation to Bid was published in
President Jesus V. Garcia, for the construction of the Wag-Wag Shopping Mall under the BOT scheme whereby API undertook to
the Pinoy tabloid. But it was the lone bidder, API, whose proposal was eventually recommended by the PBAC and approved by the
finish the construction within 730 calendar days.[4]
SB.[6]

On February 14, 1997, the groundbreaking ceremony was held at the site once occupied by government structures which included
Petitioner emphasized that not a single centavo was spent by the municipal government for the Wag-Wag Shopping Mall
the old Motor Pool, the old Health Center and a semi-concrete one-storey building that housed the Department of Agriculture, BIR
project. It was an unsolicited proposal under the BOT law. API was required to submit pre-qualification statements containing, among
others, their accomplished projects. Eventually the SB passed a resolution authorizing him to enter into the MOA with API. The million, representing the amount of liquidated damages due under the performance security had the same been posted by the
municipal government issued the notice of award to API on September 16, 1996 in which it required the contractor to post notices contractor as required by law. As to the allegation of conspiracy, the Sandiganbayan held that such was adequately shown by the
prior to the start of the project and to submit other requirements such as performance bond. However, API did not comply as its evidence, noting that this is one case where the Ombudsman should have included the entire Municipal Council in the information
counsel, Atty. Lydia Y. Marciano said these are not required under the BOT law (R.A. No. 7718) since there will be no government for the latter had conspired if not abetted all the actions of the petitioner in his dealings with API to the damage and prejudice of the
undertaking, equity or subsidy in the project. After securing an environmental clearance certificate from DENR, the groundbreaking municipality.
ceremony was held on February 1, 1997. API, as promised, paid P500,000.00 as disturbance or relocation fee considering that the
municipal government has caused the demolition of old buildings at the site. A certification[7] of such payment was issued by City The dispositive portion of the decision reads:
Treasurer Luzviminda P. De Leon and City Accountant June Franklyn A. Fernandez on February 5, 2007. The materials were then
ACCORDINGLY, accused Efren L. Alvarez is found guilty beyond reasonable doubt
utilized for the construction of the new motor pool and new City Library. Thereafter, API began excavating an area of 30 x 30 for [sic] violation of Section 3 (e) of Republic Act No. 3019 and is sentenced to suffer in prison the penalty
meters (1,000 sq. ms.), about 3 meters deep. However, only the sales office was constructed. The project was not completed and API of 6 years and 1 month to 10 years. He also has to suffer perpetual disqualification from holding any public
office and to indemnify the City Government of Muoz (now Science), Nueva Ecija the amount of Four Million
gave as excuse the 1997 financial crisis. They wrote a letter to Mr. Garcia reminding him of the 730-days completion period but then Eight Hundred Thousand Pesos (Php 4,800,000.00) less the Five Hundred Thousand Pesos (Php 500,000.00)
API earlier paid the municipality as damages.
he was nowhere to be found and did not answer the letter. Hence, the SB authorized him to file a case against API, and later also
granted him authority to enter into a compromise agreement in Civil Case No. 161-SD 98). Their compromise agreement was Costs against the accused.
approved but they could not find a copy anymore because the Regional Trial Court at Balok, Sto. Domingo, Nueva Ecija where the
SO ORDERED.[10]
settlement was done, was burned down.[8]

On cross-examination, petitioner claimed that had the municipal government then borrowed funds from the GSIS, they The Sandiganbayan likewise denied petitioners motion for reconsideration. It ruled that upon examination of Section 4-

envisioned annual return of P5 million from a P40 million loan for a modest mall (but for an area of 4,000 square meters, the loan A of R.A. No. 6957 as amended by R.A. No. 7718, it was clear that petitioner, with manifest partiality and gross inexcusable

would have to be P80 million). For a period of 8 years, the municipality would have an income of P40 million and the GSIS can be negligence, failed to comply with the requirements and procedures for competitive bidding in unsolicited proposals. It also reiterated

paid. As to the contractors financial capability, it presented a credit line of P150 million to P250 million for Australian-Professionals that API was a contractor and not a mere project proponent; hence, the license requirement applies to it. Petitioners defense that he

Realty, Inc. (APRI). Petitioner clarified that API and APRI were one and the same entity having the same board of directors, but merely executed the resolutions of the SB was also rejected because as Chief Executive of the Municipality of Muoz, it was his duty

when asked if he verified this from the Securities and Exchange Commission (SEC), he answered in the negative. Petitioner asserted to protect the credits, rights and properties of the municipality and to exercise efficient, effective and economical governance for the

that it was the Vice-Mayor who is accountable for this project as he headed the working panel. As to whether API was a licensed general welfare of the municipality and its inhabitants under Section 444, R.A. No. 7160 (Local Government Code of

contractor, he admitted that he did not verify this before awarding the BOT contract involving an infrastructure project. He insisted 1991). Significant acts of the petitioner also showed that he opted to enter into the contract with API despite reckless disregard of

that the Wag-Wag Shopping Mall Project, being an unsolicited proposal under BOT law, is exempt from the pre-qualification the law.

requirement although they still conducted it. As far as he knows, the project proponent in this case is the Municipality of
Muoz. However, petitioner admitted that he is not familiar with the BOT law. He also admitted that the Invitation published stated a Hence, this petition raising the following issues:
shorter period of submission of proposal (30 days instead of 60 days provided under the BOT law) and that he just signed the said
1. Whether or not the Honorable Sandiganbayan failed to observe the requirement of proof beyond
notice without consulting their legal counsel.[9] reasonable doubt in convicting the Accused-Petitioner;

2. Whether or not the Honorable Sandiganbayan failed to appreciate the legal intent of the BOT project;
On November 16, 2009, the Sandiganbayan rendered judgment convicting the petitioner after finding that: (1) petitioner
railroaded the project; (2) there was no competitive bidding; (3) the contractor was totally unqualified to undertake the project; and 3. Whether or not the Honorable Sandiganbayan utterly failed to appreciate that the BOT was a lawful
project of the Sangguniang Bayan and not the project of the Mayor Accused-Petitioner herein; and
(4) the provisions of the BOT law and relevant rules and regulations were disregarded and not followed. The said court also found
that the municipal government suffered damage and prejudice with the resulting loss of several of its buildings and offices, and 4. Whether or not the Honorable Sandiganbayan utterly failed to appreciate that there was no damage on
the then Municipality of Muoz as contemplated by law, to warrant the conviction of the Accused-
having deployed its resources including equipment, personnel and financial outlay for fuel and repairs in the demolition of the said Petitioner.[11]
structures. Damage suffered by the municipal government was quantified at P4.8 million, or 2% of the total project cost of P240
We deny the petition. The Court En Banc likewise held in Fonacier v. Sandiganbayan[17] that proof of the extent or quantum of damage is not essential. It
is sufficient that the injury suffered or benefits received can be perceived to be substantial enough and not merely negligible.[18] Under

Petitioner was charged with violation of Section 3(e) of R.A. No. 3019. To be convicted under the said provision, the the second mode of the crime defined in Section 3(e) of R.A. No. 3019 therefore, damage is not required. In order to be found guilty

following elements must be established: under the second mode, it suffices that the accused has given unjustified favor or benefit to another, in the exercise of his official,
administrative or judicial functions.[19]
1. The accused must be a public officer discharging administrative, judicial or official functions;

2. He must have acted with manifest partiality, evident bad faith or inexcusable negligence; and The third element of Section 3(e) of R.A. No. 3019 may be committed in three ways, i.e., through manifest partiality,

3. That his action caused any undue injury to any party, including the government, or giving any private party evident bad faith or gross inexcusable negligence. Proof of any of these three in connection with the prohibited acts mentioned in
unwarranted benefits, advantage or preference in the discharge of his functions.[12] Section 3(e) of R.A. No. 3019 is enough to convict.[20] Damage or injury caused by petitioners acts though alleged in the information,
thus need not be proven for as long as the act of giving any private party unwarranted benefits, advantage or preference either through
manifest partiality, evident bad faith or gross inexcusable negligence was satisfactorily established. Contrary to petitioners assertion,
In this case, the information alleged that while being a public official and in the discharge of his official functions and taking
the prosecution was able to successfully demonstrate that he acted with manifest partiality and gross inexcusable negligence in
advantage of such position, petitioner acting with evident bad faith or gross inexcusable negligence or manifest partiality unlawfully
awarding the BOT contract to an unlicensed and financially unqualified private entity.
gave API unwarranted benefits, advantage or preference by awarding to it the contract for the construction of the Wag-Wag Shopping
Mall under the BOT scheme despite the fact that it was not a licensed contractor and does not have the experience and financial
qualifications to undertake such costly project, among others, to the damage and prejudice of the public service. R.A. No. 6957 as amended by R.A. No. 7718, requires that a BOT project be awarded to the bidder who has satisfied the minimum
requirements, and met the technical, financial, organizational and legal standards provided in the BOT Law. Section 5 of said law
provides:
Petitioner argues that he cannot be held liable under Section 3(e) of R.A. No. 3019 since the Municipality of Muoz did
not disburse any money and the buildings demolished on the site of construction have been found to be a nuisance and declared SEC. 5. Public Bidding of Projects. - x x x
structurally unsafe, as per notice issued by the Municipal Building Official. He points out that in fact, a demolition permit has been
In the case of a build-operate-and-transfer arrangement, the contract shall be awarded to the bidder
issued upon his application in behalf of the municipal government. API also paid P500,000.00 demolition/relocation fee. who, having satisfied the minimum financial, technical, organizational and legal standards required by
this Act, has submitted the lowest bid and most favorable terms for the project, based on the present value of
its proposed tolls, fees, rentals and charges over a fixed term for the facility to be constructed, rehabilitated,
operated and maintained according to the prescribed minimum design and performance standards, plans and
We disagree. specifications. x x x (Emphasis supplied.)

This Court has clarified that the use of the disjunctive word or connotes that either act of (a) causing any undue injury to any party,
Foremost of these minimum legal standards is the license accreditation of a contractor required under R.A. No. 4566 otherwise
including the Government; and (b) giving any private party any unwarranted benefits, advantage or preference, qualifies as a violation
known as the Contractors License Law. The Philippine Licensing Board for Contractors created under said law is mandated to ensure
of Section 3(e) of R.A. No. 3019, as amended.[13] The use of the disjunctive or connotes that the two modes need not be present at
that prospective contractors possess at least two years of experience in the construction industry, and knowledge of the building,
the same time. In other words, the presence of one would suffice for conviction. [14]
safety, health and lien laws of the Republic of the Philippines and the rudimentary administrative principles of the contracting
business which it deems necessary for the safety of the contracting business of the public.[21] In fact, a contractor must show that he
As we explained in Bautista v. Sandiganbayan[15]:
is licensed by the board before his bid will be considered. [22] As a general rule therefore, the prospective contractor for government
Indeed, Sec. 3, par. (e), RA 3019, as amended, provides as one of its elements that the public officer infrastructure projects must have been duly licensed as such pursuant to R.A. No. 4566.API not being a licensed contractor as per
should have acted by causing any undue injury to any party, including the government, or by giving any private
party unwarranted benefits, advantage or preference in the discharge of his functions. The use of the the Certification[23] issued by Philippine Contractors Accreditation Board (PCAB) board secretary Aaron C. Tablazon, is thus not
disjunctive term or connotes that either act qualifies as a violation of Sec. 3, par. (e), or as aptly held qualified to participate in the bidding and much less be awarded the BOT project for the construction of Wag-Wag Shopping Mall.
in Santiago, as two (2) different modes of committing the offense. This does not, however, indicate that each
mode constitutes a distinct offense, but rather, that an accused may be charged under either mode or
under both.[16] (Underscoring supplied.)
firm commitments from reputable financial institutions to provide, upon award, sufficient credit lines to cover
Petitioner claimed that there was compliance with the law saying that API was not a contractor but a mere project proponent, for the total estimated cost of the project.
which a license is not a requisite to undertake BOT projects. But the Sandiganbayan correctly rejected this theory as the clear terms
(l) Contractor - Any entity accredited under Philippine laws which may or may not be the project
of the MOA itself confirm that API itself undertook to construct the Wag-Wag Shopping Mall, thus: proponent and which shall undertake the actual construction and/or supply of equipment for the project.

TERMS AND CONDITIONS

I. THE PROJECT SITE Aside from the clear language of the MOA, the attendant circumstances unmistakably showed that API is both the project

1. The FIRST PARTY [Municipality of Muoz] shall make available unto the SECOND PARTY a FOUR proponent and contractor of the BOT project, as it was the one who submitted the proposal and bid to the SB, through its President
THOUSAND (4,000) SQUARE METERS lot located at Muoz, Nueva Ecija where the SECOND
executed the MOA with petitioner, deployed manpower and equipment for the clearing of the site, conducted groundbreaking,
PARTY [API] shall build for the FIRST PARTY a commercial building in accordance with this
Memorandum of Agreement, RA 6957 AND RA 7718 as well as RA 7160 otherwise known as the Local performed excavation and initial construction works, and took responsibility for the stoppage and non-completion of the project when
Government Code of 1991.
it entered into a compromise with the Municipality of Muoz. It is to be noted that even as project proponent, API failed to meet the
II. PLANS AND SPECIFICATIONS minimum financial standard considering that it has no adequate financial base to implement the Wag-Wag Shopping Mall project.

1. The commercial building, to be known as the WAG-WAG SHOPPING MALL, shall be constructed by APIs paid-up capital was only P2.5 million, while its stand-by credit line issued by Brilliant Star Capital Lending Co., Inc. was only
the SECOND PARTY strictly in accordance with plans, specifications, engineering and construction for the amount of P150 million, way below the P240 million total project cost.
designs prepared by the SECOND PARTY and duly reviewed and approved by the FIRST PARTY. x x
x

xxxx While APIs proposal passed through the pre-qualification stage, it failed to submit, except for the SEC registration
certificate, a complete set of documents required for a BOT project, in accordance with the BOT Law Implementing Rules and
III. CONSTRUCTION
Regulations (IRR):
xxxx
Sec. 5.4. Pre-qualification Requirements. - To pre-qualify, a project proponent must comply with the
3. The FIRST PARTY shall issue a written Notice to Proceed in favor of the SECOND PARTY. The SECOND following requirements:
PARTY, shall mobilize within 60 days from clearing of the site for official groundbreaking.

4. The SECOND PARTY hereby warrants that it shall finish the construction of the WAG-WAG
SHOPPING MALL within SEVEN HUNDRED THIRTY (730) CALENDAR DAYS counted from the a. Legal Requirements
date of the official groundbreaking.
i. For projects to be implemented under the BOT scheme whose operations require a public utility
xxxx franchise, the project proponent and the facility operator must be a Filipino or, if a corporation, must be
duly registered with the Securities and Exchange Commission (SEC) and owned up to at least sixty
6. x x x Compliance with all existing laws, rules and regulations regarding the construction of the percent (60%) by Filipinos.
project shall be [the] responsibility of the SECOND PARTY itself to save and hold the FIRST PARTY xxxx
harmless from any and all liabilities in respect thereto or arising from violations thereof. v. If the contractor to be engaged by the project proponent to undertake the construction works of the
project under bidding needs to be pre-identified as prescribed in the published Invitation to Pre-qualify
IV. BUILD-OPERATE-AND-TRANSFER SCHEME and Bid and is a Filipino, it must be duly licensed and accredited by the Philippine Contractors
Accreditation Board (PCAB). However, if the contractor is a foreigner, PCAB registration will not be
1. The WAG-WAG SHOPPING MALL be constructed by the SECOND PARTY for the FIRST PARTY in required at pre-qualification stage, rather it will be one of the contract milestones.
accordance with this Memorandum of Agreement and with the Build-Operate-and-Transfer Scheme b. Experience or Track Record: The proponent-applicant must possess adequate experience in terms of the
outlined RA 6957 and RA 7718. This Agreement is of course subject to the provisions of RA 7160 and following:
other pertinent laws.
i. Firm Experience: By itself or through the member-firms in case of a joint venture/consortium or
x x x x[24] through a contractor(s) which the project proponent may have engaged for the project, the project
proponent and/or its contractor(s) must have successfully undertaken a project(s) similar or related to the
subject infrastructure/development project to be bid. The individual firms and/or their contractor(s) may
individually specialize on any or several phases of the project(s). A joint venture/consortium proponent
shall be evaluated based on the individual or collective experience of the member-firms of the joint
Section 2 of R.A. No. 6957 as amended by R.A. No. 7718, defined the terms Contractor and Project Proponent as follows:
venture/consortium and of the contractor(s) that it has engaged for the project.

(k) Project Proponent - The private sector entity which shall have contractual responsibility for the
xxxx
project and which shall have an adequate financial base to implement said project consisting of equity and
vi. Key Personnel Experience: The key personnel of the proponent and/or its contractor(s) must have SEC. 4-A. Unsolicited Proposals. -- Unsolicited proposals for projects may be accepted by any
sufficient experience in the relevant aspect of schemes similar or related to the subject project, as government agency or local government unit on a negotiated basis: Provided, That, all the following
specified by the Agency/LGU. conditions are met: (1) such projects involved a new concept or technology and/or are not part of the list of
e. Financial Capability: The project proponent must have adequate capability to sustain the financing priority projects, (2) no direct government guarantee, subsidy or equity is required, and (3) the government
requirements for the detailed engineering design, construction and/or operation and maintenance phases agency or local government unit has invited by publication, for three (3) consecutive weeks, in a newspaper
of the project, as the case may be. For purposes of pre-qualification, this capability shall be measured in of general circulation, comparative or competitive proposals, and no other proposal is received for a period
terms of: of sixty (60) working days: Provided, further, That in the event another proponent submits a lower price
proposal, the original proponent shall have the right to match that price within thirty (30) working days.
(i) proof of the ability of the project proponent and/or the consortium to provide a minimum amount of
equity to the project measured in terms of the net worth of the company or in the case of joint ventures
or consortia the combined net worth of members or a set-aside deposit equivalent to the minimum equity
required, and We note that it was the SB which invited the API to provide information on the construction of a shopping mall project
under the BOT scheme. It cannot be said thus that the development project originated from the proponent/contractor. Nonetheless,
(ii) a letter testimonial from reputable banks attesting that the project proponent and/or members of
the consortium are banking with them, and that they are in good financial standing. The government even if the proposal is deemed unsolicited, still the requirements of the law have not been complied with.
Agency/LGU concerned shall determine on a project-to-project basis, and before pre-qualification, the
minimum amount of equity needed. In addition, the Agency/LGU will inform the proponents of the
minimum debt-equity ratio required by the monetary authority for projects to be financed by foreign
The IRR specified the requirement of publication of the invitation for submission of proposals, as follows:
loans.

SEC. 10.11. Invitation for Comparative Proposals. - The Agency/LGU shall publish the invitation
x x x x (Emphasis supplied.)
for comparative or competitive proposals only after ICC/Local Sanggunian issues a no objection clearance
of the draft contract. The invitation for comparative or competitive proposals should be published at least
once every week for three (3) weeks in at least one (1) newspaper of general circulation. It shall indicate the
time, which should not be earlier than the last date of publication, and place where tender/bidding
We have held that the Implementing Rules provide for the unyielding standards the PBAC should apply to determine the financial documents could be obtained.It shall likewise explicitly specify a time of sixty (60) working days reckoned
capability of a bidder for pre-qualification purposes: (i) proof of the ability of the project proponent and/or the consortium to provide from the date of issuance of the tender/bidding documents upon which proposals shall be received. Beyond
said deadline, no proposals shall be accepted. A pre-bid conference shall be conducted ten (10) working days
a minimum amount of equity to the project and (ii) a letter testimonial from reputable banks attesting that the project proponent after the issuance of the tender/bidding documents. (Emphasis supplied.)
and/or members of the consortium are banking with them, that they are in good financial standing, and that they have adequate
resources. The evident intent of these standards is to protect the integrity and insure the viability of the project by seeing to it that the
The above provision highlighted other violations in the bidding procedure for the subject BOT project. First, there was no prior
proponent has the financial capability to carry it out.[25] Unfortunately, none of these requirements was submitted by API during the
approval by the Investment Coordinating Committee of the National Economic Development Authority (ICC-NEDA) of the Wag-
pre-qualification stage.
Wag Shopping Mall project. Under the BOT Law, local projects to be implemented by the local government units concerned costing
above P200 million shall be submitted for confirmation to the ICC-NEDA.[27] Such requisite approval shall be applied for and should
Petitioner assails the Sandiganbayan for allegedly failing to appreciate the legal intent of the BOT Law which allows
be secured by the head of the LGU prior to the call for bids for the project. [28] Second, the law requires publication in a newspaper of
contracts on a negotiated basis for unsolicited proposals like the Wag-Wag Shopping Mall project. It asserts that the procedure and
general circulation. To be a newspaper of general circulation, it is enough that it is published for the dissemination of local news and
requirements for bidding have been complied with when the Municipality of Muoz caused the publication of the invitation to submit
general information, that it has a bona fide subscription list of paying subscribers, and that it is published at regular intervals. Over
comparative bids for the BOT project was published in Pinoy, a newspaper of general circulation for three consecutive weeks. Since
and above all these, the newspaper must be available to the public in general, and not just to a select few chosen by the
no comparative bid/proposal was received within sixty (60) days, the BOT project was rightfully awarded to API, the original
publisher.[29]Petitioner did not submit in evidence the affidavit of the publisher attesting to Pinoy tabloid as such newspaper of general
proponent.
circulation. And third, even assuming that Pinoy was indeed a newspaper of general circulation, the invitation published indicated a
shorter period of submission of comparative proposals, only thirty (30) days instead of the prescribed sixty (60) days counted from
The contention fails. the date of issuance of tender documents.

Unsolicited proposals refer to project proposals submitted by the private sector to undertake infrastructure or development projects There is likewise no showing that API complied with the submission of a complete proposal required under the IRR:
which may be entered into by a government agency or local government unit. [26] Section 4-a of R.A. No. 6957 as amended by R.A.
SEC. 10.5 Submission of a Complete Proposal. - For a proposal to be considered by the
No. 7718 governs unsolicited proposals: Agency/LGU, the proponent has to submit a complete proposal which shall include a feasibility
study, company profile as outlined in Annex A, and the basic contractual terms and conditions on the
obligations of the proponent and the government. The Agency/LGU shall acknowledge receipt of the proposal After the concerned government agency or local government unit (LGU) has received, evaluated,
and advice the proponent whether the proposal is complete or incomplete. If incomplete, it shall indicate what and approved the pursuance of the project subject of the unsolicited proposal, the subsequent steps are
information is lacking or necessary. (Emphasis supplied.) fundamentally similar to the bidding process conducted for ordinary government projects.

The three principles of public bidding are: the offer to the public, an opportunity for competition,
and a basis for an exact comparison of bids, all of which are present in Sec. 10.9 to Sec. 10.16 of the
As correctly pointed out by the Sandiganbayan, APIs proposal showed that it lacked the above requirements as it did not include a IRR. First, the project is offered to the public through the publication of the invitation for comparative
proposals. Second, the challengers are given the opportunity to compete for the project through the submission
company profile and the basic contractual terms and conditions on the obligations of the proponent/contractor and the government. of their tender/bid documents. And third, the exact comparison of the bids is ensured by using the same
Had such company profile been required of API, the municipal government could have been apprised of the fact that said requirements/qualifications/criteria for the original proponent and the challengers, to wit: the proposals of the
original proponent and the challengers must all be in accordance with the requirements of the Terms
contractor/proponent had been in existence for only three months at that time and had not yet completed a project, although APRI, of Reference (TOR) for the project; the original proponent and the challengers are required to post bid bonds
equal in amount and form; and the qualifications of the original proponent and the challengers shall be
which actually undertook the Calamba and Lemery shopping centers also under BOT scheme, is allegedly the same entity as API
evaluated by the concerned agency/LGU using the same evaluation criteria. (Additional emphasis supplied.)
which have the same set of incorporators and directors.But more important, the municipality could have realized earlier, on the basis
of financial statements and experience in construction included in the company profile, that API could not possibly comply with the
huge financial outlay for the Wag-Wag Shopping Mall project. It could have also noted the fact that the aforesaid BOT shopping In this case, the only attempt made to comply with the bidding requirements is the publication of the invitation which, as
centers in Lemery and Calamba being implemented by APRI at that time were not yet finished or completed. In any event, such already mentioned, was even defective. As noted by the Sandiganbayan, there was no in-depth negotiation as to the project scope,
existing BOT contract of APRI with another LGU neither justified non-compliance by API with the submission of a complete implementation and arrangements and concession agreement, which are supposed to be used in the Terms of Reference (TOR). Such
proposal for the Wag-Wag Shopping Mall project for a competent evaluation by the PBAC. TOR would have provided the interested competitors the basis for their proposed cost, and its absence in this case is an indication
that any possible competing proposal was intentionally avoided or altogether eliminated. The essence of competition in public

Indeed, contrary to petitioners stance, the process of unsolicited proposals does involve public bidding where, in the end, the bidding is that the bidders are placed on equal footing.[32]In the award of government contracts, the law requires a competitive public

government is free to choose the bid or proposal most advantageous to it.[30] Thus we held in Asias Emerging Dragon Corporation bidding. This is reasonable because [a] competitive public bidding aims to protect the public interest by giving the public the best

v. DOTC[31]: possible advantages thru open competition. It is a mechanism that enables the government agency to avoid or preclude anomalies in
the execution of public contracts.[33]
The protestation by AEDC of our characterization of the process on unsolicited proposal as public
bidding is specious.
Despite APIs obvious lack of financial qualification and absence of basic terms and conditions in the submitted proposal,
We call attention to the following relevant sections of Rule 10 of the IRR specifically on
Unsolicited Proposals: petitioner who chaired the PBAC, recommended the approval of APIs proposal just forty-five (45) days after the last publication of
the invitation for comparative proposals, and subsequently requested the SB to pass a resolution authorizing him to enter into a MOA
Sec. 10.9. Negotiation With the Original Proponent. - Immediately after
ICC/Local Sanggunians clearance of the project, the Agency/LGU shall proceed with the in-depth with API as the lone bidder for the project. It was only in the MOA that the details of the construction, terms and conditions of the
negotiation of the project scope, implementation arrangements and concession agreement, all of parties obligations, were laid down at the time API was already awarded the project. Even the MOA provisions remain vague as to
which will be used in the Terms of Reference for the solicitation of comparative
proposals. The Agency/LGU and the proponent are given ninety (90) days upon receipt of ICCs the parameters of the project, which the Sandiganbayan found as placing API at an arbitrary position where it can do as it pleases
approval of the project to conclude negotiations. The Agency/LGU and the original proponent shall
negotiate in good faith. However, should there be unresolvable differences during the negotiations, without being accountable to the municipality in any way whatsoever. True enough, when API failed to execute the construction
the Agency/LGU shall have the option to reject the proposal and bid out the project. On the other works and abandoned the project, the municipality found itself at extreme disadvantage without recourse to a performance security
hand, if the negotiation is successfully concluded, the original proponent shall then be required
to reformat and resubmit its proposal in accordance with the requirements of the Terms of that API likewise failed to submit.
Reference to facilitate comparison with the comparative proposals. The Agency/LGU shall
validate the reformatted proposal if it meets the requirements of the TOR prior to the issuance of
the invitation for comparative proposals.
Petitioner as the local chief executive failed to ensure that API which was awarded the BOT contract, will submit such

Sec. 10.10. Tender Documents. - The qualification and tender documents shall be other requirements specified under the IRR:
prepared along the lines specified under Rules 4 and 5 hereof. The concession agreement that
will be part of the tender documents will be considered final and non-negotiable by the challengers. Sec. 11.7. Conditions for Approval of Contract. - The Head of Agency/LGU shall ensure that all
Proprietary information shall, however, be respected, protected and treated with utmost of the following conditions have been complied with before approving the contract:
confidentiality. As such, it shall not form part of the bidding/tender and related documents.
a. Submission of the required performance security as prescribed under Section 12.7 hereof;
xxxx
b. Proof of sufficient equity from the investors and firm commitments from reputable financial a dishonest purpose or some moral obliquity and conscious doing of a wrong; a breach of sworn duty through
institution to provide sufficient credit lines to cover the total estimated cost of the project; some motive or intent or ill will; it partakes of the nature of fraud. Gross negligence has been so defined as
negligence characterized by the want of even slight care, acting or omitting to act in a situation where there is
c. ICC clearance of the contract on a no-objection basis; a duty to act, not inadvertently but wilfully and intentionally with a conscious indifference to consequences in
so far as other persons may be affected. It is the omission of that care which even inattentive and thoughtless
men never fail to take on their own property.[35]
Failure by the winning project proponent to submit the requirements prescribed under items a, b
and c above within the time period specified by the concerned Agency/LGU in the Notice of Award or failure
to execute the contract within the specified time shall result in the disqualification of the bidder, as well as
the forfeiture of the bid security of the bidder.
We sustain and affirm the Sandiganbayan in holding that petitioner violated Section 3(e) of R.A. No. 3019, and that he
xxxx cannot shield himself from criminal liability simply because the SB passed the necessary resolutions adopting the BOT project and
authorizing him to enter into the MOA. We find no error or grave abuse in its ruling, which we herein quote:
Sec. 12.7. Performance Guarantee for Construction Works. - To guarantee the faithful
performance by the project proponent of its obligations under the contract including the prosecution of
the construction works related to the project, the project proponent shall post in favor of the Agency/LGU It is apparent that the unwarranted benefit in this case lies in the very fact that API was allowed to
concerned, within the time and under the terms prescribed under the project contract, a performance security present its proposal without compliance of [sic] the requirements provided under the relevant laws and
in the form of cash, managers check, cashiers check, bank draft or guarantee confirmed by a local bank (in the rules. To begin with, the municipal government never conducted a public bidding prior to the execution of the
case of foreign bidders bonded by a foreign bank), letter of credit issued by a reputable bank, surety bond contract. The project was immediately awarded to the API without delay and without any rival proponents,
callable on demand issued by the Government Service Insurance System (GSIS) or by surety or insurance when it was not qualified to participate in the first place. The legality and propriety of the agreement executed
companies duly accredited by the Office of the Insurance Commissioner, or a combination thereof, in with the contractor is totally absent based on the testimonies of both the prosecution and the defense.
accordance with the following schedules:
This Court also considers these particular acts significant. First. From the testimony of then Vice-
a. Cash, managers check, cashiers check, irrevocable letter of credit, bank draft a minimum of two Mayor Ruiz, Jesus V. Garcia, the president of API, attended the SB session after paying a courtesy call to the
percent (2%) of the total Project Cost. Accused who was then the Mayor. Second. It was the Accused who signed and posted the Invitation to Bid
(Exhibit N) giving proponents 30 days to submit their proposals. Third. The Accused is the head of the Pre-
Qualification Bids and Awards Committee which according to him recommended the approval of APIs
b. Bank Guarantee a minimum of five percent (5%) of the total Project Cost. proposal. This was the reason he used in requesting authority from the SB to grant him the authority to contract
with API. Fourth. The Accused requested the SB to give him authority to enter into an agreement with API
c. Surety Bond a minimum of ten percent (10%) of the total Project Cost. (Emphasis supplied.) through a resolution (Exhibit S)[.] Fifth. It was the Accused who invited the SB members to go to the Mayors
office to witness the signing of the Memorandum of Agreement between the municipality and API.[36]

In the Notice of Award dated September 16, 1996, petitioner directed API to submit the above requirements. However, APIs counsel,
As the local chief executive, petitioner is not only expected to know the proper procedure in the bidding and award of infrastructure
Atty. Lydia Y. Marciano, wrote in reply that such requirements do not apply because APIs project does not involve any government
contracts such as BOT projects, he is also duty bound to follow the same and his failure to discharge this duty constitutes gross and
undertaking. API at that point should have been disqualified and its bid security forfeited, pursuant to Section 11.7 of the IRR. Yet,
inexcusable negligence.[37]
API was allowed to proceed with the execution of the project albeit only the site clearing, excavation and construction of a sales
office were accomplished.
Petitioner further assails the Sandiganbayan in not considering the previous dismissal of the criminal complaint filed by Alberto
Castaeda against petitioner also involving the Wag-Wag Shopping Mall project. The Sandiganbayan pointed out that said case
Under the facts established, it is clear that petitioner gave unwarranted benefits, advantage or preference to API considering that said
(OMB-1-97-1885) was dismissed by the Office of the Deputy Ombudsman for Luzon on March 26, 1999 at the time the construction
proponent/contractor was not financially and technically qualified for the BOT project awarded to it, and without complying with the
works were supposedly only temporarily stopped by API, while in this case it is already apparent that the latter abandoned the project
requirements of bidding and contract approval for BOT projects under existing laws, rules and regulations.
and reneged on its obligation.

The word unwarranted means lacking adequate or official support; unjustified; unauthorized or without justification or
We find nothing illegal in the reversal by the Ombudsman upon review of the September 9, 2002 resolution of the Office of the
adequate reason. Advantage means a more favorable or improved position or condition; benefit, profit or gain of any kind; benefit
Deputy Ombudsman for Luzon which recommended the dismissal of the complaint-affidavit filed by Domiciano R. Laurena IV upon
from some course of action. Preference signifies priority or higher evaluation or desirability; choice or estimation above
the ground that a similar criminal complaint filed by Castaeda had been dismissed in OMB-1-97-1885. The Office of the Ombudsman
another.[34] As to partiality, bad faith, and gross inexcusable negligence, we have explained the meaning of these terms, as follows:
Chief Legal Counsel granted the petition for review filed by complainant Laurena IV and recommended that petitioner be indicted
Partiality is synonymous with bias which excites a disposition to see and report matters as they are before the Sandiganbayan for violation of Section 3(e) of R.A. No. 3019. It pointed out that the dismissal of OMB-1-97-1885 was
wished for rather than as they are. Bad faith does not simply connote bad judgment or negligence; it imputes
a chance for the prosecutor, or in this case the Office of the Ombudsman, to review and re-evaluate its
premised on the authority of a local legislature to accept unsolicited proposals and enter into a BOT project under R.A. No. 6957 as findings and the evidence already submitted. (Emphasis supplied.)
amended by R.A. No. 7718, and the lack of any showing of undue injury to the Municipality of Muoz as a result of the temporary
work stoppage. However, the issue of lack of APIs construction license was never brought out in the earlier case while in the present
case, the PCAB attested to the fact that API is not a licensed contractor and petitioners approval of APIs proposal is a clear badge of As to the propriety of damages awarded by the Sandiganbayan, we find that the same is proper and justified. The term undue injury

giving unwarranted benefit, preference or advantage through manifest partiality, evident bad faith, or at the very least, gross in the context of Section 3(e) of the Anti-Graft and Corrupt Practices Act punishing the act of causing undue injury to any party, has

inexcusable negligence. The OMB found that petitioner could have easily discovered such fact with basic prudence considering that a meaning akin to that civil law concept of actual damage. Actual damage, in the context of these definitions, is akin to that in civil

a P240-million infrastructure was involved, but apparently he threw all caution to the wind and relied solely on the self-serving law.[42]

representation of API that it possesses the requisite contractors license.[38] This ruling of the OMB Chief Legal Counsel was affirmed
upon review by the Special Prosecutor and approved by Ombudsman Merceditas N. Gutierrez on August 4, 2006. [39] Article 2199 of the Civil Code provides that except as provided by law or by stipulation, one is entitled to an adequate compensation
only for such pecuniary loss suffered by a party as he has duly proved. Liquidated damages, on the other hand, are those agreed upon

It may be recalled that on motion of petitioner, the Ombudsman even conducted a reinvestigation of the case pursuant to the January by the parties to a contract, to be paid in case of a breach thereof. [43]

15, 2007 directive of the Sandiganbayan. In a memorandum[40] dated March 5, 2007, then Special Prosecutor Dennis M. Villa-Ignacio
approved the finding of probable cause against the petitioner and the recommendation that the information already filed in this case, For approved BOT contracts, it is mandatory that a performance security be posted by the contractor/proponent in favor of the LGU
for which petitioner had already been arraigned, be maintained. Petitioner cannot claim denial of his right to due process, as he had in the form of cash, managers check, cashiers check, irrevocable letter of credit or bank draft in the minimum amount of 2% of the
been given ample opportunity to present evidence on his defense in the proceedings before the Ombudsman and Sandiganbayan. total project cost.[44] In case the default occurred during the project construction stage, the LGU shall likewise forfeit the performance
security of the erring project proponent/contractor.[45] The IRR thus provides:

No grave abuse of discretion was committed by the Ombudsman in reversing the previous dismissal of a similar criminal complaint SEC. 12.13. Liquidated Damages. - Where the project proponent of a project fails to satisfactorily
against the petitioner involving the anomalous award of the BOT contract to API. Indeed, the Ombudsman is not precluded from complete the work within the construction period prescribed in the contract, including any extension or grace
period duly granted, and is thereby in default under the contract, the project proponent shall pay the
ordering another review of a complaint, for he or she may revoke, repeal or abrogate the acts or previous rulings of a predecessor in Agency/LGU concerned liquidated damages, as may be agreed upon under the contract by the parties. The
parties shall agree on the amount and schedule of payment of the liquidated damages. The performance
office. Thus we held in Trinidad v. Office of the Ombudsman[41]:
security may be forfeited to answer for any liquidated damages due to the Agency/LGU. The amount of
liquidated damages due for every calendar day of delay will be determined by the Agency/LGU. In no case
Petitioners arguments that res judicata applies since the Office of the Ombudsman twice found no however shall the delay exceed twenty percent (20%) of the approved construction time stipulated in the contract
sufficient basis to indict him in similar cases earlier filed against him, and that the Agan cases cannot be a plus any time extension duly granted. In such an event the Agency/LGU concerned shall rescind the contract,
supervening event or evidence per se to warrant a reinvestigation on the same set of facts and circumstances forfeit the proponents performance security and proceed with the procedures prescribed under Section 12.19. b.
do not lie.

Res judicata is a doctrine of civil law and thus has no bearing on criminal proceedings.
Had the requirement of performance security been complied with, there is no dispute that the Municipality of Muoz would have been

But even if petitioners argument were to be expanded to contemplate res judicata in prison grey or entitled to the forfeiture of performance security when API defaulted on its obligation to execute the construction contract, at the
the criminal law concept of double jeopardy, this Court still finds it inapplicable to bar the reinvestigation
very least in an amount equivalent to 2% of the total project cost. Hence, said LGU is entitled to such damages which the law
conducted by the Office of the Ombudsman. For the dismissal of a case during preliminary investigation
does not constitute double jeopardy, preliminary investigation not being part of the trial. mandates to be incorporated in the BOT contract, the parties being at liberty only to stipulate the extent and amount thereof. To rule
otherwise would mean a condonation of blatant disregard and violation of the provisions of the BOT law and its implementing rules
Insisting that the case should be barred by the prior Joint Resolution of the Ombudsman, petitioner
posits that repeated investigations are oppressive since he as respondent and other respondents would be made and regulations which are designed to protect the public interest in transactions between government and private business
to suffer interminable prosecution since resolutions dismissing complaints would perpetually be subject to
reopening at any time and by any party. Petitioner particularly points out that no new evidence was presented entities. While petitioner claims to have entered into a compromise agreement as authorized by the SB and approved by the trial
at the reinvestigation. court, no evidence of such judicial compromise was submitted before the Sandiganbayan.

Petitioners position fails to impress.


WHEREFORE, the petition is DENIED. The Decision dated November 16, 2009 and Resolution dated June 9, 2010 of the
The Ombudsman is not precluded from ordering another review of a complaint, for he or she
may revoke, repeal or abrogate the acts or previous rulings of a predecessor in office. And Roxas v. Hon. Sandiganbayan in Criminal Case No. SB-06-CRM-0389 are AFFIRMED.
Vasquez teaches that new matters or evidence are not prerequisites for a reinvestigation, which is simply
With costs against the petitioner.

SO ORDERED.

Anda mungkin juga menyukai